You are on page 1of 10

Chapter 5

126

5. MLLN A/T
5-1 General:Managed leased line network, why managed?
It is centrally monitored and allotment of circuits, deletion of circuits, fault monitoring
and intimation to the maintenance staff, all these functions is being carried out by main
NMS at Bangalore and Pune disaster NMS.
MLLN system comprises of following entities starting from customer to Bangalore NMS,
5-1.1 Abbreviations :1. NTU: - Network Terminating Unit (At customer end)
2. V-MUX: - Versatile Multiplexer.
3. DXC/ DACC: - Digital Cross Connect/ Digital Access Cross Connect.
4. ROT: - Remote Operator Terminal.
5. NMS: - Network Management System.
Please see the block schematic of the network. V-Mux is installed at every station and all
V-MUX are brought to DXC slave rack which after all controlled by DXC second master
and cluster rack.
Some salient features:- Allotment of point to point and point to multipoint circuits.
- Bandwidth 64 Kbps or N X 64 Kbps Maximum 2240 Kbps.
- Provides fully managed and controlled service by using NMS.
- Continuous performance monitoring, Fault monitoring is possible.
- DXC is Tellabs 8170 where as V-MUX Tellabs 8150 and NMS is Tellabs.
- Phase II version was 5.0 whereas phase III version is 6.0.
5-1.2 There are four types of V-MUX which are as follows:Type
Type 1
Type 2
Type 3 ( DC version)
Type 3 (AC version)

64 Kbps
32
16
8
8

Requirements
N x 64 Kbps
Hot line
8
4
4
4
4
4

E1
12
4
2
2

There are four types of DXC-

- 64 ports up gradable to 128 ports


- 96 ports up gradable to 128 ports
- 128 ports up gradable to 256 ports
- 256 ports (32 ports x 8 slave sub rack)
V- MUX sub rack contains following modules,
PFU, VCM, OMH HCQ, QMH, QMH G.703, XCG and CCS.
DXC Slave sub rack contains following modules:PFU, QMH-8, SXU, SCU
DXC Cluster Master Sub rack contains following modules:PFU, CXU, CCU.
Please see MLLN DXC, V-MUX Rack in Fig. 5-1 and block schematic, internal wiring
of MLLN network in Fig. no.s 5-2, 5-3 & 5-4.

149

127

5-1.3 Some important abbreviations of Modules:SR DXC


: - Sub regional DXC.
R- DXC
: - Regional DXC.
OMH
: - Octet Module Housing, 8 customer of 2 MB.
QMH/ HCG: - Quadrate Module Housing, 4 E1 Termination.
XCG
: - Cross Connect Grooming.
QMH/G 703:- Quadrate Module Housing
PFU
: - Power Fuse Unit
SXU
: - Slave X- Connection Unit
SCU
: - Slave Control Unit
CCU
: - Cluster Control Unit
5-1.4 Acceptance Testing comprises of - 1] V- MUX A/T,
2] DXC A/T,
3] ROT A/T.
4]Validation of NMS at NOC (Network
Operating Center) at Pune is over in phase I, DXX,GATEWAY Server in phase II and
DXX, fault, GATEWAY, HP OV Server, LAN switch in phase III,DCN to be offered.
There are two types of tests. 1. Pre power on test. 2. Post power on test.
Pre power on tests: - This test is related with infra structure and Hardware conformity
along with physical verification.
Post power on test: - All tests are NMS related by using ROT at DXC station.
Open Toolbox -- 1. Select
for object selection and its parameters.
2. Move To move Nodes, NTUs , locations to new positions.
3. 8150 Basic - for the addition of new nodes and locations.
4. CTUR
To add new modems.
5. 2 M
To create new trunks between the nodes.
6. SCC To add system control computer.
7. Node Editor- To add units and modules.
8. Interface binder- To bind the trunks and modems.
9. Node Manager - To open Node Manager for the selected Nodes.
MLLN THREE RACKS: DXC SLAVE
SLAVE-1,8150
BASIC MODE

DXC CLUSTER MASTER


8170 MASTER

V- MUX
POWER
VMUX-1

SLAVE-2

8170 CLUSTER

VMUX-2

DDF 1

TERMINATION

DDF 2
SLAVE- 3

Fig. 5-2

SLAVE -4

VMUX-3

150

128

129

5-1.5The NTU types: 64/128 Kbps NTU with v.35 interface


64/128 Kbps NTU with G.703 interface
64/128 Kbps NTU with Ethernet interface
N x 64 Kbps NTU with V.35 interface
N x 64 Kbps NTU with G.703 interface
N x 64 Kbps NTU with Ethernet interface
NMS is at Bangalore and disaster NMS is in Pune
5-2 V- Mux and DXC A/T:A/T should be offered now in atoms: In Acceptance testing of MLLN all tests are related to NMS Bangalore and that too, you
have to check all these commands on ROT.
5-2.1Infra structure check: - Obtain layout of floor plan.
- Check of earthing system: - Mostly earthing system is existing only, you have to
note down earth resistance within six months taken by maintenance staff, if not,
carry out earth measurement.
- Fire alarm system whether FDs are provided or not?
- All details about A/C availability, type of A/C and temperature to be noted down.
- All details about Power plant, Battery and Engine alternator to be noted down.
- Check location, Rigidity and Alignment.
- See whether all documents are related to MLLN available or not?
- Voltage drop to be measured as usual Limit 1.0 V
- Get purchase order and check hardware as per purchase order.
- See cable laying and termination as per BSNL standard done or not?
5-2.2 Acceptance Testing
- Physical verification test to be done as per schedule, actual A/T test starts from
Post power on Test from Test no 1.0, V- Mux nodes creation test to last Test
no.11 Messaging system test.
All these tests commands/ steps are mentioned in test schedule and printout of
circuit creation etc. can be taken out.
In through test BER test is to be conducted between 64 Kbps/ 2 Mbps. circuits of
different NTUs connected to different V-Mux for 60 minutes to be taken.
For example DXC loop test, proceed as Node Editor- click nodes sub rack viewnew DXC- open Router window- click circuit-add- PDH 1/0 PP add cct windowtype name as AT TEST slave no as S1 add select node as new DXC 544 -1st
node-CNDS (Center Node Data Server)-view sub rack close window-next nodeCNDS-click on required slave double click, color changes, close.-bind
MUAP(Multi User Access Point)-Edit, Auto bind, Edit, save all.
5-2.3
ROT Test: ROT test also to be carried out when MLLN is first time installed at a station. It
includes physical verification and basic level tests, Start up, and shut down test all
the tests no. 1 to 5 proceed as per steps given in tests schedule which are very
clear for acceptance testing.
N.B. Please see Trunk creation in DXC, DXC sub rack and loop test on ROT in
Fig. 5-5,5-6, & 5-7 respectively.
130

131

132

133

134

You might also like