Given: Need date - 02.01.

2017, Inhouse production time - 3 days, Float before production - 2


days, Float after production - 1 days
(assumptions: GR time - 1, Opening Period - 10 days, Release period - 5 days, 5 working days
per week & with holidays)
Basic Finish Date - 02.01.2017
Scheduled Finish Date - 29.12.2016 (because Float after prodn is 1 days) as Saturday and
Sunday are holydays 01 jan is also holiday on Sunday.
Scheduled Start Date - 29.12.2016 (because Float before production - 2 days) it will added to
basic start date.
Scheduled Release Date - 21.12.2016 (because Release period - 5 days)
Basic Start Date - 27.12.2016 (because Inhouse prod time - 3 days) 3 days calculated 28, 29,30
Dec