You are on page 1of 16

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

DESIGN SUBGRADE CBR FOR FLEXIBLE


PAVEMENTS: COMPARISON OF PREDICTIVE
METHODS
A. Nataatmadja, Roads and Maritime Services, New South Wales,
Australia
S.Y. Tao, Roads and Maritime Services, New South Wales,
Australia
K. Chim, Roads and Maritime Services, New South Wales, Australia
ABSTRACT
Subgrade performance is a function of a soil's strength and its behaviour under traffic loading.
The subgrade should be sufficiently stable to prevent excessive rutting and shoving during
construction, provide good support for placement and compaction of pavement layers, limit
pavement rebound deflections to acceptable limits, restrict the development of excessive
permanent deformation (rutting) in the subgrade during the service life of the pavement and
minimise effect of changes in moisture level.
When the subgrade does not possess these attributes, corrective action in the form of a
subgrade treatment is needed. The method of excavation and replacement is commonly
adopted in situations where the subgrade soaked CBR is less than the assumed design soaked
CBR. This paper discusses various methods used to obtain the design (effective) subgrade
CBR for use in a mechanistic design procedure for flexible pavements. The results from the
Odemark Transformation Method, both with and without a correction factor, are compared with
the results from multi-layered elastic analyses for both isotropic and anisotropic conditions. A
new method for calculating the effective subgrade CBR is proposed and validated based on the
performance of a number of typical pavement structures.

INTRODUCTION
In case of weak subgrade, it is common to use capping materials or working platforms of
suitable quality such as select material, chemically modified soil, geogrid reinforced soil, etc. In
this case, the effective or the composite strength of its subgrade and the capping material given
would then be used for the design of flexible pavements.
The RMS Austroads Guide Supplement to Pavement Technology Part 2 (RMS 2010) gives
presumptive subgrade CBR values which may be used in pavement design for various working
platforms (Table 1).

ARRB Group Ltd and Authors 2012

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

Table 1: Presumptive effective subgrade CBR for various working platforms

Source: RMS (2010).

On the other hand, the 2010 version of Austroads Guide to Pavement Technology Part 2
(Austroads 2010) specified that (in Section 3.14.1):

The above clause is no longer mentioned in the current Austroads Guide Part 2 (Austroads
2012) since it is generally accepted in practice that the thickness and strength of working
platform or capping layer should be taken into account to achieve the nominated effective
subgrade strength.
For pavements with thin bituminous surfacing, Figure 8.4 of Austroads Guide Part 2 seems to
suggest that it may be used to calculate the thicknesses of capping layers and other pavement
layers above the original subgrade for a certain design ESA. For example, from Figure 1 it may
be inferred that 110 mm of material with a CBR of 3% may be used as a capping layer on top of
a natural subgrade with a CBR of 2% to produce a subgrade with an effective CBR of 3% for a
6
DESA of 10 (Figure 2). This is certainly not in agreement with RMS Supplement as shown in
Table 1.
The chart shown as Figure 1 has been empirically developed to determine the layer
composition of a pavement with thin bituminous surfacing. It can be shown that for such a
pavement, CIRCLY modelling (with maximum base modulus = 500 MPa) can produce similar
layer thicknesses based on the limiting strain criterion of the natural subgrade. However, if the
chart is used to obtain the capping layer thickness for subgrade improvement, the thickness so
obtained may not be appropriate for other pavement configurations where pavement life may be
controlled by a layer other than the natural subgrade.
This paper examines the issue of selecting an effective material property, CBR or modulus
value, for the combination of a capping layer and a semi-infinite subgrade. In this case, it is
important to note that for a certain traffic loading it is possible to find one pavement
configuration that will perform similarly on a homogeneous semi-infinite subgrade and a twolayer subgrade (capping plus homogeneous semi-infinite subgrade). However, the equivalency
of both subgrade types may not hold for other pavement configurations or traffic loadings.

ARRB Group Ltd and Authors 2012

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

In the subsequent sections of this paper, empirical methods for finding the effective CBR are
presented and their validity examined. The results from the calculations are compared with
those obtained from multilayered elastic theory on the basis of equal surface deflection so that
the effective subgrade CBR so obtained will be applicable to any flexible pavement types and
not affected by the choice of pavement materials and their fatigue characteristics.

Source: Austroads (2012).

Figure 1: Austroads chart for designing thin bituminous pavement

Figure 2: Thickness of capping layer inferred from Fig. 8.4 of Austroads (2012) for an
effective CBR of 3%

ODEMARKS METHOD OF EQUIVALENT THICKNESS


Odemark has developed an approximate method to calculate stresses and strains in multiplayer
pavement systems by transforming this structure into an equivalent one-layer system with
equivalent thicknesses of one elastic modulus. This concept is known as the Method of
Equivalent Thickness (MET) or Odemarks Method, which assumes that the stresses and
strains below a layer depend only on the stiffness of that layer. If the thickness, modulus and
Poissons ratio of a layer is changed, but the stiffness remains unchanged, the stresses and

ARRB Group Ltd and Authors 2012

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

strains below the layer should also remain (relatively) unchanged. According to Odemark, the
stiffness of a layer is proportional to the following term (Ullidtz 1987):
(1)

h E
1

where
h

thickness of the layer (m)

elastic modulus (MPa)

Poissons ratio.

For the two layers of different materials shown below, it can be stated that both are of equivalent
stiffness if

3
1

1
2

3
2

2
2

For the case of two materials with equal Poissons ratio, the following equation will hold:

h =3

3
1

=h

E
1

1
2

Therefore, for a system with two finite layers with equal Poissons ratio as shown below, layer 1
of modulus E1 can be represented by an equivalent thickness (he) of modulus E2:

h =h
e

E
1

1
2

Note that the correction factor f of Odemarks method is different from f = Ev / (1 + v) used in
the CIRCLY computer program.
Researchers reported that the value of the correction factor f depends on the layer
thicknesses, modular ratios, and the number of layers in the pavement structure. However, it

ARRB Group Ltd and Authors 2012

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

was mentioned that the use of f values of 0.8 to 0.9 leads to a reasonably good agreement
between the two methods (Subagio et al. 2005).

APPLICATION OF ODEMARKS METHOD


If a finite subgrade layer of (h1, E1) is placed on top of another finite subgrade layer of (h2, E2)
then an equivalent subgrade layer (he, Ee) can be defined by means of the previously described
principle of layer equivalency.
(2)

For layer 1:

e1

= f h

E
1

1
e

For layer 2:

e 2

= f h

E
2

2
e

Therefore,

h = f h
e

E
1

h = f E
e

E
1/ 3

+ f h

E
2

(h E
1

1/ 3
1

2
e

+h E
2

1/ 3

Thus,

E =
e

(h 1E 1 1 / 3+ h 2 E 2 1 / 3)
f

he

Note that in the above equation, Ee and he are variables. If he is taken as (h1 + h2), then

E =
e

(h 1E 1 1 / 3+ h 2 E 2 1 / 3)
f

h1 + h 2

and if there are i layers to be combined, the following equation can be used to find Ee:

ARRB Group Ltd and Authors 2012

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

E =
e

n h E 1 / 3
i i

f 1 n

1 h i

(3)

This equation is known as the Japan Equation in the Austroads Guide Part 2 (Austroads 2012),
where CBRi replaces Ei, with f =1 and hi = 1 metre. The Japan Equation (Japan Road
Association 1989) implicitly assumes the following condition:
all layers are isotropic and have the same Poissons ratio
both the original structure and the transformed structure have the same stress & strain
distribution (f = 1)
the existence of a semi-infinite subgrade thickness is ignored. Figure 3 (a) and 3 (b) shows
that only 1 metre upper layer depth is considered. In other words, the effect of applied stress
is assumed to be negligible below this depth. This is an assumption that may be acceptable
for designing concrete pavements but is erroneous in the case of flexible pavements.

Figure 3: Application of subgrade equivalency based on the Japan Equation


Figure 4 shows the required capping thickness according to the Japan Equation to achieve a
design (effective) CBR of 3% for a semi-infinite subgrade CBR of 1% to 3.5%. The capping
materials in this figure can have a CBR between 4% and 10%. It is seen that for an original
subgrade CBR of 2%, a 560 mm thick capping layer of CBR 4% would be needed to produce an
effective CBR of 3%.
Japanese Formula - Target CBR 3%

900
Capping CBR 4%

Thickness of Capping (mm)

800

Capping CBR 5%
700

Capping CBR 6%

600

Capping CBR 7%

500

Capping CBR 8%
Capping CBR 9%

400

Capping CBR 10%


300
200
100
0
1

1.5

2.5

3.5

Original CBR (%)

Figure 4: Thickness of capping layer from the Japan Equation (effective CBR = 3%)

ARRB Group Ltd and Authors 2012

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

ODEMARKS METHOD VERSUS ELASTIC ANALYSIS


From the above, it is clear that a multilayered elastic half-space analysis which considers
anisotropic soils layers (such as CIRCLY) will produce capping thicknesses (and effective
CBRs) that are different from those obtained from the use of the Japan Equation. Note that the
sublayering technique used to simulate the nonlinear modulus variation (Austroads 2012) will
also affect the results.
El-Badawy and Kamel (2011) carried out an extensive study to quantify the influence of layer
thickness, depth, and modular ratios on the correction factor f of the Odemarks transformation
method. A two-layer isotropic system with the first layer thickness (h1) values of 50, 150, 250
and 375 mm were used in the analysis. A total of 5 different modular ratios of E1/E2 = 3.33,
16.67, 33.33, 50.00, and 66.67 for each thickness were analysed. A Poissons ratio of 0.35 was
assumed in all computations. Figure 5 shows the applied load and the properties of the two
layer system used in their analysis.
A linear elastic analysis was performed on the two-layer isotropic subgrade using the KENPAVE
software to calculate the vertical and radial stresses at different depths measured from the
surface of the upper layer under the centerline of the load. Then Odemarks method was used
to convert the two-layer problem into one layer with equivalent thicknesses and one modulus. A
comparison between stresses calculated from both systems was made. The influence of the
correction factor f on the computed stresses of the transformed system using Odemarks
method was studied.
Comparing Odemarks method without using a correction factor (f = 1) to KENPAVE solution
yielded different stress values at the points of interest. A correction factor f was then introduced
into the equation to calculate the corrected equivalent depth. First, a unique f value was applied
to all points of interest for each modular ratio. The results showed good agreement only for the
vertical stresses calculated at the interface between the two layers when using f of 0.8 to 0.9.
However, at any depth other than the interface between the two layers the results showed a
significant difference between the two solutions (Figure 6). This means that the correction factor
f is also dependent on the depth.

Source: El-Badawy and Kamel (2011).

Figure 5: Two-layer model used by El-Badawy and Kamel

ARRB Group Ltd and Authors 2012

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

Figure 6: Variation of correction factor (f) with depth (after El-Badawy and Kamel 2011).

FURTHER COMPARISON WITH ISOTROPIC ELASTIC


ANALYSIS
Considering the highly variable nature of the correction factor f, the authors of the present study
did not attempt to find the exact value or correct variation of f. Rather, the objective of this study
was focussed on finding a typical f value that can be used to correct Odemarks method for the
purpose of finding the thickness of capping layer required to convert a subgrade with low CBR
values to reach an equivalent half-space CBR of 3% based on surface deflection calculation.
For the purpose of this study, a subgrade with original (semi-infinite) CBR values of 1, 1.5, 2
and 2.5 percent and a capping layer with CBR values of 4, 5, 6, 7, 8, 9 and 10 percent were
chosen. While research overseas and in Australia has shown that non-stress dependent
relationships between CBR and resilient modulus have some limitations (Austroads 2009), in
this paper it is assumed that E (in MPa) = 10 CBR for subgrade soils.
To simplify the analysis, a 5-layer linear elastic computer program CHEVRON was used instead
of CIRCLY since both programs can produce similar results for isotropic conditions. Firstly,
CHEVRON analyses were carried out to find the thickness of capping layer that will produce the
same magnitude of surface deflection (i.e. method of equivalent deflection) under a circular
loading representing a dual wheel assembly with 550 kPa tyre pressure (lower than the actual
tyre pressure acting on the pavement surface), at point A (centre of the load) as shown below in
Figure 7.
The method of equivalent surface deflection is based on the premise that if a correct thickness
of a capping layer of a certain CBR value is used over a subgrade with a certain CBR value, the
two layer system can represent a semi-infinite subgrade with a single design (effective) CBR
(Reddy et al. 2001). By using this method, the capping thickness so calculated is not going to
be influenced by the choice of pavement type (and the corresponding fatigue equations) and
hence, can be used for designing flexible pavement of any configurations.

ARRB Group Ltd and Authors 2012

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

Figure 7: Subgrade model used in the present study (isotropic case)


Figure 8 shows comparison between the capping thickness requirements based on CHEVRON
and the Japan Equation, which suggests that the latter requires greater capping thickness over
a subgrade of various CBR values to produce an effective design CBR of 3%. It is seen that for
a subgrade of CBR 2%, CHEVRON suggests that a 280 mm capping layer with CBR 4% can be
used to reach an effective CBR of 3%.
It is interesting to note that Equation 3 indicates that the equivalent CBR of a multilayered
subgrade would be less than what is predicted from the Japan Equation if f < 1 and thus the
correct capping thicknesses should be greater than those suggested by the formula. The
calculated capping thickness values vary with the case studied (Table 2); however, in all values
but one, it was found that the capping thicknesses from CHEVRON linear elastic and isotropic
analyses are less than those obtained from the Japan Equation. While the Japan Equation
seems to produce adequate capping thicknesses if the soil layers are assumed to be linear
elastic and isotropic, such assumptions are not in accordance with current method for pavement
design (Austroads 2010, 2012).

Figure 8: Comparison capping thicknesses Japan Equation vs. CHEVRON for an


effective CBR of 3%
Table 2: Capping thickness ratios - Japan Equation vs. CHEVRON
Subgrade
CBR (%)

Capping CBR (%)

10

1.0

Japan/CHEVRON

0.9805

1.2952

1.4125

1.4578

1.4783

1.4819

1.4845

1.5

Japan/CHEVRON

1.4769

1.7533

1.8115

1.8084

1.7846

1.7569

1.7251

2.0

Japan/CHEVRON

2.0036

2.1094

2.0311

1.9510

1.8779

1.8049

1.7436

2.5

Japan/CHEVRON

2.3654

2.1140

1.8878

1.7191

1.5904

1.5128

1.4267

ARRB Group Ltd and Authors 2012

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

COMPARISON WITH ANINSOTROPIC ELASTIC ANALYSIS


In accordance with the current Austroads mechanistic pavement design procedure both capping
layer and subgrade soil were considered cross-anisotropic with EV/EH = 2. The Poissons ratio
was assumed 0.45 for both the capping and subgrade layers. Sublayering of the capping was
done according to Austroads (2012).
Similar to the previous case, the load chosen for this study was a half-axle configuration with
550 kPa tyre pressure. CIRCLY analyses were carried out to find the thickness of capping layer
that can convert a subgrade with lower CBR values to an equivalent half-space CBR of 3, 4, 5,
6 and 7 percent for the same magnitude of surface deflection (i.e. method of equivalent
deflection) under a dual wheel assembly, at point A (centre of the wheel) as shown in Figure 9.
For the purpose of this study, a semi-infinite subgrade CBR of 2, 3, 4 and 5 percent and a
capping layer with CBR values of 5, 6, 7, 8, 9 and 10 percent were chosen.

Figure 9: Subgrade model used in the present study (anisotropic case)


Furthermore, to match the calculated capping thicknesses from CIRCLY runs with those from
Odemarks method (Equation 3 with hi = 1 metre), a trial and error process was done by
inputting f values such that the sum of differences between two corresponding capping
thickness values could be minimised (Table 3).
In contrast with the results of Subagyo et al. (2005) the f values obtained from the present study
is variable, which support the results of El-Badawy and Kamel (2011). When the ratios between
effective CBR over original subgrade CBR are plotted against the f values, it becomes clear that
f varies with the ratio between effective CBR to the original, semi-infinite, subgrade CBR (Figure
10). Therefore, the following equation can be used to find the correction factor f:

CBREffective
f = 1.52510.5251

CBROriginal

(4)

Figures 11 and 12 show the variation of capping thickness with the original subgrade CBR to
achieve an effective CBR of 3% and 5%, respectively (for this study the maximum capping layer
thickness was 1000 mm). The existence of double curvature relationships is evident in both
charts, which is similar to that of the previous CHEVRON isotropic analysis (Figure 8).

ARRB Group Ltd and Authors 2012

10

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

Table 3: Calculation of coefficient f by minimising sum of differences


CBR eff.
(%)
3

CBR of capping layer (%)

CBR
original
(%)

Method

CIRCLY

765

615

535

490

455

430

ODEMARK

793

640

546

482

435

399

Differences

-28

-25

-11

20

31

CIRCLY

980

875

800

ODEMARK

965

871

798

Differences

15

10

Capping thickness (mm)

CIRCLY

680

545

480

435

400

ODEMARK

714

569

480

420

376

Differences

-34

-24

15

24

CIRCLY

980

835

745

ODEMARK

972

850

761

Differences

-15

-16

CIRCLY

640

515

445

405

ODEMARK

669

528

442

384

Differences

-29

-13

21

CIRCLY

905

765

ODEMARK

893

776

Differences

12

-11

CIRCLY

960

615

490

425

ODEMARK

918

642

503

419

Differences

42

-27

-13

CIRCLY

845

ODEMARK

848

Differences

-3

ARRB Group Ltd and Authors 2012

CBR
effective
CBR
original

1.5

0.71

Sum
of
diff.

-5

0.52
21

1.33

0.8
-19

1.67

0.64
-23

1.25

0.85
-18

1.5

0.72
1

1.2

0.88
8

1.75

0.77
-3

11

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

Figure 10: Variation of coefficient f with CBREff/CBROriginal


(one point was ignored as it was from one pavement configuration only)

Figure 11: Capping thicknesses Proposed chart to obtain an effective CBR of 3%

Figure 12: Capping thicknesses Proposed chart to obtain an effective CBR of 5%

ARRB Group Ltd and Authors 2012

12

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

In contrast with the previously described methods, it has been found that for a subgrade of CBR
2%, it is not practical to place a capping layer with a CBR of 4% in order to obtain an effective
CBR of 3% (the required capping layer thickness would have to be much greater than 1000
mm). Instead, a 750 mm capping layer with CBR 5% would be needed. It is also interesting to
note that a typical RMS subgrade treatment is to place a 900 mm material with soaked CBR 8%
on top of the subgrade which would, according to these two charts, produce an effective
subgrade soaked CBR of 3% if the original subgrade soaked CBR is about 1.5% or an effective
soaked CBR of 5% if the original subgrade soaked CBR is about 3%.

VALIDATION OF THE PROPOSED METHOD


As previously explained, Equation 4 was derived through the calculation of the surface
deflection of the capping layer so that the resulting thickness should be applicable to any type of
pavements. In spite of that, the process of pavement design involves certain assumptions about
the material properties e.g. non-linearity, anisotropy, and fatigue characteristics. Therefore, it is
important to validate the formula via mechanistic design of a number of flexible pavement types,
which include granular, full depth asphalt and deep strength asphalt pavements (Table 4).
Table 4 shows that in all cases, pavements containing the calculated capping thicknesses
produced pavement lives comparable to those obtained from CIRCLY analyses with a
homogenous semi-infinite subgrade. It is interesting to note that for all pavement types, failures
occurred in a layer other than subgrade.
The results also show that for deep strength asphalt pavement, in order to produce an equal
cumulative damage factor (CDF), the LMC thickness may need to be increased by 2.5 mm
when a capping layer is used. This additional thickness, which is related to the fatigue
characteristics of LMC, may be considered insignificant since in practice, tolerances of
10-20 mm may be applied.

CONCLUSIONS
It has been demonstrated that the effects of combining layers of different soils may alter not
only the stress and strain distributions within the individual layers but also the surface deflection.
Odemarks method simplifies the effect of layering to produce an equation to predict the
combined modulus but does not produce an accurate representation of stress and strain
distribution within multilayered pavement foundation. Correction factors have been proposed to
improve the accuracy of Odemarks method for a combined modulus, but their accuracy may be
questionable.
This paper presented the results of a preliminary investigation on the effect of layering and nonlinearity on the combined modulus of a multilayered subgrade. The study was limited to a twolayer subgrade, being a capping layer with a maximum thickness of one metre, on top of a
semi-infinite subgrade. Limited CBR combinations were analysed using the CIRCLY computer
program with Austroads sublayering and anisotropy assumptions, which produced an equation
that can be used to find the appropriate correction factor for use with the Odemarks method.
Subsequently, charts that can be used to obtain the capping layer thickness on top of a
subgrade were proposed to obtain an effective subgrade CBR for pavement design purposes.
Since the charts have been developed independent from pavement configurations, they can be
used for any type of flexible pavement.
The results of this study indicate that the use of the Odemarks method without a correction
factor (i.e. the Japan Equation) will underestimate the capping thickness requirement if
anisotropy and nonlinearity are considered. The validation process employed in the present
study demonstrates the accuracy of the proposed correction factor and the resulting charts.
Further studies will be conducted to more comprehensively analyse the application of the
method for a wider range of CBR values, number of layers and layer thicknesses.

ARRB Group Ltd and Authors 2012

13

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

Table 4: Results of validation process


Pavement
type

DESA

Effective
subgrade
CBR (%)

Input vertical
modulus
(MPa)

Pavement

Layers (critical
Thicknesses
layer is
(mm)
underlined)
350
Base
270
5
150
SMZ
300
50
Subgrade
Semi-infinite
Granular
1.43E+07
350
Base
270
150
SMZ
300
5**
90
Capping
834
30
Subgrade
Semi-infinite
1700
Wearing AC
40
4000
AC14
50
4000
AC20
260
3
150
SMZ
300
50
UZF
300
30
Subgrade
Semi-infinite
1700
Wearing AC
40
4000
AC14
50
4000
AC20
260
3**
150
SMZ
300
50
UZF
300
50
Capping
743
20
Subgrade
Semi-infinite
Full depth
1.52E+08
1700
Wearing AC
40
asphalt
4000
AC14
50
4000
AC20
260
3**
150
SMZ
300
50
UZF
300
70
Capping
512
20
Subgrade
Semi-infinite
1700
Wearing AC
40
4000
AC14
50
4000
AC20
260
3**
15
SMZ
300
50
UZF
300
100
Capping
374
20
Subgrade
Semi-infinite
1000
Wearing AC
40
2500
AC14
50
2700
AC20
85
3
10000
LMC
195
150
SMZ
300
50
UZF
300
30
Subgrade
Semi-infinite
1000
Wearing AC
40
2500
AC14
50
2700
AC20
85
10000
LMC
197.5
Deep
3**
strength
3.65E+07
150
SMZ
300
asphalt
50
UZF
300
50
Capping
743
20
Subgrade
Semi-infinite
1000
Wearing AC
40
2500
AC14
50
2700
AC20
85
10000
LMC
197.5
3**
150
SMZ
300
50
UZF
300
70
Capping
512
20
Subgrade
Semi-infinite
** With capping layer thicknesses from Equations 3 and 4 to improve the original subgrade CBR.

ARRB Group Ltd and Authors 2012

Cumulative
Damage Factor
(CDF)

9.08 E-01

9.57E-01

9.48E-01

9.72E-01

9.68E-01

9.70E-01

7.86E-01

7.9E-01

7.9E-01

14

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

REFERENCES
Austroads (2009), Review of Relationship to Predict Subgrade Modulus from CBR (California
Bearing Ratio), Sydney, Australia.
Austroads (2010), Guide to Pavement Technology Part 2: Pavement Structural Design, Sydney,
Australia.
Austroads (2012), Guide to Pavement Technology Part 2: Pavement Structural Design, Sydney,
Australia.
El-Badawy, M. and Kamel, M.A. (2011), Assessment of Improvement of the Accuracy of the
Odemark Transformation Method, International Journal of Advanced Engineering Sciences and
Technologies, 5 (2), pp.105-110.
Japan Road Association (1989), Manual for Asphalt Pavement, Japan Road Association,
Tokyo.
Reddy, M.A., Reddy, K.S. and Pandey, B.B. (2001), Design CBR of Subgrade for Flexible
Pavements, IRC Highway Research Bulletin, 64, pp. 61-69.
RMS (2010), Austroads Guide Supplement to Pavement Technology Part 2, Sydney, Australia.
Subagio, B., Cahyanto, H., Rahman A. and Mardiyah, S. (2005), Multi-layer Pavement
Structural Analysis Using Method of Equivalent Thickness, Case Study: Jakarta-Cikampek Toll
Road, Journal of the Eastern Asia Society for Transportation Studies, Vol. 6, pp. 55-65.
Ullidtz, P. (1987), Pavement Analysis, Development in Civil Engineering, Vol.19, Elsevier,
Amsterdam, the Netherlands.

ACKNOWLEDGEMENTS
The comments and views expressed in the paper are those of the authors and not necessarily
of the Roads and Maritime Services of NSW. The authors thank Messrs. D. Hazell and P.
Tamsett for reviewing the manuscript.

AUTHOR BIOGRAPHIES
Andreas Nataatmadja, BE (Hons) Petra, MEng AIT, PhD Monash, GradCert (Env) Melb.,
MIEAust
Dr. Nataatmadja is the Supervising Pavement Engineer (Design & Analysis) of Roads Traffic
Authority-New South Wales in Parramatta. His previous position was Senior Lecturer in
Geotechnical and Pavement Engineering at QUT, Brisbane. He has published numerous
papers in geotechnical engineering and pavement technology. With a research interest in the
areas of material science, geotechnical and pavement engineering, Andreas has been working
in the broad area of civil engineering for more than 30 years in industrial, consulting, research
and teaching environments.
Ms. Su Yin Tao, BSc (App. Chem) UTS, Dip.Sci.Prac UTS, GradCert (Pavement Tech.) CPEE
Su Yin Tao joined the RMS in 2006 on the Graduate Program. She has worked in Materials
Technology, Environmental Assessment, Geotechnical Science, Pavement Design and
Analysis, and Bridge Technology areas of the RMS. She recently completed the Pavement
Technology Graduate Certificate with CPEE and currently works at RMS in the Design and
Analysis Unit, focusing on pavement wear and design review.

ARRB Group Ltd and Authors 2012

15

th

25 ARRB Conference Shaping the future: Linking policy, research and outcomes, Perth, Australia 2012

Mr. Kevin Chim, BE (Civil) Sydney


Kevin Chim joined the RMS in 2006 on the Graduate Recruitment and Development (GRAD)
Program. He has worked in Ballina Road Services, Sydney Asset Management, Sydney Project
Services, Hunter Project Management Service, as well as Road Design areas of the RMS. He is
currently a Pavement Engineer of the Design & Analysis Unit in RMS Pavement Structures
Section, and also involved in pavement material assessments (for Sydney region), section's
quality system, pavement design reviews, and pavement investigations.
Copyright Licence Agreement
The Author allows ARRB Group Ltd to publish the work/s submitted for the 25th ARRB Conference,
granting ARRB the non-exclusive right to:
publish the work in printed format
publish the work in electronic format
publish the work online.
The Author retains the right to use their work, illustrations (line art, photographs, figures, plates) and
research data in their own future works
The Author warrants that they are entitled to deal with the Intellectual Property Rights in the works
submitted, including clearing all third party intellectual property rights and obtaining formal permission from
their respective institutions or employers before submission, where necessary.

ARRB Group Ltd and Authors 2012

16

You might also like