You are on page 1of 369

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

MEMBER OF GROUP AND SUPERVISORS

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

ACKNOWLEDGEMENT

First and foremost, thank you to Allah S.W.T for giving us the strength to finish up this
project report. Without Your Willingness we would not be able to complete this project.
It would be impossible to acknowledge adequately all the people who have been
influential, directly or indirectly in forming this project.
We would like to take this opportunity to express our deepest gratitude to our
supervisors, Encik Mohd Imran Bin Zainuddin and Puan Sunita Binti Jobli who has
given us his constant encouragement constructive advises and his patient in
monitoring our progress in this project.
Our appreciation and special thanks goes, Puan Hasnora Binti Jafri, Puan Junaidah
Binti Jai, Encik Aziz Bin Ishak for supplying the valuable information and guidance for
this project.
We greatly indebted to Encik Napis Bin Sudin for his cooperation and willingness to be
interviewed and for provide us with invaluable information and for his resourcefulness
in gathering material.
Special thanks owe to Puan Masni Bt Ahmad for her willingness to be interviewed and
for the painstaking care she has shown in assisting us throughout the project.
We also would like to express our appreciation to the Malaysia Industrial Development
Authority (MIDA), Pusat Informasi Sirim Berhad, Petronas Resource Center, Jabatan
Perangkaan Malaysia and Tiram Kimia Sdn.Bhd. (Kuala Lumpur) for their generous
supply of relevant documents and material needed research.
Last but not least to all my lecturers, family, friends and collegues for their
encouragement and kind support when we need it most.

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

ABSTRACT

The purpose for this MTBE or Methyl tertiary Butyl Ether plant is to produce 300,000
metric tonne/year. MTBE is the simplest and most cost effective oxygenate to produce,
transport and deliver to customers. The additive works by changing the oxygenate /
fuel ratio so that gasoline burns cleaner, reducing exhaust emissions of carbon
monoxide, hydrocarbons, oxides of nitrogen, fine particulates and toxic. Two units will
be considered which are the fluidizations, (Snamprogetti) Unit and the Etherification
Unit. The raw materials used are isobutane, methanol, and water as feedstock. In
addition, two types of catalysts are chromia alumina catalyzed compound in
Snamprogetti Unit, while sulphonic ion exchanged resin catalyzed is used in the MTBE
reactor. A good deal of catalyst has been devoted to improve the activity, selectivity,
and the lifetime of the catalysts.
In the Design Project 2, we emphasize in the individual chemical and mechanical
designs for selected equipments in the plant. The chosen equipments are Catalytic
Cracking Reactor, Multitubular Fixed Bed Reactor, MTBE Distillation Column, LiquidLiquid Extraction Column and Heat Exchanger.
Design Project 2 also includes Process Control, Safety, Economic Evaluation, Process
Integration and as well as Waste Treatment, which are considered as group works.

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

CONTENTS

TITLE

PAGE

DECLARATION

II

CERTIFICATION

III

ACKNOWLEDGEMENT

ABSTRACT

VI

LIST OF TABLES
LIST OF FIGURES
LIST OF NOMENCLATURES

REPORT 1
CHAPTER 1 PROCESS BACKGROUND AND INTRODUCTION
1.1 Introduction
1.2 Historical Review of MTBE Production Process
1.2.1 UOP Oleflex Process
1.2.2 Philips Star Process
1.2.3 ABB Lummus Catofin Process
1.2.4 Snmprogetti Yartsingtez FBD Process

1
2
3
3
3
4

CHAPTER 2 PROCESS SELECTION


2.1
2.2

Method Consioderation
Detailed Process Description
2.2.1 Snaprogetti Yarsingtez fbd Process
2.2.2 MTBE Unit
2.2.3 Distillation Column Unit
2.2.4 Liquid-Liquid Extraction Unit

5
7
7
8
8
9

CHAPTER 3 ECONOMIC SURVEY


3.1
3.2
3.3

3.4

Market Survey
3.1.1 World Market
Asia Market
Demand
Production Capacity

10
10
11
11
14

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.5
3.6

3.7

Supply
Market Price
3.6.1 Methanol
3.6.2 Isobutane
3.6.3 Catalyst
3.6.4 Conclusion
Economic Analysis
3.7.1 Break Even Analysis
3.7.2 Data Calculation1

14
15
15
16
16
16
17
17
20

CHAPTER 4 PLANT LOCATIONS & SITE SELECTION


4.1
4.2

4.3

4.4

Plant Location
24
General Consideration On the site Selection
24
4.2.1 Location with Respect To Marketing Area 25
4.2.2 Raw Material supply
25
4.2.3 Transport Facilities
25
4.2.4 Availability Of Labor
25
4.2.5 Availability Of Utilities
26
4.2.6 Environmental Impact and Effluent Disposal 26
4.2.7 Local Community Considerations
26
4.2.8 Land (Site Consideration)
26
4.2.9 Political and Strategic Consideration
27
Overview on Prospective Locations
27
4.3.1 Teluk Kalong
28
4.3.2 Tanjung Langsat
28
4.3.3 Bintulu
29
Conclusion
33

CHAPTER 5 ENVIRONMENTAL CONSIDERATION


5.1
5.2
5.3

Introduction
Stack gas
5.2.1 Gas Emission treatment
Wastewater Treatment
5.3.1 Wastewater characteristic
5.3.1a) Priority pollutants
5.3.1b) Organic
5.3.1c) Inorganic
5.3.1d) pH and Alkalinity
5.3.1e) Temperature
5.3.2 Liquid waste treatment
5.3.2a) Equalization treatment
5.3.2b) Solid waste treatment
5.3.3 Waste Minimization

34
35
35
35
35
36
36
37
37
38
38
38
39
41

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

CHAPTER 6 SAFETY CONSIDERATION


6.1
6.2

6.3

Introduction
42
Material Safety Data Sheet
43
6.2.1 Isobutane
43
6.2.1.1 Product Information
43
Physical & Chemical Properties
43
6.2.1.2 Immediate Health Effects
44
6.2.1.3 First Aid Measure
44
6.2.2 N-Butane
44
6.2.2.1 Handling and Storage
45
6.2.3 Methanol
45
6.2.4 MTBE
46
6.2.4.1 Physical State and Appearance46
6.2.4.2 Physical Dangers
46
6.2.4.3 Chemical Dangers
47
6.2.4.4 Inhalation Risks
47
6.2.5 TBA
47
6.2.5.1 Recognition
48
6.2.5.2 Evaluation
48
6.2.5.3 Controls
48
Hazard Identification & Emergency Safety & Health Risk 49

CHAPTER 7 MASS BALANCE


7.1
7.2
7.3
7.4

7.5
7.6

7.7
7.8
7.9

Snamprogetti -Yarsingtez FBD Unit


Separator
Mixer
MTBE Reactor
7.4.1 1st Reaction in rector
7.4.2 2nd Reaction in reactor
7.4.3 3rd Reaction in reactor
7.4.4 Overall reaction
Distillation Column
Liquid Extraction Column
Distillation Column
Overall reaction system; flow diagram
Scales Up Factor

51
53
53
54
55
56
57
58
59
60
61
62
63

CHAPTER 8 ENERGY BALANCES


8.1
8.2

Energy Equation
Energy balance: Sample of calculation
8.2.1 Pump 1
8.2.2 Cooler 1
8.2.3 Separator
8.2.4 MTBE Reactor
8.2.5 Pump 2

64
65
73
75
76
78
79

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

8.2.6
8.2.7
8.2.8
8.2.9
8.2.10
8.2.11
8.2.12
8.2.13
8.2.14
8.2.15
8.2.16

Mixer
Expander 1
Cooler 1
Distillation Column 1
Cooler 2
Pump 3
Extraction Column
Pump 4
Pump 5
Distillation Column 2
Cooler 3

CHAPTER 9 HYSYS

80
81
82
84
86
87
88
89
91
92
93

95

APPENDICES

REPORT 2
CONTENTS
PAGE

CHAPTER 1 CHEMICAL DESIGN AND MECHANICAL DESIGN


SECTION 1 CATALYTIC CRACKING DESIGN

2.2

1.1
Introduction
1.2
Estimation of Cost Diameter of Reactor
1.3
Calculation of TDH Height
1.4
Minimum Fluidization Velocity
1.5
Calculation for Terminal Velocity
1.6
Find the Value Kih
1.7
Find the value Eo
1.8
Calculation of Solid Loading
1.9
Calculation for Holding Time
1.10 Calculation for Pressure Drop
1.11 Determine the Direction and Flowrate
1.12 Design of Cyclone
1.13 Calculation for Mechanical Design
Mechanical Design
2.2.1
Introduction
2.2.2
Design stress
2.2.3
Welded Joint Efficiency

1
3
4
4
5
8
9
10
12
14
15
17
21
58
59
59

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

2.2.4
2.2.5
2.2.6
2.2.7
2.2.7.1

2.2.8
2.2.9
2.2.10
2.2.11
2.2.12
2.2.13
2.2.14
2.2.15
2.2.16
2.2.17
2.2.18
2.2.19
2.2.20
2.2.21

Corrosion allowance
Minimum thickness of cylindrical section of shell
Minimum thickness of domed head
Loading stress
Dead weight load
1.2.7.1
Dead Weight of Vessel
1.2.7.2
Weight of the Tubes
1.2.7.3
Weight of Insulation
1.2.7.4
Weight of Catalyst
1.2.7.5
Total Weight
1.2.7.6
Wind Loading
1.2.7.7
Analysis of Stresses
Dead Weight Stress
Bending Stress
Radial Stress
Check Elastic Stability
Vessel Support
Skirt Thickness
Height of the Skirt
Bending Stress at Base of the Skirt
Bending Stress in the Skirt
Base Ring and Anchor Bolt Design
Compensation for Opening and Branches
Compensation for Other Nozzles
Bolted Flange Joint
2.2.20.1
Type of Flanges Selected
2.2.20.2
Gasket
Flange face

SECTION 3
3.1
3.2
3.3

3.4

59
59
60
61
61
61
62
62
63
63
63
64
65
65
66
67
68
68
69
70
70
71
73
74
74
74
75
75

MTBE DISTILLATION COLUMN

Introduction
Selection f Construction Material
Chemical Design
3.3.1 Determine the Number of Plate
3.3.2 Determination of Number of Plate
3.3.3 Physical Properties
3.3.4 Determination of Column Diameter
3.3.5 Liquid Flow Arrangements
3.3.7 Plate Layout
3.3.8 Entrainment Evaluation
3.3.9 Weeping Rate Evaluation
3.3.13 Number of Holes
3.3.14 Column size
Mechanical Design
3.4.1 Material construction
3.4.2 Vessel Thickness
3.4.3 Heads and closure
3.4.4 Total Column Weight

78
79
79
81
88
89
89
90
91
91
94
95
96
98
98
99

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.5

3.4.5 Wind Loads


3.4.6 Stiffness Ring
Vessel Support Design

SECTION 4
4.1
4.2

4.3

5.1
5.2

5.3

DESIGN OF LIQUID-LIQUID EXTRACTION COLUMN

Introduction
Chemical Design
4.2.1 Choice of Solvent
4.2.2 Estimation the Physical Properties
4.2.3 Determination the Number of Stage
4.2.4 Sizing of Sieve Tray
4.2.5 Number of Holes
4.2.6 Column Parameter
4.2.7 Weeping Evaluation
Mechanical Design
4.3.1 Material Construction
4.3.2 Vessel Thickness
4.3.3 Design of Domed Ends
4.3.4 Column Weight
4.3.4.1 Dead Weight of Vessel
4.3.4.2 Weight of Plate
4.3.4.3 Weight of Insulation
4.3.4.4 Total weight
4.3.4.5 Wind Loading
4.3.5 Analysis of Stress
4.3.5. 1 Longitudinal & Circumferential Pressure Stress
4.3.5.2 Dead weight
4.3.5.3 Bending Stress
4.3.5.4 Buckling
4.3.6 Vessel Support Design
4.3.6.1 Skirt Support
4.3.6.2 Base Ring and Anchor
4.3.7 Piping Sizing

SECTION 5

100
100
100

103
104
104
104
105
107
107
107
108
110
111
111
112
112
113
113
113
114
114
115
115
115
115
116
117
117
119
122

HEAT EXCHANGER DESIGN

Introduction
5.1.1 Designing the heater
Chemical Design
5.2.1 Physical Properties of the Stream
5.2.2 The Calculation
5.2.3 Number of Tubes Calculation
5.2.4 Bundle and Shell Diameter
5.2.5 Tube Side Coefficient
5.2.6 Shell Side Coefficient
5.2.7 Overall Heat Transfer Coefficient
5.2.8 Tube Side Pressure Drop
5.2.9 Shell Side pressure Drop
Mechanical Design
5.3.1 Design Pressure

127
129
130
130
131
133
134
135
137
139
140
140
142
142

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

5.3.2
5.3.3
5.3.4
5.3.5
5.3.6
5.3.7
5.3.8
5.39
5.3.10
5.3.11
5.3.12
5.3.13
5.3.14
5.3.15

Design Temperature
Material of Construction
Exchanger Type
Minimum Thickness
Longitudinal Stress
Circumferential Stress
Minimum Thickness of Tube wall
Minimum Thickness of Head and Closure
Minimum Thickness of the Channel Cover
Design Load
Pipe Size Selection for the Nozzle
Standard Flanges
Design Of Saddles
Baffles

142
142
143
143
144
144
144
145
146
147
150
150
152
152

CHAPTER 2 PROCESS CONTROL AND INSTRUMENTATION


2.1
2.2
2.3

Introduction
Objective of control
Control system design sheet
2.3.1 Heat Exchanger
2.3.2 Catalytic cracking fluidized bed reactor
2.3.3 Compressor
2.3.4 Condenser
2.3.5 Separator
2.3.6 Fixed bed reactor
2.3.7 Distillation Column
2.3.8 Liquid -liquid extraction Column
2.3.9 Distillation Column
2.3.10 Mixer
2.3.11 Expander

154
155
156
156
157
158
159
160
161
162
163
164
165
166

CHAPTER 3 SAFETY CONSIDERATION


3.1
3.2
3.3

3.4

Introduction
Hazard and Operability Study
Plant Start Up and Shut Down Procedure
3.3.1 Normal Start Up and Shut Down the Plant
3.3.1.1 Operating Limits
3.3.1.2 Transient Operating and Process Dynamic
3.3.1.3 Added Materials
3.3.1.4 Hot Standby
3.3.1.5 Emergency Shut Down
3.3.2 Start up and Shut down Procedure for the main
Equipment
3.3.2.1 Reactor
3.3.2.2 Distillation Column
3.3.2.3 Liquid-Liquid Extraction Column
3.3.2.4 Heat Exchanger
Emergency Response Plan (ERP)

167
168
170
171
171
172
172
172
172
172
172
173
174
175
175

10

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.5

3.4.1 Emergency Response Procedures


3.4.2 Evacuation Procedures
3.4.3 Fires
3.4.4 Explosion, Line Rupture or Serious Leak
3.4.5 Other Emergencies
Plant Layout

176
176
177
177
177
178

CHAPTER 4 ECONOMIC EVALUATION


4.1
4.2
4.3

4.4

Introduction
Cost Estimation
Profitability Analysis
4.3.1 Discounted Cash flow
4.3.2 Net Present Value
4.3.3 Cumulative Cash flow Diagram
4.3.4 Rate of Return
4.3.5 Sensitivity Analysis
4.3.6 Payback Period
Conclusion

184
187
199
199
202
203
204
205
206
208

CHAPTER 5 PROCESS INTEGRATION AND PINCH TECHNOLOGY


5.1
5.2
5.3
5.4
5.5

Introduction
Pinch Technology
The Problem Table Method
The Heat Exchanger Network
Minimum number of exchangers

209
209
210
214
216

CHAPTER 6 WASTE TREATMENT


6.1
6.2
6.3
6.4
6.5
6.6

Introduction
Wastewater Treatment
Wastewater Treatment Plant Design
Sludge Treatment
Waste Treatment Plant Layout
Absorption tank using granular activated carbon
6.6.1 Analysis of the absorption process
6.6.2 Breakthrough Absorption capacity

220
221
224
229
230
231
232
233

APPENDICES

11

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

LIST OF TABLES OF DESIGN I

TABLE

TITLE

1.1

The Physical and Chemical Properties of MTBE

2.1

The Comparison of the UOP Oleflex, Philips Star

PAGE
2

SP-Isoether FBD Process

3.1

Trade Balance of MTBE in Asia and Pacific

12

3.2

MTBE Balances for Asia and Pacific

13

3.3

Production, Import, Export & Consumption in Europe in


Year 2000

14

3.4

Supplies MTBE Plant in Asia & Pacific

15

3.5

Standard Price for Isobutane

16

3.6

Cost of Producing MTBE 500000 tonne/year

18

3.7

Value in US Dollar Converted to RM

20

3.8

Value in US Dollar Converted to RM per tonne

20

3.9

Data Calculation by using Microsoft Excel in RM

23

4.1

The Comparison of the Potential Site Location

30

4.2

The Comparison of Location in term of Weightage Study

31

4.3

The Electricity Tariffs (Industrial Tariff) for Peninsular


Malaysia and Sarawak

33

12

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

LIST OF TABLES OF DESIGN II

TABLE

TITLE

PAGE

Chapter 1
Section 1
1.1

Calculation for Terminal Velocity in Different Size of dp.

1.2

Correlation of Three Investigators

10

1.3

Data Calculation to Find Solid Loading

12

1.4

Summary of Mechanical Design

40

3.1

The Composition in Feed Stream

80

3.2

The Composition in Top Stream

80

3.3

The Composition in Bottom Stream

80

3.4

The Average Relative Volatility,

3.5

The Non-key Flow of the Top Stream

82

3.6

The Non-key Flow of the Bottom Stream

83

3.7

MTBE Equilibrium Curve

85

3.8

Provisional Plate Design Specification

97

3.9

Summarized Results of Mechanical Design

101

3.10

Design Specification of the Support Skirt

102

4.1

Provisional Plate Design Specification

106

4.2

Summary of the Mechanical Design

118

4.3

Stress Analysis for Liquid-Liquid Extraction Column

119

4.4

Design Specification of the Support Skirt

119

4.5

Piping Sizing for Liquid-liquid Extraction Column

120

Section 3

82

Section 4

Section 5
5.1

Properties of Raw Material (Isobutane and N-butane)


and Steam for (E100)

5.2
5.3

130

Summary of Chemical Design For


Heat Exchanger In Series

141

By taking D = 100 mm, the selected tube nozzle

149

13

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

TABLE

TITLE

PAGE

5.4

By taking D = 500 mm, the selected tube nozzle is:

149

5.5

Standard Flange for Inlet isobutene

150

5.6

Standard Flange for Outlet isobutene

151

5.7

Standard Flange for Inlet Steam

151

5.8

Standard Flange for Outlet Steam

151

5.9

Using Ds = 600mm, the Standard Steel Saddles


for Vessels up to 1.2m

5.10

152

Summary of Mechanical Design For


Heat Exchanger in Series

153

2.1

Parameter at Heat Exchanger

151

2.2

Parameter at Catalytic Cracking Fluidized Bed Reactor

152

2.3

Parameter at Compressor

153

2.4

Parameter at Condenser

154

2.5

Parameter at Separator

154

2.6

Parameter at Fixed Bed Reactor

155

2.7

Parameter at MTBE Distillation Column

156

2.8

Parameter at Liquid-liquid Extraction Column

157

2.9

Parameter at Distillation Column

158

2.10

Parameter at Mixer

159

2.11

Parameter for Expander

160

Important Features in a HAZOP Study

170

4.1

Labor Cost

189

4.2

Estimation Cost of Purchase Equipment

197-198

4.3

Annual Cash flow Before Tax

200

4.4

Annual Cash flow After Tax

201

4.5

Present Worth Value

202

Chapter 2

Chapter 3
3.1
Chapter 4

14

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.6

After Tax Cumulative Cash Flow

TABLE

203

TITLE

PAGE

4.7

Present Value (RM) When i = 30% & i = 40%

204

4.8

Future Value (RM) When MARR = 15%

205

4.9

Simple Payback Period

206

4.10

The Interpolation Simple Payback Period

206

4.11

Discounted Payback Period

207

4.12

The Interpolation Discounted Payback Period

207

5.1

Shows the process data for each stream.

210

5.2

Interval Temperature for Tmin = 10oC

211

5.3

Ranked order of interval temperature

212

5.4

Problem Table

213

Chapter 5

Chapter 6
6.1

Parameter Limits for Wastewater and Effluent under the Environmental Quality
Act 1974

6.2

208

Functions of Pumps in the Waste Treatment Plant

215

15

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

LIST OF FIGURES OF DESIGN I

FIGURE
3.1

TITLE

PAGE

MTBEs Role in US Gasoline grew rapidly


Through 1995

10

3.2

World MTBE Demand (1998-2010) Mod Scenario

11

3.3

MTBE supply & Demand Asia and Pacific

13

3.4

Breakeven Analysis Chart Calculated by using Excel

19

5.1
.

Functional Elements in a Solid-Waste Treatment System

40

16

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

LIST OF FIGURES OF DESIGN II

FIGURE

TITLE

PAGE

Chapter 1
Section 1
1.1

Illustration Diagram of the Reactor

1.2

CDRe2 and CD/Re vs. Reynolds Number

Analysis of Stresses

67

3.1

MTBE Distillation Column

78

3.2

McCabe-Thiele Diagram

86

5.1

Heat Exchanger in Series for the Heating Process

129

5.2

Steel Pipe Nozzle

149

5.3

Standard Flange

150

2.1

Control Scheme for the Heat Exchanger

156

2.2

Control Scheme for Catalytic Cracking

Section 2
2.1
Section 3

Section 5

Chapter 2

Fluidized Bed Reactor

157

2.3

Control Scheme for the Compressor

158

2.4

Control Scheme for the Condenser

159

2.5

Control Scheme for the Separator

160

2.6

Control Scheme for the Fixed Bed Reactor

161

2.7

Control Scheme for the MTBE Distillation Column

162

2.8

Control Scheme for the Liquid-liquid Extraction Column

163

2.9

Control Scheme for the Distillation Column

164

2.10

Control Scheme for the Mixer

165

2.11

Control Scheme for the Expander

166

17

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

FIGURE

TITLE

PAGE

Chapter 3
3.1

Methyl tert-Butyl Ether (MTBE) Plant Layout

180

3.2

Methyl tert-Butyl Ether (MTBE) Plant Evacuation Routes

181

3.3

PID before HAZOP

182

3.4

PID after HAZOP

183

Cumulative Cash Flow (RM) Versus Year

203

5.1

Diagrammatically representation of process stream

210

5.2

Intervals and streams

211

5.3

Heat Cascade

212

5.4

Grid for 4 stream problem

213

5.5

Grid for 4 Stream Problem

214

5.6

Proposed Heat Exchanger Network

216

6.1

The Sludge Treatment System

229

6.2

Waste Treatment Plant Layout

231

Chapter 4
4.1
Chapter 5

Chapter6

18

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Ar

Archimedes number

acceleration

settling chamber longitudinal cross-sectional area

dimension

constant

CD

drag coefficient

concentration

system diameter

particle diameter

de

effective fiber diameter

E,

field intensity

cross-sectional area

Pr

Fronde number

gravitational acceleration

height

precipitation constant ,

Cross sectional area of catalytic reactor

Aor

Area of orifice

C Ag

Concentration of gas reactant

CD

Drag coefficient

d Bv

Diameter of bubble in the bed

dp

Particle diameter

Diffusivity

Dt

Diameter of catalytic reactor

Thickness

Activation energy

19

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

FBo

Mass flow of coal to the catalytic reactor

FC

Fixed carbon mass fraction

Hbed

Height of bed

Hh

Height of Catalytic reactor

Joint factor

Reaction rate constant

Reaction rate constant

K eq

Equilibrium constant

Height above the bed

Total no of orifice

No of holes in 1 m2 area

Nor

No of orifice in 1 m2 area

PCO , PH 2 O

Pi

Design stress

Partial pressure

rC , rS -

Rate of reaction

Ideal gas constant

Ret

Reynolds number

Rp

Radius of particle

Total holding time

Temperature

Uo

Superficial gas velocity

Umf

Minimum fluidization velocity

Ut

Terminal velocity

VBed

Volume of bed

WBed

Weight of coal in bed

WC

Total mass of carbon

Conversion factor

Fitting parameter (for this design is 0.21)

Fitting parameter (for this design is 0.66)

Gas density

Molar density

Bulk density of catalyst

Particle density

20

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Gas viscosity

Time for complete conversion of reactant particle

Pressure drop

total elutriation rate of particles

Ef

frictional force of particles

Ei

entrainment rate of panicle size i

Ei

elutriation rate of particle size i

Eo

total entrainment rate at bed surface

total elutriation rate of particles

gravitational acceleration constant

gc

gravitational conversion constant, m kg/s2 kg -force

Gi

solids flow rate

height above dense bed surface

Rep

particle Reynolds Number = g (U o U ts ) d p /

Ret

dpU g /

time

Umf

minimum fluidization velocity

Uo

superficial gas velocity

Usi

solid velocity (upward)

Us

single particle terminal velocity of particle size i

weight fraction of bed

Ws

weight of solid particles in verlical pipe having length h

Xi

weight fraction of particle size i in bed

Greek Symbols

voidage in freeboard

21

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

voidage in freeboard for system having only particle size i

solid friciion coefficient

gas density

particle density

22

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

CHAPTER 1

PROCESS BACKGROUND AND INTRODUCTION

1.1

INTRODUCTION

Methyl tertiary butyl ether (MTBE) is produced by reacting isobutene with methanol
over a catalyst bed in the liquid phase under mild temperature and pressure. Isobutene
can be obtained from stream cracker raffinate or by the dehydrogenation of isobutane
from refineries. Ether in general is a compound containing an oxygen atom bonded to
two carbon atoms.
In MTBE one carbon atom is that of a methyl group CH3 and the other is the central
atom of a tertiary butyl group, -C (CH3)). At room temperature, MTBE is a volatile,
flammable, colorless liquid with a distinctive odour. It is miscible with water but at high
concentrations it will form an air-vapour explosive mixture above the water, which can
ignite by sparks or contact with hot surfaces.
MTBE has good blending properties and about 95% of its output is used in gasoline as
an octane booster and an oxygenate (providing oxygen for cleaner combustion and
reduced carbon monoxide emissions). It is also used to produce pure isobutene from
C4 streams by reversing its formation reaction. It is a good solvent and extractant.

Table 1.1: The Physical and chemical properties of MTBE

23

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Chemical formula
Molecular structure
Oxygen content
Physical state (at normal

C5H12O
(CH3)4CO
18.2 wt%
Colorless liquid

temperature and pressure)


Boiling point
Melting point
Flash point
Autoignition temperature
Flammable limits in air
Relative density
Vapour pressure
Reactive index
Color
Water solubility

55.2oC
-108.6 oC
30 oC
425 oC
1.5 8.5%
0.7405g/ml at 20 oC
245 mm Hg at 25 oC
1.3690 at oC
Colorless
42000mg/l at 25 oC (<10% in
water, miscible with ethanol and

1.2

Partition coefficient n-

diethyl ether)
1.06

octanol/water (log10)
Henrys Law Constant

65.4 Pa/m3/mol

HISTORICAL REVIEW OF MTBE PRODUCTION PROCESS

The MTBE plants actually consist of six units: Isomerization Unit (including
deisobutanizer), Dehydrogenation Unit, MTBE Unit, Methanol Recovery Unit,
Oxygenate Removal Unit and Olefin Saturation Unit. A common offsite utility system
will be incorporated to distribute the required utilities to each unit. There are four
method of producing MTBE implemented under license as the following:
1. UOP-Oleflex Process
2. Phillips STAR Process
3. ABB Lummus Catofin Process
4. Snamprogetti-Yarsingtez FBD (SP-Isoether) Process.
1.2.1

UOP-Oleflex Process

24

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

The UOP-Oleflex process uses multiple side-by-side, radial flow, moving-bed reactors
connected in series. Preheated feed and interstage heaters supply the heat of reaction.
The reaction is carried out over platinum supported on alumina, under near isothermal
conditions. The catalyst system employs UOP's Continuous Catalyst Regeneration
(CCR) technology. The bed of catalyst slowly flows concurrently with the reactants and
is removed from the last reactor and regenerated in a separate section. The
reconditioned catalyst is then returned to the top of the first reactor.
processes

involved

are

the

deisobutenization,

the

isomerisation

The typical
and

the

dehydrogenation process that has been commercial in Malaysia.


1.2.2

Philips Star Process

The second one is the Philips Steam Active Reforming (STAR) Process. The Phillips
Steam Active Reforming (STAR) Process uses a noble metal-promoted zinc aluminate
spinel catalyst in a fixed-bed reactor. The reaction is carried out with steam in tubes
that are packed with catalyst and located in a furnace. The catalyst is a solid,
particulate noble metal. Steam is added to the hydrocarbon feed to provide heat to the
endothermic reaction, to suppress coke formation, and to increase the equilibrium
conversion by lowering partial pressures of hydrogen and propane.
1.2.3

ABB Lummus Catofin Process

The ABB Lummus Catofin Process uses a relatively inexpensive and durable
chromium oxidealumina as catalyst. This catalyst can be easily and rapidly
regenerated under severe conditions without loss in activity. Dehydrogenation is
carried out in the gas phase over fixed beds. Because the catalyst cokes up rapidly,
five reactors are typically used. Two are on stream, while two are being regenerated
and one is being purged. The reactors are cycled between the reaction and the
reheat/regeneration modes, and the thermal inertia of the catalyst controls the cycle
time, which is typically less than 10 minutes. The chromium catalyst is reduced from
Cr6+ to Cr3+ during the dehydrogenation cycle. The raw materials used to produce
MTBE by using this method are butanes, hydrogen and as well as recycled isobutene
from the system itself. In this process, there is an isostripper column, which separates
the heavies, and the light ends from which then could produce MTBE.

25

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

1.2.4

Snamprogetti-Yartsingtez FBD (SP-Isoether)

The Snamprogetti-Yarsingtez SP-Isoether (FBD) Process uses a chromium catalyst in


equipment, which is the fluidized bed that resembles conventional fluidized catalytic
cracking technology used in the oil refinery. The catalyst is recirculated from the
reactor to the regeneration section on a 3060-min cycle. The process operates under
low pressure and has a low-pressure drop and uniform temperature profile.
Snamprogetti has been presenting and marketing their hydrogenation technology,
ISOETHER 100, since 1997. This process is to be used to convert MTBE units by
utilizing Snamprogettis MTBE Water Cooled Tubular Reactor Technology. In this SPIsoether Process, the products are MTBE and isooctagenas (iso octane gas). In this
SP-Isoether Process the catalyst used in the isoetherification reactor is the same as
those other typical processes, which is Platinum. (Please refer Appendix A Figure
1.3).
Four method processes of the MTBE above are favorable among the
petrochemical firms.

CHAPTER 2

PROCESS SELECTION

26

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Suitable process, which is gives a lot of profit and less problem is an important in order
to determinant for the success of a plant. This chapter will briefly discuss the best
process selected based on a few criteria. It covers general consideration, detailed
consideration for process selection and conclusion on the process selection.

2.1

METHOD CONSIDERATION.

From the processes mentioned earlier, there are many ways to produce MTBE. It is
essential to choose the best method that will be used to produce MTBE. The selection
of the method must consider the safety of the plant, minimum waste or by product
generated, efficient and economical. Snamprogetti-Yarsingtez SP- Isoether FBD
process will be chosen as the method to produce MTBE. More detailed reasons for the
selection of this process are: High conversion (greater than 98 %) with few by-products
compared to other process. From the economy aspect,Snamprogetti-Yarsingtez FBD
Process can reduce the cost of setting up the plant as it can be implied in any of typical
MTBE-produced plant, known as Financial Safety Net.(When an MTBE plant faces an
oversupplied MTBE market, Isoether makes it possible to switch production from
MTBE to a superior Alkylate.). As for the safety aspects of the plant, as the
Snamprogetti-Yarsingtez FBD is a safe process as it just use the fluidize bed to the
process of producing MTBE. The process operates under low pressure and has a lowpressure drop and this means that the fluidized bed is physically not harmful to anyone.
As for the temperature, it operates under uniform temperature profile. As the
temperature is not high, this means that the process is not as dangerous as other hightemperature-operated process. But, precautions should be taken seriously all the time,
as we do not know when an accident could happen even in the safest place. As for the
waste by using the Snamprogetti-Yarsingtez FBD Process, the product of the process
is only MTBE and other effluent and as well as flue gas which are not harmful to the
environment.
Table 1.1 The comparison of the UOP-Oleflex, Philips Star, ABB Lummus Catofin and
Snamprogetti- Yartsingtez SP-Isoether FBD process.

27

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Method and

UOP-Oleflex

STAR Philip

ABB Lummus

Snamprogetti-

Consideration

Process

process

Process

Yarsingtez FBD

Investment cost

Investment cost

Lower capital

process
Reduce the cost

is very modest

were evaluated

investment

of setting up the

Economic

for 700 BPSD

plant as it can be

Consideration

(650tonne/day)

implied in any of

feed capacity

typical MTBE-

Efficiency

97-99%

98%

99 .99%

produced
Greater than 98%

1. Higher per

1. The Stabilized

1.CD Tech

1.Environmental

pass

Product Is Near

Efficiently Uses

Friendly

conversion and

Equilibrium

The Heat

2.Financial

at least 1-2%

Mixture Of

Released By An

Safety Net.

higher catalyst

Isobutane.

Exothermic

(When an MTBE

selectivity as a

2.The Light-End

Reaction.

plant faces an

result of lowest

Yield Fr. Cracker

2.Conducting 2

oversupplied

operating

Is Less Than 1

Unit Operations

MTBE market,

pressure and

Wt% Butane

In 1 Equipment

Isoether makes it

temperature.

Feed

(Isobutylene
Selectivity)
Advantages

possible to switch

2. No catalyst

production from

losses.

MTBE to a
superior Alkylate.)

Disadvantages

1. Less

1. Much heat is

1. The Reaction

1. Not widely

efficiencies

needed as

Must Take Place

practiced in

furnace is used.

In The Liquid

industry, as it

Phase Catalyst

needs thorough

Must Remain

research to

Completely

implement it.

Wetted.
2.The Reaction
Cannot Be Overly

28

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Endothermic

2.2.1

DETAILED PROCESS DESCRIPTION

2.2.2

Snamprogetti-Yartsingtez SP-Isoether (FBD) Process

The Snamprogetti-Yarsingtez SP-Isoether (FBD) Process uses a chromium catalyst in


equipment, which is the fluidized bed that resembles conventional fluidized catalytic
cracking technology used in the oil refinery with 65% isobutane (i-C4H10) conversion to
produce isobutene.
Dehydrogenation reaction that occur in this process:
iC4H10

iC4H8 + H2

The main feature of this process is that the catalyst filled annuli are connected in such a way
that small, discrete amounts of catalyst can be withdrawn from the bottom of a reactor,
and sent to the top of the reactor. Catalyst withdrawn from the bottom of the reactor is
sent to a separate regeneration section for regeneration prior to being sent to the top of
the reactor. The catalyst is recirculated from the reactor to the regeneration section on
a 3060-min cycle. The reactor and regeneration sections are totally independent of
each other. The regeneration section can be stopped, even for several days, without
interrupting the dehydrogenation process in the reactor section. The vaporized
isobutane is fed along with fresh catalyst to the first, called reactor, and the spent
catalyst is separated from the products and sent to the regenerator, where air (O 2) is
added to oxidize the carbon. The reactor cracks the isobutane and forms coke on the
catalyst. Then in the regenerator the coke is burned off and the catalyst is sent back
into the reactor. The magic of this process is that the reactor-regenerator combination
solves both the heat management and coking problems simultaneously. Burning off the
coke is strongly exothermic, and this reaction in the regenerator supplies the heat
(carried with the hot regenerated catalyst particles) for the endothermic cracking
reactions in the reactor.
The process operates under low pressure and has a low-pressure drop and
uniform temperature profile. Products that have been produced from this unit are

29

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

isobutene. Isobutene available in the C4 stream from the Snamprogetti-Yarsintez FBD


unit will be combining with methanol, which is sourced from the Sabah Gas Industries
methanol plant in Labuan to produce, fuel-grade MTBE with a high-octane value in the
MTBE unit.
2.2.3

MTBE Unit

The MTBE unit includes two sections such as the main reaction section and the
finishing reaction. In the main reaction section, 98% conversions of isobutene occurs
mainly in the main reactor which are designed to provide the mechanical ands thermal
conditions required by the expanded catalyst bid technology.
Reactions occur in this unit are:

1.

iC4H8 (isobutene) + CH3OH (methanol)

2.

CH3OH + CH3OH

(CH3)2O + H2O (DME)

3.

iC4H8 + H2O

C4H10O (TBA)

C5H12O (MTBE)

The reactor is operated in an up-flow direction with an external liquid recycle to


remove the heat of reaction and to control the expansion of the catalyst bed. This
selective reaction of methanol with isobutene is conducted in liquid phase at moderate
temperature on an ion exchange resin type catalyst. The expansion of the catalyst bed
in the reactor is ensured by pump around circulation loop with a cooling water cooler to
control the reactor feed temperature to remove the heat of reaction. Resin traps on top
of each reactor to trap resin in case of carryover with the liquid. In the finishing reactor
section, isobutene final conversion is achieved in a catalytic column where reaction
and distillation are performed simultaneously.

2.2.4

Distillation Column Unit

30

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

This column includes a separation column yielding MTBE product at the bottom and
(isobutene, isobutene, normal butane, water and DME) with methanol entrained by
azeotropy at the top. The reaction section bed is contained in the upper part of this
column. An excess of methanol is maintained corresponding to the amount leaving the
tower in the azeotrope. The required methanol is passed through guard beds and
filtered prior to being charged to the catalytic column to achieve final conversion.
Bottom MTBE product and the other by-product such as TBA, DME is sent to rundown
tanks under level control after cooling in feed/bottom exchanger and trim cooler.
The overhead of the column is condensed in the air-cooled condenser under
pressure control. One part of the liquid is sent to the column as reflux and the other
part to the liquid-liquid extraction unit after cooling.
2.2.5

Liquid-Liquid Extraction Unit

In this unit methanol will extract from the isobutene, isobutene, normal butane to
produce C4 raffinate from the overhead of the column and at the bottom, methanol and
water are produced. C4 raffinate from this unit we decided to sell to the Korea.

CHAPTER 3

ECONOMIC SURVEY

31

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.1 MARKET SURVEY


3.1.1

World Market

The MTBE market has been in strong continuous growth since 1992. For instance, the
1998 world consumption was approximately 19.5 million tonnes, about double that of
1992, representing an annual growth rate of about 12%. Present trends indicate a mild
growth in 2000, up to 20 million tonnes, with US consumption slightly declining and
other parts of the world growing (EEA 2000). The MTBEs role in U.S. gasoline grew
rapidly through 1995 given away in figure 3.1.

Figure 3.1 MTBEs role in U.S. gasoline grew rapidly through 1995
(Sources: Local Issues, Global Implications)

3.2 ASIA MARKET

Most Asia countries such as South Korea, Japan, Hong Kong, Taiwan, China, Malaysia,
Singapore, Philippines and Thailand, have already phased lead out of their gasoline pool
and are replacing it with oxygenates such as MTBE. Due to MTBEs relative ease in
blending into gasoline, easy transportation and storage, as well as relatively cheap and
abundant supply, MTBE is the most widly use oxygenate in Asia.
However, the use of MTBE in gasoline blending is not mandatory for countries
like South Korea and Thailand. South Korea, for instance, requires a 1.3% - 2.3%
32

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

oxygenate content in gasoline during the winter, compared to a minimum of 0.5% for
the summer. In other Asian Countries, MTBE is mainly use as an octane booster to
replace lead. (source: features mtbe asias.html).

3.3 DEMAND
World demand of MTBE mod scenario is about 4.1 mil ton per annum consumption in
US West Coast at stake due to the legislation from 1998 to 2010. It has as an impact
on 80% of PETRONAS MTBE exports to the US. This mod scenario is representing in
figure 3.2.

Figure 3.2: World MTBE demand (1998-2010) mod scenario


(Sources: Petronass Library Kuala Lumpur City Center (KLCC)
U.S. demand is about 250,000b/d, dominates MTBE consumption. Most MTBE
is used to comply with mandated oxygen content rules for gasoline supplied to either
RFG or wintertime carbon monoxide areas. A small amount may be utilized for octane
enhancement.
In Europe, MTBE demand is estimated about 60,000 b/d. MTBE use in Europe
is essentially confined to Octane enhancement, and about 6,000 b/d is exported to the
United States. Eastern Europe currently consumed about 10,000 b/d of MTBE.

In Asia, demand for MTBE in this region is expected to grow at much more
rapid rate than elsewhere in the world. The rate will taper off late in decade from about
12% per year to about 8% by the turn of the century, since the early rapid growth has
33

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

been fed by the lead phase down which should be nearly complete by 2000. Throughout
the period, the region will be a net importer of MTBE, mostly obtained from the Middle
East. The trade balance of MTBE in Asia and Pacific is expected to be in table 3.1.
(Sources: MTBE annual Report)
Table 3.1 Trade Balance of MTBE in Asia and Pacific
(Sources: MTBE annual Report)

Capacities listed are the average available during the year. Details for 1995 and 1999
of MTBE Balance for Asia and Pacific are shown in table 3.2. These data are also
shown graphically in figure 3.3 which indicate for MTBE supply and demand Asia and
Pacific. (Sources: MTBE annual Report)

Table 3.2: MTBE Balance for Asia and Pacific


(Sources: MTBE annual Report)

34

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

MTBE supply and demand


Asia and Pacific

Figure 3.3: MTBE supply and demand Asia and Pacific


(Sources: MTBE annual Report)
Demand for MTBE expected to be marginally firmer in the near future as Asian
Countries such as Indonesia and India are working totally phase out lead from their
gasoline pool. Supply on other hand is expected to remain abundant, as Asia is able to
produce about 3 million Mt/yr of MTBE for its Captive consumption. In addition to this,
Asia attracts a regular supply of about 500,000 ton/yr of MTBE from Middle Eastern
and Europe sources.(Reference: features mtbe asias.html).

35

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.4 PRODUCTION CAPACITY

Commercial production of MTBE started in Europe in 1973 and in the US in 1979. Total
worldwide production capacity in 1998 was 23.5 million tones and the actual production
was 18 million tones
The annual production volume of MTBE in the year 2000 in the Europe was
2,844,000 tons. About 129,000 tonnes was imported and about 479 000 tonnes were
exported outside the Europe in the year 2000 ((Dewitt & Company Inc. 2002). The
majority of the exported volume (> 83%) was exported to USA and Canada. The
majority of exported volume (> 80%) was transported as non-blended MTBE and
minority as a component of petrol (blended). The annual consumption of MTBE within
the Europe was hence 2,495,000 tons in the year 2000 (see table below). For the future
no substantial increase in MTBE usage is expected. (Dewitt & Company Inc. 2002).
Table 3.3: Production, import, export and consumption in Europe in year 2000
(tonnes/year) souces: (Dewitt & Company Inc. 2002).
Production
2 844 000

Import into Europe


129 000

Export outside Europe


479 000

Consumption
2 495 000

The world's MTBE industry today is operating at about 80% of capacity. The US
is by far the largest market, having about 43% of the production capacity but
consuming 63% of total global output. On stability, the Middle East is the swing
producer, exporting more than 50,000 bbl/day to the US and elsewhere.

3.5

SUPPLY

DeWitts Company estimates for local production of MTBE a summarized in table 3.4.
Most of plants unit are refinery-based units taking isobutylene from FCCU units, or as
Raffinate I from olefins plants. Since olefin plants in the region a mostly naphthabased, they produce significant quantities of C4 olefins for this purpose. There is one
butane-based plant in Malaysia. Table 3.4 also shown for MTBE plants suppliers to
Asia and Pacific.

36

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Table 3.4 Suppliers MTBE plant in Asia and Pacific


(Sources: MTBE annual Report)

3.6 MARKET PRICE


3.6.1

Methanol

Price of methanol, as feedstock in Asia is $240 - $280 /ton. While in Europe, the prices
is $265 - $270 / ton free on board (fob) Rotterdam. In U.S. the price of methanol is 76
cts 77cts/ gal in fob.
Global Methanol demand is expected to increase to 3.5 % per year over the
next 5 years, compared to 1.0% - 1.5% growth in 2002 and 2003. Those lower growth
rates are attributable to the phase-out of Methyl tert-butyl ether (MTBE) as oxygenate
in gasoline in California, and slower economic growth in China caused by SARS.
Methanol growth in China is forecast at 7% - 8.5% per year, fueled by formaldehyde
and acetic acid demand. (Chemicals Week)

3.6.2

Isobutane

Standard price for isobutene is stated by followed:

37

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Table 3.5 : Standard price for isobutane


Grade

Purity

Grade 4.0

99.99%

Grade 3.0

99.9%

Instrument

99.5%

3.6.3

Cylinder Size
LP30
LP15
LP05
LP01
1/2 Ton
LP30
LP15
LP05
LP01
1 Ton
LP30
LP15
LP05
LP01

Volume
lbs
117
60
23
6
490
117
60
23
6
490
117
60
23
6

Price per Cylinder


RM900.00
RM600.00
RM370.00
RM200.00
RM1225.00
RM380.00
RM240.00
RM170.00
RM100.00
RM890.00
RM293.00
RM185.00
RM100.00
RM75.00

Catalyst

Price of Chromia catalyst Compound USD60 000/Rottedam (Rdam) from the existing
plant. (En Mohd. Napis, from MTBE plant, Gebeng )
3.6.4

Conclusion

Our company will import the methanol and isobutane as feedstock, from Petronas
Malaysia and United State (US) respectively. Methanol feedstock will be supplied from
Gurun, Kedah production capacity of 66,000 ton/year. For the second feedstock,
isobutane (instrument grade) will be supplied by Chevron Phillips Chemical Company
LP, 10001 Six Pines Drive, The Woodlands, Texas, US by shipping method.
MTBE is suitable as a gasoline additive which simultaneously increases the
octane rating of the fuel and adds oxygen which promotes cleaner burning. When used
in place of lead-based octane enhancers, dual environmental benefits are realized, a
reduction in atmospheric lead concentrations and reduced emissions of carbon
monoxide and other smog forming chemicals. Since the 1970s, the worldwide

38

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

consumption of MTBE has increased significantly and many new facilities have been
constructed to support the growing market (Kirschner, 1996; Riddle, 1996).
MTBE production will increase in future in Asia, Asia Pacific, Middle East and
Europe even though MTBE is banned in California but not in the entire nation of the
United States.

3.7

ECONOMIC ANALYSIS

An economic analysis used to smooth the progress of based on existing plant. This
analysis is important to ensure that the chemical plants converge and the economics is
satisfactory before the plant operate. All the data taken from MTBE Annual 1994,
DeWitt & Company

Incorporated, 16800 Greenpoint Park, Suite 120 N, Houston,

Texas, that given by Petronas Library, KLCC.


3.7.1

Break-Even Analysis

When chemical engineers determine outlay for any type commercial process, they
want these costs to be enough accuracy to provide reliable decision. To accomplish
this, they must have a complete understanding of the many factors that can affect
costs. Break-even analysis is important to ensure that the plant can give profit before
the plant can run.
The objective of break even analysis is to find the point, in dollars or in ringgits
and units, at which costs equal revenues. This point is the break even point. Break
even analysis requires an estimation of fixed costs, variable costs and revenue.
Fixed costs are costs that continue even if no units are produced. Examples
include depreciation, taxes, debt, and mortgage payments. Variable costs are those
that vary with the volume units produced. The major components of variable costs are
labor and materials. However, others cost, such as the portion of the utilities that varies
with volume, are also variable cost. The different between selling price and variable
cost is contribution. Only when total contribution exceeds total fixed cost will there be
profit.

39

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Another element in break-even analysis is the revenue function. From the


graph, revenue begins at the origin and proceeds upward to the right, increasing by
selling price of each unit. Where the revenue function crosses the total cost line (the
sum of fixed and variable costs), is the break even point, with a profit corridor to the
right and a loss corridors to the left.
Table 3.6: Cost of producing MTBE 500,000 ton/year
(Sources: DeWitt & Company Incorporated, Annual Report)

Table 3.6 showed that the cost of production of MTBE based on existing plant
producing 500,000 ton/year. From table 3.6, given data, break-even analysis can be
calculated to know the break-even point figure. Figure below indicate that break-even
chart, where it has been calculated by using excel that shown in table 3.8 and based
on the data given from table 3.6.

40

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Figure 3.4 : Break even analysis chart calculated by using excel.


From the break even chart figure above, the value of break-even point at the
existing capacity of 500,000 ton/year is 185,629.85 tons in units and RM
244,679,817.14 in Ringgit Malaysia (RM). This value indicates the minimum units and
values needed to be sold. The given capacity of 500,000 tons/year can give profit to
the company. The margin of safety (MOS) calculated from the graph, which is
314,370.15 tons and RM414,373,182.86. Margin of safety (MOS) in percentage of
sales is 62.87%. The sale is allowed to drop about 62.87% before the company will
incurred a loss.
In other word, at selling 300,000 tons/year capacity will also give profit to our
company. The margin of safety from the graph for 300,000 ton/year calculated is
114,370.15 tons and RM150,751,982.86. The margin of safety (MOS) as percentage of
sales is 38.12%. The sale is allowed to drop about 38.12% before the company will
incurred a loss. All the data calculation is shown in the next section.

41

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.7.2

Data Calculation

All the data based on 500,000 tons/year producing MTBE from existing plant.
Table 3.7 Values in USD converted to RM
(Sources: Data collected from table 3.6)
Total revenue, TR
Total variable cost, TVC
Total fixed cost, TFC

RM 659,053,000.00
RM 504,754,000.00
RM 57,285,000.00

Total Revenue (TR), MTBE (500,000 ton),


TR

= Quantity of MTBE X Price of MTBE


= QMTBE X PMTBE
= 500,000 tons X USD346.87 X 3.8
= RM 659,053,000

Total cost
TC

= total fixed cost + total variable cost


= TFC + TVC

Where,
Total fixed cost

= 500,000 ton X USD30.13 X 3.8


= RM 57,285,000.00

Total variable cost

= 500,000 ton X USD (226.4 + 39.26) X 3.8


= RM 504,754,000.00

Total cost, TC

= RM57,285,000.00 + RM 504,754,000.00
= RM 562,039,000.00

Tables 3.7 represent cost per unit ton converted into Ringgit Malaysia (RM), taking
datas directly from the table 3.6.
Table 3.8 Values in USD converted to RM per ton
(Sources: Data collected from table 3.6)
Revenue (RM) per ton
RM1,318.00
Variable cost (RM) per ton
RM 1,009.51
Fixed cost (RM) per ton
RM114.57
Break-even point in ton can be calculated based on formula equation, which given by
follow:

42

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Break-even point, BEP (tons)

= Total Fixed cost


Contribution/ton

where,
Contribution/ton

= revenue / ton - variable cost / ton

BEP (tons) =

______RM 57,285,000.00_____
(RM1, 318.00 - RM 1,009.51)

185,629.85 tons (the minimum capacity)

Next, Break-even point in RM can be calculated based on formula equation, which


given by follow:
BEP (RM)

Break-even point, BEP (tons) X revenue / ton

185,629.85 tons X RM1, 318.00

RM 244,679,817.14

Beside that, margin of safety and percentage of sale can be calculated as follows:
For 500,000 ton/year production,
Margin of safety (MOS) in units = Budgeted sale (units) - BEP (units)
= 500,000 tons - 185,629.85 tons
= 314,370.15 tons
Margin of safety (MOS) in RM = Budgeted sale (RM) - BEP (RM)
= RM 659,053,000.00 - RM 244,679,817.14
= RM 414,373,182.86
Margin of safety (MOS) as percentage of sales = MOS (RM) x 100%
Sales(RM)
= RM 414,373,182.86 x 100%
RM 659,053,000
= 62.87%

43

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

For 300,000 ton/year production,


Margin of safety (MOS) in units = Budgeted sale (units) - BEP (units)
= 300,000 tons - 185,629.85 tons
=

114,370.15 tons

Margin of safety (MOS) in RM = Budgeted sale (RM) - BEP (RM)


= RM 395,431,800 - RM 244,679,817.14
= RM 150,751,982.86
Margin of safety (MOS) as percentage of sales = MOS (RM) x 100%
Sales(RM)
= RM150,751,982.86 x 100%
RM 395,431,800
= 38.12%
Table 3.9 shown that the calculation of break-even point by using excel.

Table 3.9: Data calculation by using excel in RM


(Sources: Data taking from table 3.7)

44

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

CAPACITY

TFC1

57,285,000.00

10000

57,285,000.00

20000

TVC1
0

TR1

TC1

57,285,000.00

10,095,080.00

13,181,060

67,380,080.00

57,285,000.00

20,190,160.00

26,362,120

77,475,160.00

40000

57,285,000.00

40,380,320.00

52,724,240

97,665,320.00

60000

57,285,000.00

60,570,480.00

79,086,360

117,855,480.00

80000

57,285,000.00

80,760,640.00

105,448,480

138,045,640.00

100000

57,285,000.00

100,950,800.00

131,810,600

158,235,800.00

120000

57,285,000.00

121,140,960.00

158,172,720

178,425,960.00

140000

57,285,000.00

141,331,120.00

184,534,840

198,616,120.00

160000

57,285,000.00

161,521,280.00

210,896,960

218,806,280.00

180000

57,285,000.00

181,711,440.00

237,259,080

238,996,440.00

200000

57,285,000.00

201,901,600.00

263,621,200

259,186,600.00

220000

57,285,000.00

222,091,760.00

289,983,320

279,376,760.00

240000

57,285,000.00

242,281,920.00

316,345,440

299,566,920.00

260000

57,285,000.00

262,472,080.00

342,707,560

319,757,080.00

280000

57,285,000.00

282,662,240.00

369,069,680

339,947,240.00

300000

57,285,000.00

302,852,400.00

395,431,800

360,137,400.00

320000

57,285,000.00

323,042,560.00

421,793,920

380,327,560.00

340000

57,285,000.00

343,232,720.00

448,156,040

400,517,720.00

360000

57,285,000.00

363,422,880.00

474,518,160

420,707,880.00

380000

57,285,000.00

383,613,040.00

500,880,280

440,898,040.00

400000

57,285,000.00

403,803,200.00

527,242,400

461,088,200.00

420000

57,285,000.00

423,993,360.00

553,604,520

481,278,360.00

440000

57,285,000.00

444,183,520.00

579,966,640

501,468,520.00

460000

57,285,000.00

464,373,680.00

606,328,760

521,658,680.00

480000

57,285,000.00

484,563,840.00

632,690,880

541,848,840.00

500000

57,285,000.00

504,754,000.00

659,053,000

562,039,000.00

CHAPTER 4

45

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

PLANT LOCATIONS AND SITE SELECTION

4.1

PLANT LOCATION

The location of the plant can have a crucial effect on the profitability of a project and the
scope for future expansion. Many factors must be considered when selecting a suitable
site. A good location is required to optimise the production of the plant. It is important to
know that, not all Malaysian industrial park caters the need of a chemical plant. Also not
all industrial park allows the building of chemical plants. Our industrial parks are divided
into categories such as: 1. Light industrial
2. Medium industrial
3. Heavy industrial
4. General industrial
5. Hi-tech industrial

4.2

GENERAL CONSIDERATION ON THE SITE SELECTION

All the information about plant locations are based on the data gathered from the
Malaysian Industrial Development Authority (MIDA). And we refer detail information on
important factors that need to be considered in the site selection. In the process of
selecting the location, we did some evaluation. Among the principle factors considered
are:

4.2.1

Location With Respect To Marketing Area

For materil that are produced in bulk quantities, such as cement, fertilizer, raw material
of petrochemical product, where the cost of product per tone is relatively low and the
cost of transport a significant fraction of the sales price, the plant must located close to
the primary market. This consideration will be less important for low volume production,
high priced products; such as pharmaceuticals, plastisizer and etc. in an international

46

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

market, there may be an advantage to be gained by locating the plant within an area
with preferential tariff agreement.
4.2.2

Raw Material Supply

The availability and price of suitable raw materials will often determine the site location.
Plant producing bulk chemicals are best located close to the source of the major raw
material, where this is also close to the marketing area.
4.2.3

Transport Facilities

The transport of materials and products to and from the plant will be an overriding
consideration in site selection. If practicable, a site that we are consider that close to at
least two major forms of transport: road, rail, waterway or a sea port. Road transport
being increasing used, and is suitable for local distribution from central warehouse. Rail
transport will be cheaper for the long distance transport of bulk chemicals
.

Air transport is convenient and efficient for the movement of personnel and

essential equipment and supplies and the proximity of the site to a major airport also
considered.
4.2.4

Availability of Labour

Labour that will be needed for construction of the plant and its operation. Skilled
construction workers will usually be brought in from outside the site area, but there
should be an adequate pool of unskilled labour available locally and labour suitable for
training to operate the plant. Skill tradesman will be needed for plant maintenance.
Local trade union customs and restrictive practices will have to be considered when
assessing the availability and suitability of the local labour for requirement and training
.
4.2.5

Availability of Utilities

47

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Chemical processes invariably require large quantities of water for cooling and general
process used and the plant must be located near a source of water of suitable quality.
Process water may be drawn from a river, wells or purchased from a local authority.
At some site, the cooling water required can be taken from a river or lake or
from the sea; at other locations cooling towers will be needed.
Electrical power will be needed at all sites. Electrochemical processes that
required large quantities of power: for example, aluminium smelters need to be located
close to a cheap source of power. A competitively priced fuel must be available onsite
for steam and power generation.
4.2.6

Environmental Impact and Effluent Disposal

All industrial processes produce waste products and full consideration must be given to
the difficulties and cost of their disposal. The disposal of toxic and harmful effluents will
be covered by local regulations and the appropriate authorities must be consulted
during the initial site survey to determine the standards that must be met.
An environmental impact assessment should be made for each new project or
major modification of addition to an existing process.
4.2.7

Local Community Considerations

The proposed plant must fit in with and be acceptable to the local community. Full
consideration must be given to the safe location of the plant so that it does not impose
a significant additional risk to the community.
On a new side, the local community must be able to provide adequate facilities
for the plant personnel: schools, banks, housing and recreational and cultural facilities.
4.2.8

Land (site consideration)

48

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Sufficient suitable land must be available for the proposed plant for future expansion.
The land should ideally be flat, well drained suitable load-bearing characteristics. A full
site evaluation should be made to determine the need for piling or other special
foundations.
4.2.9

Political and Strategic Considerations

Capital grants, tax concessions and other inducements are often given by government
to direct new investment to preferred locations such as areas of high unemployment.
The availability of such grants can be the overriding factor in site selection.

4.3 OVERVIEW ON PROSPECTIVE LOCATIONS


Our process is a petrochemical base process; therefore we choose to locate our plant in a
petrochemical complex. The reason is quite simple; a petrochemical complex could
simplify the formation and the maintenance of a chemical plant. It could also cut the daily
operation cost and saving us the hassle of transportation.
In Malaysia there are only three such places, known as the Integrated
Petrochemical Complexes. These complexes are situated in each of the site below:
1. Telok Kalong Industrial Park.
2. Tanjung Langsat Industrial Park.
3. Bintulu Industrial Park.
Other than the above factors, the capacity of plant was also taken into consideration in
determining the suitability of site. Plant capacity will determine how big the space required
to build the plant and the storage area and also the mode of transportation to be use.
The manufacture of MTBE is classified as a petrochemical project. Several
locations of industrial area particular at Teluk Kalong Industrial Area in Terengganu,
Tanjung Langsat Industrial Area in Johor and Bintulu Industrial Area, Sarawak that we are
refer for location.

49

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.3.1

Teluk Kalong

Teluk Kalong Industrial Estate located 9.6 km from Kemaman. Total area available
167.46 hectares. The price of land in ranges RM 0.46 to RM 4.18 per Feet Square.
This area is proposed for petrochemical and heavy industry petrochemical.
The Electricity is generated at the following station. Total generation capacity is
900 MW. Local consumption is less than 1/3. No major breakdown, low frequency of
interruption. Water most plentiful with surplus capacity. Water supply capacity at
various treatment plants total 331000-meter cube per day, with planned upgrading for
additional requirement. Kenyir Lake with 39000 hectares of water with 134 metre
average depth, make Terengganu a potential export of water middle East. Water
supply is in Bukit Shah. Water tariffs (industrial) are RM1.15 metre cube. The raw
materials supplier of isobutene is availability from Chevron Philips Chemical Company
LP, United State and methanol is availability from Petronas Malaysia, Labuan.
1.

Airport facilities
Terengganu major industrial locations are serve by 3 airports
- Kuantan
- Kerteh
- Kuala Teregganu

2.

4.3.2

Kuala Teregganu
Port Facilities
Kemaman Port, Kerteh Port and Kuantan Port
Tanjung Langsat Industrial Park

Tanjung Langsat is designed as hub for heavy/medium industries with all the
necessary infrastructure and service facilities. 91.43 km distance from Johor Baharu.
The infrastructure works such as the Pasir Gudang Segamat Highway. Sungai
Johore Bridge and dedicated Port in Tanjung Langsat. Tanjung Langsat Industrial
Complex is a sprawling area just a stones through from Pasir Gudang Industrial Area.
A total hectare still available is 1,085.95. Selling price is RM8 to RM22 square feet. In
term of seaport two seaports are currently being constructed at Tanjung Pelepas,

50

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

located 40 km west of Johore Baharu city and Tanjung Langsat located 10 km east of
the Johore Port. Tenaga Nasianal Berhad (TNB) provides electricity.
Two airports in the 50km radius. There is the Sultan Ismail International Airport
(common known locally as Senai Airport) in Johore Baharu and the Changi
International Airport in Singapore. The Sultan Ismail International Airport, which is
located about 30km to the north west of JB city, is currently being expended and
upgrades to become the regional airport for southern peninsular Malaysia.
4.3.3

Bintulu

The distance from nearest town is 224.29 km from Sibu. Type of industries is light and
medium petrochemical. Area available is 77 hectares. Selling price RM2.5 to RM10 per
feet square. Electricity supplies by Sarawak Electricity Supply Cooperation (SESCO).

Airport facilities - Bintulu Airport

Port Facilities - Bintulu Port

51

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Table 4.1 The Comparison of The Potential Site Location:


Teluk Kalong
Industrial Park

Tanjung Langsat
Industrial Park

Bintulu Industrial
Park

9.6 km from Kemaman

91.43 km from Johor


Baharu

224.29 km from Sibu

Types of
Industry

Isobutane from US and


methanol from Labuan
Petrochemical and heavy
industry

Isobutane from US and


methanol from Labuan
Petrochemical light and
medium

Isobutane from US and


methanol from Labuan
Petrochemical light and
medium

Area Available

167.46 hectares

1085.98 hectares

77 hectares

RM 0.46 - 4.18

RM 8.00 - 22.00

RM 2.50 - 10.00

Electricity
Supply

Tenaga National Berhad

Tenaga National Berhad

Sarawak Electrycity
Supply Cooperation
(SESCO)

Water Supply

Bukit Shah Water


Treatment

Road Facilities

Kuala TerengganuKuantan-Kuala LumpurKuala Terengganu-KertehTeluk Kalong-KuantanKuala Lumpur

Distance from
the nearest town
Raw Material

Land Price
2

(RM/ft )

Airport Facilities
Port Facilities
Water Tariffs
3

(RM/m )

Kuala Terengganu Airport


Kerteh Airport
Kemaman Port,
Kerteh Port
Kuantan Port
RM 1.15

Syarikat Air Johor and


Logi Air Sg. Layang

Syarikat Air Sarawak

North-South Highway
from Bukit Kayu Hitam to
Singapore-

Major Road : Bintulu Sibu and Bintulu - Miri

Senai International
Airport

Bintulu Airport

Pasir Gudang Port

Bintulu Port

RM 1.68 (0-20 m 3)
RM2.24 (more than
20 m 3)

RM 0.95 (0 -25 m 3)
RM1.20 (more than
25 m 3)

(Source: MIDA)

A few proposed plant sites were narrowed down based on the above factors (table 4.2).
Table 4.2 is a summary of location and factors being considered. After detailed study of

52

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

the factors, each was given weightage and was estimated. The result tabulated in table
4.2 for the purpose of comparison.

Table 4.2 The Comparison of Location in term of Weightage Study

Weightage

Telok Kalong
Industrial
Area

Tanjung
Langsat
Industrial
Area

Bintulu
Industrial Area

Marketing Area

10

Raw Material

10

Transport

10

Availabillity of
Labour

10

Utilities

10

Total Land
Available

10

Climate

10

Price of Land

10

Local
Community
Consideration

10

Incentives

10

TOTAL

100

80

79

77

0 to 10 with 10 is the best

Table 4.3 The Electricity Tariffs (Industrial Tariff) for Peninsular Malaysia and Sarawak

53

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Tariff
Peninsular
Malaysia

Tariff D (Low Voltage, and less than 6.6


supply) for all consumptions

Cost per kWh


kV

Tariff E1 (Medium Voltage General, 6.6 kV - 66 kV


supply) for all consumptions. For each kW of maximum
demand per month: RM 17.30

25.8
19.8.

Tariff E2 (Medium Voltage Peak/Off-Peak, 6.6 kV 66kV supply)


Peak period (0800-2200 hours),

20.8

Off-Peak period (2200-0800 hours).

12.8

For each kW of maximum demand per month during


peak period: RM21.70
Tariff E3 (High Voltage Peak/Off-Peak, more than 132
kV supply)
Peak period (0800 -2200 hours),
Off-Peak period (2200 - 0800) hours).
For each kW of maximum demand per month during
peak period: RM 20.80

Sarawak

Tariff 11
1st 100kWh
In excess of 100kWh to 3000 kWh
In excess of 3000 kWh
Minimum charge per month: RM 10.00
Tariff 12
All units

17.8
10.8

40
30
21

17

For each kW of maximum demand per month: RM12.00


Minimum charge : RM 12.00 per kW x billing demand
Tariff 13 (Peak/Off-Peak)
Peak period ( 0700 - 2400 hours)
Off-Peak period ( 0000 - 0700 hours)
For each kW of maximum demand per month during
peak period: RM20.00
Minimum charge: RM 20.00 per kW x billing demand.

17
10

(Source: MIDA)

54

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.4

CONCLUSION

Based on the factor weightage studied, it can be concluded that Telok Kalong Industrial
Estate is the most suitable and practical location to choose as a site for MTBE plant.
The philosophy of in situ consumption of much of the production MTBE,
together with remaining product aimed directly at the export market and also makes the
need for port facilities of paramount importance. The Tanjung Langsat and Bintulu
Industrial Area are not impressive for MTBE plant. There are many other reasons
influences our decision including:

Nearest of the Kuantan Port, Kemaman Port and Kerteh Port facilities is more

convenient and economically for export and import purposes.

Excellent and consistent support from bulky oil, gas and chemical supplier from

Kerteh.
Constantly upgrading existing and developing new infrastructure, facilities and supporting
industries. These include the construction of roads; to increase accessibility to and from
the estates are scheduled.

55

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

CHAPTER 5

ENVIRONMENTAL CONSIDERATION

5.1

INTRODUCTION

Nowadays, environmental issues become very important. Besides this, a good waste
treatment system is also important in order to reduce and minimize
environmental pollutants. The chemical waste in the form of solid, liquid and
gases must be treated before being discharged into sewage, drain and
atmospheres.
Any chemical plant to be set up in Malaysia must follow the rules and
regulations under the Department of Environment (DOE) Malaysia, which includes the
Environmental Quality Act 1974. Under Environmental Quality Act (Sewage and
Industrial Effluents) Regulation 1979 and Environment Quality Act (Clean Air) 1978.
The plant owner or waste generator must ensure that waste generated disposed
appropriately to prevent environmental pollution. The proper and suitable methods
should be implemented in dealing with the waste disposal. Kualiti Alam Sdn. Bhd is
one of the licensed contractors specialized in the industrial waste disposal in Malaysia.
MTBE plant is not excluded from these regulations. As our plant produces
MTBE and other byproducts like raffinate but generally they are not hazardous to the
environment and human if safety measures are taken into consideration. These
environmental considerations depend on the location of our plant. The plant will follow
the Standard B of water quality measurement and also need some waste treatment
facilities to minimize the pollution from our plant.

56

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

STACK GASES
Gas Emission Treatment
Direct flame combustion was used to burn the excess gas. Flare is usually open ended
combustion unit. Therefore, the combustion process will be controlled by flow
rate of gases mixture to prevent incomplete combustion.
Another treatment is thermal combustion. It is an incinerator used in the cases
where the concentration of combustible gases is too low to make direct flame
incineration insufficient condition. The temperature of operation depends upon the type
of pollutant in waste gas. Thermal combustion must be carefully designed to provide
safe, efficient operation and to prevent incomplete combustion. Time, temperature, and
oxygen must be carefully monitored. (Howard et. al 1985)
Stack gas means the product of combustion process usually occur at machine or
generator. It is usually the fuels used occurred in the complete combustion
process, but it produced unwanted gas such as carbon monoxide, sulphur oxide
and other gases.
In our MTBE plant, the stack gases is only Hydrogen and it is stored in a
special tank before being sold to interested company at market price.

5.3
5.3.1

WASTEWATER TREATMENT
Wastewater Characteristics

Wastewater characteristics vary widely from industry to industry. Obviously, the


specific characteristics will affect the treatment techniques chosen for use in meeting
discharge requirements. Because of the large number of pollutant substances,
wastewater characteristics are not usually considered on a substance-by-substance
basis. Rather, substances of similar pollution effects are grouped together into classes
of pollutants or characteristics are indicated below.
5.3.1(a) Priority Pollutants

57

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Recently, greatest concern has been for this class of substances for the reasons given
previously. These materials are treated on an individual-substance basis for regulatory
control. Thus each industry could receive a discharge permit that lists an acceptable
level for each priority pollutant.
5.3.1(b) Organics
The organic composition of industrial wastes varies widely, primarily due to the
different raw materials used by each specific industry. These organics include proteins,
carbohydrates, fats and oils, petrochemicals, solvents, pharmaceutical, small and large
molecules, solids, and liquids. Another compilation is that a typical industry produces
many diverse waste streams. Good practice is to conduct a material balance
throughout an entire production facility. This survey should include a flow diagram,
location and sizes of piping, tanks, and flow volumes, as well as an analysis of each
stream.
An important measure of the waste organic strength is the 5-day biochemical
oxygen demand (BOD5). As this test measures the demand for oxygen in the water
environment caused by organics released by industry and municipalities, it has been
the primary parameter in determining the strength and effects of a pollutant. This test
determines the oxygen demand of a waste exposed to biological organisms (controlled
seed) for an incubation period of five days. Usually this demand is caused by
degradation of organics according to the following simplified equation, but reduced
inorganics in some industries may also cause demand (i.e., Fe2+, S2- and SO32-).
Organic waste + O2

CO2 +H2O

In general, low-molecular-weight water-soluble organics are biodegraded


readily. As organic complexity increases, solubility and biodegrability decrease. Soluble
organics are metabolized more easily than insoluble organics. Complex carbohydrates,
proteins and fats and oils must be hydrolyzed to simple sugars, aminos, and other
organics acids prior to metabolism. Petrochemicals, pulp and paper, slaughterhouse,

58

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

brewery, and numerous other industrial wastes containing complex organics have been
satisfactorily treated biologically, but proper testing and evaluation is necessary.
5.3.1(c) Inorganics
The inorganics is most industrial wastes are the direct result or inorganic compounds in
the carriage water. Soft-water sources will have lower inorganics than hard-water or
saltwater sources. However, some industrial wastewaters can contain significant
quantities of inorganics which result from chemical additions during plant operation.
Many food processing wastewaters are high in sodium.
While domestic wastewaters have a balance in organics and inorganics, many
process wastewaters from industry are deficient in specific inorganic compounds.
Biodegration of organic compounds requires adequate nitrogen, phosphorus, iron, and
trace salts. Ammonium salts or nitrate salts can provide the nitrogen, while phosphates
supply the phosphorus.
5.3.1(d) pH and Alkalinity
Wastewaters should have pH values between 6 and 9 for minimum impact on the
environment. Wastewaters with pH values less than 6 will tend to be corrosive as a
result of the excess hydrogen ions. On the other hand, raising the pH above 9 will
cause some of the metal ions to precipitate as carbonates or as hydroxides at higher
pH levels. Alkalinity is important in keeping Ph values at the right levels. Bicarbonate
alkalinity is the primary buffer in wastewaters. It is important to have adequate alkalinity
to neutralize the acid waste components as well as those formed by partial metabolism
or organics.
Many neutral organics such as carbohydrates, aldehydes, ketones, and
alcohols are biodegraded through organics acids which must be neutralized by the
available alkalinity. If alkalinity is inadequate, sodium carbonate is a better form to add
than lime. Lime tends to be hard to control accurately and results in high pH levels and
precipitation of the calcium which forms part of the alkalinity. In a few instances,
sodium bicarbonate may be the best source of alkalinity.

59

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

5.3.1(e) Temperature
Most industrial wastes tend to be on the warm side. For the most part, temperature is
not a critical issue below 37oC if wastewaters are to receive biological treatment. It is
possible to operate thermophilic biological wastewater-treatment systems up to 65oC
with acclimated microbes. Low-temperature operations in northern climates can result
in very low winter temperatures and slow reaction rates for both biological treatment
systems and chemical treatment systems.
Increased viscosity of wastewaters at low temperatures makes solid separation
more difficult. Increased viscosity of wastewaters at low temperatures makes solid
separation more difficult. Efforts are generally made to keep operating temperatures
between 10 and 30oC if possible.
5.3.2

Liquid Waste Treatment


5.3.2(a) Equalization Treatment

Liquid treatment generally is necessary in any plant. In our plant, we also have liquid
treatment but in general, we only state the general method, as our plant does not
produce any significant liquid waste. In any liquid waste treatment, we need
equalization treatment. The equalization treatment is an initial procedure in liquid waste
treatment. The purpose of equalization is to minimize and control the fluctuation in
liquid waste characteristic. Besides it provides the suitable and optimum condition for
biological and chemical treatment. It also provides adequate damping to minimize the
chemical consumption. The procedure will occur in the equalization tank. The size of
tank and time of equalization process depend on the liquid waste amount.
The Activated Sludge process will be used for this treatment. It is carried out in
Aerobic condition. The main purpose of activated sludge process is to remove soluble
and insoluble organic matter that converted into flocculants microbial suspension and
settable microbial. It also permits the use of gravitational solid liquid separation
technique for the above requirement.
The organic matter where measured in the form of BOD and COD serves as
food and energy source for microbial growth. It converts the pollutant into microbial cell

60

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

and oxidized end product such as CO2 and H2O by microbial activities. Therefore,
Submersible Aerator as mixing device will supply the oxygen and nutrient into aeration
tank and therefore improves the quality of the liquid. (Howard et. al, 1985)

5.3.2(b)

Solid Waste Treatment

The solid waste treatment will be minimized by regenerating the catalyst. Regeneration
processes depend on the characteristic of catalyst after whole reaction. Licensed
contractor will dispose the solid waste to follow the DOE regulation. By the way,
the scheduled maintenance activities will be implemented.
Dewatering system will be used to solidify and extract the catalyst. Therefore,
clarifier and filter press were used in these treatments. Clarifier is used to clarify any
impurities before going through the filters. The size of equipment depends on the flow
rate and holding time of these processes. Maintenance activities will be scheduled
based on the availability of workers and machines. Skilled and experienced workers
will do the maintenance activities, (Bailed, 1995).

61

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Industrial
Process

Waste
Reduction

Waste
Generation
Re-use

Storage
Transfer/
Transport

Processing/
Recovery

Collection

Disposal

Recycling/
Reuse

Figure 5.1 Functional Elements in a Solid-waste Treatment System.


62

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

5.3.3 Waste Minimization


Waste minimization means the optimization process to minimize the waste come out of
the plant. It will be done by source reduction and recovery of the sources. The source
reduction refers to preventative measured taken to reduce the amount of waste, which
produced in this process. Recovery of the sources is aimed to reuse the excess
methanol to produce the MTBE.
Waste production from the plant could be reduced by implementing these
procedures:
-

Raw material modification,

Product reformulation,

Process modification,

Improvement in operating practices.

The most important is by improving the product yield and this means
minimization of waste generation. It will be accomplished through improvement in
catalyst efficiency and proper maintenance activities.

63

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

CHAPTER 6

SAFETY CONSIDERATION

6.1

INTRODUCTION

For years, those employed in the chemical industry have known that the safe operation of
chemical plant is essential to the industrys continued ability to survive. The human,
political and financial costs of having accidents are just too high for the chemical
industry to not exhibit excellence in their efforts to operate plants in safe and
environmentally responsible ways. The chemical industry has an outstanding record in
both transportation safety and the safe operations of its processes. That effort has
resulted in a dramatic and steady decline in releases and waste produced at chemical
sites.

Actions that should be taken to avoid serious chemical plant accidents are as follows:
1. In most cases involving large volumes of highly hazardous chemicals, excess
flow valves are in place that would stop a rapid flow of the chemicals
2. When highly hazardous chemicals are involved, processes have fixed
protection, as well as trained emergency response teams that could handle the
incident.
3.

Appropriate reaction control or inhibiting systems are in place to interrupt


runaway reactions if cooling, heating and pressure relief are not considered
adequate.

4. Control systems are designed to detect heat or pressure of a chemical reaction


and to control that reaction.
5. Work more closely with local and state law enforcement groups.

64

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

6.2

MATERIAL SAFETY DATA SHEET

6.2.1

Isobutane (Instrument Grade)

Product Number(S): 0001020533, 0001020534, 0001020535, 0001020536


Synonyms: Methylpropane; Iso
Company Identification:
Chevron Phillips Chemical Company Lp
10001 Six Pines Drive
The Woodlands, Tx 77380
6.2.1.1 Product Information:
Msds Requests: (800) 852-5530
Technical Information: (800) 852-5531
Colorless liquefied gas, odorless.
- Flammable gas. May cause flash fire
- Contents under pressure
- Detection of leak via sense of smell may not be possible if odorant has degraded
- Contact with liquefied gas can cause frostbite
- Liquid can cause eye and skin injury
- Reduces oxygen available for breathing
6.2.1.2 Physical And Chemical Properties
Appearance and odor: colorless liquefied gas, odorless.
Ph: na
Vapor pressure: 72 psia @ 37.8 c
Vapor density (air=1): 2.1
Boiling point: -12c (10.4f)
Solubility: negligible
Percent volatile: 100 % volume
Specific gravity: 0.564 @ 15.6 c
Evaporation rate: >1

65

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

6.2.1.3 Immediate Health Effects:


Eye: Because the liquid product evaporates quickly, it can have a severe chilling effect
on eyes and can cause local freezing of tissues (frostbite). Symptoms may include
pain, tearing, reddening, swelling and impaired vision.
Skin: Because the liquid product evaporates quickly, it can have a severe chilling
effect on skin and can cause local freezing of tissues (frostbite). Symptoms may
include pain, itching, discoloration, swelling, and blistering. Not expected to be harmful
to internal organs if absorbed through the skin.
Ingestion: Material is a gas and cannot usually be swallowed.
Inhalation: This material can act as a simple asphyxiant by displacement of air.
Symptoms of asphyxiation may include rapid breathing, in coordination, rapid fatigue,
excessive salivation, disorientation, headache, nausea, and vomiting.
Convulsions, loss of consciousness, coma, and/or death may occur if exposure to high
concentrations continues.
6.2.1.4 First Aid Measures
Eye: Flush eyes with water immediately while holding the eyelids open. Remove
contact lenses, if worn, after initial flushing, and continue flushing for at least 15
minutes. Get immediate medical attention.
Skin: Skin contact with the liquid may result in frostbite and burns. Soak contact area
in tepid water to alleviate the immediate effects and get medical attention.
Ingestion: No specific first aid measures are required because this material is a gas
and cannot usually be swallowed.
Inhalation: For emergencies, wear a niosh approved air-supplying respirator. Move
the exposed person to fresh air. If not breathing, give artificial respiration. If breathing is
difficult, give oxygen. Get immediate medical attention.
6.2.2

N-Butane

N-Butane synonym with I-Butane, Butane, and Normal Butane is a flammable gas. NButane is heavier than air and may travel considerable distance to an ignition source.

66

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

N-Butane is listed under the accident prevention provisions of section 112(r) of the
Clean Air Act (CAA) with threshold quantity (TQ) of 10000 pounds.

Physical and Chemical Properties


Parameter

value

Physical state

units

: Gas
o

Vapor pressure at 70 F

: 31

psia

Vapor density at STP

: 2.07

Evaporation point

: not available

Boiling point

: 31.1

Freezing point

: -0.5

pH

: not available

Solubility

: insoluble

Odor and appearance

: a colourless and odourless gas

Stability

: stable

Condition to avoid

: high temperature

6.2.2.1 Handling and storage


Protect cylinders from physical damage. Store in cool, dry, well- ventilated area away
from heavily trafficked areas and emergency exits. Do not allow the temperature where
cylinders are stored to exceed 130oF. Cylinders should be stored upright and firmly
secured to prevent falling or being knocked over. Full and empty cylinders should be
segregated. Use a first in first out inventory systems to prevent full cylinders from
being stored for excessive periods of time. Never carry a compressed gas cylinder or a
container of a gas in cryogenic liquid form in an enclosed space such as a car trunk,
van or station wagon. A leak cans re4sult in a fire, explosion, asphyxiation or a toxic
exposure.
6.2.3

Methanol

Methanol synonyms with Methyl alcohol and in chemical family alcohol with the
formula CH3OH. Methanol is a clear, colourless, mobile, volatile, flammable liquid and
its soluble in water, alcohol and ether.

67

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Physical and Chemical properties:


Parameter

value

Physical state

: liquid

Boiling Point

: 64.7oc

Vapor Pressure (20oc)

: 128 mb

Vapor Density (air=1)

: 1.11

Solubility in water ,%wt

: full

Specific Gravity

: 0.792 g/cm3

Appearance and odor

: liquid-colorless-odor specific

Fire and Explosion Hazard data:


Flash point

: closed cup: 12oc

Flammable limits, % vol

: Lel: 6, Uel : 36.5

Extinguishing media

: Foam CO2 halogenated agents

Special fire fighting

: Avoid contact with oxidizing materials

Unusual fire and explosion : Moderate


Reactivity Data:
Stability

: Medium

Conditions to avoid

: Oxidizing materials

Incompatibility

: Sulfo-chromic mixtures

Special Precautions
Precaution to be taken in handling and storing Methanol: store in iron or steel
containers or tanks. Small quantities can be stored in reinforced glass containers.
6.2.4

MTBE

6.2.4.1 Physical state, appearance


MTBE is chemically stable; it does not polymerize, nor will decompose under normal
conditions of temperature and pressure. Unlike most ether, MTBE does not tend to
form peroxides (auto-oxidize). The physical state of MTBE is that MTBE is in the form
of liquid at room temperature (25oC). It is a colourless liquid with the billing point at

68

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

55.2oC 131.4oF. The freezing point of MTBE is 108.6oC 163.5oC. The density of
MTBE at 25oC is 735g/cm3.
6.2.4.2 Physical dangers
MTBE is non-reactive. It does not react with air, water, or common materials of
construction. The reactivity of MTBE with oxidizing materials is probably low. However,
without definitive information, it should be assumed that MTBE reacts with strong
oxidizers, including peroxides.
6.2.4.3 Chemical dangers
MTBE is highly flammable and combustible when exposed to heat or flame or spark,
and it is a moderate fire risk. Vapours may form explosive mixtures with air. It is
unstable in acid solutions. Fire may produce irritating, corrosive or toxic gases. Runoff
from fire control may contain MTBE and its combustion products.
Occupational exposure limits (OELs)
Routes of Exposure
6.2.4.4 Inhalation risk
Like other ethers, inhalation of high levels of MTBE by animals or humans results in the
depression of the central nervous system. Symptoms observe red in rats exposed to
4000 or 8000 ppm in air included labored respiration, ataxia, decreased muscle tone,
abnormal gait, impaired treadmill performance, and decreased grip strength. These
symptoms were no longer evident 6 hours after exposure ceased. A lower level of
MTBE, 800ppm did not produce apparent effects (Daughtrey et al., 1997).
A number of investigations have been conducted to examine the self-reported
acute MTBE in gasoline vapors during use by consumers. This research includes both
epidemiological studies and studies involving controlled exposure of volunteers to
MTBE at concentrations similar to those encountered in refueling an automobile
(Reviewed in USEPA, 1997, and California EPA, 1998). In general, the studies
involving controlled human exposures in chambers to levels of MTBE similar to those
experienced during refueling and driving an automobile have not shown effects of

69

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

MTBE on physical symptoms (e.g. irritation), mood, or performance based tests of


neurobehavioral function.
6.2.5

TBA (TERT - BUTYL ACOHOL)

CAS Number: 75-65-0


Synonyms:

tert-Butanol
2-methyl-2-propanol
TBA
t-butylhydroxide
1,1-dimethylethanol
trimethylmethanol
trimethylcarbinol

6.2.5.1 Recognition
NIOSH/OSHA Health Guideline. Summarizes pertinent information about for workers
and employers as well as for physicians, industrial hygienists,and other occupational
safety and health professionals who may need such information to conduct effective
occupational safety and health programs.
6.2.5.2 Evaluation

1. Health Hazards. Routes of exposure, summary of toxicology, signs and


symptoms, emergency procedure.

2. Workplace Monitoring and Measurement.


3. Medical Surveillance. Workers who may be exposed to chemical hazards
should be monitored in a systematic program of medical surveillance that is
intended to prevent occupational injury and disease. The program should
include education of employers and workers about work-related hazards,
placement of workers in jobs that do not jeopardize their safety or health, early
detection of adverse health effects, and referral of workers for diagnosis and
treatment.

70

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

6.2.5.3 Controls

1. Exposure Sources and Control Methods.


2. Personal Hygiene Procedures.
3. Respiratory Protection. Conditions for respirator use, respiratory protection
program.

4. Personal Protective Equipment. Protective clothing should be worn to prevent


any possibility of skin contact. Chemical protective clothing should be selected
on the basis of available performance data, manufacturers' recommendations,
and evaluation of the clothing under actual conditions of use.

5. Emergency Medical Procedures. Material Safety Data Sheets (MSDS's) include


chemical specific information on emergency medical and first aid procedures as
referenced under the OSHA Hazard Communication standard, 29 CFR
1910.1200, (g)(2)(X). This standard requires chemical manufacturers and
importers to obtain or develop an MSDS for each hazardous chemical they
produce or import. Employers shall have an MSDS in the workplace for each
hazardous chemical, which they use.

6. Storage.
7. Spills and Leaks. In the event of a spill or leak, persons not wearing protective
equipment and clothing should be restricted from contaminated areas until
cleanup has been completed.

6.3

HAZARD IDENTIFICATION & EMERGENCY SAFETY & HEALTH RISK


ASSESSMENT

Safety & Health Risks vary with the type of industry & the magnitude of the emergency.
The severity of the risk too will vary with especially where there are chemicals,
combustible gases, potential for fire & explosion etc. These hazards may not only pose
a danger to the health of working in a particular plant but also the adjacent community.
In the event of a major disaster property both within and outside the plant will be
damaged. The real and potential hazards at the work place must be identified and the
Safety & Health Risks that they pose assessed. This will require a close scrutiny of all

71

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

work place buildings, their design, electrical wiring, transport and storage facilities, the
work processes, workstation design, safe operating procedures, list of chemicals
substances used, their quantity, storage, daily transfer, safe usage and disposal.
MSDSs of the chemical too have to be studied as regards their toxicity, volatility, and
their potential for a fire and/or explosion and adverse health affects both short term and
long term.
The possible emergencies/disaster in a industry could be:

Fire/ explosion

Chemical spill

Radioactive material spill

Biological material spill

Personal injury
The best action plan is prevention from an emergency. This is where one has to

work closely with operation personnel to make sure that all operations are safe and
comply with OSH Legislations. All persons at work are aware of the safe procedure
and also follow those procedures. Unfortunately in the real world, mostly human
factors- accident & emergency do occur. This is why emergency response plans have
to be written up, communicated to all concerned and tested for effectiveness.
Depending on the gravity the workplace emergency can be categorized in to Level 1,
Level 2, or Lever 3 emergency.
Level 1 Emergency- the first responder without having to call the disaster
response team or outside help can effectively manage such incident. Examples; a
small fire easily smothered, chemical spill easily contained and cleaned, injury minor
and treated at site by rendering first aid.
Level 2 Emergency - an incident that requires technical assistance from the
disaster response team and may need outside help. Examples; fire that need technical
from trained personnel and specialized equipment spill that can only be properly
contained by specialized equipment.

72

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Level 3 Emergency- these are major disaster that are difficult to contain even
with trained personnel and outside help. Examples, spill that cannot be properly
contained or abated even by highly trained team and the use of sophisticated special
equipment. Fire involving toxic material that is too large to control and are to burn. This
may require the evacuation of civilians across jurisdictional boundaries

73

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

CHAPTER 7

MASS BALANCE

7.1

SNAMPROGETTI UNIT (REACTOR AND REGENERATOR)

Stream S5 = 164.74 kgmole/hr


0.393 C4H8
0.393 H2
0.212 iC4H10
0.002 nC4H10

100 kgmole/hr
0.996 iC4H10
0.004 nC4H10

S2
Given from
MSDS

Assume steady-state system,


Basis = 100 kgmole/hr of S2

74

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

The fraction at stream S2 acquired from isobutane instrument grade, MSDS.


Reaction occurred in the reactor,
iC4H10

C4H8

H2

Flowrate in kgmole/hr of iC4H10 in the feed stream of S2

= 0.996 (100)

= 99.6 kgmole/hr iC4H10


Balanced Based upon the stoichoimetric ratio with 65% conversion of iC4H10 to obtain
C4H8.
Since, 65% conversion in the reactor,
kgmole/hr of C4H8 obtained

= 0.65 (99.6)
= 64.74 kgmole/hr

35% of iC4H10 unreacted

= 99.6

64.74

= 34.86 kgmole/hr
Based upon stoichiometric ratio
(inert)

(unreacted)

n C4H10

+ iC4H10

0.4

C4H8

99.6

H2

64.74

(kgmole/hr)

iC4H10

64.74

+ n C4H10

34.86

0.4

(kgmole/hr)

Input
S2

Stream
Component

(inert)

MW

Molar flow

Output
S5

Mass flow kg/hr

Molar flow

Mass flow kg/hr

kg/kgmole

kgmole/hr

C4H8

56

kgmole/hr

64.74

3625.44

H2

64.74

129.4

iC4H10

58

99.6

5776.8

34.86

2021.88

n C4H10
Total

58

0.4

23.2
5800

0.4

23.4
5800

75

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

7.2

SEPARATOR

Stream S10 = 64.74 kgmole/hr


1 H2

Stream S9 = 164.74 kgmole/hr


0.393 C4H8
0.393 H2
0.212 iC4H10

Stream S11 = 100 kgmole/hr

0.002 nC4H10

0.6474 C4H8
0.3486 iC4H10
0.0040 nC4H10

Input
S9

Stream
Component

Output
S10

S11

MW

Molar flow

Mass flow

Molar flow

Mass flow

Molar flow

Mass flow

kg/kgmole

kgmole/hr

kg/hr

kgmole/hr

kg/hr

kgmole/hr

kg/hr

C4H8

56

64.74

3625.44

H2

64.74

129.4

64.74

129.4

iC4H10

58

99.6

5776.8

34.86

2021.88

n C4H10
Total

58

0.4

23.2
5800

129.4

0.4

23.4
5670.6

7.3

MIXER

S13 = 64.74kgmole/hr

S14 = 71.62 kgmole/hr

1 CH3OH

0.996 CH3OH
0.004 H2O

S27 = 0.406 kgmole/hr


0.3596 CH3OH
0.6404 H2O

76

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Input
Stream
Component

S13
MW

Molar flow

Output
S14

S27

Mass flow

Molar flow

Mass flow

Molar flow

Mass flow

kg/kgmole

kgmole/hr

kg/hr

kgmole/hr

kg/hr

kgmole/hr

kg/hr

CH3OH

32

71.214

2278.848

0.146

4.67

71.36

2283.52

H2O
Total

18

2278.848

0.26

4.68
9.356

0.26

4.685
2288.205

7.4

MTBE REACTOR
Assumption : 98% conversion of C4H8 (2% remains unconverted)
Reactions involve in the reactor,

1. C4H8

CH3OH

2. 2CH3OH
3. C4H8

C5H12O

C2H6O
H2O

H2O

C4H10O

Stream S11 = 100 kgmole/hr


0.6474 C4H8
0.3486 iC4H10
0.0040 nC4H10

R
e
ac
to
r

S15

kgmole/hr
C4H8
iC4H10
nC4H10

S14 = 71. 214 kgmole/hr


CH3OH

CH3OH

H2O

C5H12O
C4H10O
C2H6O
H2O

7.4.1

1st REACTION IN REACTOR


C4H8

CH3OH

C5H12O

77

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

kgmole/hr of C4H8 in the stream S11 = 100(0.6474)


=

64.74 kgmole/hr C4H8

Balance based upon stoichiometric ratio with 98% conversion.


CH3OH is classified an excess.
The unreacted of CH3OH (excess) = (71.36 - 64.74)
=

6.62 kgmole/hr

Since 98% conversion in the reactor,


kgmole/hr of C5H12O obtained = 0.98 (64.74)
= 63.44 kgmole/hr C5H12O obtained
From the stoichiometric ratio,
98%

C4H8
64.74

CH3OH

conv.

71.214

C5H12O +

C4H8

63.44

1.3

CH3OH
7.92

unconverted

kgmole/hr

kgmole/hr

64.74 kgmole/hr
1 C4H8
R
e
ac
to
r

kgmole/hr
C4H8
CH3OH
C5H12O

64.74 kgmole/hr
1 CH3OH

Component

MW

Input
Molar flow
Mass flow

Output
Molar flow
Mass flow

78

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

C4H8

(kg/kgmole)
56

(kgmole/hr)
64.74

(kg/hr)
3625.44

(kgmole/hr)
1.3

(kg/hr)
72.8

CH3OH

32

71.36

2283.52

7.92

253.44

C5H12O
Total

88

5908.96

63.44

5582.72
5908.96

7.4.2

2nd REACTION IN REACTOR

From 2nd reaction, stoichiometric ratio shown below:


Since the ratio between methanol and dimethylether is 2CH3OH : 1C2H6O ,
98% conversion methanol (CH3OH) into dimethylether (C2H6O) = 1.3 (0.98)
2
=

0.637 kgmole/hr

98%

2CH3OH

conv.

7.92

C2H6O +
3.88

H2O

2CH3OH

3.88

0.16
unconverted

kgmole/hr

7.92 kgmole/hr
1 CH3OH

kgmole/hr
R
e
ac
to
r

kgmole/hr
CH3OH
C2H6O
H2O

Input

Output

79

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Component

MW

Molar flow

Mass flow

Molar flow

Mol

Mass flow

kg/kgmole

kgmole/hr

(kg/hr)

(kgmole/hr)

Fraction

(kg/hr)

CH3OH

32

7.92

253.44

0.16

0.02

5.12

C2H6O

46

3.88

0.49

178.48

H2O

18

3.88

0.49

69.84

1.0

253.44

Total

7.4.3

253.44

3rd REACTION IN REACTOR

The 3rd reaction and its stoichiometric below,


From 1st reaction, kgmole/hr of C4H8 remain is 1.3 and 3.88 kgmole/hr of H2O is
obtained in 2nd reaction.
Since C4H8 is limiting reactant to react with H2O, only 1.3 kgmole/hr of H2O needed to
react with C4H8
H2O is classified an excess.
The unreacted of H2O (excess) = (4.14 - 1.3)
=
C4H8

1.3

H2O
4.14

2.84 kgmole/hr
C4H10O +
1.274

C4H8
0.026

H2O
2.866

unconverted

kgmole/hr

kgmole/hr

1.3 kgmole/hr
1

C4H8

80

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

R
e
ac
to
r

4.166 kgmole/hr
0.3058C4H8
0.3058C4H10O
0.688H2O

4.14 kgmole/hr
1 H2O

Input
Component

MW

Molar flow

Mass

Molar

Mass

Molar

Mass

kg/kgmole

kgmole/hr

flow

flow

flow

flow

flow

kgmole/hr
-

(kg/hr)
-

kgmole/hr
0.026

(kg/hr)
1.456

4.14

74.52

2.866

51.588

1.274

94.276

4.166

147.32

C4H8

56

1.3

(kg/hr)
72.8

H2O

18

C4H10O

74

Total

7.4.4

Output

1.3

72.8

4.14

74.52

OVERALL MASS BALANCE ON MTBE REACTOR

S11 = 100 kgmole/hr


0.6474 C4H8
0.3486 iC4H10
0.0040 nC4H10

81

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

R
e
ac
to
r

S15 = 100.676 kgmole/hr


0.0002 C4H8
0.3261 iC4H10
0.0037 nC4H10
0.0015CH3OH
0.5934 C5H12O

S14 = 71.36 kgmole/hr

0.0119 C4H10O

1 CH3OH

0.0363 C2H6O
0.0268 H2O

Input

Input

Output

S11

S14

S15

MW

Molar flow

Mass

Molar flow

Mass

Molar flow

Mass

(kg/kg

(kgmole/hr)

flow

(kgmole

flow

(kgmole/h

flow

C4H8

mole)
56

64.74

(kg/hr)
3625.44

/hr)
-

(kg/hr)
-

r)
0.026

(kg/hr)
1.456

iC4H10

58

34.86

2021.88

34.860

2021.88

n C4H10

58

0.4

23.2

0.4

23.2

CH3OH

32

71.36

2283.52

0.16

5.12

C5H12O

88

63.44

5582.72

C2H6O

46

3.88

178.48

C4H10O

74

1.274

94.276

H2O

18

0.26

2.866

51.588

106.906

7958.72

Component

Total

7.5

100

5670.52

71.62

4.68
2288.2

DISTILLATION COLUMN
Assume that 90% of methanol in bottom.

82

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

S17 = 40.321 kgmole/hr


0.0006 C4H8

S15 = 100.906 kgmole/hr


0.0002 C4H8

0.8646 iC4H10

0.3261 iC4H10

0.0099 nC4H10

0.0037 nC4H10

0.0037 CH3OH

0.0015 CH3OH

0.0249 H2O

0.5934 C5H12O

0.0962 C2H6O

0.0119 C4H10O

S16 = 66.585 kgmole/hr

0.0363 C2H6O

0.9528 C5H12O

0.0268 H2O

0.0191 C4H10O
0.0279 H2O
0.0002 CH3OH

S15
Component

MW
kg/kgmole

Molar

Mass

S16
Molar flow
Mass

S17
Molar flow
Mass

flow

flow

(kgmole/hr)

flow

(kgmole/hr)

flow

C4H8

56

kgmole/hr
0.026

(kg/hr)
1.456

(kg/hr)
-

0.026

(kg/hr)
1.456

iC4H10

58

34.86

2021.88

34.86

2021.88

n C4H10

58

0.4

23.2

0.4

23.2

CH3OH

32

0.16

5.12

0.011

0.352

0.003

4.768

C5H12O

88

63.44

5582.72

63.44

5582.72

C2H6O

46

3.88

178.48

3.88

178.48

C4H10O

74

1.274

94..276

1.274

94..276

H2O
Total

18

2.866
106.906

51.588
7958.72

1.860
66.585

33.48
5710.828

0.013
40.321

18.108
2247.892

7.6

LIQIUD LIQUID EXTRACTION

S 20 = 12.029 kgmole/hr
1 H2O

S 21 = 39.166 kgmole/hr
0.0007 C4H8
0.8901 iC4H10
0.0102 nC4H10
0.0991 C2H6O

83

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

S18 = 40.321 kgmole/hr

S23 = 13.184 kgmole/hr

0.0006 C4H8

0.0113 CH3OH

0.8646 iC4H10

0.9887 H2O

0.0099 nC4H10
0.0037 CH3OH

0.0962C2H6O
0.0249 H2O

Input

Output

S18

S20
Mass

MW

Molar flow

kg/kgmole

(kgmole/hr)

C4 H8

56

0.026

(kg/hr)
1.456

Component

flow

Molar flow
(kgmole/hr)

S21
Mass
flow

(kg/hr)
-

Molar flow
(kgmole/hr)

S23
Mass
flow

0.026

(kg/hr)
1.456

Mass

Molar flow

flow

(kgmole/hr)
-

(kg/hr)
-

iC4H10

58

34.86

2021.88

34.86

2021.88

n C4H10

58

0.4

23.2

0.4

23.2

CH3OH

32

0.149

4.768

0.149

4.768

C5H12O

88

C2H6O

46

3.88

178.48

3.88

178.48

C4H10O

74

H2O
Total

18

1.006
40.321

18.108
2247.892

12.029
12.029

216.522
216.522

39.166

2225.016

13.035
13.184

234.63
239.398

7.7

DISTILLATION COLUMN

S26 = 0.407 kgmole/hr


S24 = 13.185 kgmole/hr
0.0113 CH3OH
0.9887 H2O

0.146 CH3OH
0.260 H2O

84

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

S25 = 12.778 kgmole/hr


1 H2O

S24
Component

MW
kg/kgmole

Molar

Mass

S25
Molar flow
Mass

S26
Molar flow
Mass

flow

flow

(kgmole/hr)

flow

(kgmole/hr)

flow

C4H8

56

kgmole/hr
-

(kg/hr)
-

(kg/hr)
-

(kg/hr)
-

iC4H10

58

n C4H10

58

CH3OH

32

0.149

4.776

0.003

0.096

0.146

4.680

C5H12O

88

C2H6O

46

C4H10O

74

H2O
Total

18

13.035
13.185

234.63
239.411

12.775
12.778

229.95
230.046

0.260
0.407

4.685
9.365

OVERALL REACTION SYSTEM, FLOW DIAGRAM

S3

S17

S18

S9
Liquid
d
liquid
liquid
extra
extrac
ction
tion

Liqui

Distill
ation
colu
mn

S11

Distill
ation
colu
mn

7.8

85

Re
act
or

R
Se
ea
pa
rat
ct
or
or

Ca
tal
ytic
rea
cto
r

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

S2

S10

S12

S15

Overall mass balance is shown below:


Input

S4
Molar flow

Mass flow

kgmole/hr

(kg/hr)
5800

output

Input
S13
Molar flow
Mass flow

Molar flow

(kgmole/hr)

(kgmole/hr)

(kg/hr)

2278.848

Total input

S20
Mass flow
(kg/hr)
216.522

8295.37

Output
S10
Molar flow
Mass
(kgmole/hr

flow

(kg/hr)
129.48

S16
Molar flow
(kgmole/hr)

Total

S26
Mass
flow
(kg/hr)
5710.828

Molar flow
(kgmole/hr)

S21
Mass
flow
(kg/hr)
230.046

Molar flow
(kgmole/hr)

Mass
flow
(kg/hr)
2225.016

8295.37

output

7.6 SCALE-UP FACTOR


Determination of the scale-up factor for the end product (MTBE)
With a basis 100 kgmole/hr of feed at stream S2, the product at stream S12 acquired is
5658.934 kg/hr.
This amount if converted to kg/yr, by conversion unit,
5582.72kg/hr * 7920 hr/yr = 44.215142 * 106 kg/yr of MTBE
Targeted production of MTBE = 300 X106 kg/yr (300,000 metric tonnes/yr)

86

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Therefore, the scale-up factor = Targeted Amount


Actual Amount
= 300,000 x103 kg/yr
44.8188 x106 kg/yr
= 6.785005854
6.785
To determined whether the scale-up factor can proceed or not,
Target amount

Actual Production x Scale-up factor

44.215 x 106 x 6.785

299.9997385 x106

300 x106 kg/yr at stream S14

Therefore, the scale-up factor of 6.785 is acceptable for this process.

CHAPTER 8

ENERGY BALANCE
8.1

ENERGY EQUATION

The equation that we used to calculate the power Q or W at each equipment is:

87

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Q W = HR + (-Hin) + (Hout) + (KE) + (PE)


To calculate H, first we need to find the Cp values for every component in each of the
stream. To find the Cp values, we need to use this equation to find the values of Cp

= a + bT + cT2 + dT3

The values of a, b, c and d are taken from Appendix D, Coulson and Richardson
Chemical Engineering, Volume 6. If the temperature and pressure is more than the
critical temperature and pressure of the component, we need to find the (C p Cpo) for
that specific component. But as for all of our temperatures and pressures none of them
exceed the critical temperature and pressure; we need not to find the (Cp Cpo).
To find the value of H, we use this equation:

H =

T2

C
T1

dT x (n)

Should there is any reaction in the process; we need also to find the values of HR
which takes place in the equipment. The equation, which we used to find HR is:

HR = (F product - F reactant) x n
and if the equipment has KE and PE, we also need to calculate the values by using
this equation:
KE = 0.5 m(vout2 - vin2)
PE = mg x (zout zin)
so, after we have calculated all the values of the energy for each and every of the
stream, we then can calculate the value of Q or W.
And for this sample of calculations, listed are the values of constants in the ideal gas
heat capacity equation based on R. K Sinnot, Coulson & Richardson, Chemical
Engineering, Volume 6, Third Edition, Butterworth Heinemann:

88

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Table 8.1 Table of Constant in the Ideal Heat Capacity


Component
C5H12O
CH3OH
H2O
C4H8
i-C4H8
i-C4H10
C4H10O
n-C4H10
(CH3)2O
H2
8.2

Delta HF
kJ/kmol.K
kJ/kmol
-1
-4
-8
2.53
5.14 x 10 -2.60 x 10 4.30 x 10 -292990
2.12 x 101 7.09 x 10-2 2.59 x 10-5 -2.85 x 10-8 -201300
32.243
1.93 x 10-3 1.06 x 10-5 -3.60 x 10-9 -242000
-2.994
3.53 x 10-1 -1.98 x 10-4 4.46 x 10-8
-130
16.052 2.8043 x 10-1 -1.091 x 10-4 9.098 x 10-9 -16900
-1.39
3.85 x 10-1 -1.85 x 10-4 2.90 x 10-8 -134610
1
-4.86 x 10 7.17 x 10-1 -7.08 x 10-4 2.92 x 10-7 -312630
9.85
3.31 x 10-1 -1.11 x 10-4 -2.82 x 10-9 -126.23
1.70 x 101 1.79 x 10-1 -5.23 x 10-5 -1.92 x 10-9 -184180
2.71 x 101 9.27 x 10-3 -1.38 x 10-5 7.65 x 10-9
0

ENERGY BALANCE: SAMPLE OF CALCULATIONS

(Methods of calculations are based on, Coulson & Richardson, Chemical Engineering,
Volume 6, page 78).
8.2.1

P-100 (Pump 1)
S2
T = -150C
P = 750 Kpa
(liquid)

S1
T = -180C
P = 450
Calculations
are Kpa
based on Yunus A. Cengel, Micheal A. Boles, Thermodynamics:
(Liquid)
An Engineering Approach, WCB/Mc Graw-Hill, 1989, page, 354-355.
Assumptions:
1. Steady operating conditions exist
2. Kinetic and potential energy negligible
3. The process is to be isentropic
Specific volume:
Isobutane = 0.255 m3/mol
n-butane = 0.263 m3/mol

89

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

(Data of these specific volumes are based on Coulson & Richardson, Chemical
Engineering, Volume 6, Third Edition, Butterworth Heinemann, page 947)
Isobutane
0.255m3/mol x 1000mol/kmol x 1kmol/58kg = 9.11 m3/kg
n-butane
0.263m3/mol x 1000mol/kmol x 1kmol/58kg = 4.53 m3/kg
Vavg = (9.11 + 4.53) m3/kg / 2 = 6.82 m3/kg
(Which remains essentially constant during the process)
2

Win = Vdp
1

= V1 (P2 P1 )
= 6.82m 3 /kg(750 450)kpa(1k J/1kpa.m
= 6.82(300)

= 2046.00kJ/ kg
2046kJ/kg x 39353kg/hr
= 80516238kJ /hr = 22365.62kW

8.2.2

E-100 (Heat Exchanger 1)

S2
T = -15 oC
P = 750Kpa
(Liquid)

S3
T = 117 oC
P = 450Kpa
(Gas)

Stream 2
Component
i-C4H10
n-C4H10

Flowrates
Kmol/hr
675.786
2.714

F
kJ/Kmol
-1.35 x105
-1.26 x105

To
K
298
298

T, K
258
258

H
kJ/hr
-690.04
-2.81

90

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

H =
-692.86

Stream 3
Component
i-C4H10
n-C4H10

Flowrates
Kmol/hr
676.786
2.714

F
kJ/Kmol
-1.35 x105
-1.26 x105

To
K
298
298

T, K
390
390

H
kJ/hr
1902.85
7.66

H =
1910.51

Sample of calculations for i-C4H10 at stream 3


H =

T2

C
T1

T2

C
T1

dT =

dT x (n)
T2

T1

a + bT + cT 2 + dT 3

b(T 2 T1 ) 2 c(T 2 T1 )3 d(T 2 T1 ) 4


a(T

T
)
+
+
+
= 2
1

2
3
4

= ( 1.390 )( 390 298 ) +


+

38 .473 10 2 (390 - 298 ) 2


2

( 1.846 10 4 )( 390 - 298 )3


3

28 .952 10 9 (390 - 298 ) 4


4

= 10100 kJ/kmol
H

= 10100 kJ/kmol x 675.786 kmol/hr


= 6825438.6 kJ/hr
= 1902.85 kW (for i-C4H10)

And as for n-C4H10, the H

So

= 7.66 kW

H = 1910.51

Energy balance,

91

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Q=(

H)

out

H)

in

= 1910.51- (-692.86)
= 2603.37kW
Steam flowrate, Q = mCpT
Cp of isobutane, 2155 J/kg oC (Elementary Principles of Chemical Processes,

W.

Rousseau et. al)

m=

Q
Cp T

2603370 J/s
2155J/g o C x (117 - (-15))
= 9.152g/s
=

Therefore the supply of steam flow rate required is 9.152 g/s.


8.2.3

E-101 (Heat Exchanger 2)

S3
T = 117 oC
P = 450 kPa
(Gas)

S4
T = 250 oC
P = 325 kPa
(Gas)

Stream 3
Component
i-C4H10
n-C4H10

Flowrates
Kmol/hr
676.786
2.714

F
kJ/Kmol
-1.35 x105
-1.26 x105

To
K
298
298

T, K
390
390

H
kJ/hr
1902.85
7.66

H =
1910.51

Stream 4
Component
i-C4H10
n-C4H10

Flowrates
Kmol/hr
676.786
2.714

F
kJ/Kmol
-1.35 x105
-1.26 x105

To
K
298
298

T, K
523
523

H
kJ/hr
5356.57
21.46

92

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

H =
5378.03

Sample of calculations for i-C4H10 at stream 4


H =

T2

C
T1

T2

C
T1

dT x (n)
T2

dT =

T1

a + bT + cT 2 + dT 3

b(T 2 T1 ) 2 c(T 2 T1 )3 d(T 2 T1 ) 4


a(T

T
)
+
+
+
= 2
1

2
3
4

= ( 1.390 )( 523 298 ) +


+

38 .473 10 2 (523 - 298 ) 2


2

( 1.846 10 4 )( 523 - 298 )3


3

28 .952 10 9 (523 - 298 ) 4


4

= 28500 kJ/kmol
H

= 28500 kJ/kmol x 675.786 kmol/hr


= 19259901 kJ/hr
= 5349.97 kW (for i-C4H10)

And as for n-C4H10, the H

So

= 21.46 kW

H t = 5371.43kW
ou

Energy balance,
Q=(

H)

out

H)

in

= 5371.43- (1910.51)
= 3460.92kW
Steam flowrate, Q = mCpT

93

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Cp of isobutane, 2155 J/kg oC (Elementary Principles of Chemical Processes,

W.

Rousseau et. al)

m=

Q
Cp T

3460920 J/s
2155J/g o C x (250 - 118) o C
= 12.17g/s
=

Therefore the supply of steam flow rate required is 12.17 g/s.


8.2.4

R-101 (Snamprogetti Fluidized Bed Reactor)

S5
Air Out
S4
T=250oC
P=325kPa
(gas)

S6
Air In

S7
T=180oC
P=110kPa
(Liquid)
Stream 4
Component
i-C4H10
n-C4H10

Flowrates
Kmol/hr
676.786
2.714

F
kJ/Kmol
-1.35 x105
-1.26 x105

To
K
298
298

T, K
523
523

H
kJ/hr
5356.57
21.46

H =
5378.03

Stream 7

94

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Component
i-C4H8
i-C4H10
n-C4H10
H2

Flowrates
Kmol/hr
237
2.71
439
439

F
kJ/Kmol
-1.30 x10-1
-1.35 x105
-1.26 x105
0.00

To
K
298
298
298
298

T, K
453
453
453
453

H
kJ/hr
1056.59
13.82
2236.41
549.84

H =
3856.66

To calculate the value of HR:


1) i-C4H10 C4H8 + H2
so,
R = (F C4H8) + (F H2) -(F i-C4H10)
= (-130) + (0) (-134610)
= 134480 kJ/kmol
therefore,
HR = (R kJ/kmol x 236.53 kmol/hr)
= (134480 kJ/kmol x 236.53 kmol/hr)
= 31808554.4 kJ/hr
= 8835.71 kJ/s
= 8835.71 kW
Although there is stream flow, but the KE is too small and negligible and there is also
now work so, W is zero and as for the PE, the value is neglected, as it is also too
small.
Now we calculate the value of Q,
Q W 0= HR + (-Hin) +(Hout) +KE 0+ PE0
Q = HR + (Hout) - (Hin)
Q = 8835.71 + (1980.66) - (3856.66)
Q = 6959.71kW (heat have been absorbed)
8.2.5

C-100 (Compressor 1)

95

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

S7
T = 1800C
P = 110 Kpa
(Gas)

S8
T = 1930C
P = 120 Kpa
(Gas-liquid)

T7 = 453K

T8 =?

P7 = 1.1 bar

P8 = 1.2 bar

T4 = 453K,

P4 = 1.1 bar,

P8 = 1.2 bar is based on the literature review of process

Snamprogetti fluidized bed.


By assuming polytropic and ideal gas condition:
T7= T6(P7/P6)m (Coulson & Richardson, Chemical Engineering, Volume 6, page 85)
m = 1/ Ep

= CPmean/CV = CPm/CPm R

Where R = 8.314 kJ/kmol.K


For hydrogen, a = 27.143, b = 97.38 x 10-4, c = -1.31 x 10-5, d = 76.451 x 10-10
1000K

CPHydrogen =

453K

a + bT + cT 2 + dT 3 = 16200 kJ/kmol.K

For butene, a = -2.994 , b = 3.53 x 10-1 , c = -1.98 x 10-4 , d = 4.46 x 10-8 ,


CPbutene =

1000K

453K

a + bT + cT 2 + dT 3 = 89400 kJ/kmol.K

For Isobutane, a = -1.39 , b = 3.85 x 10-1 , c = -1.85 x 10-4 , d = 2.90 x 10-8 ,


CPisobutane =

1000K

453K

a + bT + cT 2 + dT 3 = 103000 kJ/kmol.K

For n-butane, a = 9.85 , b = 3.31 x 10-1 , c = -1.11 x 10-4 , d = -2.82 x 10-9,


1000K

CPn-butane =

Cpmean =

0.25 (Cp , Hydrogen + Cp , butene + Cpisobu tan e + Cp , n bu tan e)


(466 453 )

453K

a + bT + cT 2 + dT 3 = 103000 kJ/kmol.K

0.25(16200 + 89400 + 103000 + 103000)


= 167.5kJ/km ol.K
1000 453

So , = CPm/CPm R = 167.5/(167.5-8.314) = 1.07

96

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

To find Ep(efficiency),
Flow rate =

1117.76kmo l
453
1
x22.4x
x
3600s
273 0.5

= 23 .08 m 3 / s
From Figure 3.6, Coulson & Richardson, Chemical Engineering, Volume 6, page 83,
Ep = 75%
m = (1/ Ep) = 1.07-(1/1.07 (0.75) ) = 0.3690
To determine T6,
T8 = T7(P8/P7)m = 453(1.2/1.1)0.3690 = 466.83K (193oC)
Tc and Pc for H2, isobutene, isobutane and n-butane, Tc = 417.07K, Pc = 38.17 bar
Trmean = (T7 + T8)/2Tc = (453+ 466.83K)/2(417.07) = 1.10 K
Prmean = (P5 + P6)/2Pc = (1.1+1.2)/2(38.17) = 0.030 bar
From Figure 3.8, Compressibility factors (Coulson & Richardson, Chemical
Engineering, Volume 6, page 87).
Z = 1.00
Then find n, n = 1/(1-m) = 1/(1-0.3456) = 1.53
Polytropic work = zRT1(n/n-1)x((P1/P2)(n-1/n) 1)
=

1.53

1.00 (8.314 )( 453 )( 0.53

0.53

1.2 1.53
) x
1

1.1

= 332.69 kJ/kmol
Actual work = Polytropic work / Ep
= 332.69 /0.75
= 443.60 kJ/kmol
Compressor power = 443.60 kJ/kmol x 1117.76 kmol/hr x 1hr/3600s
= 137.73 kW
Therefore the compressor power required to increase the pressure from 1.1 bar to 1.2
bar is 137.73kW.

8.2.6

E-102 (Cooler 1)
S8
T = 193oC
P = 120 Kpa
(Liquid)

S9
T = 530C
P = 100 Kpa
(Liquid)

97

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Sample of Calculation for Cooler 1


Stream 8
Component
C4H8
i-C4H10
n-C4H10
H2

Flowrates
Kmol/hr
4.39x1002
2.37x102
2.71x100
4.39x102

F
kJ/Kmol
-1.69x10-4
-1.35x105
-1.26x105
0.00

To
K
298
298
298
298

T, K
466
466
466
466

H
kJ/hr
2155.41
1323.43
15.15
596.20

H =
4090.20

Stream 9
Component
i-C4H8
i-C4H10
n-C4H10

Flowrates
Kmol/hr
6.47x101
3.49x 101
4.00x101

F
kJ/Kmol
-1.69x104
-1.35 x104
-1.26 x105

To
K
298
298
298

T, K
326.3
326.3
326.3

H
kJ/hr
47.45
27.84
0.32

H =
75.61

Energy balance,
Q=(

H)

out

H)

in

= 75.61 4090.20
= -4014.59 kW (heat is being released to the surrounding)
Steam flowrate, Q = mCpT

98

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Cp of pure water, 4.184 J/g oC (Elementary Principles of Chemical Processes,


W.Rousseau et. al)
Q
mCp T
4014590J/s
=
4.184J/g o C x (193 - 53.3)
=6869.36 g/s

m=

Therefore the supply of steam flow rate required is 6869.36 g/s.

8.2.7 V-100 (Separator)


S10
T = 53.3oC
P = 90 kPa
(gas)
S9
T= 53.3oC
P= 100kPa
(liquid-gas)
S11
T=53.3oC
P=100kPa

Sample of Calculation for Hydrogen Splitter Vessel


Stream 9
Component
C4H8

Flowrates
Kmol/hr
2.37x102

i-C4H10
n-C4H10
H2

2.71x102
4.39x102
4.39x102

F
kJ/Kmol
-1.69x104
1.35Ex105
-1.26x105
0.00

To
K
298

T, K
326.3

H
kJ/hr
166.03

298
298
298

326.3
326.3
326.3

2.17
353.50
99.88

99

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

H =
621.57

Stream 10
Component

H2

Flowrates
Kmol/hr

F
kJ/Kmol

To
K

T, K

H
kJ/hr

4.39x102

0.00

298

326.3

99.88

Flowrates
Kmol/hr
439.26
236.53
2.71

F
kJ/Kmol
-16910
-134610
-126230

To
K
298
298
298

T, K

H
kJ/hr
321.92
188.89
2.18

H =

Stream 11
Component
C4H8
i-C4H10
n-C4H10

326.3
326.3
326.3

H =
512.99

Energy balance,
Q=(

H)

out

H)

in

= (512.99)-(621.57+99.88)
= -208.46 (heat is being released to the surroundings)
8.2.8

R-102 (MTBE Reactor)


S11
T = 53.3oC
P = 2000kPa
(liquid)

S14
T = 27oC
P = 100kPa
(liquid)

S15
T = 101oC
P = 2000kPa
(liquid)

100

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

The pressure increases from 100kPa to 2000kPa. As there is a heat exchanger (heater)
in the MTBE reactor.
Stream 11
Component
C4H8
i-C4H10
n-C4H10

Flowrates
Kmol/hr
439.26
236.53
2.71

F
kJ/Kmol
-16910
-134610
-126230

To
K
298
298
298

T, K
326.3
326.3
326.3

H
kJ/hr
321.92
188.89
2.18

H =
512.99

Stream 14
Component
CH3OH
H2O

Flowrates
Kmol/hr
4.84x102
1.76

F
kJ/Kmol
-2.01x104
-2.42x105

To
K
298
298

T, K
300
300

H
kJ/hr
11.81
-4.79

H =
7.02

Stream 15
Component
C5H12O
CH3OH

Flowrates
Kmol/hr
4.30x102
1.09

F
kJ/Kmol
-2.93x105
-2.01 x105

To
K
298
298

T, K
374
374

H
kJ/hr
1339.10
1.07

101

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

H2O
i-C4H8
i-C4H10
C4H10O
n-C4H10
(CH3)2O

1.94
0.176
2.37x102
8.64
2.71
26.3

-2.44 x105
-0.123
-1.35 x105
-3.13 x105
-1.26 x105
-1.84 x105

298
298
298
298
298
298

374
374
374
374
374
374

13.94
0.35
539.59
22.49
6.22
39.56

H =
1962.32

Q=(

H)

out

H)

in

= 1962.32 7.02 512.99


= 1442.31 kW
To calculate the value of HR:
1.) C4H8 + CH3OH
2.) 2CH3OH

C5H12O
C2H6O + H2O

3.) C4H8 + H2O

C4H10O

so,
R 1 = (F C5H12O) - (F CH3OH) + (F C4H8)
= (-292990) ((-201300) + (-130))
= -91820 kJ/kmol
R 2 = (F C2H6O) + (F H2O) -(2 F CH3OH )
= (-242000) + (-184180) (2 x -201300)
= -23580 kJ/kmol
R 3 = (F C4H10O) (F H2O) -(F C4H8)
= (-312630) - (-184180) (-130)
= -128270 kJ/kmol
Therefore,
HR = (R 1kJ/kmol x (63.44kmol/hr) + (R 2kJ/kmol x 0.039kmol/hr) +
(R 3kJ/kmol x 0.624kmol/hr)
=(-91820kJ/kmolx63.44kmol/hr)+(-23580kJ/kmolx0.039kmol/hr) +
102

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

(-128270 kJ/kmol x 0.624kmol/hr)


= -5906020.9 kJ/hr
= -1640.56 kW
Although there is stream flow, but the KE is too small and negligible and there is also
now work so, W is zero and as for the PE, the value is neglected, as it is also too small
Now we calculate the value of Q
Q W 0= HR + (-Hin) +(Hout) +KE 0+ PE0
Q = HR + (-Hin) +(Hout)
Q = -1640.56 + 1442.31 = -198.25 kW
8.2.9

P-101 (Pump 2)

S13
T = 270C
P = 115 Kpa
(liquid)
S12
T = 270C
P = 110 Kpa
(Liquid)
Calculations are based on Yunus A. Cengel, Micheal A. Boles, Thermodynamics: An
Engineering Approach, WCB/Mc Graw-Hill, 1989, page, 354-355.
Assumptions:
4. Steady operating conditions exist,
5. Kinetic and potential energy negligible
6. The process is to be isentropic
Specific volume:

103

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

methanol = 0.118 m3/mol


(Data of these specific volumes are based on Coulson & Richardsons)
Methanol
0.118m3/mol x 1000mol/kmol x 1kmol/32kg = 3.6875 m3/kg
Vavg = 1.78 m3/kg
Which remains essentially constant during the process
2

Win = Vdp
1

= V1 (P2 P1 )
= 3.6875m 3 /kg(115 110)kpa(1k J/1kpa.m
= 18 .44 kJ/kg
18.44kJ/kg x 15462 kg/hr
= 285080.63k J/hr = 79.19 kW

8.2.10 M-101 (Mixer)

S13

S14

T= 27oC
P=115kPa
(liquid)

T= 27oC
P= 115kPa
(liquid)

S29
T=27oC
P=130kPa
(liquid)
Stream 13
Component

CH3OH

Flowrates

To

Kmol/hr

kJ/Kmol

4.83 x102

-2.01 x102

298

T, K

H
kJ/hr

H =
300

11.79

104

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Stream 29
Component
CH3OH

Flowrates

Kmol/hr

kJ/Kmol

9.91 x10

H20

1.76

To

T, K

H
kJ/hr

-2.01 x10

298

300

0.02

-2.42 x10

298

300

0.03

H =
0.06

Stream 14
Component
CH3OH

Flowrates

Kmol/hr

kJ/Kmol

4.84 x10

H20

1.76

To

T, K

H
kJ/hr

-2.01 x10

298

300

11.81

-2.42 x10

298

300

0.03

H =
11.84

Energy balance = out - in


Q=(

H)

out

H)

in

= 11.84 0.06 11.79


= 0.04 kW
8.2.11 EX-100 (Expander 1)

S15

S16

T = 1010C
P = 2000 kPa
(liquid)

T = ?0C
P = 450 Kpa
(Gas-liquid)

T15 = 453K

T16 =?

P15 = 2 bar

P16 = 0.45 bar

105

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

By assuming polytropic and ideal gas condition:


T16= T15(P16/P15)m (Coulson & Richardson, Chemical Engineering, Volume 6, page 85)
m = 1/ Ep

= CPmean/CV = CPm/CPm R

Where R = 8.314 kJ/kmol.K


For MTBE, a = 2.533 , b = 51.372 x 10-2 , c = -2.59 x 10-4 , d = 43.04 x 10-9 ,
CPMTBE =

1000K

374K

a + bT + cT 2 + dT 3 = 151000 kJ/kmol.K

For TBA, a = 3.266 , b = 41.80 x 10-2 , c = -2.242 x 10-4 , d = 46.85 x 10-9 ,


CP(TBA) =

1000K

374K

a + bT + cT 2 + dT 3 = 126000 kJ/kmol.K

For DME, a = 17.015 , b = 19.907x 10-2 , c = -5.23 x 10-5 , d = -1.918 x 10-9 ,


CP(DME) =

1000K

374K

a + bT + cT 2 + dT 3 = 70700 kJ/kmol.K

For CH3OH, a = 21.152 , b = 70.924 x 10-3 , c = 25.870 x 10-6 , d = -2.852 x 10-8 ,


CP(methanol) =

1000K

374K

a + bT + cT 2 + dT 3 = 44900kJ/km ol.K

For H2O, a = 27.143 , b = 92.738 x 10-4 , c = -1.381 x 10-5 , d = 76.451 x 10-10 ,


CP(water) =

1000K

374K

a + bT + cT 2 + dT 3 = 23500kJ/km ol.K

For butene, a = -2.994 , b = 3.53 x 10-1 , c = -1.98 x 10-4 , d = 4.46 x 10-8 ,


CPbutene =

1000K

374K

a + bT + cT 2 + dT 3 = 113000 kJ/kmol.K

For Isobutane, a = -1.39 , b = 3.85 x 10-1 , c = -1.85 x 10-4 , d = 2.90 x 10-8 ,


CPisobutane =

1000K

374K

a + bT + cT 2 + dT 3 = 126000 kJ/kmol.K

For n-butane, a = 9.85 , b = 3.31 x 10-1 , c = -1.11 x 10-4 , d = -2.82 x 10-9,


CPn-butane =

Cpmean=
=

1000K

374K

a + bT + cT 2 + dT 3 = 113000 kJ/kmol.K

0.125(Cp, M TBE+ Cp, TBA + Cp, DM E+ Cp, methanol+ Cp, H2 + Cp, butene+ Cpisobu
(1000 453)

0.125(1510 00 + 126000 + 70700 + 44900 + 23500 + 113000 + 126000 + 113000)


= 153.37kJ/k mol.K
1000 374

So , = CPm/CPm R = 153.37/(153.37-8.314) = 1.06

106

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

To find Ep(efficiency),
Flow rate =

53999.92km ol
374
1
x22.4x
x
3600s
273 0.5

= 920 .61m 3 / s
From Figure 3.6, Coulson & Richardson, Chemical Engineering, Volume 6, page 83,
Ep = 85%
m = 1/ Ep = (1.06-1/1.06 (0.85)= 0.0665
To determine T6,
T16 = T15(P16/P15)m = 374(0.45/2.0)0.0665 = 338.68K (65.6oC)
Tc = 417.07K, Pc = 38.17 bar
Trmean = (T15 + T16)/2Tc = (374+ 228.68K)/2(417.07) = 0.723 K
Prmean = (P15 + P16)/2Pc = (2+0.45)/2(38.17) = 0.0321 bar
From Figure 3.8, Compressibility factors (Coulson & Richardson, Chemical
Engineering, Volume 6, page 87).
Z = 0.8
Then find n, n = 1/(1-m) = 1/(1-0.0665) = 1.07
Polytropic work = zRT1(n/n-1)x((P15/P16)(n-1/n) 1)
=

1.07

1.00 (8.314 )( 374 )( 0.07

0.07

2 1.07
) x
1

0.45

= 4872.06 kJ/kmol
Actual work = Polytropic work / Ep
= 4872.06 /0.80
= 6090.07 kJ/kmol
Compressor power = 6090.07 kJ/kmol x 53999.12x 1hr/3600s
= 91349kW
Therefore the compressor power required to decrease the pressure from 2 bar
(2000kPa) to 0.45 bar (450kPa) is 91349kW.
8.2.12 E-103 (Cooler 1)
S16
T = 193oC
P = 120 Kpa
(Liquid)

S17
T = 64.50C
P = 100 Kpa
(Liquid)

107

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Sample of Calculation for Cooler 1


Stream 16
Component
C5H12O
CH3OH
H2O
i-C4H8
I-C4H10
C4H10O
n-C4H10
(CH3)2O

Flowrates
Kmol/hr
4.30 x102
5.02
1.21 x102
8.16
2.37 x102
6.65 x101
2.71
1.21 x102

F
kJ/Kmol
-2.93 x105
-2.01 x105
-2.42 x105
-1.69 x105
-1.35 x105
-3.13 x105
-1.26 x105
-1.84 x105

To
K
298
298
298
298
298
298
298
298

T, K
466
466
466
466
466
466
466
466

H
kJ/hr
3270.13
11.81
194.19
40.93
1323.40
4.26
15.17
438.54

H =
5298.44

Stream 17
Component
C5H12O
CH3OH
H2O
i-C4H8
I-C4H10
C4H10O
n-C4H10
(CH3)2O

Flowrates
Kmol/hr
4.30 x102
5.02 x102
1.21 x102
8.16
2.37 x102
0.665
2.71
1.21 x105

F
kJ/Kmol
-2.93 x105
-2.01 x105
-2.42 x105
-1.69 x105
-1.35 x105
-3.13 x105
-1.26 x105
-1.84 x105

To
K
298
298
298
298
298
298
298
298

T, K
337.5
337.5
337.5
337.5
337.5
337.5
337.5
337.5

H
kJ/hr
665.50
2.50
44.96
8.45
267.64
0.85
3.09
91.16

H =
1084.15

Energy balance,

108

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Q=(

H)

out

H)

in

= 1084.15 5298.44
= -4214.29 kW (heat is being released to the surrounding)
Steam flowrate, Q = mCpT
Cp of pure water, 4.184 J/g oC (Elementary Principles of Chemical Processes,
W.Rousseau et. al)
Q
mCp T
4214290J/s
=
4.184J/g o C x (193 - 64.5)
=7838.44 g/s

m=

Therefore the supply of steam flow rate required is 7838.44 g/s.


8.2.13 T-101 (Distillation Column 1)

S19
P = 305 Kpa
T = 53.3 oC
(gas)
S17
P = 450 Kpa
T =64.5 oC
( liquid )
S18
P = 400 Kpa
T = 103.3oC
( liquid )
Sample of Calculations:
R = L/D
Overall:
(NL), L = D x 1.5

109

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

= 451.779 x 2.5
= 1129.45 kmol/hr
(NV), V = L + D
= 1129.45+ 451.779
= 1581.23 kmol/hr

Stream 17
Component
C5H12O
CH3OH
H2O
i-C4H8
I-C4H10
C4H10O
n-C4H10
(CH3)2O

Flowrates
Kmol/hr
4.30 x102
5.02
1.21 x102
8.16
2.37 x102
0.665
2.71
1.21 x102

F
kJ/Kmol
-2.93 x105
-2.01 x105
-2.42 x105
-1.69 x105
-1.35 x105
-3.13 x105
-1.26 x105
-1.84 x105

To
K
298
298
298
298
298
298
298
298

T, K
337.5
337.5
337.5
337.5
337.5
337.5
337.5
337.5

H
kJ/hr
665.50
2.50
44.96
8.45
267.64
0.85
3.09
91.16

H =
1084.15

Stream 19
Component

Flowrates

To

T, K

CH3OH
H2O
i-C4H8
(CH3)2O
i-C4H10
n-C4H10

Kmol/hr
1.01E+00
6.83E+00
1.76E-01
2.63E+01
2.37E+02
2.71E+00

kJ/Kmol
-2.01 x105
-2.42 x105
-1.69 x104
-1.84E+05
-1.35 x105
-1.26 x105

K
298
298
298
298
298
298

376.3
376.3
376.3
376.3
376.3
376.3

kJ/hr
1.03
5.04
0.38
40.85
557.49
6.42

H =
611.21

Stream 18
Component

Flowrates
Kmol/hr

F
kJ/Kmol

To
K

T, K

H
kJ/hr

110

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

CH5H12O
CH3OH
C4H10O
H2O

4.30E+02
7.50E-02
8.64E+00
1.26E+01

-2.93 x105
-2.01 x105
-3.13 x105
-2.42 x105

298
298
298
298

326.3
326.3
326.3
326.3

469.97
0.03
7.82
3.35

H =
481.17

Energy balance,
Q=(

H)

out

H)

in

= (481.17 + 611.21) 1084.15


= 8.23 kW
8.2.14 Cooler 2 (E-104)

S19
T = 53.3oC
P = 305 Kpa
(Liquid)

S20
T = 400C
P =100 Kpa
(Liquid)

Sample of Calculation for Cooler 1


Stream 19
Component

Flowrates

To

T, K

CH3OH
H2O
i-C4H8
(CH3)2O
i-C4H10
n-C4H10

Kmol/hr
1.01E+00
6.83E+00
1.76E-01
2.63E+01
2.37E+02
2.71E+00

kJ/Kmol
-2.01 x105
-2.42 x105
-1.69 x104
-1.84x105
-1.35 x105
-1.26 x105

K
298
298
298
298
298
298

376.3
376.3
376.3
376.3
376.3
376.3

kJ/hr
1.03
5.04
0.38
40.85
557.49
6.42

H =
611.21

Stream 20
Component

Flowrates
Kmol/hr

F
kJ/Kmol

To
K

T, K

H
kJ/hr

111

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

CH3OH

1.01E+00

H2O

6.83E+00

i-C4H8

1.76E-01

(CH3)2O

2.63E+01

I-C4H10

2.37E+02

N-C4H10

2.71E+00

-2.01
x105
-2.42
x105
-1.69
x104
-1.84
x105
-1.35
x105
-1.26
x105

298

313

0.19

298

313

0.96

298

313

0.07

298

313

7.33

298

313

98.29

298

313

1.14

H =
107.97

Energy balance,
Q=(

H)

out

H)

in

= 107.97 611.21
= -503.24 kW
Steam flowrate, Q = mCpT
Cp of pure water, 4.184 J/g oC (Elementary Principles of Chemical Processes,
W.Rousseau et. al)
Q
mCp T
503240J/s
=
4.184J/g o C x (53.3 - 40) o C
=9043.40 g/s

m=

Therefore the supply of steam flow rate required is 9043.40 g/s.


8.2.15 P-102 (Pump 3)

S22
T = 270C
P = 30 kPa
(liquid)
S21
T = 270C
P = 25 kPa
(Liquid)

112

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Calculations are based on Yunus A. Cengel, Micheal A. Boles, Thermodynamics: An


Engineering Approach, WCB/Mc Graw-Hill, 1989, page, 354-355.
Assumptions:
7. Steady operating conditions exist,
8. Kinetic and potential energy negligible
9. The process is to be isentropic
Specific volume:
Water = 0.056m3/mol
(Data of these specific volumes are based on Coulson & Richardsons)
(Which remains essentially constant during the process)
Water
0.056m3/mol x 1000 mol/kmol x 1 kmol/18kg = 3.11 m3/kg
Which remains essentially constant during the process.
2

Win = Vdp
1

= V1 (P2 P1 )
= 3.11m 3 /kg(30 25)kpa(1kJ /1kpa.m 3 )
= 3.11(5)
= 15.55kJ/kg
15.55kJ/kg x 1469kg/hr
= 22851 kJ/hr = 22.85kW

8.2.16 T-102 (Extraction Column)

113

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

S22
T=27oC
P=30kPa
(liquid)

S23
T=40oC
P=250kPa
(liquid)

S20
T=40oC
P=100kPa
(liquid)

S25
T=27oC
P=100kPa
(liquid)

Sample of Calculation for Extraction Column


Stream 20
Component

Flowrates
Kmol/hr

CH3OH

1.01E+00

H2O

6.83E+00

i-C4H8

1.76E-01

(CH3)2O

2.63E+01

I-C4H10

2.37E+02

N-C4H10

2.71E+00

F
kJ/Kmol
-2.01
x105
-2.42
x105
-1.69
x104
-1.84
x105
-1.35
x105
-1.26
x105

To
K

T, K

H
kJ/hr

298

313

0.19

298

313

0.96

298

313

0.07

298

313

7.33

298

313

98.29

298

313

1.14

H =
107.97

Stream 22
Component

H2O

Flowrates
Kmol/hr

F
kJ/Kmol

To
K

T, K

8.16E+01

-2.42
x105

298

300

H
kJ/hr

H =
1.53

114

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Stream 23
Component

Flowrates
Kmol/hr

i-C4H8

1.76E-01

(CH3)2O

2.63E+01

i-C4H10

2.37E+02

n-C4H10

2.71E+00

F
kJ/Kmol
-1.69
x104
-1.84
x105
-1.35
x105
-1.26
x105

To
K

T, K

H
kJ/hr

298

313

0.07

298

313

7.33

298

313

98.30

298

313

1.14

H =
106.83

Stream 25
Component
CH3OH
H2O

Flowrates
Kmol/hr
1.01E+00
8.84E+01

F
kJ/Kmol
-2.01 x105
-2.42 x105

To
K
298
298

T, K
300
300

H
kJ/hr
0.02
1.65

H =
1.68

Energy balance,
Q=(

H)

out

H)

in

= (106.83+1.68) (107.97+1.53)
= -0.91 kW
8.2.17 Pump 4 (P-103)

S24
T = 40OC
P=
300 Kpa
(liquid)
115

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Calculations are based on Yunus A. Cengel, Micheal A. Boles, Thermodynamics: An


Engineering Approach, WCB/Mc Graw-Hill, 1989, page, 354-355.
Assumptions:
1. Steady operating conditions exist,
2. Kinetic and potential energy negligible
3. The process is to be isentropic
Specific volume:
(Data of these specific volumes are based on Coulson & Richardsons)

Specific volumes:
DME = 0.178m3/mol
Butene = 0.240 m3/mol
Isobutane = 0.255m3/mol
n-butane =0.263 m3/mol

DME
0.178m3/mol x 1000mol/kmol x 1kmol/46kg = 3.87 m3/kg

butene
0.240m3/mol x 1000mol/kmol x 1kmol/56kg = 4.29 m3/kg
Isobutane
0.255m3/mol x 1000mol/kmol x 1kmol/58kg = 9.11 m3/kg
n-butane
0.263m3/mol x 1000mol/kmol x 1kmol/58kg = 4.53 m3/kg
Vavg = (3.87 + 4.29 + 9.11 + 4.53) m3/kg / 4 = 5.45 m3/kg
Which remains essentially constant during the process

116

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Win = Vdp
1

= V1 (P2 P1 )
= 5.45m 3 /kg(300 250)kpa(1k J/1kpa.m
= 5.45(50)

= 272.50kJ/k g
272.50kJ/k g x kg/hr
= 4113932.50 kJ/hr = 1142.76kW

8.2.18 Pump 5 (P-104)

S26
T = 27OC
P=
150 Kpa
( liquid
) on Yunus A. Cengel, Micheal A. Boles, Thermodynamics: An
Calculations are based
Engineering Approach, WCB/Mc Graw-Hill, 1989, page, 354-355.
Assumptions:
4. Steady operating conditions exist,
5. Kinetic and potential energy negligible
6. The process is to be isentropic
Specific volume:
Water = 0.056 m3/mol
Methanol = 0.118m3/mol
(Data of these specific volumes are based on Coulson & Richardsons)
Water
0.056 m3/mol x 1000mol/kmol x 1kmol/18kg = 4.26 m3/kg
Methanol
0.118m3/mol x 1000mol/kmol x 1kmol/32kg = 3.6875 m3/kg

117

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Vavg = (4.26 m3/kg + 3.6875 m3/kg)/2


= 3.974 m3/kg
Which remains essentially constant during the process.
2

Win = Vdp
1

= V1 (P2 P1 )
= 3.974m 3 /kg(150 100)kpa(1k J/1kpa.m
= 3.974(50)

= 198.7kJ/kg
198.7kJ/kg x 1624.32kg/ hr
= 322752.384 kJ/hr = 322 .75 kW

8.2.19 T-102 (Distillation Column 2)

S28
T=530C
P=100kPa
(liquid)
S26
T=27oC
P=150kPa
(Liquid)

Sample of Calculations:

S27
T=30oC
P=70kPa
(liquid)

R = L/D
Overall:
(NL), L = D x 1.5
= 88.44 x 1.5
= 132.66 kmol/hr
(NV), V = L + D

118

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

= 132.66 + 88.64
= 221.30 kmol/hr
Stream 26
Component

Flowrates

To

T, K

CH3OH
H2O

Kmol/hr
9.91E-01
1.76E+00

kJ/Kmol
-2.01 x105
-2.42 x105

K
298
298

300
300

kJ/hr
0.02
-4.79

H =
-4.77

Stream 27
Component

Flowrates

To

T, K

CH3OH
H2O

Kmol/hr
2.00E-02
8.67E+01

kJ/Kmol
-2.01 x105
-2.42 x105

K
298
298

300
300

kJ/hr
0.00
-235.48

H =
-235.48

Stream 28
Component

Flowrates

To

T, K

CH3OH
H2O

Kmol/hr
1.10E-02
8.84E+01

kJ/Kmol
-2.01 x105
-2.42 x105

K
298
298

326
326

kJ/hr
0.00
-240.26

H =
-240.26

Energy balance,
Q=(

H)

out

H)

in

= (-235.48+(-240.26)) (-4.77)
= -470.97 kW
8.2.20 Cooler 3 (E-105)

S28
T = 53oC
P = 100Kpa
(Liquid)

S29
T = 270C
P = 130 Kpa
(Liquid)

119

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Sample of Calculation for Cooler 1


Stream 28
Component

Flowrates

To

T, K

CH3OH
H2O

Kmol/hr
1.10E-02
8.84E+01

kJ/Kmol
-2.01 x105
-2.42 x105

K
298
298

300
300

kJ/hr
0.00
-240.26

H =
-240.26

Stream 29
Component

Flowrates

To

Kmol/hr

kJ/Kmol

T, K

CH3OH

9.91E-01

-2.01 x105

298

300

0.02

H20

1.76E+00

-2.42 x105

298

300

0.03

kJ/hr

H =
0.06

Energy balance,
Q=(

H)

out

H)

in

= 0.06 (-240.26)
= 240.32 kW
Steam flowrate, Q = mCpT
Cp of pure water, 4.184 J/g oC (Elementary Principles of Chemical Processes,
W.Rousseau et. al)
Q
mCp T
240320 J/s
=
4.184J/g o C x (53 - 27) o C
= 2209.15 g/s

m=

120

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Therefore the supply of steam flow rate required is 2209.15 g/s.

CHAPTER 9

121

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

HYSYS

9.0

THE DESIGN MADE BASED ON HYSYS SIMULATION

There are two method that was used in calculating the mass balance and energy
balance for the process which is:
i)

Manual calculation

ii)

Hysys simulation

Hysys program was used to see whether the design could be run or not. Using
Hysys the calculation of the process was calculated automatically when the parameter
that needed was insert. Then if the parameter that was insert is logic so Hysys program
can calculated the result and the equipment can converge. If the data that was inserted
was illogical the equipment cannot converge and the calculation cannot be done.
At the back of this page show the simulation using Hysys that was converge
and include with the manual log book.

REFERENCES
Alber V.G Hahn (1970). The Petrochemical Industry Market & Economics, USA
Mc Graw Hill Book Company. 363- 372.

122

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Coulson & Richardsons, Chemical Engineering Volume 6 Third Edition, Butterworth


Heinemann.
Norman N. Barish and Seymour Kaplan, Economic Analysis for Engineering and
Managerial Decision Making, Second Edition, Mc Graw Hill
Robert H. Perry and Don W. Green, Perrys Chemical Engineerings Handbook,
Seventh Edition, Mc Graw Hill.
Encik Mohd Napis Bin Sudin. 2003, Production of MTBE, Malaysia, Kuantan. Interview,
8 July
Puan Masri. 2003. Information of MTBE production, Malaysia, Kuantan. Interview, 28
Jun.
Lanny P. Schmidt (1998), The Engineering of Chemical Reaction, Oxford University
Press.
James, G. Speight, Baki Ozum (1985). Petroleum Refining Process, Apex
Engineering Inc. Marcell Dekkir New York.
MTBE and Oxygenates (1990), An International Marketing Guide Dewitt & Company
Incorporated 16800 Greenport park, Suite 120N Houston, Texas 77060-2386.
Page 51-62.
The 1992-1995 Worldwide Catalyst Product, Process Licensing & Service DirectoryTechnical articl-1992/3. Page 9.
Annual Report 1994, Section 4. Area Summary for asia and the Pacific. Page 135-169.
Ray/Johnston (1989). Chemical Engineering Design Project, a case study approach,
volume 6. Gordon and Breach Science Publishers.
Wentz (1998). Safety, Health, And Environmental Protection, Mc Graw Hill
Companies, Inc.
Wiley (2000). Elementary Principles of Chemical Processes, John Willey & sons,
Inc.
Chemical Week June 11, 2003 Volume 165 page 31
George S. Brandy ,Henry R.Clauser & John A. Vaccari. Material Handbook 4th
editionJoshua D.Tayloy, Jerrey I. Steinfeld and Jefferson W.Tester Ind. Eng. Chem. Res
2001,40, 67-74 page 71.
Monica Bianchi & Rachl Uctas,ECN ACN/CMR/ ECN NPRA Supplement, March 2002.
Petronas Resource Center, Tingkat 4, Menara 2, Menara Berkembar Petronas, Kuala
Lumpur City Center.

123

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Malaysia Industrial Development Authority

(MIDA), Plaza Central, K L Sentral. Kuala

Lumpur.
Pusat Informasi SIRIM Berhad. 1, Persiaran Dato Menteri, PO Box 7035, Seksyen 2,
40911 Shah Alam.
Jabatan Perangkaan Malaysia, Pusat Pentadbiran Kerajaan, Putrajaya.
Tiram Kimia Sdn. Bhd, Tingkat 1, Bangunan Shell, Off Jalan Semantan, Damansara
Heights, 50490 Kuala Lumpur.
http://www.Manufacturing.net/pur/index.asp
http://www.ceh.sric.sri.com/Publichtml
http://ww2.cemr.wvu/edu/~wwwche/publications/project/index.html
http://www.illallc.com/engarticle.html
http://www.huntsman.com/pertochemicals/ShowPage.cfm
http://www.cmt.anl.gov/science_technology/basicci/onestep_phenol.shtml
http://www.illallc.com/engpatent3am.html
http://www.wikipedia.org/w/wiki.phtml
http://www.ccohs.ca/oshanswers/chemicals/chem_profiles/acetone/basic_ace
http://www.atsdr.ede.gov/toxfag.html
http://www.shellchemicals.com/chemicals/products/1,1184,806,00.html
http://www.mida.gov.my
http://eneken.ieej.or.jp/en/data/pdf/142.pdf
http://www.matheson-trigos.com/mathportal/-pdfs/product/isobutane.pdf
http://www.specialgas.com/isobutane.html
http://www.gas.com.pdf/gas.pdf
http://www.boc.com/microsite/america/products/gases/mixed/isobutane.html
http://www.boc.com/microsite/america/products/gases/aps/geiger.html
http://www.airliquide.com/safety/msds/en/129-AlEn.pdfhttp://www.cpchem/msds/specchem/isobutaneinstrumengradi.pdf

124

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

DESIGN
PROJECT II

125

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

SECTION 1

Catalytic Cracking Design

1.1 INTRODUCTION
A bed of solid particles can be fluidized by a stream of gas through it. The fluidization
of solids in a stream of gas occurs only if the gas velocity achieved a certain value
which is called minimum fluidization velocity Umf. Once the gas velocity achieved this
value, the bed expands and pressure drop across the fluidized bed remains constant
once fluidization occurred.
In this commercial fluidized-bed catalytic cracking reactor, catalysts flow up through the
reaction regeneration section in a riser type of flow regime. The over head catalyst
captured by cyclones is returned to the hopper where it is fluidized with air to recapture
any entrained hydrocarbon vapor. The catalyst was then discharged from the hopper,
down through a standpipe. The solids flow through the standpipe was controlled by
slide valve located at the base. From there, the solids went into the riser where they
are carried by stream of air to the regenerator vessel.
The regenerator operation in these plants resembled that of the reactor except for the
systems use of air instead of oil vapor. A portion of the catalyst from the regenerated
catalyst hopper was returned to the regenerator through catalyst fresh feed
exchangers. This action controlled the regenerator temperature and served to preheat
the feed. Another bypass line from the hopper to the regenerator was used to control
the dense bed level or holdup in the regenerator. Catalyst from the regenerated
catalyst hopper flowed through a standpipe back into riser where the feed was injected.
The commercial cracking catalysts used most widely is silica-alumina. High content
catalysts are characterized by higher equilibrium activity level and surface area. These

126

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

catalysts could be offered at a lower price. An advantage of this catalyst grade is that a
lesser amount of adsorbed, unconverted, heavy products on the catalyst were carried
over to the stripper zone and regenerator. As a result, a higher yield of more valuable
products and also smoother operation of the regenerator was achieved.
Basically the design of the fluidized bed system can be divided into several sections:
1. Reaction vessel which included:
Fluidized bed portion
Gas disengaging space or freeboard
Gas distributor
2. Solids feeder or flow control
3. Solids discharge
4. Dust separator for the exit gas
5. Instrumentation and control
6. Gas supply

Figure 1.1 : Illustration diagram of the reactor

127

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

1.2

Estimation of diameter of reactor

The fluidized bed diameter depends on the operating gas velocity. A larger diameter is
required for a low gas velocity while for a high gas velocity, a small diameter is
required.
However the gas velocity must exceed the terminal velocity (Ut) of the particle
transport of solid particles may occur. The operating velocity should be between
minimum fluidization velocity and terminal falling velocity to maintain fluidization of
solids.

Operating gas velocity, Uo =


Where

d p2 g ( p g )
18 g

dp = diameter of particle

= density of particle

= density of gases

= viscosity of gases
g = gravitational acceleration
so, the value of Uo =

(80 10 6 ) 2 9.81 (1282 1.484 )


18 (1.15 10 5 )

= - 0.388 m/s (rising)


= 0.388 m/s
Flowrate of gas stream , Q = 39353 kg/hr
=

39353
m3/s
1.484 3600

= 7.366 m3/s
The bed diameter will be depending on the area of reactor used:
Cross sectional area, A =
=

Q
V
7.366
0.388

= 18.985 m2

128

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Diameter of bed, D =

4A

4 18 .985

= 4.9164 m
5m
1.3

Calculation of the Transport disengagement height, TDH

According to M. Rhodes (1998), the TDH region is considered as the region where
located above the bed surface to the top of disengagement zone. While the
disengagement zone is the region above the splash zone or region just above the bed
surface in which the upward flux and suspension concentration of fine particles
decrease with increasing in height.
There are so many correlations that can be used to find the TDH value. For this
design Amitin et al. (1968) was used.

TDH ( F ) = 0.85U 0
TDH ( F ) = 7.740968

1 .2

( 7.33 1.2 log 10 U 0 )

(1.1)

8m

1.4 Minimum fluidization Velocity


The minimum fluidization velocity (Umf) is determined from Ergun equation:
For Reynolds number, 0.01 < Re < 1000:
According to the Martin Rhodes (1999), Ar =

Re =

d p2 g ( p g ) g
18 g

and

U mf D p f

129

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Ar = 150

And

(1 ) Re + 1.75

1
Re 2
3

(1.2)

By rearranging the equation (1.2) above we can get the new equation for minimum
fluidization, Umf. As a result, the equation is becomes:
Re =

U mf D p f

U mf =

g d p

(1135 .7 + 0.0408 Ar ) 0.5 33 .7

1.15 10 5
(1135 .7 + 0.0408 72 .44 ) 0.5 33 .7
6
1.484 80 10

U mf = 0.00425 m / s

1.5

Calculation for the value of terminal velocity U t

The value of Re

need to be calculated first, then the value of U t can be calculated.

The range of particle size is 65 m to 95 m. The mean particle size is 250 m.


6
When d p = 80 10 m

4 g ( p g ) gd p
C D Ret =
2
3
g

C D Re t

4 1.484 (1282 1.484 ) 9.81 80 10 6


=
2
3
1.15 10 5

C D Re t = 96.227883
2

From the chart of C D Re t and

CD
vs Reynolds number, for value of
Re t

130

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Figure 1.1 : CDRe2 and CD/Re versus Reynold number


2
C D Re t = 96.227883 the value of Re t = 3

Now from this we can calculate the value of U t , where

Re t =

3=

g U t d p
g

1.484 U t 8 10 6
1.15 10 5

U t = 0.290599 ms 1

131

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

6
when d p = 85 10 m

C D Re t

C D Re t

4 g ( p g ) gd p
=
3
2

4 1.484 (1282 1.484 ) 9.81 85 10 6


=
2
3
1.15 10 5

C D Re t = 115.421775 5

From the chart of C D Re t and

CD
vs Reynolds number from figure 1.1 for value
Re t

2
of C D Re t = 115.421775 5 the value of Re t = 3.5

Now from this we can calculate the value of U t , where

Re t =

3=

g U t d p
g

5.54 U t 85 10 6
5.0 10 5

U t = 0.3190899 ms 1

Table 1.1 : Calculation for terminal velocity in different size of dp.

132

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Sieve

Weight,

Weight

size dp,

%, xi

fraction,

3.5
7.5
24
44
9.5
7
4.5

xi
0.035
0.075
0.24
0.44
0.095
0.07
0.045

m
0.000095
0.00009
0.000085
0.00008
0.000075
0.00007
0.000065

1.6

CDReT2
161.1394175
137.0119672
115.4217755
96.22788368
79.28933286
64.46516426
51.61441905

Reynold

Terminal

number
4.5
4
3.5
3
2.5
2
1.8

velocity, Vt
0.367073344
0.344414495
0.3190899
0.29059973
0.258310872
0.221409318
0.214596724

Find the value of K i*

Using the correlation for estimating entrainment rates are reported in the literature. The
entrainment rate can be expressed by the following equation, as follows:
Ei = Ei + (Eio -Ei)exp (-afh)

( 1.3)

Where Ei = entrainment rate at a point h above bed surface


af = a constant in freeboard
Ei = rate of elutriation of the fines with diameter dpi above the TDH
Ei = K i Xi

(1.4)

Where Ki is the elutriation rate constant for which numerous correlations have
been reported. Table 2.2 from Appendix lists various published correlations
for the elutriation rate constant.
The constant, af, in equation (1.2) is independent of the beds composition and can be
evaluated from experimental data for Fi as a function of h. Following Chen et al. (1979),
is the entrainment rate of particles at the bed surface, where:
Eio = KoXi

(1.5)

Where Ko = Elutriation rate constant at bed surface


Xi = weight fraction of the particle cut size dpiA

1.7

Find the value of Eo

133

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.07 10 9 g
Eo
=
Ad eqmt
2 .5

Eo =

3.5

g 0 .5

(U U )

2..5

mf

3.07 10 9 (1.484 ) 3.5 (9.81) 0.5 ( 0.388 0.00425416 7 )


(1.15 10 5 ) 2..5

2.5

(18 .98 )( 5)

Eo = 10.676 kg/m2s
The following correlation is used to calculate the value of E i* by using three different
investigators which is :
Merrick and Highley (1974)
0.5

E i
v U mf
= A +130 exp 10 .4 t
g U

U
U U mf

0.25

Geldart et al. (1979) revised

E i
v

= 23 .7 exp 5.4 t
gU
U

and Colakyan et al (1979)

E i

= 331 t
U

From this correlation we find that the average of the correlation for these three
investigators, shown in the table below:

134

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Table 1.2 : Correlation of three investigators


Merrick and Highley

Geldart et al.

(1974)
Ki*
2.810456563
3.115064954
3.509080841
4.035580234
4.76909596
5.849694145
6.085514067

(1981)
Ki*
0.008247282
0.011304929
0.016081902
0.023907858
0.037471784
0.062625124
0.068853496

Colakyan (1979)
Ki*
10.27741771
8.238989106
6.227114828
4.299839595
2.545780992
1.100824216
0.8993437

1.8

Ki*, average
4.36537385
3.788452996
3.25075919
2.786442562
2.450782912
2.337714495
2.351237088

Calculation of solid loading

First find the value of Kih ,


K ih = K i* + ( E o K i* ) exp( a i h)
= 4.36537385
= 4.36537385

+ (10.676996 53 - 4.36537385

)(2.69398E

- 12)

kg/m 2 s

R = Ri = RmRi

m Bi =

Fm Fi
( F R ) + K i A

135

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

m Bi =

10 .93 0.035
(10 .93 R ) + 4.36537385

18 .98

10 .93 0.075
(10 .93 R ) + 3.78845299 6 18 .98

10 .93 0.024
(10 .93 R ) + 3.25075919

10 .93 0.0095
10 .93 0.07
+
(10 .93 R ) + 2.45078291 2 18 .98 (10 .93 R ) + 2.33771449 5 18 .98

10 .93 0.0045
(10 .93 R ) + 2.35123708 8 18 .98

18 .98

10 .93 0.044
(10 .93 R ) + 2.78644256 2 18 .98

So the value of Rih calculated by excel is = 0.564147556 kg/s

Eih =

RT
A
0.5641475
=
18.98
= 0.0297 kg / m 2 s

Rti = Kih* A

= 4.36537385

1 8.98

2.78644256

2 1 8.98

2.35123708

8 1 8.98

+ 3.78845299
+ 2.45078291

6 1 8.98
2 1 8.98

+ 3.25075919
+ 2.33771449

1 8.98

5 1 8.98

= 404.8578835 kg/s
Ri = Kih A. Xi
= 4.36537385
2.78644256
2.35123708
= 55.90386

18.98 0.035
+ 3.78845299
6 18.98 0.075
+ 3.25075919
18.98
2 18 .98 0.44
+2.45078291
2 18.98 0.095
+ 2.33771449
5 18.98 0
8 18.98 0.045
kg/s

136

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Table 1.3 : Data calculation to find solid loading

Total

Mbi
0.004103705
0.009964059
0.03640034
0.076031739
0.018254549
0.013978087
0.008943974
0.167676452

MRi
0.602699773
1.269994045
3.981014237
7.127685256
1.505148839
1.099367014
0.707506537
16.2934157

Ki*
4.36537385
3.788452996
3.25075919
2.786442562
2.450782912
2.337714495
2.351237088

Rti
82.85479568
71.90483787
61.69940943
52.88667983
46.51585967
44.36982112
44.62647993

Ri
2.899918
5.392863
14.80786
23.27014
4.419007
3.105887
2.008192
55.90386

a) Solid loading unreturned = 0.029723 / 0.388


= 0.076606351kg/s
b) solid loading return =
=

55.90386 / 18.98
2.94540903 kg/s

1.9 Calculation of holding time and residence time


The outlet concentration of a plug flow reactor is related to the inlet concentration of the
reactant by the same equation as in a batch reactor with the same residence time -.
For an equilibrium reaction between A and B, is first order.
Based on studied of Khabtou, S., Chevreau, T., and Lavalley, J.C., Micropor. Mat. 3,
133 (1994), express the rate per catalyst mass instead of reactor volume.

k mA =
=

1
0.75
0.35

ln 1 0.35
151 .92 0.75 +1
0.75

4.785 10 3 m 3 kg

hr

where x is the conversion in this process,

x = ([A] 0 - [A]) / [A]0 = 0.35,

137

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

[A] is experssed in concentration in mol/m3, K the rate mol m-3 s-1, kA in s-1.
The value K = [i-C4=]eq/[i-C4]eq = 0.75 and ST = 151.94 g.hr/m3 based on study by
Yamamoto, S. Asaoka, et al (1997).
Then from below equation given, w can find :
k = (1 A ) ln

1
A X A
1 X A

1
0.41(065 )
1 0.65

= (1 0.41 ) ln

= 2256.48/ 4.785x10-3

= 417574.39 hr

= 115.99 s

when the total holding time are calculate then the weight of the bed of fluidized bed can
be calculated. The formula used is as below:

t=

W Bed
FB 0

WBed
830
=
3600
39353
W Bed = 95679.7761 7 kg

1.10

Calculation for the pressure drop PB

The equation that can be used to calculate the pressure drop across the bed is:

138

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

g
W Bed W Bed
p

( p ) =
A

( p ) =

( 95679.78

1.484
9.81 ) ( 95679.78 9.81 )

1282
18 .985

( p ) = 49382 .78 Pa

49 .383 kPa

According to Kunii and Levenspield, the pressure drop across the distributor p d is

10% from the value of pressure drop across the bed when fluidized PB . So the value
of p d is:

( p d ) = 10 %( p B )
( p d ) = 10 % (49 .382 kPa )
( Pd ) = 4.938 kPa

0.5035 kgm 2

According to Kunii and Levenspield (1991), to determine the number of holes in the
distributor the Re

need to be calculated first:

Re t =

g U 0 Dt
g

Re t =

1.484 0.388 5.0


1.15 10 5

Re t = 250344

1.11

Determine the direction and flow rate of gas passing between the vessels.

139

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Assuming that in fluidized flow the apparent weight of the solids will be supported by
the gas flow, the equation below gives the pressure gradient for fluidized bed flow:

( P ) = (1 ) ( ) g
p
g
H

( P )

= (1 0.42 ) (1282 1.484 ) 9.81

= 7411.499

Pa / m

Actual pressure gradient =

( 3.25 2.89 ) 10 5
10

= 3600 Pa / m

Since the actual pressure gradient is well below that for fluidized flow, the standpipe is
operating in packed bed flow.
The pressure gradient in packed bed flow is generated by the upward flow of gas
through the solids in the standpipe. The Ergun equation above provides the
relationship between gas flow and pressure gradient in packed bed.
Knowing the required pressure gradient, the packed bed voidage and the particle and
gas properties, equation below can solve for IUrelI, the magnitude of the relative gas
velocity:

( P )
H

2
f (1 )

(1 )
2
= 150 2
!
U
!
+
1
.
75

!U rel !
rel
2
x sv
x sv

For standpipes it is to take downward velocities as positive. In order to create the


pressure gradient in the required direction, the gas must flow upwards relative to the
solids. Hence, IUrelI is negative:
IUrelI = -0.291 m/s

140

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

From the continuity for the solid,

Solid flux, =

Gp
A

= U p (1 ) p

The solid flux calculated is 55.9 kg/m2s as and so


Up =

55 .9
(1 0.41 ) 1282

= 0.072715 m /s

Solids flow is downward, so Up = + 0.072715 m/s


The relative velocity, Urel = Uf - Up
Hence, actual gas velocity, Uf = - 0.291 + 0.072715
= - 0.21829 m/s (upwards)

Therefore the gas flows upwards at a velocity of 0.21829 m/s relative to the standpipe
walls. The superficial gas velocity is therefore :
U = Uf = -0.0895 m/s (upward )
From the continuity for the gas, mass flow rate of gas,
Mf = U f p A
= -0.10431 kg/s
So, for the standpipe operate as required, 0.10431 kg/s of gas must flow from the lower
vessel to the upper vessel.

1.12

Design of cyclone

Size a cyclone separator for removing particles above 80 m in diameter entrained in a


flue gas stream. The following information is supplied:

141

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

0.21

0.66
dp =
0.00008 m
gas volumetric flow =
1.8 m3/s
particle density =
1282 kg/m3
gas density =
1.484 kg/m3
viscosity gas = 0.0000115 Ns/m
kinematic viscosity v = 0.0000278 m2/s
inlet gas velocity =
0.388 m/s
specific wall thickness
=
5 mm
The particles are approximately round with a shape factor of 0.77
All dimensions of a cyclone of any design are selected depending on the width of inlet
duct b or on the diameter of cyclone Dc. The problem is to properly select one of these
dimensions from which the other dimensions are proportionally evaluated.
The cyclone diameter, settling velocity, gas velocity, and parameters of the suspension
to be separated are all interrelated parameters. Therefore, we select a preliminary
diameter for approximate calculations and then refine our estimate to a more exact
design.
According Nicholas P. Cheremisinoff at al. (1984), the relative dimensions of the
cyclone are specified as:
b = DC

and

hin = DC

For the chosen cyclone = 0.21 and = 0.66


The continuity equation for the inlet nozzle is:

bh =

Vsec
Win

(1.5)

142

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

where win is the inlet gas velocity; which for a primary cyclone operation is typically 18
to 22 m/s. Expressing b and hin in terms of diameter DC, equation above is rearranged
to solve for the cyclone diameter:

Vsec
DC =
w
in

0.5

0.5

1.8

0.21 0.66 18
= 0.85 m

For design purposes, assume a value of 0.9 m for DC.


The diameter of the discharge pipe is:
Dd = 0.58Dc = 0.58 x 0.9 = 0.52 m
The gas velocity in discharge pipe is thus:

Wd =

4 Vsec
4 1.8
=
2
Dd
3.142 0.52 2

= 8.5m / s

Specifying a wall thickness = 5 mm for the gas discharge pipe, its outside diameter
will be:
Dd ,out

Dd + 2

= 0.52 + 2(0.005 )

= 0.53 m

The width of the circular gap between the pipe and cyclone shell is:

Dc Dd ,out

2
2

= 0.45 0.265

= 0.185 m

The height of the circular gap from a spiral surface to the lower edge of discharge pipe
is:
H = 0.775 Dc = 0.775 X 0.9

= 0.7 m

The calculated dimensions of the cyclone can be checked by comparing the particle
settling time:

143

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

0 =

Rc Rd ,out
wo

wo

to the residence time of gas in the cyclone:

2 Rav n
wg

where Rc and Rd,out are the radii of the cyclone and discharge pipe, respectively; n =
number of gas rotations around the discharge pipe (we may assume n = 1.5)
The peripheral velocity of gas is:
wg =

Vsec
=
H

1 .8
0.7 0.185

= 13 .9 m / s

For this cyclone, this value must be in the range of 12 to 14 m/s


The average radius of the gas rotation is :

Rav =

Dd ,out

0.53 0.185
+
2
2

= 0.357 m

The centrifugal acceleration (at the average radius) is:

a=

w g2
Rav

13.9
= 542 m / s 2
0.357

The separation criterion is:


Ks

a
g

542
9.81

= 55 .2

In this case, the centrifugal field in the cyclone is 55.2 times more intensive than the
gravitational.
The Archimedes number is:

144

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

g d 3 p g

Ar =
g
2

9.81 (80 10 5 ) 3 (1282 1.484 ) 1.484


=
(1.15 10 5 ) 2
= 77.44
The settling number is:
S1 = Ar x 1 x

Ks = 72.44 x

55.08843

= 3999
Because

3.6 < S1 < 82,500 the flow regime through the cyclone is transitional.

Therefore, the theoretical velocity of the particles is:

f 2
w = 0.22 d

0.333

f 2
= 0.22 d

0.333

5.42 10 2 1282
= 0.22 10 10 5

1.15 10

4.638 m / s

The particles have a shape factor of = 0.77 and the gas inlet gas stream contains a
low volume of solid particles. Based on the operating conditions specified, the settling
velocity is
Ws = R w = 0.77 x 4.634 = 3.568 m/s

Because the concentration of the suspension is low, we may assume R = 1

145

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

The settling time is therefore:

0 =

= 0.0518s

The residence time for the gas is:

2Ravg n
wg

2 3.142 0.357 1.5


= 0.2424 s
13 .9

Since 0 <

the diameter of the cyclone selected is acceptable and we may now

specify the other dimensions as based on the recommended proportions.


As a final calculation for the design, we evaluate the hydraulic resistance of the
cyclone:
P=

1
C D win2 Where CD is the typical number of cyclone.
2

= 0.5 x 1 x 1.484 x 182


= 240.4 N/m2

1.13

Calculation for mechanical design

For mechanical design, the temperature and pressure are imperative properties in
calculate the thickness and the stress of the material. For that reason, the safety factor
also required as safeguard and determined by certain consideration such as corrosion
factor, location and process characteristic.
From Hysys data, the operating temperature inlet into the reactor is 250oC and
regenerator is 180oC. The design temperature is related to the operating temperature.
The design pressure and temperature for this reactor are showed as follow:
Reactor
1. Design Pressure
Operating pressure

2.89 bar

0.289 N/mm2

146

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

For safety reason take pressure 10% above operating pressure


Design Pressure, Pi
Design Temp. , T

0.289 N/mm2x 1.1

0.3179 N/mm2

200C

2. Material Construction

The material used is stainless steel (18Cr/8Ni, 304). For this material, the design stress
at 200 C, R.K.Sinnot (1999).
Design stress, f

115 N/mm2

Diameter vessel, Di

5.0 m

Tensile strength,

510 N/mm2

3. Vessel Thickness
e

Pi Di
2 jf Pi

(0.3179 )( 5000 )
2(1)(115 ) (0.3179 )

7 mm + 4 mm

11 mm

From R.K.Sinnot (1999), this value should not be less than 12 mm (including 2 mm of
corrosion allowance). For vessel diameter around 5 m, this take e = 15 mm. A much
thicker wall will be needed at the column base to withstand the wind and dead weight
loads.

4.

Heads and Closure

This section covers the choice of closure to be used in the design. Basically there are
two types of ends, which are domed ends. A standard torispherical heads and
ellipsoidal heads as well as the flat heads are calculated in order to select the most
economical head regarding its thickness. All the calculation is referring to the R.K.
Sinnot, Coulson and Richardson Vol.6 page 815-817.
Take, crown radius, Rc

= Di

= 5.0 m

147

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Knuckle radius, Rk

= 6% Rc

= 0.03 m

A head of this size would be form by pressing: no joints, so J = 1.0

Cs

1
3+
4

Rc
Rk

1
3 +
4

5 .0

0 .3

= 1.77
Therefore, minimum thickness:

=
=

Pi Di
2 Jf Pi ( Cs 0.2)

( 0.3179 )( 5000 )
2(1)(115 ) 0.3179 (1.77 0.2 )

= 11 mm
5.

Column Weight

Dead weight of vessel, Wv


For a steel vessel,
Wv

240 Cv Dm (Hv + 0.8Dm) t

mean diameter, m

(Di + t)

Cv

a factor, take 1.15

Hv

height or length between tangent lines, m

wall thickness, m

Where,
Dm

148

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

To get a rough estimate of the weight of this vessel is by using the average thickness,
11mm
Therefore,
Dm

5 + 2 x 0.011

5.022 m

240 (1.15) (5.022) [7.6 + 0.8(5.022)] 0.011

177.13 N

0.17713 kN

So,
Wv

Weight of insulation, WI
Assume material is Mineral wool.
of Mineral wool

thickness

75 mm

130 kg/m3

Volume of insulation
=

(5.022) (7.622) (0.075)

9.018967m3

x Dm x Hv x thickness of insulation

Weight of insulation, WI
=

Volume of insulation x x g

9.018967 x 130 x 9.81

11501.89N

11.50189kN

Double this value to allow fittings, so weight of insulation will be = 23.004 kN


Weight of bed

149

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Weight of bed in reactor


WB

= 95679.78 x 9.81
= 938618.6 N
= 938.6186 kN

Weight of cyclone
Volume of cyclone in reactor = 2.438 m3
Weight of cylone = 2.438 x 9.81 x 1282
= 30661.31 N
= 30.661 kN
There fore,
Total weight

= Wv +WI +WB + Wc
= (177.1311 + 23003.78 + 938618.6 + 30661.31)N
= 992.461 kN

For Regenerator
1.

Design Pressure
Operating pressure

2.6 bar

0.26 N/mm2

For safety reason take pressure 10% above operating pressure


Design Pressure, Pi
Design Temp. , T
2.

0.26 N/mm2x 1.1

0.286 N/mm2

180C

Material Construction

The material used is stainless steel (18Cr/8Ni, 304). For this material, the design stress
at 200 C, R.K.Sinnot (1999).
Design stress, f

121 N/mm2

Diameter vessel, Di

6.5 m

150

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Tensile strength,
3.
e

510 N/mm2

Vessel Thickness
=

Pi Di
2 f Pi

(0.286 )( 6500 )
2(1)(121 ) (0.286 )

8 mm + 4 mm

12 mm

Heads and Closure

This section covers the choice of closure to be used in the design. Basically there are
two types of ends, which are domed ends. A standard torispherical heads and
ellipsoidal heads as well as the flat heads are calculated in order to select the most
economical head regarding its thickness. All the calculation is by referring to the R.K.
Sinnot, Coulson and Richardson Vol.6 page 815-817
Take, crown radius, Rc

= Di

= 6.5 m

Knuckle radius, Rk

= 6% Rc

= 0.39 m

A head of this size would be form by pressing: no joints, so J = 1.0

Cs

1
3+
4

Rc
Rk

1
3 +
4

6.5
0.39

= 1.77

Therefore, minimum thickness:

Pi Di
2 Jf Pi ( Cs 0.2)

151

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

( 0.286 )( 5000 )
2(1)(121 ) 0.286 (1.77 0.2 )

= 14 mm

5.

Column Weight

Dead weight of vessel, Wv


For a steel vessel,
Wv

240 Cv Dm (Hv + 0.8Dm) t

mean diameter, m

(Di + t)

Cv

a factor, take 1.15

Hv

height or length between tangent lines, m

wall thickness, m

Where,
Dm

To get a rough estimate of the weight of this vessel is by using the average thickness,
12 mm
Therefore,
Dm

6.5 + 2 x 0.012

6.524 m

240 (1.15) (6.524) [8 + 0.8(6.524)] 0.012

285.6337 N

0.2856 kN

So,
Wv

Weight of insulation, WI
Assume material is Mineral wool.
of Mineral wool

130 kg/m3

152

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

thickness

75 mm

Volume of insulation
=

(6.524) (8) (0.075)

12.29745 m3

x Dm x Hv x thickness of insulation

Weight of insulation, WI
=

Volume of insulation x x g

12.29745 x 130 x 9.81

15682.94N

15.68294kN

Double this value to allow fittings, so weight of insulation will be = 31.36588kN


Weight of bed
Weight of bed in reactor
WB

= 75060.19 x 9.81
= 736340.5 N
= 736.3405 kN

Weight of cyclone
Volume of cyclone in reactor = 2.438 m3
Weight of cylone = 2.438 x 9.81 x 1282
= 30661.31 N
= 30.661 kN
There fore,
Total weight

= Wv +WI +WB + Wc
= 0.2856 + 31.36588 + 736.3405 + 30.661
= 798.652 kN

153

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Total weight for reactor and regenerator = 992.461 + 798.652 kN


= 1791.113 kN
6.

Wind Loads

Take,
Win speed, Uw =

160 km/hr

For a smooth cylindrical column stack, the following semi-empirical equation can be
used to estimate wind pressure.
Pw

0.05Uw2

0.05(160)2

1280 N/m2

Loading per Unit Length of column, Fw


Fw

Pw Deff]

Where,
Deff

= Effective column diameter


= Diameter + 2(tshell + tinsulation )
= 6.5 + 2(12 + 75 ) x 10-3
= 6.68 m

Therefore,
Fw

1280 x 6.68

8550.4 N/m

Bending Moment

Mx

Fw ( X ) 2
2

154

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Where,
X

= Distance measure from the free end


=8m

Therefore,
Mx

7.

8550 .4 (18 ) 2
2

1385164.8 Nm

1385.1648 kNm

Analysis of Stress

From bottom tangent line,


Longitudinal pressure stress,

Pi Deff
2t

(0.286 )( 6680 )
2(12 )

79.6033N/mm2

Circumferential pressure stress,

Pi Deff
4t

(0.286 )( 6680 )
4(12 )

39.802 N/mm2

Dead weight stress,

( Di + t )t

155

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

1791 .113 10 3
(6500 +12 )12

7.2958 N/mm2

Bending Stress,

M Di

+ t

Iv 2

where,
M

= total bending moment

Iv

Iv

= second moment of area

64

(D

Di

which,
Di

= 6500 mm

Do

= (6500+ 2(12))
= 6524 mm

so,
Iv

(6524
64

1.3013 x 1012 mm4

6500 4 )

Therefore,

1385164 .8 1000 6500

+ 12

12
1.3013 10
2

3.47 N/mm2

The resulted longitudinal stress, z is:

z(upwind)

39.802 - 7.2958 + 3.47

35.9762 N/mm2

156

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

z(downwind)

39.802 - 7.2958 - 3.47

29.0363 N/mm2

=
8. Elastic Stability
Critical bulking stress

t
= 2 x 104
D
m

12

= 2 x 104
6512
= 36.855 N/mm2
Maximum compressive stress will occurs when the vessel not under pressure
=

= 7.2958 + 3.472
= 10.768 N/mm2
This is below critical bulking stress, so acceptable.
9. Vessel Support Design (Skirt Design)
Type of support

: Straight cylindrical skirt

: 80

Material construction : Carbon steel


Design stress, fs

: 135 N/mm2 at ambient temperature, 20C

Skirt height

: 4.0 m

Young modulus

: 200, 000 N/mm2

Therefore,
The total weight of vessel from calculation before = 1791.113 kN
Wind load,
Fw

= 8550.4 N/m
= 8.5504 kN/m

157

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Bending moment at skirt base,

Ms

( H v + H skirt ) 2
= Fw

(18 + 2 ) 2
= 8.5504

= 1710.08 kNm
As a first trial, take skirt thickness as same as the thickness of the bottom section of
the vessel, ts = 12 mm
Bending stresses in skirt,

bs

4 Ms
[ ( Ds + ts )ts Ds ]

Where,
Ms

= maximum bending moment (at the base of the skirt)

ts

= skirt thickness

Ds

= inside diameter of the skirt base


= 3.0 m

Therefore,

bs

4(1710 .08 )(1000 )(1000 )


[ ( 6500 +12 ) (12 )( 6500 )]

= 4.287 N/mm2
Dead weight stress in the skirt,

ws

2W
[ ( D s + t s ) t s ]

Where,

158

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

= Total weight of the vessel and content


= 1791.113 kN

Therefore,

(test)

ws

2 1791 .113 1000


[( 6.5 + 0.012 ) (0.012 )]

= 14591753.05 N/m2
= 14.592 N/mm2

bs,

(operating)

1791 .113 1000

[( 6.5 + 0.012 ) (0.012 )]

= 7295876.525 N/m2
= 7.2958 N/mm2

Thus, the resulting stress in the skirt,


Maximum s (compressive) =

ws

(test) +

bs

= 14.592 + 4.287
= 18.879 N/mm2
Maximum s (tensile)

bs

ws

(operating)

= 4.287 - 7.2958
= 0.0323 N/mm2

10.

General consideration for design

Take the joint factor J as 0.85,

159

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

s (tensile)

< fs J sin s

s (compressive)

< 0.125 E

ts
sin s
Ds

Where ,
fs

= maximum allowable design stress for the skirt material


= 135 N/mm2

= weld joint factor

= base angle of a conical skirt

= modulus young = 200, 000 N/mm2

Therefore,
s (tensile)

< 135 x 0.85 sin 80

0.1892 N/mm2

< 113.007 N/mm2

s (compressive)

< (0.125)(200,000)

0.4014 N/mm2

< .1214.473 N/mm2

148
sin 80
3000

Both criteria are satisfied, add 2 mm for corrosion, give design thickness of 150 mm

11.

Base Rings and Anchor Bolts

Assume pitch circle diameter

= 5.0 m

Circumference of bolt circle

= 5000

Bolt stress design, fb

= 125 N/ mm2

Recommended spacing between bolts

= 600 mm

160

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Minimum number bolt required, Nb

5000
600

= 26.18
Closest multiple of 4

= 28

Bending moment at base skirt, Ms

= 212.101 kNm

Total weight of vessel, W

= 236.7534 kN

Area of bolt,

Ab

4M s

W
N b f b Db

1
4( 212 .101 )(1000 )

(184 .046 )(1000 )

28 (125 )
3. 0

E.1.19

= 28.22 mm2
bolt root diameter,

28 .22 4

= 6 mm
Total compressive load on the base ring per unit length,

Fb

4M s

Ds

Ds

4 (212 .101 ) 1000


236 .7534 1000
+
=

2
(3)
(3.0)

= 55.12 kN/m

Assuming that a pressure of 4 N/mm2 is one of the concrete foundation pad, fc


Minimum width of the base ring,

Lb

Fb
1
3
fc
10

161

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

55 .12 10 3
4 10 3

= 13.78 mm

12.

Feed Nozzle Sizing

Optimum duct diameter,


dopt,t

= 293G0.53

-0.37

Where,
G

= flow rate

= 1.32121 x 105kg/hr
= 36.7 kg/s

= density

= 30.698 kg/ m3

Therefore,
Dopt

= 293 (36.7)0.53 (30.698)-0.37


= 500 mm

Nozzle thickness,

Ps d opt
20 + Ps

Where,
Ps

= Operating pressure

= 2.74945 N/mm2

= Design stress at working temperature

= 30 N/mm2

Therefore

162

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

( 2.74945 )(118 )
20 (30 ) + 2.74945

= 0.2 mm
So, thickness of nozzle

= corrosion allowance + 0.2 mm


= 4 + 0.2 mm
= 4.2 mm
5 mm

13.

Top Product Nozzle Sizing

Optimum duct diameter,


dopt,t

= 260G0.52

-0.37

Where,
G

= flowrate

= 223938.68 kg/hr
= 62.205 kg/s

= density

= 56.69 kg/m3

Therefore,
dopt

= 226(62.205)0.50 (56.69)-0.35
= 500 mm

Nozzle thickness,

Ps d opt
20 + Ps

163

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Where
Ps

= Operating pressure

= 2.74945 N/mm2

= Design stress at working temperature

= 30 N/mm2

Therefore

( 2.74945 )(1000 )
20 (30 ) + 2.74945

= 2 mm
So, thickness of nozzle

= corrosion allowance +2 mm
=4 +2
= 6 mm
6 mm

Table 1.4 : Summary of the Mechanical Design


Design Pressure
Reactor Operating Pressure

2.89 bar

Reactor Operating Temperature

160

Reactor Design Pressure

3.179 bar

164

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Reactor Design Temperature

200

Regenerator Operating Pressure

2.6 bar

Regenerator Operating Temperature

150

Regenerator Design Pressure

2.86 bar

Regenerator Design Temperature

180

Safety Factor

0.10

Design of Domed Ends


Types

Torispherical head

Crown Radius
Knuckle Radius
Joint Factor
Stress Concentration Factor
Minimum Thickness
Corrosion Allowance
Column Weight
Dead Weight of Vessel
Weight of Bed
Weight of cyclone
Weight of Insulation
Total Weight reactor and regenerator
Wind Pressure
Loading
Bending Moment

6.5
0.039
1
1.77
14
4
389
736.34
30.66
31.366
1791.11
1280
8550.4
1385.1648

m
m
mm
mm
kN
kN
kN
kN
kN
N/m2
N/m
kNm

REFERENCES

Cheremisinoff, Nicholas P., 1984, Hydrodynamics of Gas-Solids Fluidization, 279 - 231


Amitin et al. 1985, The Hydrodynamic of Fluidization, Powder Technology,(42):

67-78

Geldart, D ,. et al., 1979, Transition Institute Chemical Engineers, 57-269.


Dolignier J. C, Marty E., Martin G. & Delfosse L., 1998, Modelling of gaseous pollutants
emission in circulating fluidized bed of municipal refuse. Elsevier Science
Ltd(77): 1399-1409
Gregory et al, 1985, The design of distributor for gas-fluidized bed, Powder
Technology. (42): 100-145

165

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Horio et al. 1980, The Hydrodynamic of Fluidization, Powder Technology,(42):


67-78
Sinclair, J.L. and R. Jackson, Gas-Particle Flow in a Vertical Pipe with Particle-Particle
Interactions, AIChE J., 35, 1473-1486 (1989)
Sinclair, J.L., Hydrodynamic Modeling, in Circulating Fluidized Beds, ed. Grace,
J.R., Avidan, A.A. and T. M. Knowlton, Chapman and Hall, Great Britain (1997)
Wang, Z., D. Bai and Y. Jin, "Hydrodynamics of Concurrent Downflow Circulating
Fluidized Bed (CDCFB)", Powder Technology, 70, 271-275 (1992)
Wei, F., Wang, Z., Jin, Y., Yu, Z. and W. Chen, Dispersion of Lateral and Axial Solids
in a Cocurrent Downflow Circulating Fluidized Bed, Powder Technology, 81, 2530 (1994)
Himmelblau M. D. 1996, Basic Principles and calculation in Chemical Engineering.
Sixth edition. United States of America: Prentice Hall International, Inc.
Levinspiel O. 1999. Chemical reaction engineering. Third edition. United States of
America: John Wiley & Sons.
Rhodes, M. 1998. Introduction to particle technology. Chichester England. John Wiley
& Sons 97-130.
Sinnot, R.K. 1999.Chemical engineering volume 6. Third edition. Great Britain:
Butterworth-Heinemann.
Zhang H, Hydrodynamics of a Gas-Solids Downflow Fluidized Bed Reactor, Ph.D.
thesis, The University of Western Ontario (1999)
Zhang, H., Zhu, J-X., Hydrodynamics in Downflow Fluidized Beds (2): Particle Velocity
and Solids Flux Profiles, Chemical Engineering Science, 55, 4367-4377 (2000)
Matsen, J. M. "Some Characteristics of Large Solids Circulation Systems". In
Fluidization Technology, Keairns, D. L., Ed.; Hemisphere: New York, Vol. 2,
Chapter1 (1976)

166

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Ouyang, S. Potter, S.E., Consistency of Circulating Fluidized Bed Experimental Data,


Ind. Eng. Chem. Res., 32, 1041-1045 (1993)
Wei, F., R. Xing, Z. Rujin, L. Guohua, J. Yong, A Dispersion Model for Fluid Catalytic
Cracking Riser and Downer Reactors, Ind. Eng. Chem. Res., 36, 5049-5053
(1997)
Yang Y.L., Y. Jin, Z.Q. Yu, Wang, Z.W., Investigation on Slip Velocity Distribution in
the Riser of Dilute Circulating Fluidized Bed, Powder Tech., 73, 67-73 (1992)
http://thor.tech.chemie.tu_muenchen.de/~tc2/eng/teaching/industr_chem_process/crac
king%20lecture%201.pdf
http://www.refiningonline.com/EngelhardKB/npra/NPR8851.htm
http://iglesia.cchem.berkeley.edu/ChemicalCommunications_1764_2003.pdf
http://www.caer.uky.edu/energeia/PDF/vol10-3.pdf
http://www.netl.doe.gov/publications/proceedings/96/96ps/ps_pdf/96ps3_2.pdf
http://tetra.mech.ubc.ca/CFD03/papers/paper29AF3.pdf
http://www.netl.doe.gov/products/r&d/annual_reports/2001/stpt/cfb%20operating
%20regimes%20cork.pdf
http://www.flotu.org/~weifei/twophase-ces.pdf
http://www.gtchouston.com/articles/GTC%20online%20reprint%2011-99.pdf

167

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

SECTION 2

MULTITUBULAR FIXED BED REACTOR

2.1

CHEMICAL DESIGN

2.1.1 INTRODUCTION

168

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Fixed bed reactors are the most important type of the reactor for the synthesis of large
scale basic chemicals and intermediates. In these reactors, the reaction takes place in
the form a heterogeneous catalyst. In addition to the synthesis of valuable chemicals,
fixed bed reactors have been increasingly used in recent years to treat harmful and
toxic substances. The most common arrangement is the multi tubular fixed bed reactor,
in which the catalyst is arranged in the tubes, and the heat carrier circulates externally
around the tubes. Fixed bed reactor for industrial synthesis are generally operated in a
stationary mode under constant operating conditions over prolonged production runs,
and design therefore concentrates on achieving an optimum stationary operation.
However, the non stationary dynamic operation mode is also great importance for
industrial operation control.

CATALYST FORM FOR FIXED BED REACTOR


The heart of fixed bed reactor and the site of the chemical reaction is the catalyst. The
processes taking place on the catalyst may formally be subdivided into the following
separate steps:
1. Mass transfer of reactants from the main body of the fluid to the gross exterior
surface of the catalyst particle.
2. Molecular diffusion /Knudsen flow of reactants from the exterior surface of the
catalyst particle into the interior pore structure.
3. Chemisorption of at least of the reactants on the catalyst surface.
4. Reaction of the surface
5. Desorption of absorbed species from the surface of the catalyst.
6. Transfer of products from the interior catalyst pores to the gross exterior
surface of the catalyst by ordinary molecular diffusion/Knudsen flow.
7. Mass transfer of products from the exterior surface3 of the particle into the bulk
of the fluid.

169

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

For industrial use, a particle size is a compromise between the speed of the exchange
reaction (which is greater with small beds) and high flow rates (which require coarse
particles to minimize the head loss). Standard resins contain particle with diameter
from 0.3 to 1.2 mm, but coarser or finer grades are available. For the MTBE production
process, the fine sulphonic ion exchange resin particles with its size less than 1.0 mm
have to be enveloped in various conceivable shapes
The catalyst properties are as below:
Shape of Catalyst

Spheres

Diameter of catalyst (dc)

0.6 mm (ref: Jon J.Ketta)

Effective Diameter surface dp

0.5mm

Bulk Density of Catalyst (b)

810 kg/m3

Specific Solid Sphere surface

34.25 m2/g
(ref:PerrysHandbook,pg 16.10)

2.1.2

Voidage (b)

0.32 (ref:Tech Info.Buletin)

Surface Area (Sa)

45 m2/g

Specific Surface

0.034 m2/g

Specific Gravity

in range 1 to 1.4

Internal Void Fraction (p)

0.54

Molecular Weight

98 g/mole

PARTICLES SOLID DENSITY

Particle solid density (p) can be obtained from the equation below (ref: Particle
Technologys book):

b
1-b

810
1 - 0.32

1191.2

kg/m3

170

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

2.1.3

VOID VOLUME OF CATALYST

Void volume of catalyst, Vg can be determined as below:


Vg

2.1.5

p
p

0.32
1191.2

0.268 cm3/g

(2.1)

PORE RADIUS OF CATALYST

Pore radius of particle, r is the determined,


r

2.1.6

2. Vg
Sa

2 * 0.268
45 x 104

1.194 x10-5 m

(2.2)

KNUDSEN DIFFUSIVITY

Knudsen Diffusivity is given by the equation below:


Dk
where M
T

Dk

9.7 x103 r (T)1/2


(M)

molecular weight of the catalyst

98 g/mole

operating temperature

393 K

9.7 * 103 * 1.194 *10-5 *( 393)1/2

(2.3)

171

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

98
=

0.013 cm2/ s

The effectiveness factor is given in term of Thiele Modulus as:

2.1.7

3 ( - 1)
2 tan h

(ref: Jon J.Mc Ketta)


(2.4)

0.928 where = 1.1 (ref: Perry,s Handbook)

REACTION RATE

The synthesis of MTBE from methanol and isobutylene catalyzed by Amberlyst-15


or similar sulphonic ion exchange resin catalyst is a reversible etherification as shown
in equation 1:
iC4H8 (isobutene) + CH3OH (methanol)

C5H12O (MTBE)
k1

CH3C(CH3)=CH2(B) + CH3OH

CH3C(CH3)2OCH3 (M)
K2

Reaction kinetics:
According to Yang et al, the forward reaction of reaction above is first order with
respect to the isobutylene concentration and zero order with respect to the methanol
concentration, respectively, and the reverse reaction is first order with respect to the
MTBE concentration as shown below:
Table 1:

Arhenius parameters of rate constant K1 and K2 for MTBE

synthesis catalyzed by Sulphonic ion exchange acidic resin catalyst. (Ref: Chem. Eng.
Journal)

172

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

A1

A2

E1(J/mole)

E2(J/mole)

6.50E+05

1.36E+08

4.74E+04

7.04E+04

-rB = k1CB k2CM


where: k1 = A1 exp (-E1/RT) & k2 = A2 exp (-E2/RT)
k1 = A1 exp (-E1/RT)

(2.5)

= 6.5 * 105 exp (-4.74*104/ 8.314 * 326 K)


= 0.0165 / min
k2 = A2 exp (-E2/RT)

(2.6)

= 1.36 * 108 exp (-7.04 * 104 / 8.314 * 326 K)


= 0.00071/ min

The main side reactions are the dimerization of isobutylene to diisobutylene, and the
hydration of isobutylene to tert-butyl-alcohol (TBA) as shown below:
2CH3C(CH3)=CH2
CH3C(CH3)=CH2 + H2O

CH2=C(CH3)CH2C(CH3)2CH3 (DIB)
CH3C(CH3)2OH (TBA)

(3)
(4)

The kinetic study shows that reaction (3) can only take place when the addition of
methanol is unsufficient. Since the methanol addition is carefully arranged to allow the
molar ratio of methanol to isobutylene to be higher than 0.8, the reaction (3) can be

173

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

neglected. For reaction (4), the minor water in hydrocarbon and methanol feedstock is
consumed in the pre-reactor before it is fed into reactor. Therefore, reaction (4) can
also neglect. The products of the two side reaction are considered in the vapor-liquid
equilibrium calculation, whereas the reaction kinetics is not included in the calculation.
-rB = k1CB k2CM
= k1(CBo CBXB) k2( MCBo CBXB)
CB = CBo since Pi = 2000Kpa and Ti = 326 K
CBo = Pi /RT
= 73.79 mol /m3
M = CMo / CBo = 0.138
Substitute all the value, -rB = 173.8 mole/ m3hr
2.1.8 WEIGHT OF CATALYST
The weight of catalyst can be determined from the equation,
W = dX
F
r

2.7)

Where r = overall reaction rate


W = weight of catalyst needed for the conversion
F = mole flow rate of the feed to the reactor
Substitute all the value and the by integration, the weight of catalyst is found to be
2998 kg.
2.1.9 DETAIL DESIGN OF THE REACTOR
2.1.9.1 Heat Exchanger for Reactor

174

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

For isothermal operation, heat may be supplied or removed continuously along with the
reaction path. In order to accomplish effective heat transfer with the packed bed, the
width of the bed must be small. In other words, isothermal reactors usually consist of a
number tube arranged as in large heat exchangers with the catalyst inside the tubes
and the cooling or heating medium outside the tubes.
2.1.9.2 Direction of the Reactant Flow
For the fixed bed reactor to be designed so that reactants remain isothermal, the rate
of heat required for the exothermic reaction must be exactly balance the heat transfer
from the heating medium. For any isothermal reaction of positive order, the reaction
rate falls as the reaction approaches equilibrium. Therefore a more rapid heating is
need at the reactant entrance than the reactant exit. Therefore the reactors have to be
designed as co-current to match the requirement and heat transfer.
2.1.9.3 Volume of Catalyst Bed
Volume of catalyst bed (Vb)

= W / b
= 2998
810
= 3.70 m3

(2.8)

2.1.9.4 Pressure Drop in the Bed


Pressure drop is an important variable in the rate equations. The maximum allowable
pressure drop criteria below have to be concerned.
1. The resulting force must not be exceeding the crushing strength of the
particle. For the down flow bed this force created by the pressure drop is
transmitted by contacting solid to the bottom of the bed.
2. Mass velocity through the bed must be high enough to minimize interphase
gradients and assure good distribution. Incremental increases in pressure

175

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

drop however should not exceed savings release from improved reactor
performance. In many bed systems the maximum economical pressure drop
is in the range of 3 to 5% of the total pressure.
2.1.9.5 Estimating Pressure Drop
(P)
L
Where

u2 f
dp

(2.9)

= friction factor, the correlation of Ergun (1952) will be used


= [1.75 + 150 / (1-b) / Re] (1-b)/ b3

Re

= dp u f = dp G
f
f

(2.10)

Where G is mass velocity = m/ A since m= 12.12 kg/s and G = 1.968 kg/m2s


f

= ( 0.28 E-6 + 1.001 E-3 +7.86 E-6)/3


= 3.36 E-4 kg/ms

Substitute the value, so Re = 2.928 (transition region) and = 73.75.


Since f = 796.57 kg/m3 and u= 0.0178x4/ x2.82 =0.003 m/s,
(P) will be 1060 N/m2
2.1.9.6 Height of Bed
From the criteria shown above, the optimum value of pressure drop is between 3 to
15% of the total pressure. Let the height of bed equals to 4 m, the pressure drop in the
bed is 4240 N/m2 which is equal to 4.2% of the operating pressure. Therefore, the
height of bed is taken as 4m
2.1.9.7 Total cross Section Area of the Tube
Total cross section area of the tube can be obtained by dividing the volume of the bed
with the height of the bed.
At

3.70

176

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

0.925 m2

(2.11)

2.1.9.8 Tube Diameter


If the tube diameter to particle diameter ratio is less than 10, the effect of wall can
become predominate, the void fraction and thus fluid velocity near the wall become
more dominant. However, if high value of tube to particle diameter ratio is obtained, the
heating effects through the tube wall will not be efficient. Therefore, tube with the inside
diameter Di =0.1143m and thickness 0.005m is used in this reactor, where the ratio is
approximately 11.5.
The inside diameter of the tube (Di) =
=

0.1143 2 x 0.005
0.1043 m

The cross section of the tube is then obtained from the equation:
At

Di 2 /4

0.009 m2

(2.12)

2.1.9.9 Total Number of Tubes


Total number of tube can then obtained by dividing the total cross section area of one
tube.
Nt

0.925
0.009

103 tubes

(2.13)

2.1.9.10 Tube Arrangement


The tubes in an exchanger are usually arranged in an equilateral triangular, square or
rotated square pattern. Since the triangular pattern gives higher heat transfer rates, it is
recommended for this reactor.

177

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

2.9.1.11 Pitch of the Tube


From reference (Process Heat Transfers book), the pitch of the tube is recommended
to be 1.25 times of the outside tube diameter Do.
Therefore,
Pitch of the tube (Pt)

1.25Do

1.25 x 0.1143

0.143 m

(2.14)
2.1.9.12 Bundle Diameter
The bundle diameter depends not only on the number of tubes but also can also on the
number of tube passes. For a single pass heat exchanger type reactor, the bundle
diameter can be obtained from the empirical equation base on standard tube layout as
shown:
Bundle diameter, Db =

Do ( Nt)n-1
K1

(2.15)

Where n1 and K1 = constant for use in the equation above given in reference (Process
Heat Transfers book). For single pass, n1 and K1 is given as 2.142 and 0.319
respectively. Hence,
Db =
=

0.1143 x (103 / 0.319) (1/2.142)


1.70 m

2.1.9.13 Number of Tubes In the Centre Row


The number of tubes in the centre row is then given by equation:
Nc =
=

Db / Pt
1.70/ 0.143

178

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

11.8 or 12 tubes

(2.16)

2.1.9.14 Shell Diameter


By using split ring floating head type from Fig 12.6 in Reference (Chem. Eng. Vol.6s
book),
Ds Db

95.14 mm

Where Ds

Shell Diameter

Ds

1.7 + 0.09

1.79 m

2.1.10 Baffles
Baffles are used in the shell to direct the fluid stream across the tubes, increase the
fluid viscosity and create turbulence so as to improve the rate of heat transfer. The
baffles used in this reactor are a common type i.e the single segmented baffles with
baffles cut 35 %.

2.1.11 Baffles Spacing


The optimum baffles spacing will usually be between 0.3 to 0.5 times of the shell
diameter. Here, it is taken as 0.3 times of the shell diameter.
Bs

0.3 Ds

0.3 x 1.79

0.55 m say 0.6 m

(2.17)

2.1.12 Number of Crosses


Number of crosses in the shell side,

179

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Nc

=
=

L -1
Bs
4

(2.18)

(Pt Do) * Ds * Bs
Pt

(2.19)

Area for Cross Flow


As

=
=

(0.143 - 0.114) * 1.79 * 0.6


0.143
2
0.218 m

2.1.14 Shell side heat transfer and pressure drop calculation


The flow pattern in the shell of a segmental baffled heat exchanger type of reactor is
complex, and this makes the prediction of the shell side heat transfer coefficient and
pressure drop much more difficult than for the tube side. However, Kern has developed
a method base on experimental work on commercial exchangers with standard
tolerances and gives a reasonably satisfactory prediction of the heat transfer coefficient
and pressure drop for standard design.

2.1.15 Shell side Mass Velocity


Mass velocity, Gs
Gs =

Ws
As

G =

2.211
0.218

G s =10.14 kg / m 2 s

(2.20)
Shell side velocity

180

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Gs

us =

us =

10.14
1209

u s = 0.01 m / s

(2.21)
Shell side equivalent diameter for triangular pitch arrangement
= 4(Pt/2).0.87.Pt .Do2/8
. Do/2

Das

= 0.084 m

(2.22)

Reynolds number
Re =

Re =

G s d as

(10.14)(0. 084)
0.00034

(2.23)

Re = 2505

Prandtl number
Pr =

Pr =

CP
kf
(3124.5)(0 .00034)
0.086

(2.24)

Pr =12.3

Choose buffle cut of 35%, from figure 12.30 (Coulson & Richardsons Chemical
Engineering), we can obtained
Jf

=1.3 x 10-1

181

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Assumed that the viscosity correction is negligible

hs =

k f jf Re Pr 1 / 3
de

hs =

(0.086)(0. 13)(2505)( 12.3 1/3 )


0.084

h s = 763.2 W / m 2

(2.25)

Shell side pressure drop


Reynolds number
Re = 2505
From figure 12.30 (Coulson & Richardsons Chemical Engineering),
Jf = 1.3 x 10-1

Shell side pressure drop can be calculated using equation below


P =8j f ( D d / d e )( L/I B )( s / 2 )( / w )
P =8.93kPa

-0.14

(2.26)

2.1.16 Tube side coefficient, hi


Mean temperature of the tube

182

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

t mean =

t1 + t 2
2

t mean =

53 + 27
2

(2.27)

t mean = 80 o C

cross sectional area = d12/ 4


= (3.142)(0.10432) / 4
= 0.009 m2
Tube / pass = 103 / 1
= 103 tube / pas

(2.28)

Total flow rate area = (cross sectional area)(tube / pass)


= (0.009)(103)
= 0.927 m2
velocity, Gt

= (2.211)/(0.927)
= 2.05 kg / sm2

= 0.002 kg / ms

Ratio of L / di = 4 / 0.104

(2.29)

= 38.46
Reynolds number, Re

Re =

d i

Re =

(1209) (0.002 ) (0.1043)


0.00034

Re =1000

183

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Heat transfer factor figure 12.31 (Coulson & Richardsons Chemical Engineering),
Jh = 2 x 10-2
Prandtl number, as 12.3

Pr =12.3
Tube side coefficient, hi can be calculated using equation below.

hi =

jh k f Re Pr 0.33
di

hi =

(2x 10 -1 )(0.086)(1 000)(12.3)


0.104

(2.30)

0.33

h i = 393 W / m o C

Tube side pressure drop


Reynolds number, Re = 1000

From figure 12.24 (Coulson & Richardsons Chemical Engineering),


jf = 2 x 10-1
Neglect the viscosity correction term

Pt = N p 8 jf ( L/d i )( / W ) - m + 2.5

Pt = 2 8(5 x 10 -3 )(4/0.104) + 2.5

] 2
i

] (1209 )( 02.00034 )

(2.31)

Pt =10.89 kPa

2.1.17 Correction for Tube Heat Transfer Coefficient

184

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Since the tube side heat transfer coefficient calculated is based on the inside diameter
of the tube, correction has to be done to obtain the heat transfer coefficient for outside
diameter of tube.

HO

=
=

hI . Di
Do
192 W/ moC

(2.32)

2.1.18 Overall Heat Transfer Coefficient


Uc

HO . hS
HO + hS

100.1 W/ moC

(2.33)

2.1.19 Reactor cooling system


mfCPf (t1 - t2)

mcCpc (t1 - t2)

(2.34)

Log Mean Temperature difference (LMTD) :


TLMTD

Ti To
ln(Ti-To)/(Ti-To)

(2.35)

45 oC

From this value can get mc = 39.63 kg/s where CPc=4220 and ti-t2 =135 oC

2.2

MECHANICAL DESIGN

2.2.1 INTRODUCTION
The mechanical design of chemical plant are of particular interest to chemical
engineers, but not usually be called on to undertake the detailed mechanical design of

185

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

the plant, especially the reactor vessels. However, the chemical engineer will be
responsible for developing and specifying the elementary design information for the
reactor, and need to have a general appreciation of pressure vessel design to work
effectively with the specialist designer.
Therefore, the design of wall thickness, head, column support, flange joint,
reinforcement and maximum allowable pressure are considered here.
Material of construction:
In this design, reference will mainly be based on the current British Standard BS 5500
and Bs 1515 where the current addition of Bs 5500 covers vessels fabricated in carbon
steel. The most common types used in the petroleum industry are Types 304, 316,321,
and 347.Because of their inherent high temperature strength propertied and high
corrosion resistance, they are particularly suitable for use in this process, in areas of
moderate and high temperature, and where substantial resistance such as in heater
tubes, reactors, reactor effluent exchangers and piping. In this design, material of
construction: can be constructed by using carbon steel. Type 304

DESIGN STRESS
It is necessary to decide a value for the maximum allowable stress that can be
accepted in the material of construction, for example, it can withstand without failure
under standard test conditions. The nominal design strengths (allowable design stress)
for the range of materials covered are listed in BS 5500. By using carbon steel (semi
killed or silicon Killed), the design stress is given, D as 125 N /mm2 at design
temperature.
WELDED JOINT EFFICIENCY
The strength of a welded joint will be depending on the type of joint and the quality of
the welding. The soundness of welds is checked by visual inspection and non
destructive testing (radiography).
For the reactor, it is assumed that the joint is equally as strong as the virgin plate; this
is achieved by radio graphing the complete weld length and cutting out and remarking

186

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

any defects. Therefore, the non destructive testing is assumed to be 100% and the
joint efficiency, J is taken as 1.0.
2.2.4 CORROSION ALLOWANCE

1. Corrosion and erosion or scaling will cause material lost, so an additional thickness
of material called corrosion allowance must be added to be calculated wall
thickness.
MINIMUM THICKNESS OF CYLINDRICAL SECTION OF SHELL
The minimum thickness of cylindrical section of shell to resist the internal pressure can
be determined by using equation below:
e

PD DIs
2J D - PD

2.0*1.8
2.125-2

0.015 m

(2.36)

By adding corrosion allowance 2 mm,


e

0.015 + 0.002m

0.017 m

MINIMUM THICKNESS OF DOMED HEAD


There are three types of commonly used domed head:
1. Hemispherical heads
2. Ellipsoidal heads
3. Torispherical heads

187

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

The selection of head depends on the cost and the thickness required for the head.
The design equations and charts for the various types of domed head are given in the
codes and standards (BS 5500) used in this design.
A standard dished head (torisphere) is used as first trial. The crown radius of this head
equals to the diameter of the shell, DIS. On the other hand, the knuckle radius is taken
as 6% of the crown radius. Since this type of head is formed by pressing, no joint is
needed. Therefore, the joint factor is taken as 1.
For the torispherical head, the minimum thickness of the head can be determined from
equation below:
eh

P D RC CS
2 J TD + PD(CS 0.2)

(2.37)

where Rc is the crown radius, equal to DIS in this case.


CS = stress concentration factor for torispheriical head.
It is given by equation below:
CS

1 / 4(3 + (Rc + Rk) 1/2)

(2.38)

Since Rk is 0.06 of Rc,


CS

1 / 4 (3 + (1/ 0.06)1/2)

1.771

2.0 x1.8 x1.771


2 x 1x125 + 2.0 (1.771 - 0.2)

0.025 m

Therefore,
eh

However, for a standard ellipsoidal head,


eh

PDDIs
2J D - 0.2PD

0.014 m

(2.39)

Therefore, an ellipsoidal head would probably be the most economical to be used. For
convenience, the thickness is taken to be as same of wall thickness 17 mm.

188

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

LOADING STRESSES
2.2.7.1 Dead Weight of Loading
2.2.7.2 Dead Weight Of vessel
The major source of dead weight loads are:
1. vessel shell
2. vessel fitting : manway, nozzles
3. internal fittings: where the main item is tube
4. insulation
5. catalyst
The preliminary calculation of the approximate weight of a cylindrical vessel with
domed ends, and uniform wall thickness can be estimated from the following equation,
Wv

Cv..m.Dm.g.(Hv + 0.8Dm)t x 10-3

Where Wv

total weight of the shell, excluding internal fitting

Cv

a factor to account for the weight of nozzles, internal


support etc.
Cv is given as 1.08 for vessels with only a few internal
fitting.

Hv

height between 2 tangent lines, 4m in this case

gravitational acceleration, 9.81 m/s2

wall thickness, mm

density of vessel material, kg/m3. by using carbon steel,


m = 6870 kg/m3

Dm

mean diameter of vessel

DIs + t * 10-4

Since the wall thickness = 0.017 m


Therefore, Dm = 1.8 + 0.014
= 1.817 m
As a result, by substituting into the equation above:
Wv

39000 N

39 KN

189

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Weight of the Tubes


From BS 3059, the mass per length of tubes is equal to 13.5 kg/ m for carbon steel.
Therefore, the weight of one tube
=

13.5 x 3 x g

4.529 * 104 N

45 KN

(2.40)

Total weight of the tubes,


Wt

103 x 13.5 x3 x9.81

4.1x104

Weight of Insulation

To avoid heat loss from the surface of the shell, mineral wool is used as the insulator.
From (Chem. Eng. Vol. 6s book),

Density of mineral wool

= 130 kg/m3

Let the thickness of mineral wool

= 75 mm

The approximate weight of the insulator,


Wi

2Hvtiig

2 x3 x0.075 x30 x9.81

1.803 x103 N

(2.41)

This value should be double to allow for fittings, etc.


=

3.6 x103 N

190

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Weight of Catalyst

Weight of catalyst, Wc = 2998 kg


= 2.998 x104 N

Total Weight
Since only 4 baffles are used in the reactor, their weight is neglected compared to
others.
W

Wv + Wi + Wt +Wc

39000N+ 4.1x104 N+ 3.6x103 N +2.998x104 N

1.1x 105 N

Wind Loading
Take dynamic wind pressure as 1300 N/m2
Mean Diameter, including insulation = 2+2(17+75) x10-3
= 2.18 m

The wind loading is then given by equation below:


Fw

P w Dm

1300 x2.18 m

2.8 x 103 N/m

(2.42)

Therefore, the bending moment at bottom tangent line can be determined from
equation below:
Mx

Fw L2

191

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

(2.43)

2.8 x 103 x 42
2

2.24 x104 N

2.2.7.8 ANALYSIS OF STRESSES


Uniform thickness is used for analyzing stresses in the column. If it is found satisfactory
at the bottom of the vessel which is the highest loading point, then the entire column
structure is feasible.
At bottom tangent line, the longitudal and circumferential stresses due to pressure is
given by:
Longitudal,

Circumrerential, h

P i Di
4t

2.0 x1.8
4 x 0.017

53 N /mm2

P i Di
4t

2.0 x1.8
2 x 0.017

106 N /mm2

(2.44)

Dead Weight Stress


The direct stress is mainly due to the weight of vessel, its contents and any attachment
which is often called the dead weight stress. The stress is compressive since it is at the
bottom of the vessel to support the direct loading.

192

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Dead Weight stress, W =

=
=

W
(Di + ti) * t
1.1 x 105
(1800 + 17) x 17

(2.45)

1.13 N /mm2 (compressive)

Bending Stress
The second moment of area of the vessel about the plane of bending,
Iv

Where Do

Iv

(Do4 Di4)
64

outer diameter of vessel

Di + 2t

1.8 + 2 x 0.017

1.834 m

(18344 18004)
64
4.0 x1010 mm4

(2.46)

Therefore, the bending stress is then given by equation below:


b

=
=

Mx (Di /2 + t)
Iv

(2.47)

0.51 N/mm2

The resultant longitudal stress


Z

L + W + b

53 1.13 + 0.51

52.38 N/mm2

For upwind,

For downwind,

193

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

53 1.13 - 0.51

51.36 N/mm2

Pi = 2.0
2
2

Radial Stress

(2.48)

1.0 N/mm2

Since radial stress obtained is a small value and there are torsional stress in the
system, therefore the principle stress will be Z and h

52.38 N/mm2

Figure 2.1:

51.36 N/mm2

Analysis of Stresses

194

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Therefore, the greatest difference between the principles stresses,


d

h - Z ( downward)

106 51.36

54.64 N/mm2

The value obtained is well bellow the maximum allowable design, 125 N/mm2.
2.2.11 CHECK ELASTIC STABILITY
The design of this vessel have to be checked to ensure that the maximum value of the
resultant axial stress does not exceed the critical value at which buckling will occur.
By applying a factor of safety of 12, the critical buckling stress gives:
C

2x104 (t/Do)

185.4 N/mm2

(2.49)

The maximum compressive stress will occur when the vessel is not under pressure,
=

W + b

1.13 + 0.51

1.64 N/mm2

Which is well below the critical buckling stress, C .


2.2.12 VESSEL SUPPORT
The method used to support a vessel will depend on the size, shape and weight of the
vessel; the design temperature and pressure; the vessel location and arrangement;
and the internal and external fittings and attachment. Since the reactor is a vertical
vessel, skirt support is used in this design.

195

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

A skirt support consists of a cylindrical or conical shell welded to the base of the
vessel. A flange at the bottom of the skirt transmits the load to the foundations. The
skirt may be welded to the bottom, level of the vessel.
Skirt supports are recommended for vertical vessels as they do not imposed
concentrated loads on the vessel shells; they are particularly suitable for use with tall
columns subject to wind loading.
2.2.13 SKIRT THICKNESS
The skirt thickness must be sufficient to withstand the dead weight loads and bending
moments imposed on it by the vessel; it will not be under the vessel pressure.
The resultant stresses in the skirt will be:
S (tensile)

bS - WS

S (compressive)

bS + WS

and

where bS

=
=

WS

=
=

bending stress in the skirt


4Ms
(Ds + ts) tsDs

(2.50)

the dead weight stress in the skirt


W
(Ds + ts) ts

Where Ms

maximum bending moment, evaluated at the base of the skirt.

total weight of the vessel and contents

Ds

inside diameter of the skirt, at the base

ts

skirt thickness

196

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

The skirt thickness should be such that under the worst combination of wind and dead
weight loading the following design criteria are followed:
S (tensile)

< fs.J sin s

S (compressive)

< 0.125 E (ts/Ds) sin s

Where fs is the maximum allowable design stress for the skirt material, normally taken
at ambient temperature, 20oC.
J

weld joint factor

base angle of conical skirt, 90o is used in this design

The maximum thickness should not less than 6mm.


2.2.14 HEIGHT OF THE SKIRT
The height of the skirt, Hs is taken to be 1m.

2.2.15 BENDING STRESS AT BASE OF THE SKIRT


Mbs

=
=

Fw (Hv + Hs)21
2

(2.51)

2.8x 103 (4 + 1)2


2
3.5 x 104 Nm

BENDING STRESS IN THE SKIRT


As the first trial, the thickness of skirt is taken to be 20 mm.
Substitute into the equation (19),
bS

4 x 2.24 x104
(1.9 + 0.020) 1.9x0.020
3.9 x 105 N/m2

197

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

WS

1.1 x 105
(1.9 +0.020)*0.020

9.1 x 105 N/m2

The maximum stress (compressive),


S

bS + WS

3.9 x 105 N/m2 +9.1x 105 N/m2

1.3 x 106 N/m2

The maximum stress (tensile),


S

bS - WS

3.9 x 105 N/m2 9.1 x 105 N/m2

5.2 x 105 N/m2 (negative)

Let the joint factor for skirt support, J = 0.85


Criteria for design,
fs.J sin s

125 x 0.85 xsin( 90o)

10.63 * 107 N/m2

>

S (tensile) , therefore it satisfied.

(2.52)

Modulus Young = 200,000 N/mm2 at ambient temperature, (from Bs 5500:1998),


0.125 E (ts/Ds) sin s =

0.125x2x105 (0.02/1.9) sin 90o

26.3 x 107 N/m2

>

S (compressive) , therefore it satisfied

Both criteria are satisfied, add 2mm for corrosion allowance, and give a design
thickness of 22 mm.

198

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

BASE RING AND ANCHOR BOLT DESIGN


The loads carried by the skirt are transmitted to the foundation slab by the skirt base
ring (bearing plate). The moment produced by wind and other lateral loads will tend to
overturn the vessel. Since the reactor can be considered as the small vessel, the
simplest types, rolled angle ring are used. The preliminary design of base ring is done
by using Scheimans short cut method.
The anchor bolts are assumed to share the overturning load equally, and the bolt area
required is given by:
=

1 (4.Mbs W)
Nbfb
Db

(2.53)

Where Ab

area of one bolt at the root of the thread, mm2

Nb

number of bolts

fb

maximum allowable bolts stress, typical design = 125 N/mm2

Mbs

bending (overturning) moment at the base, Nm

weight of the vessel, N

Db

bolt circle diameter, m

Scheiman gives the following guide rules which can be used for the selection of the
anchor bolts.
1. bolts smaller than 25 mm diameter should not be used
2. minimum number of bolts = 8
3. use multiples of 4 bolts
4. bolts pitch should not be less than 600 mm
The base ring must be sufficiently wide to distribute the load to the foundation. The
total compressive load on the base ring is given by:
fb

(4 Mbs + W ) = 28255 N/mm


Ds2
Ds

(2.54)

Where Fb is the compressive load on the base ring and Ds = skirt diameter, m
The minimum width of the base ring is given by:

199

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Lb

Where Lb
fc

fb
fc

1
103

(2.55)

= base ring width, mm


= the maximum allowable fc on the concrete foundation pad,
And typically range from 3.5 to 7 N/mm2

fb

= 28255 N/mm

Take the bearing pressure as 5 N/mm2, fc = 5 N/mm2


Substitute into the equation above,
Lb

=
=

28255
5 x103
5.65 mm

This is the minimum width required; actual width will depend on the chair design
Actual width required= Lr + ts +50 mm
Where Lr = the distance from the edge of the skirt to the outer edge of the ring, mm
= 64 mm (from BS 4190:1967)
Therefore, actual width required = 64 + 22 +50
= 136 mm
Actual bearing pressure on concrete foundation:
fc

=
=

tb

28255
136 x103
0.21 N/mm
64 ( 3 x 0.21)
140

(2.56)

200

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.3 mm

COMPENSATION FOR OPENING AND BRANCHES


All process vessels will have opening for connections, man ways, sight holes, hand
holes and instrument fittings. The presence of an opening weakens the shell, and gives
rise to stress concentrations. The stress at edge of a hole will be considerably higher
than the average stress in the surrounding plate. To compensate for the effect of an
opening, the wall thickness is increased in the region adjacent to the opening.
Sufficient reinforcement must be provided to compensate for the weakening effect of
opening without altering the general dilation pattern of the vessel opening.

2.2.19 COMPENSATION FOR OTHER NOZZLES


Pipe size for inlet and outlet of the reactor are all less than 10 mm, therefore, the
reinforcement area can be usually is provided by increasing the wall thickness of the
branch pipe. This already done on piping, where extra thickness is provided, thus no
compensation area needed.
2.2.20 BOLTED FLANGE JOINT
Flanged joints are used to connect pipes and instruments to vessels and from
removable vessel heads when ease of access is required. Flanges may also be used
on the vessel body, when it is necessary to divide the vessel into section for transport
or maintenance. Flanged joints are also used to connect pipes to other equipment,
such as pumps, valves.
2.2.20.1 Type of Flanges Selected
a) Welding neck Flanges

201

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Have a long tapered lub between the flange ring and the welded joint. This gradual
transition of the section reduces discontinuity stresses between flange and branch,
and increases the strength of the flange assembly.
Welding neck flanges are suitable for extreme service conditions, where the flange
is likely to be subjected to temperature, shear and vibration loads.. For this reactor,
the welding neck flanges are suitable for use in connecting the inlet and outlet
piping of reactor.
b) Gasket
Gaskets are used to make a leak tight joint between two surfaces. It is impractical to
machine flanges to the degree of surface finish that would be required to make a
satisfactory seal under pressure without a gasket. Gasket are made from semi plastic
materials, which will deform and flow under load to fill the surface inequalities between
the flange faces, yet retain sufficient elasticity to take up the changes in the flange
arrangement that occur under load.
Several factors must be considered when selecting a gasket material:
1. The process condition: pressure, temperature, corrosive nature of
process fluid.

2. Whether repeated assembly and disassembly of the joint is required


3. The type of flange and flange face.
Judging from process conditions, where the operating temperature is quite high, 393K,
metal reinforced gaskets is recommended, since it have a quite good heat resistance
property.
2.2.21 Flange Face
The raised face, narrow feed flange are used for all the flanges. Where the flange has
a plain face, as for the flange faces mentioned above, the gasket is held in place by
friction between the gasket and flange surface.

202

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

SUMMARY OF CHEMICAL DESIGN PARAMETERS

Reactor Design
Catalyst weight required

2998 kg

Volume of Catalyst bed

3.7 m3

Height of Bed

4.0 m

Diameter of Bed

1.817 m

Tube inside pressure drop

1.06E-4 N/m2

% of pressure drop

0.042

Tube inner diameter

0.1043 m

Total number of tubes

103 tubes

Tube arrangement

equivalent triangular pitch

Tube side heat transfer coefficient

293 W/moC

Pitch of tube

0.143 m

Bundle diameter

1.70 m

203

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Shell diameter

1.79 m

Baffles cuts

0.35

Baffles Spacing

0.6 m

Number of crosses

Inlet flow rate

0.647 kg/s

Inlet temperature

326 K

Outlet temperature

373 K

Shell side heat transfer coefficient

191 W/moC

Shell side pressure drop

0.557 kPa

Design overall heat transfer area

100.1 W/moC

SUMMARY OF MECHANICAL DESIGN PARAMETERS

204

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Operating Conditions and Material of construction


Design pressure

2.0 bar

Design temperature

323 K

Material of construction

Carbon Steel plate (Type 304)

Design Stress

125 N/mm2

Welded joint efficiency

Corrosion allowance

2 mm

Designed Column Diameter


Shell thickness

17 mm

Domed end thickness(ellipsoidal heads)

17 mm

Vessel Support (skirt)


Skirt thickness

22 mm

Skirt diameter

1.9 m

Skirt height

1m

Base Ring and Anchor Bolt


Base ring

Rolled angle rings

Minimum ring thickness

4.5 mm

Minimum base ring width

7.06 mm

Anchor bolt

M24

Number of bolts

Bolt root diameter

21.2 m

205

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

SECTION 3

MTBE DISTILLATION COLUMN


3.1

INTRODUCTION

Distillation is a method used to separate the components of a liquid solution, which


depends upon the distribution of these various components between a vapor
and a liquid phase. All components are present in both phases. The vapor
phase is created from the liquid phase by vaporization at the boiling point.
MTBE is our main product that needs to be separated. For individual design,
MTBE distillation column was chosen. The characteristics required in the chosen types
of distillation column are the separation objective satisfied in the column, the cost of
construction and the design of the selected distillation column.

R e lief Va lve

C on den se r

T=53.3oC
T=6 4.5oC

TC

LC

R e bo iler

T=10 3.3oC

Figure 3.1 MTBE Distillation Column


3.2

SELECTION OF CONSTRUCTION MATERIAL

206

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Materials chosen are based on the characteristics of the component in the distillation
column, the location and the environmental consideration of the MTBE plant. Stainless
steel 304 is used in construction of the MTBE distillation column - The stainless steels
are the most frequently used corrosion resistant materials in the chemical industry
Coulson & Richardson, Chemical Engineering, Volume 6, page 295.
Carbon steel is used in skirt support material and the insulation material used is
fiberglass. The selection is based on the chemical and mechanical design as stated in
Coulson & Richardson, Chemical Engineering, Volume 6. Most parameters used in
design were referred to mass, energy balance data and also data generated by
Chemical Engineering Simulation Software; HYSIS Version 3.2. Other materials
chosen were based on the British Standard BS 5500, BS4505 and BS 750.

3.3

CHEMICAL DESIGN
In the MTBE distillation column design, the McCabe-Thiele method in

determining the number of stages needed was used.

The McCabe-Thiele method is

based upon representation of the material-balance equations as operating lines on the


X-Y diagram. The lines are made straight (and the need for the energy balance
obviated) by the assumption of constant molar overflow. The liquid-phase flow is
assumed to be constant from tray to tray in each section of the column between
addition (feed) and withdrawal (product) points. If the liquid rate is constant, the vapour
rate must also be constant.

Table 3.1 The Composition in Feed Stream


FEED

Component

T (K)

Operating

Op Pressure,

Feed Flowrate

Fraction, zi

207

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

T (K)

kPa
kmol/hr

i-C4H10

313

337.5

450

34.860

0.3261

n-C4H10

313

337.5

450

0.400

0.0037

C4H8
DME

313
313

337.5
337.5

450
450

0.026
3.880

0.0002
0.0363

CH3OH

313

337.5

450

0.160

0.0015

H2O

313

337.5

450

2.866

0.0268

MTBE
TBA

380
380

337.5
337.5

450
450

63.44
1.274
=106.906

0.5934
0.0119
= 1.0000

Table 3.2 The Compositions in Top Stream


Top

Component

T (K)

Operating
T (K)

Op Pressure,
kPa

Top Flowrate

Yi

kmol/hr

S16
(top)

i-C4H10

313

326.3

305

33.860

0.839760919

n-C4H10

313

326.3

305

0.400

0.009920389

C4H8

313

326.3

305

0.026

0.000644825

DME

313

326.3

305

3.880

0.096227772

CH3OH

313

326.3

305

0.149

0.003695345

H2O

313

326.3

305

1.006

0.024949778

MTBE

313

326.3

305

1.000

0.024800972

=40.321

=1.0000

Table 3.3 The Composition in Bottom Stream


Bttm

S14
(bttm)

Component

T (K)

Operating
T (K)

Op Pressure,
kPa

Bttm
Flowrate
kmol/hr

Xi

i-C4H10

380

376.3

400

1.000

0.015018398

MTBE

380

376.3

400

62.44

0.937748742

TBA

380

376.3

400

1.274

0.019133438

CH3OH

380

376.3

400

0.011

0.000165202

H2O

380

376.3

400

1.860
=66.59

0.027934219
=1.0000

* The T(K) is the stream temperature, while the Operating T(K) temperature is the
temperature which should be achieved by controlling the pressures.

208

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.3.1

DETERMINATION OF THE NUMBER OF PLATES USING McCABETHIELE METHOD

The components in the feed to the MTBE distillation column are i-C4H10, n-C4H10, C4H8,
DME, CH3OH, H2O, MTBE and TBA, and the feed is assumed as multicomponents
feed. By using the Hengstebecks and McCabe-Thiele method, the number of stages
required and the position of the feed in the MTBE distillation column can be
determined.
The determination of the plate by using McCabe-Thiele method was simply
because as explained in J.M Coulson, J.F Richardson, Chemical Engineering Volume
2, Third Edition, the Pergamon Textbook, page 429, which stated that This method is
one of the most important concepts in chemical engineering and is an invaluable tool
for the solution of distillation column. The assumptions of constant molar overflow is
not limiting since in very few systems do the molal heats of vaporizations differ by more
than 10 percent. The method does have limitations, however, and should not be
employed when the relative volatility is less than 1.3 or greater than 5, when the reflux
ratio is less than 1.1 times the minimum, or when more than twenty-five theoretical
trays are required. In these circumstances, the Ponchon-Savarit method should be
employed.

The vapor pressure can be determined by using the Antoines equation as follows:

Log10 P* = A -

B
T +C

(3.1)

With related at equilibrium, constant K,


Ki = P* x P

(3.2)

And related with concentration,

209

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Ki =

yi
xi

(3.3)

Where yi = concentration in vapor phase


xi = concentration in liquid phase
Calculation for the relative volatility, ,
= KLK / KHK

(3.4)

Where KLK = Light key component


KHK = Heavy key component
In this case, MTBE is as the heavy key and i-C4H10 is as the light key components. By
using goal seek in the excel programme, the value of the bubble point at bottom
column = 103.3oC and dew point at the top column is = 53.3 oC, from the values of Ki
related to the pressure, the values of relative volatilities could be determined, listed are
values of the relative volatilities for components at the top and bottom of the distillation
column.
Table 3.4 Average Relative Volatility,

Bttm,

Top,

i-C4H10 (LK)

7.699631

n-C4H10

5.654994

2.827496955

C4H8
DME
MTBE (HK)
TBA

6.948741
14.10614
1.00000
-

1.0000
0.149333

3.474370398
7.05306993
1.00000
0.074666444

CH3OH

0.67395

0.99561

0.834780143

H2O

0.152422

0.288322

0.220371796

5.084017

Avg,

Component

6.39182391

Calculations for the non-key flows,


Table 3.5 The Non-key Flow of the Top Stream

210

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

i
2.827497
3.47437
7.05307
0.83478
0.220372

TOP
n-C4H10
C4H8
DME
CH3OH
H2O

di
0.4
0.026
3.88
0.149
1.006

li = di / ( i-1)
0.218878614
0.010507724
0.640997055
-0.901828648
-1.290358653

Vi = li + di
0.618878614
0.036507724
4.520997055
-0.75282865
-0.28435865

= -1.321803909

= 4.139

Table 3.6 The Non-Key Flow of the Bottom Stream


BOTTOM

bi

TBA
CH3OH
H2O

0.074666
0.83478
0.220372

1.27
0.01
1.86

Vi= ibi / (

LK

li = vi + bi

i)
0.01506000
0.001652422
0.066417357
= 0.083127984

1.2900
0.0100
1.9300
= 3.23

Flows of combine key,


Le

= L - li

(3.5)

= (2.5 X 40.321) (- 1.3218)


= 102.1243
Ve

= V - Vi

(3.6)

= (2.5+1) x 40.321 4.139


= 136.985
Calculation of the slope for top operating line,
Le
Ve

102 .1243
136 .984

(3.7)

= 0.7455
Ve

= V - Vi

(3.8)

= (2.5+1) x 40.321 0.08313


= 141.04
Le

= L - li

(3.9)

= (2.5+1) x 40.321 + 66.59 3.23


= 204.48

211

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Calculation of the slope for bottom operating line,


Le '
Ve '

141 .04
204 .48

(3.10)

= 1.45

Xb

flow .LK
flow ( LK + HK )

1
(1 +62 .47 )

at bottom,

(3.11)

at top,

(3.12)

at feed,

(3.13)

= 0.016

Xd

flow .LK
flow ( LK + HK )

Xd

33 .86
(33 .86 +1)

= 0.9713

Xf

Xf

flow .LK
flow ( LK + HK )
34 .86
(34 .86 +63 .44 )

= 0.3546
For vapor liquid equilibrium curve, we use the equation of

.x
[1 + ( 1) x]

6.391 x
[1 + ( 5.391 ) x]

from LK component

(3.14)

Table 3.7 MTBE Equilibrium Curve

y=
x

6.391 x
1 + 5.391 x
y

212

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0

0
0.41527398
0.61508201
0.73257407
0.80992987
0.86471539
0.9055511
0.93716326
0.96235974
0.9829137
1.0000

So from the data as above, the McCabe-Thiele diagram was constructed to determine
the number of plates. The top operating line and the bottom operating line were
determined first before the number of plates required could be calculated.
And from the graph plotted, the number of stages needed for the MTBE
distillation column is 11 with the feed point location is at stage number six from bottom.

213

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

McCabe-Thiele Diagram
1

0.9

0.8

Top
Operating
Line

0.7

0.6

Equilibrium
Curve

0.5

Line for
Number
Stages

0.4

0.3
Bottom
Operating Line

0.2

0.1

0
0

0.2

0.4

0.6

0.8

Xb = 0.016

Xf = 0.35

Xd = 0.97

At bottom

At feed

At top

214

the
of

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Figure 3.2 McCabe-Thiele Diagram


From the graph plotted, the number of plate can be determined by calculating the stage
plotting at graph and the number of stages needed is 11 stages. The feeding stage
also can be determined from the graph, feed at stage 6 from bottom.
Calculation for minimum reflux ratio, Rmin,
To get the value of minimum reflux ratio, use the Underwood equation was used,
(J. Douglas, 1988),

Rmin

=
1

X D.L K X D.H K

X F .H K X F .H K

(3.15)

1
1.0

33 .86
6.391

6.391 1 63 .44
63 .44
= 0.0803
Optimum reflux ratio is 0.0803 x 1.5 = 0.1204
Where,
XD.LK

= Light key component at top flow

XD.HK

= Heavy key component at top flow

XF.LK

= Light key component at feed flow

XF.HK

= Heavy key component at feed flow

In the calculation, the optimum reflux ratio as 2.5 was used (based on Coulson
& Richardson, Chemical Engineering, Volume 6, and J.M Coulson, J.F Richardson,
Chemical Engineering, Volume Two, Third Edition) as 0.1204 is too low for the
calculation, based on statement from R. K. Sinnot, Coulson & Richardson, Chemical
Engineering, Volume 6, Butterworth Heinemann, 2001, page 495 At low reflux
ratios the calculated number of stages will be very dependent on the accuracy of the
vapor-liquid equilibrium data available. If the data are suspect a higher than normal
ratio should be selected to give more confidence in the design.

215

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.3.2

DETERMINATION OF THE NUMBER OF PLATES USING FENSKES


EQUATION

The Fenskes equation (1932) can be used to estimate the minimum stages required at
total reflux. The derivation of the equation is for binary system and applies equally to
multicomponents system. But in the design only the calculation of plates using
McCabe-Thiele method as the design plate number was taken into consideration.

Nmin

Nmin

x x
log LK HK
x HK d x LK b
log LK

33 .86 62 .44
log

1.000 1.000
log 6.392

4.13

5 stages

(3.16)

Normally after using the Fenskes Equation, the value of Nmin is given by the equation
below to get the number of stages, NT,
NT

2 (Nmin)

2 (5)

10 stages

To get the real number of stages, the efficiency of the process must be considered,
and the efficiency is calculated based on the equation by OConnells (J. Douglas,
1988),
Eo

0.5

( ) 0.25

0.5
( 0.224 x 6.392 ) 0.25

0.457

(3.17)

216

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.3.3

NT
Eo
=

11
0.457

24.07

24 plates

THE PHYSICAL PROPERTIES

The properties consider in this design are liquid flow rate, LW, vapor flow rate, VW, liquid
surface tension, , liquid density, l and vapor density, v. This physical properties
evaluated at the system temperature by using HYSIS generated data or by manual
calculations the from mass and energy balance data. The useful properties data are
from HYSIS, mass and energy balance data is given as below:
Liquid flow rate, LW

38747.97 kg/hr (10.7633 kg/s)

Vapor flow rate, VW

15251.95 kg/hr (4.2367 kg/s)

Liquid surface tension,

0.0351 N/m

Liquid density, l

746.74 kg/m3

Vapor density, v

3.8402 kg/m3

Data evaluated are at system temperatures and pressures.

3.3.4

DETERMINATION OF COLUMN DIAMETER

The principal factor that determines the columns diameter is the vapour flow-rate. The
vapour velocity must be below that which would cause excessive liquid entrainment or
a high-pressure drop. The equation below which is based on the well-known Souders
and Brown equation, Lowenstein (1961), Coulson & Richardson, Chemical
Engineering, Volume 6, page 556, can be used to estimate the maximum allowable
superficial vapour velocity, and hence the column area and diameter,

217

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

( L v)
u = ( 0.171 l2t + 0.27 lt 0.047 )

1/ 2

(3.18)

2
( 746 .74 3.8402
=
0.171 ( 0.9 ) +0.27 ( 0.9) 0.047
3.8402

1/ 2

= 0.7997 m/s

Where,

= maximum allowable vapour velocity, based on the gross (total)


column cross-sectional area, m/s,

= plate spacing, m (range 0.5 1.5).

Based on the equation below, the column diameter could be determined,

Dc

Dc

Dc

4 vw

vu v

(3.19)

4(0.6244 )

(3.8402 )( 0.7997 )

0.51 m

0.51 x 1.5

0.765 m

For safety reason, the approximate diameter was increased 50% more than the
calculated value, as it deals with vapour, which is in high pressure.

218

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.3.5

DETERMINATION OF PLATE SPACING

The overall height of the column will depend on the plate spacing. Plate spacings from
0.15 m (6 in.) to 1m (36 in.) are normally used. The spacing chosen will depend on the
column diameter and the operating conditions. Close spacing is used with smalldiameter columns, and where head room is restricted, as it will be when a column is
installed in a building. In the MTBE distillation column, the plate spacing was assumed
0.9 m as it is in the range of 0.5 m to 1 m recommended by Coulson and Richardson,
Chemical Engineering, Volume 6.

3.3.6

LIQUID FLOW ARRANGEMENTS

Before deciding liquid flow arrangement, maximum volumetric liquid rate were
determined by using equation below,

VL

Lw

(3.20)

VL

38747 .97
746 .74

VL

51.89 m3/hr

0.0144 m3/s

Based on the values of volumetric flow rate and column diameter, Dc. Figure
11.28 from Coulson & Richardson, Chemical Engineering, Volume 6, page 568.
Therefore, types of liquid flow could be considered as single pass.

3.3.7

PLATE LAYOUT

The value of downcomer area, active area, hole area, hole size, and weir height were
determined based on above value calculated, trial plate layout column area determined
by using the equation below,

219

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Column area, Ac

Where Um

Um
Uv (0.9)

4.181
0.7997 (0.9)

5.81 m2

Velocity at below plate,

(3.21)

Down comer area were found by assume 20% of column area and using equation
below,
Down comer Area Ad

0.2 Ac

0.2(5.81 m2)

1.162 m2

Net area and active area were determined by using equations below,
Net Area, An

Active area, Aa

Ac - Ad

5.181 -1.162

4.02 m2

Ac - 2Ad

5.181 - 2(1.162)

2.857 m2

Hole Area, AH are determine with trial value of 10% active area by equation below,
Hole Area, Ah

0.10(Aa)

0.10(2.857)

0.2857 m2

Weir Length, lw was calculated by referring Figure 11.31 from Coulson Richardson,
Chemical Engineering, Volume 6, page 572 which was determined based on the
value of the ratio of Ad/Ac to get the ratio of lw/ Dc .
The weir height determined and other dimensions are as below:

220

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.3.8

Weir Height, hw

50 mm (standard)

Hole diameter, dh

5 mm (standard)

Plate Thickness

5 mm (standard)

Weir Length, Iw

612 mm (80% x 765)

ENTRAINMENT EVALUATION

The entrainment checking can be done by determine actual flooding percentage, Uv by


using equation below,
Uv

Um
Ac

4.181
5.181

0.807 m/s

(3.22)

Liquid flow rate were determine by using below equation by using liquid vapor flow
factor.

FLV

0.5

Lw
Vw

38747 .97 3.8402

15251 .95
746 .74

0.182

(3.23)
0.5

Where FLV is liquid vapor factor.

Based on value of FLV and assumption made for initial tray spacing (0.9m) by
referring to Figure 11.27 from Coulson & Richardson, Chemical Engineering, Volume
6, page 567, the data were used to determine the constant, K1 for the estimation of
flooding velocity. Before that, correction factor are used as equation below:
0.2

K1 =

k1 0.02

(3.24)

221

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

0 .2

0.0351
0.1

0.02

0.112

And flooding velocity, Uf determine by equation below (correlation given by Fair,


Coulson & Richardson, Chemical Engineering, Volume 6, page 567,
Uf

l v

K1 v

l v

0.112 v 0.5

746 .74 3.8402

3.8402

0.112

1.56 m/s

(3.25)

0 .5

Actual % of flooding =

Uv
100
Uf

0.807
100
1.560

51.8%

(3.26)

Fractional entrainment is calculated based on this percentage and FLV by


referring to Figure 11.29 from Coulson & Richardson, Chemical Engineering, Volume
6, page 570, if unsatisfied, recalculation were done based on chosen diameter and
plate spacing acceptable to determine the lowest value. However, fractional
entrainment = 0.02, is below the initial guest of 0.1 and entrainment is acceptable.

3.3.9

WEEPING RATE EVALUATION

222

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Weir liquid crest were determined by using values of maximum liquid flow rate
and minimum flow rate based on the process condition and also assumption of
turndown percentage based on the liquid characteristic. Each weir liquid crest value
was determined by using equations as follow, the Francis weir formula (see also
Volume 1, Chapter 5),

Max how

Min how

2/3

Lw max
750
l (lw )

750

13.49 mm liquid

Lw min
750
l (lw )

10 .7633
750
(746 .74 )( 0.88 )

48.37 mm liquid

(3.27)
2/3

1.5860

(746 .74 )( 0.88 )

2/3

(3.28)
2/3

Where,
Iw

Weir length, 0.88 (standard)

how

weir crest

Lw

liquid flow rate

At minimum liquid flow rate, the value was determined by adding weir height H w and
weir crest, how the constant, K2 where it is found based on the value by referring to
Figure 11.30 from Coulson & Richardson, Chemical Engineering, Volume 6, page
571.
Minimum vapor velocity Uh, were determined by using the equation as below,
Uh

K 2 0.90 ( 25 .4 d h )
v 0.5
=

(3.29)

28 .60 0.90 (25 .4 0.005 )


(3.8402 ) 0.5

2.931 m/s

(3.3.10, 3.3.11 and 3.3.12: Please refer to the Appendix)

223

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.3.13 NUMBER OF HOLES


Area of hole,
AH

=
=

Number of Holes

3.3.14

d h
4

(3.30)

(0.05 ) 2
4

1.9634 x 10-3 m2

Ah
AH

0.2857
1.9634 10 3

145.49

146 units (at every sieve plate).

(3.31)

COLUMN SIZE

The column height will be calculated based on the equation given below. The equation
determines the height of the column without taking the skirt or any support into
consideration. Its determination is based on condition in the column.
Column Height

(No stage 1) (tray spacing)


+(Tray spacing x 2)
+(No stage-1) (Thickness of Plate)

(11 -1)(0.9)+(0.9)(2) + (11-1)(0.005)

10.85 m

12.00 m (including 10% safety factor)

The overall height from the calculation is 10.85 m, but in a real construction it
will be added slightly more (about 10%) because of vapor and liquid area at top and
bottom column. The space for vapor and liquid are required if uncertain condition occur

224

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

in the column, such as over flooding, over vapor pressure or upset in reaction situation.
The calculated result is tabulated in the Table 5.8 as below.
Table 3.8

Provisional Plate Design Specification

Item
Column Diameter, Dc
No of Plates
Plate Spacing
Plate Thickness
Total Column Height, Ht
Plate Pressure Drop, ht
Plate Material
Down Comer Area, Ad
Down Comer Material
Column Area, Ac
Net Area, An
Active Area, Aa
Hole Area, Ah
Number of Holes
Weir Length
Weir Height (standard)
Resident Time

Value
0.765 m
11 units
0.9 m
5 mm*
12.00 m
192.81 mm liquid*
SS 304
0.8348 m2
SS 304
5.181 m2
4.020 m2
2.857 m2
0.2857 m2
146 units
0.612 m
0.05 m
13.37 seconds*

* For the determination of these values, they are shown in the Appendix section.

3.4

MECHANICAL DESIGN

In the mechanical design, the temperature and pressure are important properties in
evaluating the thickness and the stress of material. Therefore, the safety factor also is

225

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

also added as precaution and determined by certain consideration such as corrosion


factor, location and process characteristic.
The safety factor is usually 10% above the operating pressure and as for this
MTBE distillation column, the operating pressure is 450 kPa. The chosen safety factor
is based on the process characteristics of the system. The design temperature is
related to the operating temperature. Based on the calculated result, the temperature
at the top of the column is 53.3oC and the temperature at the bottom of the column is
107oC.
Design Pressure, Pi

Design Temperature, T

3.4.1

0.450 N/mm2 x 110%

0.495 N/mm2

117.70 C (10% more than design temp.)

MATERIAL OF CONSTRUCTION

The material used in the construction of the distillation column is stainless steel
(18Cr/8Ni, 304) as the material is suitable in high temperature and less corrosive. For
this material, the design stress at 150 C is obtained from Table 13.2, page 809
Coulson & Richardson, Chemical Engineering, Volume 6.

3.4.2

Design stress, f

130 N/mm2

Diameter vessel, Di

860 mm

Tensile strength,

510 N/mm2

VESSEL THICKNESS

The minimum thickness of column required and other designs are calculated based on
equation below (Coulson & Richardson, Chemical Engineering, Volume 6, page 812):

226

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Pi Di
2Jf Pi

(0.495 )( 765 )
2(1)(145 ) (0.495 )

1.31 mm

(3.32)

Based on Table 13.4, Coulson & Richardson, Chemical Engineering, Volume 6,


page 811, this minimum thickness should be added 5 mm to withstand its own weight
and any incidental loads.
e
Assumed

1.31 mm + 5 mm

6.31 mm

7.00 mm

Where, Pi

Design pressure

Di

Column diameter

Design Stress

Joint factor (assumed = 1)

From Table 13.4, Coulson and Richardson, Chemical Engineering, Volume 6,


page 811, for diameter 1 m to 2 m the minimum thickness should not be less than 7
mm (including 2 mm of corrosion allowance). For vessel diameter around 0.5 m to 1 m,
a much thicker wall will be needed at the column base to withstand the wind and dead
weight loads.
A much thicker wall is needed at the column base to withstand the wind and
dead weight loads. As a first trial, divide the column into five sections, with the
thickness increasing by 2 mm per section. Try 7, 9, 11, 13 and 15 mm. The average
wall thickness is 11 mm.
3.4.3

HEADS AND CLOSURE

227

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Torispherical head had been chosen because of operating pressure below 10 bars and
suitable for liquid vapor phase process in inconsistent high pressure. The calculations
as below is considered,
Crown radius, Rc

= Di

= 0.765 m

Knuckle radius, Rk

= 6% Rc

= 0.046 m

Minimum Thickness =

Pi R c C s
2Jf + Pi (C s 0.2)

= 0.2137mm

(The method of calculations is shown in the Appendix section)

3.4.4

TOTAL COLUMN WEIGHT

Total Weight, Tw
Total weight is the summation of the weight of dead weight, the weight of plates and
the weight of insulation. The calculations for the dead weight, the weight of plates and
the weight of the insulation are shown in the Appendix.
Total weight, Wt

3.4.5

W v + Wp + WI

(28.46 + 68.53 + 10.63) kN

107.62 kN

WIND LOADS
The wind load is calculated based on location and the weather of surrounding.

Therefore, the value of wind speed is assumed as below and wind load is calculated
shown in the appendix. The wind load for the MTBE column is 62.91kN (methods of
calculation in shown in the appendix.
3.4.6 STIFFNESS RING (Please refer to the Appendix)
Table 3.9

Summarized Results of Mechanical Design

228

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Operating pressure, Po

0.45 N/mm2

Design Pressure, Pi

0.495 N/mm2

Safety factor

0.15

Design Temperature, TD

88.78 oC

Operating Temperature, To

80.71 oC

Heads and Closure


Types

Torispherical head.

Crown Radius, Rc = Di

0.765 m

Knuckle Radius, Rk = 6% Rc

0.046 m

Joint Factor, J

1.00

Cs

1.77

Minimum thickness head, e

0.2317 mm

Column Weight
Dead weight of vessel, Wv

28.46 kN

Weight of a plate, Wp

6.23 kN

Weight of 11 plates,Wp

68.53 kN

Weight of insulation, WI

10.63 kN

Total weight

107.62 kN

Win speed, Uw

160 km/hr

Wind pressure. Fw

1068.8 N/m2

Bending Moment (Mx)

62.91 kN

Stiffness Ring
Critical buckling pressure for ring, Pc

15 x 106 N/m2

229

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.5

VESSEL SUPPORT DESIGN (SKIRT DESIGN)

Type of Support

Straight cylindrical skirt

90

Material of Construction

Carbon steel

Design Stress, fs

135 N/mm2 at ambient temp. 20C

Skirt Height, Hv

2.5 m (standard)

Youngs Modulus

200, 000 N/mm2

Approximate Weight

8.418 kN

Total Weight

36.88 kN

230

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

(The method of calculations for other parameters in the vessel support design in shown
in the Appendix section)

Table 3.10

Design Specification of the Support Skirt


Support Data
Type of Support

Straight cylindrical skirt

Material of Construction

Carbon steel

Design Stress, at T 20C (ambient)

135 N/mm2

Skirt Height

2.50 m

Youngs Modulus

200000 N/mm2

746.74 kg/m3

Approximate Weight, Wapprox

8.418 kN

Total Weight

107.62 kN

Wind Load, Fw

1068.8 N/m2

Skirt Thickness, ts

15 mm

REFERENCES
J. M. Coulson, J. F. Richardson, Chemical Engineering, Volume Two, Third
Edition, The Pergamon Press, 1977.
R. K Sinnot, Coulson & Richardsons Chemical Engineering, Chemical
Engineering Design, Volume Six, Butterworth Heinemann, 1999.
Robert H. Perry, Don W. green, Perrys Chemical Engineers Handbook,
Seventh Edition, McGraw-Hill, 1998.
James, M. Douglas, Conceptual Design of Chemical Processes, McGraw-Hill
Book Company, 1988.
Martyn S. Ray and David, W. Johnston, Chemical Engineering, Design Project:
A Case Study Approach, Gordon and Breach Science Publishers, 1989.
Carl R. Branan, Rules of Thumb for Chemical Engineers, Gulf Publishing
Company, 1994.

231

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Billet, R., Distillation Engineering, Heydon Publishing, 1979.


King, C. J., Separation Processes, Second Edition, McGraw-Hill, 1992.
Kister, H. Z., Distillation Design, McGraw-Hill, 1992.
Lockett, M. J., Distillation Tray Fundamentals, Cambridge University Press,
1986.
Normans, W. S., Absorption, Distillation and Cooling Towers, Longmans, 1961.
Oliver, E. D., Diffusional Separation Procesess, John-Wiley, 1966.
Robinson, C.S., and Gilliland, E.R., Elements of Fractional Distillation, McGrawHill, 1950.
Smith, R., Chemical Process Design, McGraw-Hill, 1995.
Van Winkle, M., Distillation, McGraw-Hill, 1967.
Micheal J. Barber, Handbook of Hose, Pipes, Couplings and Fittings, First
Edition, The Trade & Technical Press Limited, 1985.
Louis Gary Lamit, Piping Systems: Drafting and Design, Prentice-Hall, Inc.,
1981.
David H. F. Liu, Bela. G. Liptak, Wastewater Treatment, Lewis Publishers, 2000.

SECTION 4

DESIGN OF LIQUID-LIQUID EXTRACTION COLUMN

4.1

INTRODUCTION

Liquid-liquid extraction has become an important separation technique in modern


process technology. This is has resulted in the rapid development of a great variety of

232

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

extractor types, in the evaluation of which the chemical engineer must primarily depend
on manufacturers literature.
To the design, only three components that are considered, - methanol, water
and isobutene- this is because of for most system containing more than four
components, the display of equilibrium data and the computation of stages is very
difficult. In such cases, the requirements are best obtained in the laboratory without
detail study of the equalibria. (Treybal, Mass Transfer Operations, 1987).
Beside that for multicomponent separations also, special computer programs
for these multistage operations embodying heat and material balances and
sophisticated phase equilibrium relations are best left to professionals. Most such work
is done by service organizations that specialize in chemical engineering process
calculations or by specialize in chemical engineering organizations. (Stanley M. Walas,
Chemical Process Equipment, 1988).
Sieve tray (perforated plate) Column were choose for the extraction of these
components. These multistage, countercurrent columns are very effective, both with
respect to liquid-handling capacity and with respect to extraction efficiency, particularly
for system of low interfacial tension, which do not require mechanical agitation for good
dispersion.
4.2

CHEMICAL DESIGN OF LIQUID LIQUID EXTRACTION COLUMN

4.2.1

Choice of Solvents

There is usually a wide choice of liquids to be used as solvent for extraction operations.
It is unlikely that any particular liquid will exhibit all the properties considered desirable
for extraction, and some compromise is usually necessary. The following factors need
to be considered when selecting a suitable solvent for a given extraction affinity for
solute, partition ratio, density, miscibility, safety and cost. Based on the factors that
need to be considered water was choosing as a solvent in this system.
4.2.2

Estimation or Gather the Physical Properties

233

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Most of the design parameter used were refer to mass balance, energy balance data
and generated by chemical Engineering Simulation Software, HYSIS.
The properties data as state below:
Flowrate at the dispersed phase, QD

1254.92 ft3/hr

Flowrate at the continuous phase, QC

1.785 ft3/hr

Density at the dispersed phase, D

24.10 lb/ ft3

Density at the continuous phase C

41.45 lb/ft3.

The data was evaluated at system temperature and pressure.


4.2.3

Determination of Number of Stages

To determine the theoretical stages required, by assuming the minimum solvent to feed
ratio required to remove all the minimum component, so that is the extraction factor, =
1(Schweitzer, Separation Handbook). Equation 4.1 was used. The value for X f =
0.0195 kg CH3OH/ kg water, Ys = 1.57 x 10-6 kg CH3OH/ kg water was compute from
the mass balance at this system.
Number of theoretical stage, Nf = Xf Ys/m
Xr Ys/m

Nf = 0.0195 (1.57 x 10-6 / 0.001)


(1.57 x 10-6 / 0.001)

-1

(4.1)

-1

= 10.42 stages
= 10 stages
Where,

Xf

= weight solute /weight feed solvent in the feed phase

Ys

= weight solute / weight extraction solvent in extract

Xr

= weight solute /weight feed solvent in the raffinate phase

= slope at the equilibrium line dY/dX

234

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

The number of mass transfer unit, Nor is identical to the number of the theoretical
stages when extraction factor, = 1.
Nor

= Xf Ys/m

-1

(4.2)

Xr Ys/m
Nor

= 10 units

By assuming column efficiency, E is 80%, the number of real stages, N was


determining by using equation 4.3.
N = (Nf -1)/ E

(4.3)

= (10 1)/ 0.8


= 11 stages
4.2.4

Sizing of Sieve Tray

The sieve tray sizing was base on the manufacturers literature. Usually the tray
spacing is from (6 to 24) in, and perforation diameter, do usually from (0.32 to 0.64) cm
or (1/8 to 1/4) in diameter. By take 2 ft tray spacing, Zt, 0.25 in holes on 0.75 in
triangular spacing. The downcomer area is found with equation 4.4.
h

= 4.5 Vd2 C / 2gc

h = 2

(4.4)

= 4.5 Vd2 C / 2gc

4.5(41.45)
2(4.18 x 108) 17.35

Vd

= 12471 ft/hr

Ad

= QD/ Vd

Vd2

(4.5)

= 1254.92 / 12471
= 0.1006 ft2

235

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Dd

Where,

= 4.2948 in (Downcomer diameter)

Vd

= Velocity of the dowmcomer

= Density at the continuous phase

gc

= gravitational constant

To determine the total holes area in a tray used equation 4.6 and set the velocity
through the holes, Uh are kept below 0.8 ft/sec or 2880ft/ hr to avoid formation of very
small droplet.
Total hole area, AHT

= QD/ Uh

(4.6)

= (1254.92 / 2880)
= 0.4357 ft2
To find the tray area, by using ratio of the tray area to hole area as state below:
Tray area, AT

(/4) (do) 2

Hole area, AH
=

2.21( ds/ do) 2

2.21 (0.75/0.25)2

19.89

19.89(0.4357)

8.666 ft2

3.32 ft

do

perforation diameter

ds

triangular spacing

Tray Area, AT
Tray Diameter, DT

Where,

4.2.5

0.866 (ds) 2

Number of Holes
Hole area, AH

= (/4) (do) 2

(4.7)

236

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

= (/4) (0.25) 2
=0.0245 in2
Number of hole, NH

= AHT/AH

(4.8)
2

= 0.4357ft / 0.0245 in

= 2560 units
4.2.6

Column Parameter

Number of tray, NT required and the tower high, HT is determining by using equation
4.9 and 4.10 respectively. The efficiency of the tray is base on assumption of the
column efficiency.
Number of trays, NT

= Nf / ET

(4.9)

= 10 / 0.8
= 13 trays
Column Height, CT

= Zt x NT

(4.10)

= 2 (13)
= 26 ft + 3 ft (including 1.5 ft at each end)
= 29 ft
Column diameter same with the tray diameter, so
Column diameter, DC

= 3.32 ft.

Column area, AC

= 8.67 ft2

Net area and active are were determined by using equation 4.11 and 4.12 respectively.
Net area, AN

= AC - Ad

(4.11)

= 8.67 0.1739
= 28.4961ft 2
Active area, Aa

AC - 2Ad

(4.12)

= 8.67 (2 x 0.1739)
= 8.322 ft2
Where,

Ad = downcomer area

237

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

The height equivalent to theoretical stages, (HETS) and height of transfer unit, Hor are
calculated by using equation 4.13 and 4.14 respectively.
HETS

Hor

4.2.7

CH / Nf

(4.13)

29 / 10

2.9

CH / Nor

2.9

(4.14)

Weeping Evaluation

By analogy with distillation. Weir length, lw is calculated by referring to Figure 11.31


from Coulson and Richardson Vol.6 page 572, which determined the value is base on
the ratio of Ad/AC to get the ratio of lw/DC. The weir height determine from standard form
as follows:
Weir height

= 50 mm

Hole diameter

= 5 mm

Plate thickness

= 5 mm

Weir crest were determined by using value of maximum flowrate and minimum
flowrate based on process condition. Each weir crest value determine by using
equation 4.15 and equation 4.16 respectively.
Max how

Min how

2/3

750

Lw max / D( lw)

750

3.8106/ (380.048 x 1.2705)

29.73 mm liquid

750

Lw min / D( lw)

750

0.4512/ (380.048 x 1.2705)

(4.15)
2/3

2/3

(4.16)
2/3

238

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

7.17 mm liquid

At minimum rate hw + how = 50 + 7.17 =57.17 mm


Where,

lw

= weir length

how = weir crest


Lw

= liquid flowrate

Orifice coefficient, Co was referring from figure 11.34 Coulson and Richardson Vol. 6
pg 576 and by assuming.

1.

Plate thickness : hole diameter

=1

2.

Ah/Ap

=5

Plate pressure drop, h


h

51 (Uh / Co)2 (C/D)

(4.17)

51 (0.2438/0.805) (640/380.048)

7.88 mm liquid

(12.5 x 103) / D

Residual head, hr
hr

(4.18)

12.5 x 10 / 380.048

32.89 mm liquid

Total plate pressure drop, ht


ht

h + (hw + how) + hr

7.88 + 57.17 + 32.89

97.94 mm liquid

(4.19)

Plate pressure drop, Pt


Pt =

9.81 x 10-3 ht D

(4.20)

9.81 x 10-3 (97.94) (380.048)

365.147 Pa (N/m2)

Table 4.1: Provisional Plate Design Specification


Column Diameter

1011

mm

239

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Number of Trays
Tray Spacing
Plate Thickness
Total Column Height
Plate Pressure Drop
Plate Material
Downcomer Area
Column Area
Net Area
Active Area
Hole Area
Number of Holes
Weir Length
Weir Height (standard)
Number of manhole
Manhole Diameter (BS 470:1984)
4.3

13
0.6
5
9
7.88
SS304
9.3 x 10-3
0.805
2.647
0.773
1.58 x 10-5
2560
1.2705
50
2
700

trays
m
mm
m
mm liquid
m2
m2
m2
m2
m2
units
m
mm
mm

MECHANICAL DESIGN OF LIQUID LIQUID EXTRACTION COLUMN

In mechanical design, the temperature and the pressure are important properties in
evaluate the thickness and the stress of material. Therefore, the safety factor also need
as precaution and determined by certain consideration such as corrosion factor,
location and process characteristic.
Based on Hysis data, the operating pressure is 2.75 kPa and the safety factor is
10% above operating pressure. The design temperature related to the operating
temperature. The temperature of column operated in 400C at top of column and 270C at
the bottom of the column. The design pressure and design temperature of the system
as follows:
Design Pressure, Pi
Design Temperature, T
4.3.1

0.275 N/mm2 x 1.1

0.3025 N/mm2

500C

Material Construction

The material used is stainless steel (18Cr/8Ni, 304). Design stress at 500C is gain from
table 13.2, pg 809 Coulson & Richardson Vol.6.

240

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.3.2

Design stress, f

165 N/mm2

Diameter Vessel, Di

1011 mm

Tensile Strength,

510 N/mm2

Vessel Thickness

The thickness of column is calculated based on the equation below:


e

PiDi

(4.21)

2f Pi
=

0.3025(1011)
2(165) 0.3025

0.9276 mm

Add corrosion allowance 4mm, so the thickness:


e

4.9276 mm

5 mm

From Coulson & Richardson, value for vessel diameter (m), 1 m, the minimum
wall thickness required should not be less than 5mm including corrosion allowance. A
much thicker wall will be needed at the column base to withstand the wind and dead
weight loads. As a first trial, divide the column into five sections (courses) with
thickness increasing by 2mm per section. Try 10,12,14,16, and 18mm. The average is
14 mm.
4.3.3

Design of Domed Ends

Standard torispherical head are the most commonly used end closure for vessel up to
operating pressure of 15 bar. Torispherical head had been choose because of
operating pressure below 10 bar.
Crown Radius, RC

Di

1.011m

Knuckle Radius, Rk

6%RC =

0.061 m

241

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

A head of this size would be formed by pressing: no joint, so J = one. Stress


concentration factor for torispherical heads, Cs:
Cs

(3 + (RC / Rk))

(3 + (1.011/0.061))

3.053

(4.22)

Therefore the minimum thickness:


e

PiRCCs

(4.23)

2fJ + Pi (Cs 0.2)


=

0.3025(1011) (3.053)
(2 x 165) + (0.3025(3.053 -0.2))

=
4.3.4

2.821 mm

Column Weight

4.3.4.1

Dead Weight of Vessel, Wv


Wv

240 Cv Dm(Hv + 0.8Dm) t

Where;Cv

a factor take 1.15, vessel with plates

Dm

mean diameter, m

(Di + t)

Hv

height or length between tangent line

wall thickness, m

(4.24)

To get a rough estimate of the weight of this vessel by using the average thickness 14
mm.
Dm

1.011 + 0.014

1.025 m

240(1.15) (1.025) (9 +0.8(1.025)) 14

38933.69N

Hence,
Wv

242

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

=
4.3.4.2

389 kN

Weight of plate, Wp

From Nelson (1963) pg 833 in Coulson & Richardson Vol. 6 rough guide to weight of
fittings, take contacting plates, steel including typical liquid loading, 1.2 kN/m2 plate
areas. The total of weight of plate determine by multiply the value with number of tray
design.
Tray area, AT

0.805 m2

Weight of plate

1.2 x AT

1.2(0.805)

0.966 kN

Weight of 13 trays, Wp

4.3.4.3

0.966(13)

12.558 kN

(4.25)

Weight of Insulation, Wi

The insulating material is mineral wool;


Density of mineral wool

130 kg/m3

Thickness of insulation, ti

75 mm

Volume of insulation, Vi

DiHv x ti

(1.0110) (9) (75 x 10-3)

2.144m3

Vig

2.144(130) (9.81)

2734.11 N

Weight of Insulation, Wi

(4.26)

(4.27)

Double this value to allow fittings, so weight of insulation, Wi = 5.468 kN


4.3.4.4

Total weight, W

243

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.3.4.5

Wv + Wp + Wi

389 + 12.56 + 5.47

407.03 kN

(4.28)

Wind Loading

Take dynamic wind pressure, Pw as 1280 N/m2.


Mean diameter, including insulation, Deff:
=

1.011 + 2(0.014 + 0.075)

2.791 m

Loading (per linear meter) Fw;


Fw

PwDeff

(4.29)

1280 (2.791)

3572.48 N/m

Bending moment at bottom tangent line. MX


MX

FwX2

(4.30)

2
=

3572.48 (9)2
2

Where; X

144685 Nm

Distance measured from the free end

The calculated value as the result tabulated in table 4.2. The value requires
determining in strength and suitability of column while in construction and operation. It
also required the safety consideration operation. The operating procedure of the
column should base on this value.
4.3.5

Analysis of Stress

At bottom tangent line,

244

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.3.5.1

Longitudinal and Circumferential Pressure Stress;


h

PiDi

(4.31)

2t
=

0.3025 (1011)
2 (14)

10.92 N/mm2

PiDi

(4.32)

4t
=

0.3025 (1011)
4 (14)

=
4.3.5.2

5.46 N/mm2

Dead Weight Stress


L

(4.33)

(Di + t) t
=

407030
(1011 + 14) 14

=
4.3.5.3

9.03 N/mm2

Bending Stress
b

MX / IV ((Di/2) + t)

Where;MX

Total bending moment

Second bending moment

/ 60 (Do4 Di4)

1011 + 2(14)

1039 mm

/ 60 (10394 10114)

6.32 x 109 mm4

IV

(4.34)

Which;
Do
IV
Therefore,

245

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

144685000

((1011 / 2) + 14)

6.32 x 109
=

11.89N/mm2

The result longitudinal stress, Z is:


Z

L + W b

Z (upwind)

L - W + b

5.46 11.15 + 11.89

6.2 N/mm2

L - W - b

5.46 11.15 11.89

-17.58 N/mm2

Z(downwind)

4.3.5.4

Elastic Stability (Buckling)

Critical buckling stress, C:


C

2 x 104 (t / Do)

(4.35)

2 x 10 (14 / 1039)

269.48 N/mm2

The maximum compressive stress will occurs when the vessel is not under pressure:
W + b

11.15 + 11.89

23.04N/mm2

This value is below critical buckling stress, so design is satisfactory.


Stresses analysis is tabulate in the table 4.3.
4.3.6
4.3.6.1

Vessel Supports Design


Skirt Supports

At ambient temperature.

246

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Type of support

Straight cylindrical skirt (S = 900)

Material construction :

Plain carbon steel

Design stress

135 N/mm2

Youngs Modulus

200000 N/mm2

Skirt height, Hs

3m

The maximum dead weight load on the skirt will occur when the vessel is full of the
mixture.
Approximate weight, Wapprox

Total weight

( / 4) Di2 HVLg

(4.36)

( / 4) (1.011 ) (9) (380.048) (9.81)

26936.56 N

26.9 kN

W + Wapprox

407.03 + 26.9

433.93kN

Bending moment at base of skirt, MS:


MS

Fw

(HV + HS)2

(4.37)

2
2

3.572 (12 / 2)

257.184 kNm

As a first trial, take the skirt thickness as the same as that of the bottom section of the
vessel, ts = 14 mm.
Bending stresses in skirt, bs
Where; Ms

= 4Ms / ( (Ds + ts) tsDs)

Maximum bending moment at the base of the skirt.

ts

Skirt thickness

Ds

Inside diameter of the skirt at the base

(4.38)

So,

247

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

bs

4 (257184 x 103) / (1011+14) (14) (1011)

22.5710 N/mm2

Dead weight stress in the skirt, Ws:


Ws(test)

Ws(operating)

W / ( (Ds + ts) ts)

26900 / (1011+14) (14)

0.60 N/mm2

407030 / (1011+14) (14)

9.03 N/mm2

(4.39)

Thus, the resulting stress in the skirt, s:


Max s (compressive) =

Ws(test) + bs

0.60 + 22.57

23.17 N/mm2

bs - Ws(operating)

22.57 9.03

13.54 N/mm2

Max s (tensile)

(4.40)

(4.41)

Take the joint factor, J as 0.85.


Criteria for design
s (tensile)

> fs J sin

13.54

> 0.85 (135 sin 900)

13.54

> 114.75
248

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

s (compressive)

> 0.125 E (ts/DS) sin

23.17

> 0.125 (200000) (14/1011) sin 900

23.17

> 346.19

Both criteria are satisfied; add 2mm for corrosion gives a design thickness of 16 mm.
4.3.6.2

Base Ring and Anchor Bolt

Approximate pitch circle diameter, say 2.2 m.


Circumferences of bolt circle = 2200
of bolt required, at minimum recommended bolt spacing:
=

2200 / 600

11.5

Closet multiple of 4

12 bolts

Take bolt design stress

125 N/mm2

Bending moment at skirt, MS =

301.834 kNm

Total weight vessel, W

502.53 kN

Area of bolt, Ab

1
Nbfb

Where:Nb

4MS - W

(4.42)

Db

Number of bolts

fb

Maximum allowable bolt stress

MS

Bending moment at the base

Weight of the vessel

249

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Db

Bolt Circle diameter

Therefore,
Ab

4 (257184)

12 (125)
=
Bolt root diameter

- 407030

2.2

40.35 mm2
=

(40.38 x 4) /

7.17 mm

Total compressive load on the base ring per unit length.


Fb

4MS

DS2
=

(4.43)

DS

4 (257184) +
(1.0112)

407030
(1.011)

448.5 x 103 N/m

By taking the bearing pressure as 5 N/mm2. The minimum width of the base ring, Lb:
Lb

Fb
Fc

1
103

448.5 x 103

(4.44)

5000
=

89.7 mm

Actual width can be calculated from this minimum width.


Use M24 bolts (BS 4190:1967) root area = 353 mm2 (Figure 13.30 Coulson &
Richardson Vol. 6)

250

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Actual width required =

Lr + ts + 50mm

150 + 14 + 50

214 mm

Actual bearing pressure on concrete foundation:


fc

Fb
actual width

448500
214000

2.10 N/mm2

Actual minimum base thickness:


tb

Where: fr

Lr (3 fc / fr)

150 ((3 x 2.1) / 140)

25.98 mm

(4.45)

= Allowable design stress in the ring material, typically 140 N/mm2

The design specifications of support are summarized in the table 4.4.

4.3.7

Piping Sizing

The optimum diameter for carbon steel pipe:


d, optimum =

293 G 0.53 -0.37

Where:G

Flowrate (kg/s)

Density (kg/m3)

Pipe thickness, t

P d, optimum

(4.46)

(4.47)

251

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

20 + P
Where:P

Internal pressure, bar

Design stress at working temperature, N/mm2

The piping sizing for this system are shown in table 4.5

Table 4.2 : Summary of the Mechanical Design


Design Pressure
Operating Pressure

2.75 kPa

Operating Temperature

40

0.3025 N/mm2

Design Pressure
Design Temperature

50

Safety Factor

0.10

Design of Domed Ends


Types
Crown Radius
Knuckle Radius
Joint Factor
Stress Concentration Factor
Minimum Thickness
Column Weight
Dead Weight of Vessel
Weight of Plate (per plate)
Weight of Insulation
Total Weight
Wind Pressure
Loading
Bending Moment

Torispherical head
1.011 m
0.061 m
1
3.053
2.821 mm
389
0.966
2734.11
407.03
1280
3572.48
144.685

kN
kN
N
kN
N/m2
N/m
kNm

252

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Table 4.3: Stress Analysis for Liquid-Liquid Extraction Column


Longitudinal Pressure Stress
Circumferential Pressure Stress
Dead Weight Stress
Bending Stress
Z (upwind)
Z(downwind)
Critical Buckling Stress

10.92 N/mm2
5.46 N/mm2
9.03 N/mm2
11.89
6.2
-17.58
269.48

N/mm2
N/mm2
N/mm2
N/mm2

Table 4.4: Design Specification of the Support Skirt


Types of Support

Material Construction
Design Stress
Skirt Height
Young Modulus
L
Approximate Weight
Total weight
Bending Moment at Skirt
Skirt Thickness
Bending Stress in Skirt
ws (test)
ws (operating)
Maximum s (compressive)
Maximum s (tensile)

Straight cylindrical skirt


90
Plain Carbon steel
135
3
200000
380.048
26.9
433.93
257.184
14
22.57
0.60
9.03
23.17
13.54

N/mm2
m
N/mm2
kN
kN
kN
kNm
m
N/mm2
N/mm2
N/mm2
N/mm2
N/mm2

253

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Table 4.5: Piping Sizing for Liquid-liquid Extraction Column


Feed Pipe Sizing
Flowrate, G
Density,
Internal Pressure, P
Design Stress,
Diameter Optimum, d optimum
Corrosion Allowance
Pipe Thickness, t
Solvent Pipe Sizing
Flowrate, G
Density,
Diameter Optimum, d optimum
Extract Pipe Sizing
Flowrate, G
Density,
Diameter Optimum, d optimum
Raffinate Pipe Sizing
Flowrate, G
Density,
Diameter Optimum, d optimum

4.4

13873.67
567.0445
2.75
165
55
4
4.05

kg/hr
kg/hr
bar
N/mm2
mm
mm
mm

1469.1 kg/hr
998 kg/hr
15 mm
1624.37 kg/hr
992.8161 kg/hr
15 mm
15096.74 kg/hr
564.7173 kg/hr
30 mm

PROCESS CONTROL AND INSTRUMENTATION OF THE LIQUID-LIQUID


EXTRACTION COLUMN

Control systems are very important in any of the chemical industries. It is essential for
a process to meet the design specification and products purity that imposed by the
designer or by external constrains such as government regulations and standards.

254

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Process parameters control is to compensate for the process changes with the
existence of external disturbances. Normally, an overall control strategy is design to
meet the following objectives:
1. Ensure stable plant operation conductive to power optimization
2. Maintain product quality according to specification
3. Operate the process and machinery in such a way as to estimate or minimize
the possibility of activating last resort safety measures such as relief valve and
surge system, thus ensuring safe plant operation.
Compensate for perturbations cause by external factors such as ambient and
cooling water temperature variations. Provide an intelligent man-machine interface
capable of presenting process and control system information and interactive format.
Typically, there are two types of control systems- feedback control and feed
forward control. In this case, the feedforward control is applied; in feedforward control
its take corrective action before they upset the process. In this system also, solvent use
is lighter than the material being extract, the two input indicated are of course
interchanged. Both inputs are on flow control. The light phase is removing from the
tower on LC (level control) or at the top of level maintain with an internal weir. The
bottom stream is removed on interfacial level control (ILC). The relative elevations of
feed and solvent input nozzles depend on the nature of the extraction process. The
temperature of an extraction process ordinarily is controlled by regulating the
temperature of the feed stream.

REFERENCES

Buford D.Smith, 1963. Design of Equilibrium Stage Processes, United State of


America. McGraw-Hill.
Robert C.Reid,Prausnitz & Poling,1987.The properties of Gases and Liquid, United
State of America. McGraw-Hill.

255

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Erneat J.Henley & J.D Seader, 1968.Equilibrium-Stages Separation Operations in


Chemical Engineering. Canada. John Wiley & Sons
Philip A.Schweitzer,1988. Handbook of Separations Techniques for Chemical
Engineers,2nd Edition. United State of America. McGraw-Hill.
J.D Seader & Erneat J.Henley, 1998.Separation Process Principles, United State of
America. John Wiley & Sons
R.K.Sinnott, 1999.Chemical Engineering Design, Coulson & Richardson Chemical
Engineering .3rd Edition. Volume 6 .Britain. Butterworth Heinemann
Robert H. Perry, Don W. Green, 1998 Perrys Chemical Engineers Handbook, Seventh
Edition, McGraw-Hill.
J.R Backhurst & J.H Harker.1987.Chemical Engineering Design, Coulson &
Richardson Chemical Engineering .3rd Edition. Volume 2 .United Kingdom.
Pergamon Press.
Stanley M. Walas. 1988. Chemical Process Equipment Selection and Design. United
State of America. Butterworths Series in Chemical Engineering.
Robert E.Treybal.1988. Mass-Transfer Operations,3rd Edition. Singapore, McGraw-Hill
International Series.
K.H Reissinger & Jurgen Schroter. 1980. Selections Criteria for Liquid-liquid
Extractors. Chemical Engineering Magazine, November: 274-256.
P.J Bailes,C.Hanson & M.A Hughes.1976. .Liquid-liquid Extraction: The process, the
equipment. Chemical Engineering Magazine, January 217-231.
Ariffin Marzuki & Nurul Izzi, 2004. PETRONAS Research Centre, Bangi. Interview,19
January.

SECTION 5

256

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

DESIGN OF HEAT EXCHANGER

INTRODUCTION
Shell and tube heat exchangers are the most versatile type of heat exchangers. They
are used in process industries, in conventional and nuclear power stations as
condensers, in steam generators in pressurized water reactor power plants, in feed
water heaters and in some air conditioning and refrigeration systems. They are also
proposed for many alternative energy applications including ocean, thermal and
geothermal. Shell and tube heat exchangers provide relatively large ratios of heat
transfer area to volume and weight and they can be easily cleaned.
Shell and tube heat exchangers offer great flexibility to meet almost any service
requirement. The reliable design methods and shop facilities are available for their
successful design and construction. Shell and tube heat exchangers can be designed
for high pressures relative to the environment and high pressure differences between
the fluid streams.
Shell and tube heat exchangers are built of round tubes mounted in a cylindrical
shell with the tubes parallel to the shell. One fluid flows inside the tubes, while the other
fluid flows across and along the axis of the exchanger. The major components of this
exchanger are tubes (tube bundle), shell, front-end head, baffles and tube sheets.
Shell types-various front and rear head types and shell types have been standardized
by Tubular Exchanger manufacturers Association (TEMA).
The E-shell is the most common due to its cheapness and simplicity. In this
shell, the shell fluid enters at one end of the shell and leaves at the other end that is
there is one pass on the shell side. The tubes may have a single or multiple passes
and are supported by transverse baffles. This shell is the most common for singlephase shell fluid applications. With a single-tube pass, a nominal counter flow can be
obtained. The design of a shell and tube heat exchanger is an iterative process
because heat transfer coefficients and pressure drop depend on many geometric
factors, including shell and tube diameters, tube length, tube layout, baffle type and

257

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

spacing and the numbers of tube and shell passes, all of which are initially unknown
and are determined as part of the design process.
In production of MTBE, heat exchanger is very important equipment. Heat
exchanger is used to increase or to decrease the mixture to the desired temperature. In
order to make the process of production of MTBE taking place in the system, it is
important to make the system at the correct environment. The heat exchanger that we
used here is the shell and tube exchanger. Shell and tube heat exchanger is the most
common type of heat exchanger used in the industry. This is because it has many
advantages. The advantages are: 1.

It provided a large transfer area in a small space.

2.

Good mechanical layout: a good shape for pressure operation.

3.

Used well-established fabrication techniques.

4.

It can be constructed from a wide range of materials.

5.

It can be clean easily.

6.

Well-established design procedures.

7.

Single phases, condensation or boiling can be accommodated in either


the tubes or the shell, in vertical or horizontal positions.

8.

Pressure range and pressure drop are virtually unlimited and can be
adjusted independently for the two fluids.

9.

Thermal stresses can be accommodated inexpensively.

10.

A great variety of materials of construction can be used and may be


different for the shell and tubes.

DESIGNING THE HEATER


In the production of MTBE, a heater is the most important heat exchanger in the
system. Therefore this chapter is going to describes details for this heater and the
design of this piece of equipment.

258

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Heater is used in the process to heated the raw material of MTBE consist of
isobutane and a bit of normal butane. Isobutane and normal butane from the storage is
in liquid form. The heating process is because to produce the isobutane and normal
butane in the gases form before this material is feed to the Snamprogetti Fluidized Bed
Reactor. Here the mixtures of this component initially are in the liquefied gas form at
temperature of -15 oC. It will be heated in the Heater (E-100) and Heater (E101) until it
converted into gas form at temperature of 250 oC using steam. For this heat exchanger
we use the counter current process. The temperature difference between liquid and
gas phase is quit big, so we need two heat exchanger in series. The shell and tube
heat exchanger is the floating head type.

T = 250OC

T = 350OC

STEAM IN

T = -15 OC

STREAM 2

STEAM IN

STREAM 3

STREAM 4
T = 250 OC

T = 117 C

E100

E101
STEAM OUT

T = 120 OC

STEAM OUT
T = 250OC

Figure 5.1 : Heat Exchanger In Series For The Heating Process

5.1

CHEMICAL DESIGN OF HEAT EXCHANGER

The chemical engineering design for the heat exchanger is also known as thermal. The
design requires the calculation of the heat transfer area required. From this value,
design features of the unit such as the tube and shell size, tube counts and layout is
determined. In addition, then pressure loss of the fluids across the unit is also
calculated by determined the pumping capacity required. The calculation of the design

259

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

is base on the first heat exchanger (E100). The chemical design is based on Bells and
Kern method. Bells method accounts for the major bypass and leakage streams. Kern
method was based on experimental work on commercial exchangers with standard
tolerances and will give a reasonably satisfactory prediction of heat-transfer coefficient
for standard design.
5.1.1

Physical Properties Of The Stream

Table 5.1:

Properties of Raw material (Isobutane and N-butane) and

Steam for (E100)


Component

Raw material (Isobutane

Steam

Temperature inlet, oC
Temperature outlet, oC
Specific heat, j/kg oC
Thermal conductivity, W/mK
Density, kg/m3
Viscosity, kg/ms
Feed flowrate, kg/s

and normal butane)


t1 = -15
t2 = 117
2155
0.07
485
1.30005 x 10-4
10.9314

T1 = 250
T2 = 120
2010
0.0306575
0.49375
1.55263 x 10-5
1.7649

5.1.2 The Calculation Of Tm


To determine the mean temperature, Tm
Tm = Ft Tlm

(5.1)

Where
Tm = true temperature difference

260

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Ft = temperature correction factor


Before Tm can be obtained, logarithmic mean temperature Tlm must be calculated
Using the equation:

Tlm =

(T1 - t 2 ) - (T2 - t1 )
(T - t )
ln 1 2
(T2 - t1 )

(5.2)

Where
Tlm = log mean temperature difference
T1

= inlet shell-side fluid temperature

T2

= outlet shell-side fluid temperature

t1

= inlet tube-side temperature

t2

= outlet tube-side temperature

Tlm =

( 250 - 117 ) - (120 + 15 )


(250 - 117)
ln
(120 - (-15))

Tlm = 134.00

the temperature correction factor can be obtain by using figure 12.19 (Coulson &
Richardsons Chemical Engineering)

261

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

R=

T1 - T2
t 2 - t1

R=

(250 - 120)
(117 - (-15))

(5.3)

R = 0.98

S=

t 2 - t1
T1 - t1

S=

(117 - (-15))
(250 - (-15))

(5.4)

S = 0.50

Using figure 12.19, (Coulson & Richardsons Chemical Engineering)


Ft = 0.82
Substitute the above value into equation (1.1) below :
Tm = Ft Tlm
Tm = ( 0.82 )(134 .00
Tm = 109.88

C)

From table 12.1 (Coulson & Richardsons Chemical Engineering), we take overall
Coefficient, U = 300 W/m2 0 C
Duty for this heat exchanger is obtain from the energy balance. The duty is,
Q = 3109542.883 W

262

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Then we need to calculate the surface area using equation below.

A=

Q
UTm

A=

3109542.88 3
(300 )(109 .88 )

(5.5)

A = 94.33 m2

5.1.3

Number Of Tubes Calculation

From table 12.3 (Coulson & Richardsons Chemical Engineering), we take standard
pipe of:
Inside diameter, di

= 16 mm

Outside diameter, do

= 20 mm

Length of pipe is assumed as 16 ft.


Length, L

= 4.88 m

Area of the pipe can be calculated using equation below


area = L D

(5.6)

area = (4.88)(3.142)(0.02)
area = 0.3067 m2
Using the area needed from the duty and area for each tube, the number of
Tube, Nt that we get is,

Nt =

Nt =

A
a

(5.7)

94.33
0.3067

Nt = 307.56

Therefore the number of tube, Nt = 308 tubes

263

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

5.1.4

Bundle And Shell Diameter Calculation

The tubes in heat exchanger are usually arranged in an equilateral triangular, square
or rotated pattern. The triangular and rotated square patterns give higher heat transfer
rates. Here we use the triangular pattern.
The triangular pitch of 1.25 is chosen as the tube arrangement.
Bundle diameter

Db = do (Nt / K1 )1 / n1

(5.8)

From table 12.4 (Coulson & Richardsons Chemical Engineering), for 1.25 triangular
pitch, number of passes = 2, then we can obtain
K1 = 0.249
n1 = 2.207
Db = do (Nt / K1 )1 / n1
Db = 0.02 (308 / 0.249 )1 / 2.207
Db = 0.50m

Assume using pull-through floating head type.


From figure 12.10 (Coulson & Richardsons Chemical Engineering), for bundle
diameter 0.33, bundle clearance is 93 mm.
Shell diameter, Ds
Ds = 0.50 + 0.093
= 0.60m

5.1.5 Tube Side Coefficient, hi

264

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Mean temperature of the tube


t mean =

t1 + t 2
2

t mean =

- 15 + 117
2

(5.9)

t mean = 51 o C

cross sectional area = d12/ 4

(5.10)
2

= (3.142)(0.016 ) / 4
= 0.0002 m2
Tube / pass = 308 / 2

(5.11)

= 154 tube / pass


Total flow rate area = (cross sectional area)(tube / pass)

(5.12)

= (0.0002)(154)
= 0.0308 m2
Steam mass velocity, Gt = (steam flow rate)/(total flow rate area)

(5.13)

= (1.7649)/(0.0308)
= 57.30 kg / sm2
Steam linear velocity, u1 = (Gt)/(steam density)

(5.14)

= (57.30)/(0.49375)
= 116.05 kg / ms
Ratio of L / di = 4.88 / 0.016

(5.15)

= 305

Reynolds number, Re

265

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Re =

di

Re =

(0.49375) (116 .05 ) (0.016)


1.55263 x 10 - 5

(5.16)

Re = 59047.87

Heat transfer factor figure 12.31 (Coulson & Richardsons Chemical Engineering),
Jh = 4.1 x 10-3
Prandtl number,

Pr =

Pr =

Cp

(5.17)

kf
(2.010 x 10 3 )(1.55263 x 10 - 5 )
0.0306575

Pr = 1.0180

Tube side coefficient, hi can be calculated using equation below.


jhk f Re Pr 0.33
hi =
di

hi =

(4.1 x 10 - 3 )(0.030657 5)(59047.8 7)(1.0180)


0.016

(5.18)

0.33

hi = 466.62 W / mo C

266

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

5.1.6 Shell Side Coefficient, hs


Take baffle spacing as 1/3 from the shell diameter, so Baffle spacing:
lB

= Ds / 3

(5.19)

= 0.60 / 3
= 0.20 m
Tube pitch, pt

= 1.25 do

(5.20)

= (1.25)(0.02)
= 0.025 m
Flow area, As

As =

As =

(Pt - do )(D s )(IB )


Pt

(5.21)

(0.025 - 0.02)(0.60 )(0.20)


0.025

A s = 0.0240 m2

Mass velocity, Gs
Gs =

Ws
As

Gs =

10.9314
0.0240

(5.22)

Gs = 455.48 kg / m 2 s

Shell side velocity

267

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

us =

Gs

us =

455.48
485

(5.23)

us = 0.9391 m / s

Shell side equivalent diameter for triangular pitch arrangement


de =

1.10 2
(p t - 0.917d o 2 )
do

de =

1.10
(0.025 2 - 0.917(0.02 )2 )
0.02

(5.24)

de = 0.0142 m

Calculate the Reynolds number


Re =

Re =

Gs de
Isobutane

(5.25)

(455.48)(0 .0142)
0.00013000 5

Re = 49750.52

Prandtl number
Pr =

Pr =

CpIsobutane Isobutane
kf

(5.26)

(2155)(0.0 00130005)
0.07

Pr = 4.0023

268

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Choose baffle cut of 25%, from figure 12.30 (Coulson & Richardsons Chemical
Engineering), we can obtained
Jf

= 2.70 x 10-2

Assumed that the viscosity correction is negligible

hs =

k f jf Re Pr 1 / 3
de

hs =

(0.07)(2.7 0 x 10 - 2 )(49750.52 )(4.0023 1/3 )


0.0142

hs = 10513.35 W / m2

(5.27)

5.1.7 Overall Heat Transfer Coefficient, Uo


Material of construction = carbon Steel
Thermal conductivity of the tube wall
Kw

= 38 W/moC

Assumed dirt coefficient as


hid = 8500 W/m2 oC
hod = 8500 W/m2 oC
1
1
1
d ln(d o /di )
1
( do /di ) + 1 (do /di )
=
+
+ o
+
Uo
hs hod
2k w
hid
hi
1
= 0.0039738 m2
Uo
Uo = 322.85 W / m2

5.1.8

C/W

(5.28)

Tube Side Pressure Drop

269

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Reynolds number , Re = 59047.87


From figure 12.24 (Coulson & Richardsons Chemical Engineering),
jf = 3.10 x 10-3
Neglect the viscosity correction term

Pt = Np [ 8 jf (L/d i )(/ W )- m + 2.5 ]

ii 2
2

Pt = 2[ 8(3.10 x 10 - 3 )(4.88/0.0 16) + 2.5 ]

(5.29)
( 0.49375 )(116 .05 )2
2

Pt = 66921.86 N / m2
Pt = 66.92 kPa

5.1.9

Shell Side Pressure Drop

Reynolds number
Re = 49750.52
From figure 12.30 (Coulson & Richardsons Chemical Engineering),
Jf = 2.70 x 10-2
Shell side pressure drop can be calculated using equation below
P = 8j f ( Dd / de ) ( L/I B ) ( s / 2) ( / w ) -0.14

(5.30)

P = 47.63 kPa

Table 5.2: Summary Of Chemical Design For Heat Exchanger In Series

270

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Heat Exchanger
Temperature range, (o C)
Feed flow rate, (kg/hr)
Steam flow rate, (kg/hr)
Log mean temperature

E100
Shell side
250 150
Tube side
-15 117
39353
6353.64
134.00

difference, , Tm (o C)
True temperature

109.88

difference, Tm (o C)
Overall coefficient, U (W/m2 300
o

C)
Duty, Q (w)
Surface are, A (m2)
Length of tube or shell, L
Tube diameter di (mm)
Tube diameter do (mm)
Area of pipe, a (m2)
Number of tube, Nt
Bundle diameter, Db(m)
Shell diameter, Ds(m)
Baffles spacing, IB(m)
Tube side coefficient, hi

3109542.883
94.33
4.88m or 16 ft
16
20
0.3067
308
0.50
0.60
0.2000
466.62

(W/m2 o C)
Shell side coefficient,

10513.35

hs(W/m2 o C)
Overall heat transfer

322.85

coefficent, Uo (W/m2 o C)
Tube side pressure drop,

66.92

P (kPa)
Shell side pressure drop,

47.63

P (kPa)
5.2

MECHANICAL DESIGN OF HEAT EXCHANGER

The mechanical engineering design of heat exchanger determines the physical


elements that make up the unit as well as their respective dimensions. This design
follows the procedures specified by the Tubular Heat Exchanger association (TEMA)
Mechanical Standards. It is applicable to shell and tube exchangers with internal
diameter not exceeding 60 in. (1524mm), a maximum design pressure of 3000psi (204
bar) or a maximum product of nominal diameter (in) and design pressure (psi) of

271

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

60000. In addition, the design also complies with the American Society of mechanical
Engineers (ASME) Boiler and Pressure Vessel Code, Section VIII, Division 1.

5.2.1

Design Pressure

For the design of tube and shell parts, a safety factor of 10% is included to determine
the design pressures.
Operating pressure = 1.1 bar
10% above the pressure for safety
Pi = 1.1 x 10
= 11 bar
= 1.1 N / mm2
5.2.2

Design Temperature

For the shell side and tube side the operating temperature is at 250 oC, so:
Shell-side design temperature = 1.1x 250 oC
= 275 oC
Adding 2 oC for uncertainties in temperature prediction
TD

= 275 + 2
= 277 oC

5.2.3

Material Of Construction

For the heat exchanger, the material used for construction is carbon steel. This
selection of material is depending on the economic factor and also level of
corrosiveness of the fluid used. Since the properties of the fluid both in the tube and
also in the shell are not corrosive fluid, therefore the carbon steel is used because it is
more economics compared to stainless steel.
5.2.4

Exchanger Type

For the heater design, pull through floating head exchanger is chosen as the
exchanger type. Internal floating head is versatile than other type and also suitable for

272

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

high temperature different between shell and tubes. The tube for internal floating head
also can be rod from end to ends and the bundle are easier to clean.
5.2.5

Minimum Thickness Of Cylindrical Section Of The Shell

The minimum thickness of the cylindrical section of the shell to stand the pressure can
be obtained from the calculation below.

e=

PiDi
2jf - Pi

(5.30)

Where,
Pi = design pressure
Di = shell diameter
F = design stress (from table 13.2, Coulson & Richardsons Chemical Engineering)

e=

(1.1)(600)
2(1)(85) - (1.1)

e = 3.91 mm

adding the corrosion allowance = 2 mm


e = 3.91 + 2

e = 5.91 mm
Take the round number of the thickness
e = 6.00 mm

5.2.6

Longitudinal Stress

h =

h =

PiDi
2t

(5.31)

(1.1)(600)
2(6)

h = 55.00 / mm 2

273

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

5.2.7

Circumferential Stress

h =

PiDi
4t

(5.32)

h = (1.1)(600) / 4(6)
h = 27.50 N / mm 2
5.2.8

Minimum Thickness Of Tube Wall

Minimum thickness of the tube wall can be calculated using the equation

e=

(5.30):

PiDi
2jf - Pi

e=

(1.1)(600)
2(1)(85) - (1.1)

e = 3.91 mm

adding the corrosion allowance = 2 mm


e = 3.91 + 2
e = 5.91 mm
5.2.9

Minimum Thickness Of Head And Closure

The minimum thickness of the torispherical head can be calculated by ,

e=

PiR c Cs
2jf + Pi (Cs - 0.2)

(5.33)

Rc = crown radius
Rk = knuckle radius
Cs = stress concentration factor for torispherical head

274

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Cs = 1/4 3 + R c / Rk

(5.34)

Rc = Ds = 600 mm
Rk = 0.06(500) = 36 mm
Cs = 1.77
e=

(1.1)(600) (1.77)
2(1)(85) + 1.1(1.77 - 0.2)

e = 6.80 mm

Adding corrosion allowance


e = 6.80 + 2
= 8.80 mm
5.2.10 Minimum Thickness Of The Channel Cover
e = (C p )(D e )(Pi /f) 1/2

(5.35)

where
Cp = a design constant, depend on the edge constraint (0.45)
De = nominal plate diameter
f

= design stress

e = (0.45)(600)(1.1/85)1/2
= 30.72 mm

Adding corrosion allowance = 2 mm


E = 30.72 + 2
= 32.72 33 mm
5.2.11 Design Load
Dead weight of vessel

275

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

W v = C v mDm g(H v + 0.8D m )t x 10 -3

(5.36)

where
Wv = total weight of the shell
Cv = 1.08 for vessels with only few internal fitting
Wv = (1.08) (7700)(0.602)(9.81)(4.88+0.8(0.602))(2 x 10-3)
= 1654.45 N
Weight of tubes
W t = Nt (do2 - d12 )Lmg
W t = 308 (0.02

(5.37)

- 0.016 2 )(4.88)(77 00)(9.81)

W t = 51362.08 N

Weight of insulation
Material used = mineral wool insulation
Insulation thickness = 50 mm = 0.05 m
Density = 130 kg / m3
Approximate volume of insulation

V = H v [ (r + r1 )2 - r 3 ]

(5.38)

V = (4.88) [ (0.60 + 0.05) - (0.50)


2

V = 2.64 m3
W t = V g

(5.39)

W t = (2.64)(130 )(9.81)
W t = 3366.79 N

Total weight of heat exchanger


WT = Wv + Wt + Wi

(5.40)

276

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

WT = 1654.45 + 51362.08 + 3366.79


= 56383.32 N
= 56.38 kN
5.2.12 Pipe Size Selection For The Nozzle
pipe size for isobutane inlet
material of construction

= carbon steel

density inlet isobutane,

= 600 kg / m3

flow rate isobutane at inlet, Gisobutane = 10.9314 kg / s


Diameter pipe for isobutane inlet, Disobutane
Disobutane (in) = 293G0.53

-0.37

(5.41)

Disobutane (in) = 293(10.9314) 0.53(600)-0.37


Disobutane (in) = 97.60 mm
Pipe size for isobutane at outlet,
material of construction

= carbon steel

density outlet isobutane,

= 370 kg / m3

flow rate isobutane at outlet, Gisobutane = 10.9314 kg / s


Diameter pipe for isobutane outlet, Disobutane
Disobutane (out) = 293G0.53

-0.37

Disobutane (out) = 293(10.9314) 0.53(370)-0.37


Disobutane (out) = 116.72 mm
Diameter pipe for steam at inlet stream

277

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

material of construction

= carbon steel

density inlet steam,

= 0.5654 kg / m3

flow rate steam at inlet, Gsteam

= 1.7649 kg / s

Diameter of pipe
Dsteam (in) = 293G0.53

-0.37

Dsteam (in) = 293(1.7649) 0.53(0.5654)-0.37


Dsteam (in) = 488.94 mm

Diameter pipe for steam at outlet stream


material of construction
density outlet steam,

= carbon steel
= 0.4221 kg / m3

flow rate steam at outlet, Gsteam = 1.7649 kg / s


Diameter of pipe
Dsteam (out) = 293G0.53

-0.37

Dsteam (out) = 293(1.7649) 0.53(0.4221)-0.37


Dsteam (out) = 544.79 mm

278

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Figure 5.2 : Steel pipe nozzle


Table 5.3 : by taking D = 100 mm, the selected tube nozzle is :
Nominal pipe
size, inch
4

Outside
diameter, inch
4.5 (114.30)

Schedule no.
4OST

Wall thickness,
inch
0.237
(6.02 mm)

Inside
diameter, inch
4.026
(102.26 mm)

Table 5.4 : by taking D = 500 mm, the selected tube nozzle is :


Nominal pipe
size, inch
20

Outside
diameter, inch
20 (508)

Schedule no.
4OST

Wall thickness,
inch
0.375
(9.53 mm)

Inside
diameter, inch
19.250
(488.95 mm)

(From Perry R.H and Green, Don (1984), Perrys Chemical Engineers Handbook, 7th
Edition, McGraw-Hill Book)

5.2.13 Standard Flanges

279

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Flanges used in this design are chosen from the standard flanges. Here standard
flanges are adapted from the British standard (BS 4504), nominal pressure 10 bar.

Figure 5.3 Standard Flange


Standard flange for inlet isobutane
Diameter isobutane inlet pipe = 97.60 mm
Used standard o.d pipe

= 114.3 mm

Table 5.5 : Standard Flange for Inlet isobutane


nom.
size

100

pipe
o.d
d1

114.3

210

Flange
b

16

hi

Raised face Bolting


Drilling
d4
f
No.
d2

45

148

M16

18

d3

170

130

Neck
h2

10

Standard flange for outlet isobutane


Diameter isobutane outlet pipe

= 116.72 mm

Used standard o.d pipe

= 114.3 mm

280

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Table 5.6 : Standard Flange for Outlet isobutane


nom.
size

100

pipe
o.d
d1

114.3

210

Flange
b

16

hi

45

Raised face Bolting


Drilling
d4
f
No.
d2

148

M16

18

d3

170

130

Neck
h2

10

Standard flange for inlet steam


Diameter steam inlet pipe

= 488.94 mm

Used standard o.d pipe

= 508 mm

Table 5.7 : Standard Flange for Inlet Steam


nom.
size

pipe
o.d
d1

500

508

Flange
D
b

645

24

hi

68

Raised face Bolting


Drilling
d4
f
No.
d2

570

M20

20

22

Neck
h2

d3

600

538

15

12

Standard flange for outlet steam


Diameter steam outlet pipe

= 544.79 mm

Used standard o.d pipe

= 508 mm

Table 5.8 : Standard Flange for Outlet Steam


nom.
size

pipe
o.d
d1

500

508

Flange
D
b

645

24

hi

68

Raised face Bolting


Drilling
d4
f
No.
d2

570

M20

20

22

Neck
h2

d3

600

538

5.2.14 Design of Saddles

Table 5.9: Using Ds = 600mm, the standard steel saddles for vessels up
to 1.2m :
281

15

12

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Vessel

Maximum

diamete

weight

r (m)
0.9

(kN)
56.38

Dimension (m)
C
E
J

t2

0.63 0.15 0.81 0.34 0.275 0.095 10

t1

mm
Bolt diameter

20

5.2.15 Baffles

Type : transverse baffle

Baffle diameter for plate shell is given as, Ds = the nominal diameter of the shell for
plate shell. So baffle diameter = 0.600 m = 23.63 = 600 mm

Diameter of tube holes in baffles, Dh

Dh = outer diameter of the tube


= (0.16 + 1/32) x 20.2
= 3.86 mm

Number of baffle segmental, Nb

Nb = length tube / inside diameter shell


= 4880 / 600
= 8.13 8 baffles

Vent and drain -A drain and vent connection shall be provided on the shell side

Table 5.10: Summary Of Mechanical Design For Heat Exchanger In Series


Heat Exchanger

E100

282

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Design pressure, bar

11

design temperature, oC

277

Material Of Construction

Tube side: Carbon steel


Shell side : Carbon steel
6.0

Minimum Thickness Of
Cylindrical Section Of The
Shell, mm
Longitudinal Stress,

55.0

N/mm2
Circumferential Stress

27.5

N/mm2
Minimum Thickness Of
Tube Wall, mm
Minimum Thickness Of
Head And Closure,

5.91
8.80

Minimum Thickness Of
The Channel Cover,mm

33.0

Design Load, kN
Diameter pipe for
isobutene inlet and outlet,
mm
Diameter pipe for steam
inlet and outlet, mm
Vessel diameter, m
Types of baffles
Number of baffle
segmental, Nb

56.38
100
500
0.9
transverse
8

REFERENCES
D. Brian Spalding, J.Taborek, Heat Exchanger Design Handbook, Volume 1
- Heat Exchanger Theory, Hemisphere Publishing Corporation, Washington, New
York, London, 1983.

283

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

D. Brian Spalding, J.Taborek, Heat Exchanger Design Handbook, Volume 2


-

Fluid Mechanics and Heat Transfer, Hemisphere Publishing Corporation,

Washington, New York, London, 1983.


J. M. Chenoweth, D. Chisholm, R. C. Cowie, D. Harris, A. Illingworth, J. F.
Lancaster, M. Morris, I. Murray, C. North, C. Ruiz, E. A. D. Sauders, K. V. Shipes, J.
Dennis Usher, R. L. Webb, Heat Exchanger Design Handbook, Volume 4 Mechanical Design of Heat Exchangers, Hemisphere Publishing Corporation 1983,
Washington, New York, London, 1983.
D. K. Edwards, P. E. Liley, R. N. Maddox, Robert Matavosian, S. F. Pugh, M.
Schunk, K. Schwier, Z. P. Shulman, Heat Exchanger Design Handbook, Volume 5
- Physical Properties, Hemisphere Publishing Corporation 1983, Washington, New
York, London, 1983.
E. A. D. Saunders, B. Sc. C. Eng., M. I. Mech. E. Heat Exchangers,
Selection, Design and Construction, Longman Scientific and Technical, 1998.
Yokell, Stanley, A working Guide to Shell and Tube Heat Exchangers,
McGraw-Hill Publishing Company, 1990.
Sadik Kakac, Hongtan Cin, Heat Exchangers, Selection, Rating, and
Thermal Design, CRC Press, Boca Raton, Boston London New York, Washington,
D.C, 1998.
Gupta, J. P., Working With Heat Exchangers: question and answers,
Hemisphere Publishing Corporation, A member of the Taylor and Francis Group, 1990.
Warren D. Seider, J.D. Seider, Daniel R. Lewin, Process Design Principles,
Synthesis, Analysis and Evaluation, 1997.
Stanley M. Wales, Chemical Process Equipment, Selection and Design ,
Butterworths Series in Chemical Engineering, 1990.
Frank P. Incropera, David P. Dewitt, Fundamentals of Heat and mass
Transfer, 5th Edition, John Wiley & Sons, Inc, 2002.
Holman, J.P, Heat Transfer, 7th Edition, McGraw-Hill, Inc, 1992.
Kern. D.Q, Process Heat Transfer, International Editions, McGraw-Hill, Inc,
1965.
Perry R.H and Green, Don, Perrys Chemical Engineers Handbook, 7th
Edition, McGraw-Hill Book Company, Singapore, 1984.
Bhattacharya,

B.B,

Introduction

to

Chemical

Equipment

Design,

Mechanical Aspects, Indian Institute of Technology, 1976.

284

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Holman, J.P. Heat Transfer, 7th Edition, McGraw-Hill, Inc, 1992.


Kern. D. Q Process Heat Transfer, International Editions, McGraw-Hill, Inc,
1965.
Perry R.H and Green, Don, Perrys Chemical Engineers Handbook, 7th
Edition, McGraw-Hill Book Company, Singapore, 1984.
Sinnott, R. K., Coulson & Richardson, Chemical Engineering Volume 6,
Chemical Engineering Design, Butterworth Heinemann, 1999.
Carl R. Branon, Rules Of Thumb For Chemical Engineers, Gulf Publishing
Company, 1994.
Perry R.H and Green, Don, Perrys Chemical Engineers Handbook, 7th
Edition, McGraw-Hill Book Company, Singapore, 1984.
Sinnott, R. K., Coulson & Richardson, Chemical Engineering Volume 6,
Chemical Engineering Design, Butterworth Heinemann, 1999.
Peters, max Stone, Plant Design and Economics for Chemical Engineers,
2nd Edition, McGraw-Hill Chemical Engineering Series, 1968.

CHAPTER 2

285

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

PROCESS CONTROL AND INSTRUMENTATION

2.1

INTRODUCTION

All processes are subject to disturbances that tend to change operating conditions,
compositions and physical properties of the streams. In order to minimize those ill
effects that could result from such disturbances, chemical plants are implemented with
substantial amounts of instrumentation and automatic control equipment. In critical
cases and in especially large plants, moreover, the instrumentation is computer
monitors for convenient, safety and optimization.
A chemical plant is an arrangement of processing unit. The plant overall
objective is to convert the raw materials into desired product using available sources of
energy in the most economical way. All operating unit should be monitored. Methods of
limiting hazard levels by control features include sensoring control on limits and various
aspects of sequential and continuous monitoring.
In control situations, the demand for speed of response may not be realizable
with an overly elaborate mathematical system. Moreover, in practice, not all
disturbances are measurable and the process characteristics are not known exactly.
Accordingly, feedforward control is supplemented in most instances with feedback. In a
well-designed system, typically, 90% of the corrective action is provided by feed
forward and 10% by feedback with the result that the integrated error is reduces by a
factor 10%. The main types of instrument used for chemical process plants are flow
controller, temperature controller, pressure controller and level controller.
2.2

OBJECTIVES OF CONTROLL

The most important objectives of the designer when specifying control and
instrumentation schemes are:
1.

Safe Plant Operation

286

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

To keep the process variables within known safety operating limits and
within allowable limits.

To detect dangerous situations as they develop and to provide alarms


and automatic shut down system.

To provide interlocks and alarms to prevent unsafe operating


procedures.

2.

Production Specification

To achieve the design product output

To produce the desired quality of final product

To keep the product composition within the specified quality


standards.

3.

Economics

To operate at the lowest production cost, commensurate with the other


objectives.

The operation of the plant must conform to the market condition, which
is availability of raw materials and demand of the final product.

4.

Environmental Regulations

Variable controlled must not exceed the allowable limits set by various
federal and state laws.

5.

Operational Constraint

Various type of equipments used in chemical plant have constrains


inherent to their operation. Such constraints should be satisfied
throughout the operation of plant.

Control systems are needed to satisfy all these operational constrains.

In a typical chemical processing plant these objectives are achieve by combination


of automatic control, manual monitoring and laboratory analysis.

2.3

CONTROL SYSTEM DESIGN SHEET

2.3.1

Heat Exchanger (E-100)

287

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Figure 2.1: Control Scheme for the Heat Exchanger


Table 2.1: Parameter at Heat Exchanger
Intention: To Heat Up the reactant Before Entering Reactor
Objective : To heat up the reactants to 250 oC
Objective
Measurable
Disturbances
Action
Variable
1. To control
Temperature at Change in
Control temperature
temperature of outlet stream
flow rate of the heating by V3 at
outlet stream
S4
feed
steam inlet S3

2.3.2

Set Point
E-100
Temperature
250oC

Catalytic Cracking Fluidized Bed Reactor (op-100)

288

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Figure 2.2: Control Scheme for Catalytic Cracking Fluidized Bed Reactor
Table 2.2: Parameter at Catalytic Cracking Fluidized Bed Reactor
Intention: To Separate Vapor and Liquid from Stream Leaving Heat Exchanger
Set Point
Objective
Measurable
Disturbances
Action
1. To control flow
inside phase
reactor
2. To control solid
flow to relate
speed and flow rate
3. To control
pressure between
reactor and
regenerator
4. To control
temperature
in reactor

2.3.3

Variable
Flow of gas
in phase to
reactor
Solid in and
out in the
reactor and
regenerator
flow rate of
feed into reactor
and regenerator
Temperature in
reactor and
regenerator

Change in flow
of gas in phase
of reactor
Change of solid
flow rate moving
to reactor and
regenerator
Change of feed
flow rate

Control flowrate of the


Input stream S4 by
controlling V3
Control solid in and
solid out in the
reactor and
regenerator
Control pressure by
opening or closing
valve by adjusting V5

Stream S4

Change of
temperature
In reactor and
regenerator

Control temperature
by opening or closing
valve at the air feed
V4 and product V6

180oC

95679.8kg

2.89 bar

Control at Compressor (C-101)

S7

289

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

S8

Figure 2.3: Control Scheme for the Compressor

Table 2.3: Parameter at Compressor

Objective
To maintain
pressure inside
compressor

2.3.4

Intention: To maintain the pressure inside the compressor


Objective : To keep pressure maintain at bar
Measurable
Disturbances
Action
Variable
Pressure
Power or duty
Control pressure
inside
of the
by adjusting V8 at
compressor
compressor
steam inlet S7

Set Point
C-101
pressure
bar

Control at Condenser

290

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Figure 2.4: Control Scheme for the Condenser


Table 2.4: Parameter at Condenser
Intention: To maintain the pressure inside the compressor
Objective : To keep pressure maintain at bar
Objective
Measurable
Disturbances
Action
Variable
1. To control
Temperature at Change in
Control temperature
temperature of outlet stream
flow rate of the heating by V9 at
outlet stream
S9
feed
steam inlet S8

Set Point
E-100
Temperature
50oC

2.3.5 Separator (V-100)

291

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Figure 2.5: Control Scheme for the Separator


Table 2.5: Parameter at Separator
Intention: To Separate Vapor and Liquid from Stream Leaving Heat Exchanger
Objective
Measurable
Disturbances
Action
Set Point
Variable
1. To control level
Level of liquid Change in level
Control level by
Stream
inside phase
in phase
of liquid in phase V10 at inlet stream
S9 of
separator
separator
separator
S9
liquid height
1. To control
Maintain
Change in
Control pressure by
Pressure
pressure
pressure
pressure
opening and closing 0.5 bar
phase separator in phase
of liquid in phase valve by V28 at
separator
separator
stream S10
1. To control
Flow rate at
Change in the
Control Flow at the
Flow into
Flow rate
the bottom of
flowrate of
bottom by V27 at
The feed
inside phase
the separator the separator
stream S11
At stream
separator
S11

292

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

2.3.6 Fixed Bed Reactor (R-101)

V29

V13

Figure 2.6: Control Scheme for the Fixed Bed Reactor


Table 2.6: Parameter at Fixed Bed Reactor
Objective

Intention: To React Isobutene with Methanol to Produce MTBE


Measurable
Disturbances
Action

Set Point

To regulate

Variable
Cooling

Reactant feed

Control temperature

Set the

reactor

water make

temperature and

by V13

temperature

temperature
To maintain

up rate
Pressure in

composition
Pressure feed to

Control the pressure

at 53.3 oC
Pressure at

constant

the fed of

the reactor

in the reactor by

1 bar

pressure at the

stream S15

control of V29

feed stream

2.3.7

Distillation Column (T-101)

293

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Figure 2.7: Control Scheme for the MTBE Distillation Column


Table 2.7: Parameter at MTBE Distillation Column
Intention: To Separate MTBE from Mixture Leaving Reactor
Objective
Measurable
Disturbances
Action
Variable
1. To control level Level of liquid Change of level Control level by
inside column
in column
of column
Adjusting V17
valve at raffinate outlet
Stream S19
2. To control
Temperature Change of
Control temperature by
temperature
inside column temperature
Control V16
inside column
in column
3. To control
Level in drum Change of level Control level by V15
level in drum
in drum
to maintain the
Product output

2.3.8

Set Point
Stream S19
at
15251.9kg/hr
61.2oC

Stream
S17 at
38747.97kg/hr

Liquid-Liquid Extraction Column (T-100)

294

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Figure 2.8: Control Scheme for the Liquid-liquid Extraction Column


Table 2.8: Parameter at Liquid-liquid Extraction Column
Objective
To control flow
at stream S20
To

control

flow

at

Intention: To Extract Methanol and Water from Hydrocarbon


Measurable
Disturbances
Action
Variable
flow of liquid
Change of level
Control flow by adjust
in column
of column
Valve V19 at bottom
outlet stream
Flow of liquid in Change of flow of Control at V20 to keep

stream S21
To control level at the

column
Level of

raffinate

Set Point
Stream
S20 at
40.32kg/hr
Flow inlet

at

liquid extraction
Change of level in

the flow inlet maintain


Maintain the level by

stream S21
Level output at

going out of the

the column

control V21 at stream

raffinate section

Product of S24
To control the density

column
Density level

Change of the

S24
The bottom stream

S24
Interfacial level

intermediate between

change between

removed by control

at bottom

methanol and water

water and

between two

V22

product at

methanol

phase

2.3.9

liquid

interfacial of level

stream S26

Distillation Column (T-102)

295

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Figure 2.9: Control Scheme for the Distillation Column


Table 2.9: Parameter at Distillation Column
Objective
1. To control level
inside column

2. To control
temperature
inside column
3. To control
level in drum

Intention: To Separate Methanol and water


Measurable
Disturbances
Action
Variable
Level of liquid Change of level Control level by
in column
of column
opening and closing
valve V25 at bottom
outlet stream
Temperature Change of
Control temperature by
inside column temperature
opening or closing
in column
Valve 24 at top outlet
stream
Level in drum Change of level Control level by V23
in drum
opening or closing
valve at reflux stream

Set Point
Stream
S28 : at
63.4453kg/hr
62.17oC

Stream
S27

296

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

2.3.10 Mixer (MIX-100)

Figure 2.10: Control Scheme for the Mixer

Table 2.10: Parameter at Mixer


Intention: To Mix Methanol from Recycle and Make Up Methanol
Measurable
Disturbances
Action
Set Point
Variable
1. To control the
Flowrate of
Change of
Control flowrate
M - 101
flowrate
the reactant
flowrate to the
bypass valve
Stream S14
reactor
V12
at 2.88 m3/hr
Objective

297

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

2.3.11 Expander (EX-100)

Figure 2.11: Control Scheme for the Expander

Table 2.11: Parameter for Expander


Intention: To Expand the Pressure Leaving the Reactor
Measurable
Disturbances
Action
Variable
1. To expand the
Pressure
Change of
Control pressure by
pressure
inside the
pressure
adjusting valve V14
expander
Objective

Set Point
Pressure
0.45

38

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

Figure 2.13 : PFD Diagram Before Control

39

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

Legend
TC

Process Flow

PC

Pressure Control

Control Flow

FC

Flow Control

LC

ILC -

Temperature Control

TI

Temperature Indicator

DPC -

Interfacial Level Control

Level control
Differential Pressure Control

Figure 2.13 : Process Control P and ID Diagram

40

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

41

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

REFERENCES

Luyben, W. l., (1990), Process Modelling simulation and Control for Chemical
Engineers, 2nd Edition, McGraw-Hill Chemical Engineering Series
Ogunnaike, B. A. and Ray, W. H. (1994), Process Dynamics, Modeling and
Control, New York, Pxford.
R.K.Sinnott, 1999.Chemical Engineering Design, Coulson & Richardson Chemical
Engineering .3rd Edition. Volume 6 .Britain. Butterworth Heinemann
J.R Backhurst & J.H Harker.1987.Chemical Engineering Design, Coulson &
Richardson Chemical Engineering .3rd Edition. Volume 2 .United Kingdom.
Pergamon Press.
Stanley M. Walas. 1988. Chemical Process Equipment Selection and Design.
United State of America. Butterworths Series in Chemical Engineering.
Chemical Engineering Progress, February 2001, American Institute of Chemical
Engineering.

42

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

CHAPTER 3

SAFETY CONSIDERATION

3.1 INTRODUCTION
Any organization has a legal and moral obligation to safe guard the health and
welfare of its employees and the public. Safety is also good business: the good
management practices needed to ensure safe operation would also ensure efficient
operation.
All manufacturing processes there are additional, special, hazard associated
with the chemical used and the process condition. The designer must be aware of
these hazards and ensure through the application of sound engineering practices
that the risks are reduced to acceptable levels.
Safety and loss prevention in process design can be considered under the
following broad headings :( Coulson and Richardsons Volume 6)
1. Identification and assessment of the hazards
2. Control of the hazards; for example by containment of flammable and toxic
materials
3. Control the process. Prevention of hazardous deviation in the process
variables, (pressure, temperature, flow) by provision of automatic control
system interlocks, alarms, trips, together with good operating practices and
management.
4. Limitation of the loss. The damage and injury caused if an incident occurs,
pressure relief, plant layout, provision of fire-fighting equipment.
In Malaysia, The Occupational Safety and Health Act, 1994 is a tool which
provided a new legal and administrative as a driving force to promote, encourage
and stimulate the high quality standards of health and safety at work place. Both
parties such as employers and employees must give their support and cooperate to

43

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

comply the law and not misuse safety in order to increasing the promotion of safety
awareness and effective safety organization and performance in companies.

3.2 HAZARD AND OPERABILITY STUDY


HAZOP stands for hazard and operability studies. This is asset of formal hazard
identification and elimination procedures designed to identify hazard to people,
process plants and the environment. The techniques aim to stimulate in a
systematic way the imagination of designers and people who operate plants or
equipment so they can identify potential hazard. In effect, HAZOP studies make the
assumption that hazard or operating problem can arise when there is a deviation
from the design or operating intention. Corrective actions can then be made before
a real accident occurs.
The primary goal in performing a HAZOP study is to identify, not analyse or
quantify, the hazard process. The end product of a study is a list of concerns and
recommendation for prevention of the problem, not an analysis of the occurrence,
frequency, overall effects, and the definite solution. If HAZOP is started too late in a
project, it can lose effectiveness because:
1. There may be a tendency not to challenge an already existing design.
2. Changes may come too late, possibly requiring redesign of the process.
3. There may be loss of operability and design decision data used to generate
the design.
HAZOP is a formal procedure that offers a great potential to improve the
safety, reliability and operability of process plants by recognizing and eliminating
potential problems at the design stage. It is not limited to the design stage,
however. It can be applied anywhere that a design intention. (Perrys Handbook,
1998)
When using the operability study technique to vet a process design, the
action to be taken to deal with a potential hazard will often be modification to the
control system and instrumentation, the inclusion of additional alarms, trips or
interlock. If major hazard are identified, major design changes may be necessary,
alternatives processes, material and equipment. In order to have a safe process
successfully producing to specification to the required product, a sound control
system is necessary but not sufficient. (Coulson & Richardsons, 1999).

44

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

The objectives of HAZOP study are:


1. To identify areas of the design that may posses a significant hazard
potential

2. To identify and study features of the design that influences the probability of
a hazardous incident occurring.
3. To familiarize the study team with the design information available.
4. To ensure that a systematic study is made of the areas of significant hazard
potential.
5. To identify design information not currently available to the team.
6. To provide a mechanism for feedback to the client of the study teams
detailed comments. (Sydney Lipton and Jeremiah Lynch, 1994)
The advantages of HAZOP study to the design application:

Early identification of problems areas when conceptual design stage.

Identifies need for emergency procedures to mitigate.

Provide essential information for safety case, such as on the hazards


identified and effectiveness of safety systems.

Through examination of hazard and operability problems when applied at


detailed stage.

Meets legislative requirements.

Identifies need for commissioning, operating and maintenance procedures


for safe and reliable operations.

45

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

Table 3.1: A HAZOP study contains the following important features:


Features :
Intention
Guide words
Deviations
Causes
Consequences
Action

Meaning :
Defines how the part or process is expected to
operate.
Simple word used to qualify the intention in order to
guide and stimulate creative thinking.
Departures from the intention discovered by
systematic application of guide words.
Reasons that deviations might occur.
Results of deviations if they occur.
Prevention, mitigation and control
-

Prevent causes.

Mitigate the consequences.

Control action such as provide alarms to indicate


things getting out of control: define control actions
to get back into control.

The MTBE Plant HAZOP Study is included at Appendix: Safety.

3.3

PLANT START UP AND SHUT DOWN PROCEDURE

Safe procedures must be well known for the start up and shut down of plant and
deviations from normal operating conditions. Whenever process conditions are
changed, opportunities are presented for hazardous situations to arise. Building up
the process consistency may reduce the investigating breakdown and malfunction,
availability, the design cycle, operability, flexibility including blending and recycling
experience and known how personnel.
The start-up and shutdown of the plant must proceed safely and easily, yet
be flexible enough to be carried out in several ways. The operating limits of the
plant must not exceed and dangerous mixtures must not be formed because of
abnormal states of concentration, temperature, phase, reactant, catalyst and
products.
During start-up, the catalyst in the reactor should be activated and
sufficiently warm for reaction to begin when the flow of reactant is started.
Contaminants often enter the system at this stage. Materials are added by
operations such as purging, drying and flushing. Water and other materials may

46

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

condense in unplanned location causing process levels to get out of control and
other problems. The ignition of fuel to heat the high temperature fluid during start-up
must be designed to accomplish this safely Some typical errors that could occur
during start-up of the plant include :
1. Wrong routing, involving failure to ensure that correct valves are closed.
This is especially crucial in the adsorption section where three different
processes are occurring at any one time.
2. Drain valves are left open resulting in loss of material and possibly
endangering the lives of workers.
3. Valves left closed resulting in over pressure in the vessel.
4. Failure to complete purging cycle before admission of fuel air mixture.
5. Backflow of material from high pressure to low pressure system.

6. Setting of wrong valves for operating parameters such as jacket


temperature in the reactor and reflux in the distillation column.
3.3.1

Normal Start up and Shut down the Plant

The study of the plant start up and shut down must include investigation of the
operating limits, transient operating conditions, process dynamics, contamination
and added material, emissions, hot standby and emergency shut down with plant
protection control systems and alarms.
3.3.1.1 Operating Limits
The operating limits of the plant are imposing by mechanical, electrical, civil and
process design. Where necessary, it has to be introduce additional equipment,
sampling points, instrumentation and lines, and identify their use on the engineering
line diagram,

3.3.1.2 Transient Operating and Process Dynamic


The transient operating conditions must be studied to safe time and operating cast.
The process dynamics that to be investigated includes excessive heat transfer

47

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

when more or less floe in either energy exchanging streams through activations and
warming of catalyst when the flow of reactant starts to entrance of contamination
and others
3.3.1.3 Added Materials
Materials are added by operations may not be tolerated in part of the system or
clean material may be needed for the start up of the plant. Residues or unwanted
products such as out of specification may be discharged or hold in tank for further
treatment.
3.3.1.4 Hot Standby
Time is save during restart up if plant are kept partially working such as when other
unit operation are ceased to function temporarily, the converter can be left in hot
standby conditions.
3.3.1.5 Emergency Shut Down
Special plant protection known as process trip system or emergency shut down
system is design to affect the emergency shut down through the push button by
operator or from automatic activation of a relay when necessary. The trip systems
should be reliable and operate when required to avoid a nuisance shut down of
plant.
3.3.2

Start up and Shut down Procedure for the Main Equipment

3.3.2.1 Reactor
1. It is recommended that the internal reactor vessel measurements (ID, Bed
Depth not the overall vessel height, etc.) be verified, so that product
loading is consistent with the "Estimated Performance Sheet" (EPS).
2. Prior to any loading, it is necessary to make an internal and external
inspection of the reactor vessel. In other words, there should not be any
pipes or hollow devices in the vessel, which could allow the gas to travel
without contacting the product.

48

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

3. There are two vessel types of bed supports that can be used; (1) has a
support grid permanently installed about 2 inches below the throat of the
lower manway; or (2) uses a level bed of washed gravel, ceramic balls, or
pawl rings. The bed support must be leveled.
4. Close and secure the bottom manway.
5. Through the top manway, load the remaining feed to level as stated in the
EPS. During the latter stages of loading level off the cone of the filled
product bed and continue loading until finished.
6. Close and secure the top manway.
Upon operational start-up, record the required measurements temperature,
pressure, and flow rate - from each bed (if applicable). This data should be kept on
some routine basis (daily, weekly bi-weekly, etc.) so that any problems that might
develop can be identified and corrected.
3.3.2.2 Distillation Column
Start-Up Procedure
1. Turn the switch box indicator to Distillation Control setting.
2. Switch the column power source lever to the "on" position. Turn the Reboiler
Heater Control knob clockwise. This prevents over heating of the reboiler.
3. Turn on the cold water supply ( CWS )valve until the computer stops telling
the user to increase the volume of the CWS valve.
4.

Adjust the Reflux Control to the desired setting.

5.

Assure all computer settings are as desired.

6. Allow the tray temperatures to reach a steady-state value.


7. Turn on the feed and reboiler pumps as applicable. The pump settings can
be adjusted on the computer.
Caution: DO NOT ALLOW THE WATER LEVEL TO FALL BELOW THE
CALROD HEATERS.

49

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

This will result in damage to the heaters. If the heaters are exposed turn off the
column, this allows the vapor in the column to condense and return to the
reboiler. If the liquid level is still below the heaters, more liquid must be added to
the reboiler.
Shut-Down Procedure
1. Turn the Reboiler Heater Control knob to zero.
2. Turn off the pumps (feed and reboiler).
3. Turn off the CWS valve when the temperature of the distillate is below the
boiling point of the light component of the mixture.
4.

Press the stop button.

5. Shut off the computer, by selecting the "Shut-down" option from the Special
menu.
3.3.2.3 Liquid-Liquid Extraction Column
Start Up Procedure
1. Check to see that all the drainage valves are closed.
2. Check to be sure the top water vent valve is open.
3. When the liquid level in the column reaches the top right nozzle(water in
nozzle), turn the water flowrate down to the desired setpoint. Turn on and
set the feed flowrate to the desired setpoint by adjusting the pump speed,
and close the top water vent.
4. Allow the interface to form between the top mesh and the top left nozzle.
5. Small adjustments should be made in order to keep the interface constant.

Shut down procedure


1. Turn off all inlet flowrates on the right control panel.
2. Shut off the stirrer on the right control panel.

50

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

3. Open the top water in vent valve.


4. Open the bottom centre black valve to drain the column.
3.3.2.4 Heat Exchanger
Start up Procedure
When putting a heat exchanger in operation, open the vent connections and
slowly start to circulate the cold medium only. Be sure that the entire cold side
of the exchanger is completely flooded before closing its vents. The hot medium
should then be gradually introduced until all passages are filled with fluid. Then
close the hot side vents and slowly bring the unit up to its operating
temperature.
Shut down Procedure
When heat exchanger is required to be shutdown, the hot fluid should be turned
off first. If it is necessary to stop the circulation of the cold fluid, the hot medium
should also be stopped by by-passing the heat exchanger.

3.4

EMERGENCY RESPONSE PLAN (ERP)

It is expected that every person who working in this plant will act responsibly in any
Department of Emergency. ERP procedures were state in Appendix: Safety. In most cases,
the observer of an emergency is faced with decision to leave the scene to summon help or
stay and provide help. The basic rule is as follows.
Unless we are sure that we are not putting ourselves in any danger and we know we can
make a difference, summon help.

3.4.1

Emergency Response Procedures

General Procedures

51

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

When alarm system is activated whether by break glass or by smoke detector, the
alarm that is siren sound will be triggered throughout plant. The following general
procedures should be followed if there is no immediate emergency in your area.

Do not panic and stay alert:


Stay calm and be alert and ready to response to any emergency according
to the
Plant Emergency Organization Programmed. The shift manager should go
to the security guard to identify the location of the alarm.

Access the situation around your area :

Look around and ensure that your immediate area is not in danger or affected by
the emergency. Stop all contractors from working immediately.

Wait for instruction from Supervisor/Shift Manager :

Do no evacuate from ones post unless one is immediate danger or when instructed
by ones supervisor or the shift manager.

Avoid using the telephone :

Do not use the telephone unless it is absolutely necessary, as the telephone lines
must be reserved for calling emergency services. All incidents resulting in
injuries, property damage and/ or productions loss shall be investigated and
reported for within 24 hours. Corrective action to prevent the recurrence of
the incident shall be initiated 48 hours.
3.4.2

Evacuation Procedures:
Exit building via the stairways :
It takes time to the person familiarize with evacuation routes in advance.
The maps showing the location of all emergency exits and extinguishers are
posted on all floors.

Assist the injured when possible :


Do not move the seriously injured unless there is danger of further injury. If it
is necessary to leave someone in the building, try to leave him in a relatively
secure place (example, the stairwell is one of the safer places to be in fire).
After someone has been evacuated the building, find the proper officials and
report the location and condition of persons who need assistance.

Designed persons are responsible for clearing the production floors and
offices :

52

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

Efforts to clear the production floor and offices should be limited to 5


minutes. As the areas are cleared, all doors should be closed.

Once outside the building :


Keep at least 50 feet away from the building to avoid danger from falling
glass, example Evacuate to the Emergency Assembly Area .

Do not re enter the building until safety officer or fire personnel have been
determined that it is safe.

3.4.3

Fires:

If the fire alarm sounds or a fire broke out in the plant, turn off any electrical
equipment that been operating and evacuate the building immediately.
Close all doors to help prevent fires from spreading. Exit via stairwells.

Call 994 to give location and extent of fire and notify the management to
report the fire :
State if there are any special circumstances, such as the presence of
dangerous chemicals.

Dont attempt to fight a fire unless we have been trained in fire extinguisher
use and the fire is very small :
When fighting a fire, always position ourselves between the exit and the fire
to ensure an escape route. IF THE FIRE CANNOT BE CONTAINED, GET
OUT QUICKLY!

3.4.4

Explosion, Line Rupture or Serious Leak


Do the following if possible.
1. Turn the Emergency Stop switch to Off position
2. Isolate the effected area of the limit. Block in high-pressure source
as required accomplishing this.
3. Complete the shut down

3.4.5

Other Emergencies :
Injuries :

53

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

For life threatening emergencies, CALL 991 for medical aid and for
transportation to hospital and at same time notify the management as listed
on the Notification Lists. For less serious injuries or illness, first aid can be
obtained at the nearest clinic. Report all injuries to the management.

Equipment failures :
Any equipment failures, which may harm or injured the workers, should be
reported to the Production Supervisors or the management for further action
to be taken.

3.5

PLANT LAYOUT

The process units and ancillary buildings should be laid out to give the most
economical flow of material and personnel around the site. Hazardous process
must be located at a safe distance from other buildings. Consideration must be also
being given to the future expansion of the site. The ancillary buildings and services
required on site, in addition to the main processing units (building) will include:
(Coulson and Richardsons 1999)
1. Storage for raw materials and products; tank farms and warehouses
2. Maintenance workshop
3. Stores, for maintenance and operating supplies
4. Laboratories for process control
5. Fire stations and other emergency services
6. Utilities: steam boilers, compressed air, power generation, refrigeration,
transformer stations.
7. Effluent disposal plant
8. Offices for general administration
9. Canteens and other amenity buildings, such as medical centres
10. Car parks
Normally, the process units will be sited first and arranged to give a smooth
flow of materials through various processing steps, from raw material to final
product storage. It is normally spaced at least 30 apart and for hazardous
processes, the greater spacing may be needed. Then, the principal ancillary
buildings to be located and arranged in order to minimize the time spent by the
personnel in travelling between the buildings. The administration offices and

54

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

laboratory should be located well away from potentially hazardous processes since
a many people be in here. The control rooms normally are located adjacent to the
process units but if it with the potentially hazardous processes has to be sited at
safer distance.
Besides that, the layout of the plant roads, pipe alleys and drains also must
be considered to locate the main process units. Easy access roads will be needed
to each building for construction and for operation and maintenance. The utilities
buildings should be sited to give most economical run of pipes to and from the
process units. Finally, the main storage areas should be placed between loading
and unloading facilities and the process units they serve. Storage tanks containing
hazardous materials should be sited at least 70 m (200 ft) from the site boundary.
There are 7 principal factors to be considered :
1. Economic considerations: construction and operating costs.
2. The process requirements.
3. Convenience of operation.
4. Convenience of maintenance.
5. Safety.
6. Future expansion.
7. Modular construction.
The MTBE site layout have shown in Figure 3.1.

55

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

Figure 3.1 Methyl tert-Butyl Ether (MTBE) Plan Layout


U

56

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

Figure 3.2: Methyl tert-Butyl Ether (MTBE) Plant Evacuation Routes

Legand
Evacuation Routes

57

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

Figure 3.3 PID before HAZOP

58

PRODUCTION OF 300,000 METRIC TON MTBE PER YEAR

Figure 3.4 PID after HAZOP

59

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

REFERENCES

Clarles A.Wentz, 1998. Safety, Health and Environmental Protection. United State of
America:McGraw-Hill.
R.K.Sinnot, 1999. Chemical Engineering Design. Coulson & Richardsons Chemical
Engineering 3rd Edition. Volume 6. Britain; Butterworth Heinemann.
Robert H. Perry, Don W. Green, 1998 Perrys Chemical Engineers Handbook, Seventh
Edition, McGraw-Hill.
http://www.sulfatreat.com/Documents/HTML/St/startup.html
http://www.amberjet.com/IP/start_up.htm
http://www.sulfatreat.com/Documents/PDF/SulfaTreat/ST-Start_Up_Procedure.pdf
http://chem.engr.utc.edu/Webres/435F/Proc.htm
http://www.eng.buffalo.edu/Courses/ce428/Distillation/procedure.htm
http://users.rowan.edu/~savelski/uol/liqliq.html
http://pharmaflo.com/heatexch/

60

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

CHAPTER 4

ECONOMIC EVALUATION

INTRODUCTION
Economic evaluation is very important for a proposed plant. We have to be able to
estimate and decide between alternative designs and for project evaluation. Chemical
plants are built to make a profit an estimate of the investment required and the cost of
production are needed before the profitability of a project can be assessed. The total
investment needed for a project is the sum of the fixed and working capital. Fixed
capital is the total cost of the plant ready for start up. It is the cost paid to the
contractors. Working capital is the additional investment needed, over and above the
fixed capital, to start the plant up and operate it to the point when income is earned.
Most of the working capital is recovered at the end of the project.

61

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.1.1 The Specification Of Plant


In this chapter, the costing of equipment which has been designed will be
estimated and the feasibility of MTBE production will be evaluated by
profitability analysis to make sure the project is economically attractive.
There are some general assumptions to this chapter;
i.

The plant life span is fifteen years.

ii.

The currency exchange rate of US dollar to Ringgit Malaysia is fixed at 3.8 as


fixed by Malaysian Government.

iii.

The price of raw materials, catalyst and product is fixed for the whole period of
operation.

Price of raw material

: Isobutane - RM 0.8094 / kg
: Methanol - RM 0.988 / kg

Price of product

: MTBE - RM 1.320 / kg
: TBA - RM 1.035 / kg
: DME - RM 0.655 / kg

62

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.1.2

Revenue From Sales

i.

MTBE

37878.76 kg/h =

300000 tonne
year

Price: RM 1.320/kg
=

37878 .76 kg 24 hr 365 day


RM 1.320

0.90
hr
day
year
kg

=
ii.

TBA

RM 394199710/yr

639.663 kg/h
Price: RM 1.035/kg

639 .663 kg 24 hr 365 day


RM 1.035

0.90
hr
day
year
kg

=
iii.

DME

RM 5219612/yr

1210.9868 kg/h
Price: RM 0.655/kg

1210 .9868 kg 24 hr 365 day


RM 0.655

0.90
hr
day
year
kg

=
iv.

Isobutane

RM 6253560/yr

13718.4558 kg/h
Price: RM 0.8094/kg

=
13718 .4558 kg 24 hr 365 day
RM 0.8094

0.90
hr
day
year
kg

RM

87541714/yr
v.

n-butane

157.412 kg/h
Price: RM 0.35/kg

Total revenue

157 .412 kg 24 hr 365 day


RM 0.35

0.90
hr
day
year
kg

RM 434363/yr

RM 493648959/yr

63

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.2 COST ESTIMATION


4.2.1 Capital cost estimation
Capital cost estimates are essentially paper and pencil studies. The cost of making
an estimate indicates the personnel hours required in order to complete the estimate.

The capital needed to supply the necessary manufacturing and plant facilities is called
the fixed capital investment (FC), while the additional investment needed for the plant
operation (for plant start-up and operation to the point when income is earned) form the
working capital (WC).
Capital cost estimates for chemical process plants are often based on an estimate of
the purchase cost of the major equipment items required for the process, the other
costs being estimated as factors of the equipment cost. The accuracy of this type of
estimate will depend on what stage the design has reached at the time estimate is
made and on the reliability of the data available on equipment cost.

The cost of the purchased equipment is used as the basis of the factorial method of cost
estimation and must be determined as accurately as possible. It should preferably be
based on recent prices paid for similar equipment.
Calculation of total module cost and gross roots cost (based on table 4.2)
CTC = CFC + CWC + CL
Where,
CTC

total capital cost

CFC

fixed capital cost

CWC

working capital cost

CL

cost of land & other non-depreciable costs

FP

Pressure factor to account for high pressure

FM

Material factor to account for material of constructions

CP

Purchase cost for base condition

FBM

Bare module cost factor

64

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

CBM

Bare module equipment cost for base condition

CBM

Bare module equipment cost for actual condition

Total Module Cost, CTM

Grass Root Cost, CGR

1.18 (CBM )

1.18 (3223841)

RM 3804132 x 3.8

RM 14455703

CTM + 0.35 ( CBM)

=
=

14455703 + 0.35 (12659343) x 3.8


RM 31292629

Since, Grass Root Cost (CGR) is:


CGR

CFC + CL

Area for 1 lot of land = 200000 m2


The price of land is RM 60 per m2
CL

RM 12000000

CFC

CGR - CL

RM 31292629 - RM 12000000

RM 19292629

Working capital is the additional investment needed over and above the fixed capital to
start the plant up and operate it to the point when income is earned.
Working capital cost = 5% of fixed capital costs
CWC

5% fixed capital cost (CFC)

(Coulson & Richardson,

RM 964631

1990)

Thus,
Total capital cost (CTC)

CFC + CL + CWC

RM 19292629+ RM 12000000+ RM 964631

RM 32257260

65

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.2.2

Manufacturing Cost Estimation

The cost of associated with the day to day operation of a chemical plant must be
estimated before the economic feasibility of a proposed process can be assessed.
The equation below is used to evaluate the cost of manufacture:

Cost of manufacture (COM) =

Direct Manufacturing Cost (DMC) +


Fixed Manufacturing Cost (FMC) +
General Expenses (GE)

COM = 0.304FCI + 2.73COL + 1.23(CUT + CWT + CRM)


The cost of manufacturing (COM) can be determined when the following costs are
known or can be estimated:

1. Fixed Capital Investment (FCI): (CTM or CGR)


2. Cost of Operating Labor (COL)
3. Cost of Utilities (CUT)
4. Cost of Waste Treatment (CWT)
5. Cost of Raw Material (CRM)
4.2.2.1 Cost of Operating Labor (COL)
Table 4.1 Labor Cost
Equipment type
Heat exchangers
Reactor
Vessels
Pumps
Compressor

No of

Operators per shift per

Operator per

equipment
6
2
1
5
2

equipment
0.1
0.5
0.0
0.0
0.15

shift
0.6
1.0
0.0
0.0
0.3

66

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Towers
Waste Treatment

3
1

0.35
0.5

1.05
0.5
3.45
Since, a single operators works on the average 48 weeks (3 weeks time off for
vacation and sick leave) a year, five 8-hour shifts a week.

1 operator

48 week
5 shift

Year
week

240 shift
Year

Working days for MTBE plant is 7920 hour = 330 days


Operating shift per Year

330 days
3 operating

Year
days

990 operating shift


Year

Working days for MTBE plant is 7920 hour

So, the number operator needed

990 operating shift


Year
240 shift
Year
4.125 operators

Thus,
Operating Labor

4.125 operators x 3.45 operator per shift

14.23 operator

15 operator

A mechanical engineers maximum wages per year (MIDA 2002) RM 60,000.00


Thus,
Labor Cost (1996)

15 x RM 60,000.00

RM 900,000.00

67

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.2.2.2 Cost of Utilities (CUT)


Yearly costs

flowrate x costs x period x steam factor

Since, assuming the plants operating days per year = 330 days
So,
Steam factor (SF)

no . of day ' s plant operates per year


no . of days per year

330
= 0.90
365

1. Heater (E-100)
Duty

3109542

J s = 11 .16 G J hr

From table 8.5 (W.R Wan Daud, Princip Reka bentuk Proses Kimia, 2002, page
285) cost of heater RM 19.6 / GJ.
Thus ,
Yearly cost

= (Q) (C steam) (t)


= 11 .16

GJ
19 .6
hr
day
RM
24
365
0.90
hr
GJ
day
yr

= RM 1724515
2. Heater (E-101)
Duty

3423874

J s = 12 .24 G J hr

From table 8.5 (W.R Wan Daud, Princip Reka bentuk Proses Kimia, 2002, page
285) cost of cooling water RM 0.6 / GJ.
Thus ,
Yearly cost

= (Q) (C steam) (t)


= 12 .24

GJ
19 .6
hr
day
RM
24
365
0.90
hr
GJ
day
yr

= RM1891403

68

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3. Compressor (C-100)
Power (shaft)

137.73kW

Effeciency of drives, dr

92.28% (refer to table 3.7) Appendix

Electric Power, Pr

Power output
dr

137 .73
0.9228

149.25 kW

Yearly cost
149 .25 kW

0.228
hr
day
24
365
0.90
kWh
day
yr

= RM 268285
4. Cooler 1 (E-102)
Duty

= 4014590

KJ s = 14 .4 GJ hr

From table 8.5 (W.R Wan Daud, Princip Reka bentuk Proses Kimia, 2002, page
285) cost of cooling water RM 0.6 / GJ.
Thus ,
Yearly cost

= (Q) (C steam) (t)


= 14 .4

GJ
0.6
hr
day
RM
24
365
0.90
hr
GJ
day
yr

= RM 68118
5. Cooler 2 (E-103)
Duty

= 4204290

J s = 15 .12 G J hr

From table 8.5 (W.R Wan Daud, Prinsip Reka bentuk Proses Kimia, 2002, page
285) cost of cooling water RM 0.6 / GJ.
Thus ,
Yearly cost

= (Q) (C steam) (t)


= 15 .12

GJ
0.6
hr
day
RM
24
365
0.90
hr
GJ
day
yr

= RM71524

69

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

6. Cooler 3 (E-104)
Duty

J s = 1.8 G J hr

503240

From table 8.5 (W.R Wan Daud, Princip Reka bentuk Proses Kimia, 2002, page
285) cost of cooling water RM 0.6 / GJ.
Thus ,
Yearly cost

= (Q) (C steam) (t)


GJ

0.6

hr

day

= 1.8 hr RM GJ 24 day 365 yr 0.90


= RM 8514
7. Cooler 4 (E-105)
Duty

J s = 0.72 G J hr

240320

From table 8.5 (W.R Wan Daud, Princip Reka Bentuk Proses Kimia, 2002,
page 285) cost of cooling water RM 0.6 / GJ.
Thus ,
Yearly cost

= (Q) (C steam) (t)


= 0.72

GJ
0.6
hr
day
RM
24
365
0.90
hr
GJ
day
yr

= RM 3406
8. Pump 1(P100)
Power (shaft)

327.94kW

Effeciency of drives, dr

93.71% (refer to table 3.7) Appendix

Electric Power, Pr

Power output
dr

Yearly cost
349 .95 kW

327 .94
0.9371

349.95kW

0.228
hr
day
24
365
0.90
kWh
day
yr

= RM 629053

70

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

9. Pump 2(P101)
Power (shaft)

79.19kW

Effeciency of drives, dr

91.58% (refer to table 3.7) Appendix

Electric Power, Pr

Power output
dr

79 .19
0.9158

86.47kW

Yearly cost

= 86 .47 kW

0.228
hr
day
24
365
0.90
kWh
day
yr

= RM 155434
10. Pump 3(P102)
Power (shaft)

22.85kW

Effeciency of drives, dr

86.93% (refer to table 3.7) Appendix

Electric Power, Pr

Power output
dr

Yearly cost

22 .85
0.8693

26.29kW

= 26 .29 kW

0.228
hr
day
24
365
0.90
kWh
day
yr

= RM 47258
11. Pump 4(P103)
Power (shaft)

685.64kW

Effeciency of drives, dr

95.37% (refer to table 3.7) Appendix

Electric Power, Pr

Power output
dr

685 .64
0.9537

718.93kW

71

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Yearly cost
718 .93 kW

0.228
hr
day
24
365
0.90
kWh
day
yr

= RM 1292314
12. Pump 5(P104)
Power (shaft)

322.75kW

Effeciency of drives, dr

93.67% (refer to table 3.7) Appendix

Electric Power, Pr

Power output
dr

Yearly cost
344 .56 kW

322 .75
0.9367

344.56kW

0.228
hr
day
24
365
0.90
kWh
day
yr

= RM 619366
Total cost of utilities (CUT)

= RM 6779190

4.2.2.3Cost of Raw Material (CRM)


1.

Isobutane

39353 kg/h
Price RM 0.8094/kg

2.

Methanol

39353 kg 24 hr 365 day


RM 0.8094

0.90
hr
day
year
kg

RM 251123677/yr

15462 kg/hr
Price RM 0.988/kg (Chemical week, June 2003)

15462 kg
24 hr
365 day
RM 0.988

0.90
hr
day
year
kg

RM 120439579/yr

72

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

3.

Catalyst (Alumina silica)

95679 kg

RM 9.5 1 tonne

tonne
1000 kg

RM909

RM 251123677/yr + RM 120439579/yr

RM 371563256/yr

Total cost of catalyst (for 3 year)

RM 909

Total cost

RM 371564165

Total cost of raw material

The estimation of total manufacturing cost (with catalyst):


COM = 0.304FCI + 2.73COL + 1.23(CUT + CWT + CRM)
COM = 0.304 (31292629) + 2.73 (900000) + 1.23 (6779190 + 371564165)
COM = RM 477332286/yr
The estimation of total manufacturing cost (without catalyst):
COM = 0.304FCI + 2.73COL + 1.23(CUT + CWT + CRM)
COM = 0.304 (31292629) + 2.73 (900000) + 1.23 (6779190 + 371563256)
COM = RM 477331168/yr

73

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Table 4.2: Estimation Cost Of Purchased Equipment


Equipment

Capacity/Size

Operating
Pressure
0.0 barg

Area =94.33m2
(floating head)

Material Of
Construction
Carbon
Steel
Carbon
Steel
Tube-CS
Shell-CS

C100

W=137.73kW

C101

W = 22.85kW

E 100
Heat
Exchanger
E 101
Heat
exchanger
E 102
Heat
Exchanger
E 103
Heat
Exchanger
E 104
Heat
Exchanger
E 105
Heat
Exchanger

FP

Tube- 9 barg
Shell- 9 barg

1.0
1.0

Area =95.71m2
(floating head)

Tube-CS
Shell-CS

Tube- 9 barg
Shell- 9 barg

Area =94.33m2
(floating head)

Tube-CS
Shell-CS

Area =94.33m2
(floating head)

FM

FBM

Cp

CBM

2.2

16000

264000

3.0

3536676

10610028

1.0
1.0

3.2
3.2

15000
15000

48000

1.0
1.0

1.0
1.0

3.2
3.2

16000
16000

51200

Tube- 9 barg
Shell- 9 barg

1.0
1.0

1.0
1.0

3.2
3.2

15000
15000

48000

Tube-CS
Shell-CS

Tube- 9 barg
Shell- 9 barg

1.0
1.0

1.0
1.0

3.2
3.2

15000
15000

48000

Area =94.33m2
(floating head)

Tube-CS
Shell-CS

Tube- 9 barg
Shell- 9 barg

1.0
1.0

1.0
1.0

3.2
3.2

15000
15000

48000

Area =94.33m2
(floating head)

Tube-CS
Shell-CS

Tube- 9 barg
Shell- 9 barg

1.0
1.0

1.0
1.0

3.2
3.2

15000
15000

48000

0.1 barg

Co BM

74

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Table 4.2: Estimation Cost Of Purchased Equipment


Equipment

Capacity/Size

P100

W = 327.94kW

P101
P102

W = 79.19kW
W = 22.85kW

Material Of
Construction
Cass Steel
Cass Steel
Cass Steel

Operating
Pressure
3.5 barg
0.1 barg
0.0 barg

P103

W = 685.64kW

Cass Steel

1.50 barg

P104

W = 322.75kW

Cass Steel

0.0 barg

R100

R101
T100
Sieve tray
T101
T102
Sieve tray
V100
Total

D = 6.512
H = 18m
D = 1.814m
H = 4m
D = 0.765 m
H = 10.85
11 trays
D = 1.01 m
H =9 m
D = 0.765 m
H = 10.85
11 trays

Stainless Steel

1.75 barg

Carbon Steel

1.0 barg

Stainless
Steel
Stainless
Steel
Stainless
Steel
Stainless Steel

3.5 barg

1.75 barg
3.5 barg

FP

FM

FBM

Cp

1.0
1.0
1.0
1.0
1.0
1.0
1.0
1.0
1.0
1.0
1.3
1.0
1.0
1.0
1.2
1.0

1.8
1.0
1.8
1.0
1.8
1.0
1.8
1.0
1.8
1.0
4.0
1.0
1.0
1.0
4.0
1.0

4.518
3.31
4.518
3.31
4.518
3.31
4.518
3.31
4.518
3.31
11.5
4.2
4.2
4.2
11
4
2.0
1.0
2.0
1.2
11
4
2.0
1.0

36881

1.2
1.0
1.2
1.0

4.0
1.0
4.0
1.0

CBM

Co BM
333257

244152
8571

77448
56740

1429

12912
9460

52276

472366
346067

36593

330654
121123

200000

840000
230000

19000

79800
79800

40000

440000
160000

294

9702
5821

17000

178000
68000

40000

440000
160000

294

9702
5821
7131
12659343

3223841

75

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.3

PROFITABILITY ANALYSIS
Profitability is used as the general term for the measure of the amount of profit

that can be obtained from a given situation. Profitability therefore, is the common
denominator for all business activities.
The feasibility of MTBE production in Malaysia is evaluated by profitability analysis.
The profitability of the project will be the largest factor that makes a project
economically attractive.

To this stage, almost all the design and cost information

required for the profitability analysis were obtained.

Based on the information

available, the best methods assessing the profitability of alternatives are based on
projections of the cash flows during the project file.
A proposed capital investment / project and its associated expenditures can be
recovered by revenue (or savings) over time in addition to a return on the capital that is
sufficiently attractive in view of the risks involved of the potential alternatives uses.
There are 5 common methods in performing engineering economic analysis:
1) Present Worth (PW)
2) Future Worth (FW)
3) Annual Worth (AW)
4) Internal Rate Of Return (IRR)
5) Benefits / Cost Ratio (B/C)
4.3.1

Discounted Cash Flow

The economic feasibility of this plant is evaluated using the Discounted Cash Flow
Analysis (DCF), which is the most frequently used method of economic evaluation in
the chemical industry. This method measures the profitability of the project taking into
account the time value of money. From this method, the internal rate of return (IRR) of
the project can be determined which indicates the feasibility of the project. The value of
IRR is calculated using the information obtained in the sections.

76

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Table 4.3: Annual Cash Flow Before Tax


Year

Gross Income
(RM)
0
0
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
15

Annual
Expenses (RM)

493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959

-477332286
-477331168
-477331168
-477332286
-477331168
-477331168
-477332286
-477331168
-477331168
-477332286
-477331168
-477331168
-477332286
-477331168
-477331168

Estimated salvage value

Investment &
Salvage Value
(RM)
3
-19292629
-964631
-12000000

1929262.9

10%CFC

0.1 x RM 19292629

RM 1929262.9

Before Tax
Cash Flow
(RM)
(4)= (1)+(2)+(3)
-19292629
-964631
-12000000
16316673
16317791
16317791
16316673
16317791
16317791
16316673
16317791
16317791
16316673
16317791
16317791
16316673
16317791
16317791
1929262.9

(Coulson & Richardson, 1990)

77

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Table 4.4 : Annual Cash Flow After Tax


Taxes rate at 38% is chosen referring to reference from MIDA
Year

Gross
Income
(RM)
1

0
0
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
15
15

Expenses
(RM)
2

Investment
& Salvage
Value (RM)
3

Depreciation
Cost Basis *
MACRS
Rates
4

Taxable
Income (RM)

Taxes (RM)
Taxes rates
= 38%

After Tax
Cash Flow
(RM)

(5)=(1)+(2)(4)

(6)=(5)*0.38

2756916.69
4724764.84
3374280.81
2409649.36
1722831.77
1720902.50
1722831.77
860451.25
0
0
0
0
0
0
0

13559756.32
11593026.16
12943510.19
13907023.64
14594959.23
14596888.49
14593841.23
15457339.75
16317791
16316673
16317791
16317791
16316673
16317791
16317791
1929262.9

5152707.4
4405349.94
4918533.871
5284668.982
5546084.508
5546817.627
5545659.668
5873789.104
6200760.58
6200335.74
6200760.58
6200760.58
6200335.74
6200760.58
6200760.58
733119.902

(7)=(1)+(2)+
(3)-(6)
-19292629
-964631
-12000000
11163965.6
11912441.06
11399257.13
11032004.02
10771706.49
10770973.37
10771013.33
10444001.9
10117030.42
10116337.26
10117030.42
10117030.42
10116337.26
10117030.42
10117030.42
1929262.9
12964631

-19292629
-964631
-12000000
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959
493648959

-477332286
-477331168
-477331168
-477332286
-477331168
-477331168
-477332286
-477331168
-477331168
-477332286
-477331168
-477331168
-477332286
-477331168
-477331168
1929262.9
12964631

Cumulative
Cash Flow
(RM)

-32257260
-21093294.4
-9180853.34
2218403.789
13250407.81
24022114.3
34793087.67
45564101
56008102.9
66125133.32
76241470.58
86358501
96475531.42
106591868.7
116708899.1
126825929.5
128755192.4
141719823.4

78

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.3.2 Net Present Value


4.3.2.1 Present Worth
MARR is the rate set by an organization to designate the lowest level that makes an
investment acceptable. For a risky investment, MARR should be set higher.
However, for public purpose (government, public utility), MARR is lower. For this
proposed plant, MARR that has been selected is 15%.

By using present worth, we can determine either this proposed plant is


profitable and acceptable or not. Table 4.4 shows the value of present
worth by using 15%, therefore this proposed plant is profitable
because the value of PW is > 0.
PW when MARR = 15%
Table 4.5: Present Worth Value
Year
0
0
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
15
PW

After Tax Cash


Flow (RM)
-19292629
-964631
-12000000
11163965.6
11912441.06
11399257.13
11032004.02
10771706.49
10770973.37
10771013.33
10444001.9
10117030.42
10116337.26
10117030.42
10117030.42
10116337.26
10117030.42
10117030.42
13697750.9

MARR = 15%

0.86957
0.75614
0.65752
0.57175
0.49718
0.43233
0.37594
0.3269
0.28426
0.24718
0.21494
0.18691
0.16253
0.14133
0.12289
0.12289

Present Worth
(PW), (RM)
-19292629
-964631
-12000000
9707849.57
9007473.18
7495239.55
6307548.3
5355477.03
4656614.92
4049254.75
3414144.22
2875867.07
2500556.24
2174554.52
1890974.16
1644208.29
1429839.91
1243281.87
1683316.61
33178940.2

MARR = 15%
PW = RM 33178940.2
This project is attractive and acceptable because PW > 0

79

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

4.3.3 Cumulative Cash Flow Diagram For The Evaluation Of A New


Project
Table 4.6: After Tax Cumulative Cash Flow
Year
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
15

After Tax Cash


Flow (RM)
-32257260
11163965.6
11912441.06
11399257.13
11032004.02
10771706.49
10770973.37
10771013.33
10444001.9
10117030.42
10116337.26
10117030.42
10117030.42
10116337.26
10117030.42
10117030.42
13697750.9

Cumulative Cash
Flow
-32257260
-21093294.4
-9180853.34
2218403.789
13250407.81
24022114.3
34793087.67
45564101
56008102.9
66125133.32
76241470.58
86358501
96475531.42
106591868.7
116708899.1
126825929.5
140523680.4

Cumulative Cash Flow vs Year


150000000
125000000
100000000
Cumulative 75000000
Cash Flow 50000000
25000000
(RM)
0
-25000000 0
-50000000

10

12

14

16

Year
Figure 4.1: Cumulative Cash Flow (RM) Versus Year

4.3.4

Rate Of Return (ROR)

4.3.4.1 Internal Rate Of Return

80

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

In theory, the Minimum Attractive Rate of Return (MARR) is chosen higher than the
rate expected from the bank or some safe investment that involved minimal
investment risk. The MARR for after taxes is selected at 15%. (Analysis, and
Design of Chemical Processes)

IRR is a method that produces an annual rate of profit, or return, resulting from an
investment and compared with the MARR. In determining the internal rate of return,
trial and error has been done based on the MARR that mentioned before. By trial
and error, the IRR for this plant has been found as 34.94%.
Table 4.7: Present Value (RM) when i = 30% and i = 40%
Year
0
0
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
15
PW

After Tax
Cash Flow
(RM)
-19292629
-964631
-12000000
11163965.6
11912441.06
11399257.13
11032004.02
10771706.49
10770973.37
10771013.33
10444001.9
10117030.42
10116337.26
10117030.42
10117030.42
10116337.26
10117030.42
10117030.42
13697750.9

i = 30%

0.76923
0.59172
0.45517
0.35013
0.26933
0.20718
0.15937
0.12259
0.0943
0.07254
0.0558
0.04292
0.03302
0.0254
0.01954
0.01954

Present
Value (RM)

i = 40%

-19292629
-964631
-12000000
8587657.26
7048829.62
5188599.87
3862635.57
2901143.71
2231530.26
1716576.39
1280330.19
954035.969
733839.105
564530.297
434222.946
334041.456
256972.573
197686.774
267654.053
4303026.05

0.71129
0.5102
0.36443
0.26031
0.18593
0.13281
0.09486
0.06776
0.0484
0.03457
0.02469
0.01764
0.0126
0.009
0.00643
0.00643

Present
Value (RM)
-19292629
-964631
-12000000
7940817.092
6077727.429
4154231.275
2871740.966
2002783.388
1430492.974
1021738.325
707685.5685
489664.2723
349721.7791
249789.4811
178464.4166
127465.8495
91053.27378
65052.5056
88076.5383
-4410754.867

By interpolation, IRR value is 34.94% when P is at 0 value.


IRR (34.94%) > MARR (15%). This project is profitable and acceptable.

4.3.5 Sensitivity Analysis


A sensitivity analysis is a way of examining the effects of uncertainties in the
forecasts on the viability of a project.
AW = PW (A/P, 15%, 15)

81

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

= 33178940.2 (0.17102)
= RM 5674262.32

FW = PW (F/P, 15%, 15)


= 33178940.2 (8.13706)
= RM 269979027.1
Table 4.8: Future Worth (RM) when MARR = 15%
Year
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
15

After Tax Cash


Flow (RM)
-32257260
11163965.6
11912441.06
11399257.13
11032004.02
10771706.49
10770973.37
10771013.33
10444001.9
10117030.42
10116337.26
10117030.42
10117030.42
10116337.26
10117030.42
10117030.42
13697750.9

MARR = 15%
8.13706
7.07571
6.15279
5.35025
4.65239
4.04556
3.51788
3.05902
2.66002
2.31306
2.01136
1.74901
1.52088
1.3225
1.15
-

FW

4.3.6

Future Worth
(FW), (RM)
-262479260.1
78992983.04
73294748.23
60988875.45
51325185.17
43577584.92
37890991.81
32948745.2
27781253.92
23401298.38
20347596.11
17694787.37
15386789.23
13378856.03
11634584.98
10117030.42
13697750.9
269979801.1

Payback Period

The payback period analysis is a more simplistic method of calculating the


economic feasibility of a project. This method determines the period in number of
years required for the project to recover back the initial capital investment of the
plant. In using this method, the assumptions stated above such as below still
applies:
1) The plant life is taken as 15 years.
2) The annual net profit of the plant is taken as constant.
3) The class life or recovery period is 7 years.
4) The working capital is taken as 5% of the total fixed capital cost.

4.3.6.1

Simple Payback Period

Table 4.9 : Simple Payback Period

82

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Year
0
1
2

After Tax Cash Flow


-32257260
16316673
16317791

Cumulative Cash Flow


-32257260
-15940587
377204

By interpolation,
Table 4.10 : The Interpolation Simple Payback Period
Cumulative Cash
Flow
-15940587
0
377204

Year
1
1.97
2

Therefore, MTBE plant can have payback period with:


Payback period = (1 + 0.97) years
= 1 years 12 month
2 years

4.3.6.2

Discounted Payback Period

Normally, the interest in Malaysia standardized for chemical plant. By referring to


Hong Leong Bank, the interest is 15% and use as a basis for discounted payback
period.
Table 4.11 : Discounted Payback Period
Year

Annual Cash
Flow After Tax

0
1
2
3

-32257260
16316673
16317791
16317791

Cumulative
Cash Flow

Cumulative
Cash Flow
After Tax

-32257260
-15940587
-2013884.05
14001824.34

-18331675.05
-2315966.658
16102097.99

By interpolation,
Table 4.12 : The Interpolation Discounted Payback Period
Cumulative Cash
Flow
-2315966.658
0
16102097.99

Year
2
2.03
3

Therefore, MTBE plant can have payback period with:


= 2 + (0.03) years

83

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

= 2 year 1 month

4.4 CONCLUSION
Based on this chapter, the economic evaluation of MTBE plant are made
through study in all aspect including feasibility study, process synthesis and flow
sheeting and designed of major equipment.
From the cash flow analysis, the payback period for the MTBE plant is about 2
years. Furthermore, it should be stated that the present work is primarily illustrated
based on the method of engineering economic analysis of chemical processes.
PW is positive value so the project is attractive and acceptable same as when IRR
is bigger than MARR.
By estimate the value of PW, FW and AW by using relationship between PW and
FW the answer of FW same with estimate direct from CFAT.

REFERENCES

84

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Perry R.H and Green, Don, Perrys Chemical Engineers Handbook, 7th
Edition, McGraw-Hill Book Company, Singapore, 1984.
Sinnott, R. K., Coulson & Richardson, Chemical Engineering Volume 6,
Chemical Engineering Design, Butterworth Heinemann, 1999.
Peters, max Stone, Plant Design and Economics for Chemical
Engineers, 2nd Edition, McGraw-Hill Chemical Engineering Series, 1968.

85

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

CHAPTER 5

PROCESS INTEGRATION AND PINCH TECHNOLOGY

5.1

INTRODUCTION

Process integration can lead to a substantial reduction in the energy requirements


of a process. One of the most successful and generally useful techniques is that
developed by Bodo Linnhoff and other workers: pinch technology. The term derives
from the fact that in a plot of the system temperatures versus the heat transferred, a
pinch usually occurs between the hot stream and cold stream curves. It has been
shown that the pinch represents a distinct thermodynamic break in the system and
that, for minimum energy requirements, heat should not be transferred across the
pinch, Linhoff and Townsend (1982) (Ref: Coulson & Richardsons vol. 6)
5.2

PINCH TECHNOLOGY

There are four streams to consider the problem of integrating the utilization of
energy. Two hot streams which require cooling and two cold streams that have to
be heated. Each streams starts from a source temperature Ts, and is to be heated
or cooled to a target temperature, Tt. The heat capacity of each stream is shown as
CP.
CP is given by:
CP = mCp
(5.1)
Where,

m = mass flow rate, kg/s


Cp = average specific heat capacity between Ts and Tt,
(KJ/kgoC)

Table 5.1:

Shows the process data for each stream.

86

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Heat
Stream number

Type

1
2
3
4

HOT
HOT
COLD
COLD

Heat capacity
Cp(KW/ oC)
3.2
1.3
2
4

Ts(oC)

Tt (oC)

180
150
20
75

50
30
140
135

Load
(KW)
416
156
240
240

The heat load shown in the table is the total heat required to heat or cools the
stream from the source to target temperature. The stream are shown
diagrammatically below,

Stream 1

180C

CP = 3.2 kW/C

50C

Stream 2

150C

CP = 1.3kW/C

30C

Stream 3

20C

CP = 2 kW/C

140C

Stream 4

75C

CP = 4 kW/C

135C

Figure 5.1:
5.3

Diagrammatically representation of process stream

THE PROBLEM TABLE METHOD

The problem table is a numerical method for determining the pinch temperature and
the minimum utility requirements. Firstly, it needs to convert the actual stream
temperature Tact into the interval temperatures Tint.
Hot streams Tint

Tact (Tmin/2)

Cold streams Tint

Tact (Tmin/2)

The minimum temperature difference taken from composite curve as, Tmin = 10 oC

87

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Hot a nd Cold Com posite curve s


350

Temperature

300
250
200

Hot Stre am s

150

Cold Stre am s

100
50
0
1

Enthalpy,1 0kW

Figure 5.2: Hot and cold streams composite curves


Table 5.2: Interval Temperature for Tmin = 10oC

Actual Temp. oC

Stream

Interval Temp. oC

180

50

175

45

150

30

145

25

20

140

25

145

10

75

135

80

140

The heat balance for the streams falling within each temperature interval:
For the nth interval:
Hn

(CPc - CPh) (Tn)

net heat required in the nth interval

(5.2)
Where, Hn

CPc =

sum of the heat capacities of all the cold streams in interval

CPh =

sum of the heat capacities of all the hot streams in the


interval

Tn

interval temperature difference=(Tn-1-Tn)

88

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

175
Interval 1:

145
1

Interval 2:

140
2

Interval 3:

80

Interval 4:

45

Interval 5:

25

Figure 5.3:
Table 5.3:

Intervals and streams

Ranked order of interval temperature

Rank,oC

Interval, Tn oC

Stream in interval

145

30

-1

140

4-(2+1)

80

60

(3+4)-(1+2)

45

35

3-(1+2)

25

20

(3-2)

175

Cascading the heat from one interval to the next implies that the temperature
difference is such that the heat can be transferred between the hot and cold
streams. A negative value in the column indicates the temperature gradient is in the
wrong direction and that the exchange is not thermodynamically possible.

Table 5.4:

Problem Table
CPc - CPh

Interval

Tint, C

o
n

T ,C

(Kw/oC)

Hn (KW)

surplus/deficit

89

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

175
1

145

30

-3.2

-96

140

0.5

2.5

80

60

2.1

126

45

35

-2.0

-87.5

25

20

1.0

14

Interval temperature
Rank oC
175oC

0kW

145oC

-96kW

96 kW

-96 kW

128.5 kW

140oC

2.5 kW

93.5 kW

2.5 kW

126 kW

80oC

126 kW

-32.5 kW

126 kW

0 kW

45oC

-87.5 kW

55 kW

-87.5 kW

87.5 kW

25oC

14 kW

-41 kW

14 kW

73.5 kW

32.5 kW

Figure 5.4 Heat Cascade


From figure 5.4: pinch occurs at interval temperature 80oC
At the pinch, hot stream

80 + 5

85 oC

80 5

75oC

(5.3)

Cold stream
(5.4)

5.4

THE HEAT EXCHANGER NETWORK

The grid representation of the stream is shown in Figure 5


CP

90

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

(KW/ oC)
o

85 C75 C
180oC

50 oC
3.2

1
150 oC

30 oC
1.3

2
140 oC

20 oC
2.0

3
135 oC

75 oC
4.0

Figure 5.5 Grid for 4 stream problem


For maximum energy recovery (minimum utility consumption) the best performance
is obtained if no cooling is used above the pinch. This means the hot streams
above the pinch should be brought it the pinch temperature solely by exchange with
the cold streams.
THE NETWORK DESIGN ABOVE THE PINCH
CP hot CP cold
Applying this condition at the pinch, stream 1 can be matched with stream 4, but not
with 3.
Matching streams 1 and 4 and transferring the full amount of heat required to bring
stream 1 to the pinch temperature gives;
Hex

CP (T pinch - Ts)

304 kW

(5.5)

This will also satisfy the heat load required to bring stream 4 to its target
temperature.

91

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Stream 2 can be matched with stream 3, whilst satisfying the heat capacity
restriction. Transferring the full amount to bring stream 3 to the pinch temperature:
Hex

CP (T pinch- Ts)

97.5 kW

The heat required to bring stream 3 to its target temperature, from the pinch
temperature, is:
H

2.0(140-75)

130 kW

So a heater will have to be included to provide the remaining heat load:


Hhot

130-97.5 kW

32.5 kW

(5.6)

THE NETWORK DESIGN BELOW THE PINCH


Stream 1 is matched with stream 3 transferring the full amount to bring stream 1 to
its target temperature; transferring:
Hex

3.2(85-50)

112 kW

Stream 3 requires more heat to bring it to pinch temperature; amount needed:


H

2.0(75-20)-85kW

25 kW

So transferring 25 kW will raise the temperature from the source temperature to:
20+ 25/2 =32.5 kW
and gives a stream temperature difference on the outlet side of the exchanger of:
85-32.5 = 52.5 kW

So the minimum temperature difference condition, 10oC will not be violet by this
match.
Stream 2 will need further cooling to bring its to its target temperature, so a cooler
must be included; cooling required.
Hcold =
=

1.3 (85-50)-25
73.5 kW

92

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

The proposed network for maximum energy recovery is shown in Figure 5.5

Figure 5.6 Proposed heat exchanger network


5.5

MINIMUM NUMBER OF EXCHANGERS

The network shown in figure 5.5 was designed to give the maximum heat recovery,
and therefore give the minimum consumption, and cost of the hot and cold utilities.
In figure 5.5 it is clear that there is scope for reducing the number of exchangers.
Exchanger D can be deleted and the heat loads of the cooler and heater increased
to bring stream 2 and 3 to their target temperatures. Heat would across the pinch
and the consumption of the utilities would be increased
For complex networks a more general expression is needed to determine the
number of exchangers:
Zmin = N +L S

(5.7)

Where L= the number of internal loops present in the network


S= the number of independence branches (subsets) that exist in the
network
N= the number of streams including the utilities

93

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

In a final design, there are 3 exchangers, rather than 4 before the process
integration and pinch technology, with the minimum heating and cooling loads, 32.5
kW and 73.5 kW, respectively, match those predicted from the problem table,
compare with the loads for heating and cooling before process integration: 416 kW
and 240 kW.

94

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

CHAPTER 6

WASTE TREATMENT

6.1

INTRODUCTION

Pollution is something that should be taken into serious consideration in any


petrochemical plant especially the MTBE plant. Pollution, no matter what kind of the
pollution is has serious negative effects not only to human beings, but also to
animals, plants and to the environment. Therefore, it is the responsibility of each
individual to ensure that their activities are not harmful to the environment. This
includes activities and works involved in designing a plant. Waste from any
petrochemical plant should be treated according to the local and international
standards before being released to the environment.
In the MTBE plant, the wastes are only the in liquid form and gas form. The liquid
will be treated in the wastewater treatment plant. The hydrogen gas leaving the
reactor is sent to a gas cylinder which it is then sold to interested company at
market price. The treatment processes and systems employed by the MTBE plant
is the typical processes and systems based on Howard S. Peavy, Donald R. Rowe,
George Tchobanoglous; Environmental

Engineering, McGraw-Hill, 1985 and

David H. F. Liu, Bela G. Liptak, Wastewater Treatment, Lewis Publishers, 1999.

6.2

WASTEWATER TREATMENT

95

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Wastewater treatment is a must in any plant. The wastewater from plant


cannot be channeled into the sewage system without being treated. The
wastewater from the MTBE plant may contains a small amount of the feed and
product and a small quantity of by-products such as butene, TBA and dimethylether. According to the site location selected, the wastewater from the plant is to be
treated and should comply with Standard B which is shown Table 6.1.
In the design of the wastewater treatment plant for the production of MTBE,
the COD value used is based of the COD value of wastewater from other plants
that are in operation. The COD value of 3000 mg/l will be used for design purposes.
The design of the plant consists of preliminary, primary and secondary treatment
where each treatment unit chosen is based on the characteristics of the influent to
be treated. Before being treated, all the wastewater is channeled to the holding
tank. It is then ferried for screening and the next process is the primary settling
tank. The effluent leaving this tank is sent to the active sludge reactor. After that, it
will be sent to the secondary settling tank. Finally, the effluent undergoes
adsorption by activated carbon before leaving the wastewater treatment plant.

6.2.1 Denitrification Process (Chemical Treatment)

96

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

To remove methanol in the waste water, we use the denitrification process


in our plant waste treatment. In the denitrification process, nitrate is reduced to
nitrogen gas by the same facultative, heterotrophic bacteria involved in the
oxidization of carbonaceous material. For reduction to occur the dissolved oxygen
level must be at or near zero and a carbon supply must be available to the bacteria.
Because low carbon content is required for the previous nitrification step, carbon
must be added before denitrification can proceed. A small amount of primary
effluent, bypassed around secondary and nitrification reactors, can be used to
supply the carbon. However, the unnitrified compounds in this water will be
unaffected by the denitrification process and will appear in the effluent. When
essentially complete nitrogen removal is required, an external source of carbon
containing no nitrogen will be required. The most commonly used external carbon
source is methanol, CH3OH. When methanol is added, the denitrification reaction is:

NO3- +

5
CH3OH
6

1
5
7
N2 + CO2+ H2O +OH2
6
6

Theoretically, each milligram per liter of nitrate should require 1.9 mg/L of
methanol. Under treatment plant conditions, however about 3.0 mg/L of methanol is
required for each milligram per litre of nitrate, making this process an expensive
one.

97

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Table 6.1 Parameter Limits for Wastewater and Effluent Under the Environmental
Quality Act 1974.
PARAMETER
Temperature
pH
BOD5 at 20oC
COD
Suspended solid
Mercury
Cadmium
Chromium Hexavalent
Arsenic
Cyanide
Lead
Copper
Manganese
Nickel
Tin
Zinc
Boron
Iron
Phenol
Free Chlorine
Sulfide
Oil and grease

UNIT
o
C
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l

STANDARD A
40
6.0-9.0
20
50
50
0.005
0.01
0.05
0.05
0.05
0.10
0.20
0.20
0.20
0.20
1.0
1.0
1.0
0.001
1.0
0.5
None

STANDARD B
40
5.5-9.0
50
100
100
0.05
0.02
0.05
0.10
0.10
0.5
1.0
1.0
1.0
1.0
1.0
4.0
5.0
1.0
2.0
0.5
10

* Both standards could be used and acceptable, but only one is chosen, Standard B
for the wastewater treatment for the MTBE plant.

6.3

WASTEWATER TREATMENT PLANT DESIGN

The design of the wastewater treatment plant consists of the holding tank, the
design of the screening device, then the design of the settling tank, the design of
the primary and secondary sedimentation tanks, and lastly the design for the
activated sludge process.

98

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

The next step is the sludge treatment which consists of the sludge
thickening by centrifugation, condensation by using heat treatment and lastly
dehydration by using vacuum filter.
Since the gas produced only hydrogen and no other gases, so the gas
needs no treatment. The hydrogen gas produced is stored to be sold to interested
companies like MOX Sdn. Bhd..

6.3.1

Design of Holding Tank


The purpose of the holding tank is to hold and accumulate the wastewater

before it undergoes further treatment. The design of the holding tank is as follows:
Wastewater flow rate

Volume of wastewater per day

m 3 24 hr

hr
day

1.5642

37 .54

37.54 m3

m3
day

By taking into consideration the depth of the holding tank as 3 m, and the ratio of
the length to the width as 3:1, the dimensions of the holding tank are as follows:
Depth of holding tank

3.0 m

Width of holding tank

3.0 m

Length of holding tank

9.0 m

Volume of holding tank

81.0 m3

This means that the holding time is about two days (81m3/37.54m3) and it is
acceptable.

6.3.2

Design of Screening Device


In the preliminary treatment of the wastewater, the treatment chosen is by

using screening. Fine screens made of woven-wire cloth are used. The screen is
used to remove small particles which might be in the wastewater. A screen with
small sized openings is chosen because the wastewater does not contain large
particles. The head loss is calculated by using the following equation:

99

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

1 Q
hL =

C( 2g ) A

(6.1)

Where hL

head loss, m

waste constant for screen

0.6 for clean screen (Metcalf & Eddy, 1979)

gravity, ms-2

Flow through screen, m3s-1

Effective opening area for submerged screen, m2

take as 9m2

Thus, h L =

1
0.6 2 9.81

2
4.345 x10 4

h L = 1.9799 10 10 m

6.3.3

Design of Settling Tank


For the wastewater treatment, sulfide precipitation treatment is used to

remove heavy metals from the wastewater. The precipitant used is sodium sulfide,
which will react with the metal ions and will form non-soluble sulfide metal.
However, extra care is required in this process to avoid sulfide poisoning. Pretreatment which involves the increasing of the pH of the wastewater is required to
minimize the release of hydrogen sulfide gas. The design of the settling tank is as
follows:
Take holding time

15 minutes (standard holding time)

Average flow rate

1.5642

Holding time

15 minutes

0.25 hr

Average flow rate

1.5642

0.391 m 3

Tank volume

m3
hr

Holding time

m3
0.25 hr
hr

100

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

By taking the depth as L=0.8m, and using a square tank,


Length of tank

V
L

0.391
0.8

=
6.3.4

0.70 m

Design of Primary and Secondary Sedimentation Tank


Primary sedimentation is a unit operation designed to concentrate and

remove suspended organic

solids

from the wastewater. The secondary

sedimentation tank is designed as a unit operation for the activated sludge process.
The design for the sedimentation tanks are as follows:
Take holding time

2 hr

Average flow rate

1.5642

Holding time

2 hr

Tank Volume

Average flow rate

1.5642

3.1284 m 3

m3
hr

Holding time

m3
2hr
hr

By taking the depth as L=2m,


Length of tank

6.3.5

V
L

3.1284
2

2.50 m

Design for Activated Sludge Process

The activated sludge process is a treatment process that involves the production of
a living or active microorganism which is used to stabilize the waste aerobically. A
completely mixed reactor is used in this process. This reactor is used as it is
suitable for general wastewater treatment and it has a high efficiency (85-95%) to
reduce high COD or BOD. This process involves a completely mixed reactor
followed by a secondary sedimentation tank. Part of the sludge from the secondary

101

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

sedimentation tank is recycled to the influent reactor. The design for the reactor is
as follows:
m3
hr

Average flow rate

1.5642

Holding time

3 hr

Tank Volume

Average flow rate

1.5642

4.693 m 3

Holding time

m3
3hr
hr

By taking the depth as L=2m,


Length of tank

6.3.6

V
L

4.69
2

1.53 m

Oxygen Demand and Aerator

COD (kg/day)

Influent COD

112 .62

wastewater flow rate

kg
m3

37
.
54
m3
day
kg
day

By assuming that 1kg COD requires 1kg of oxygen, thus 112.62 kg/day COD
requires 112.62 kg O2/day. The aerator used is a mechanical aerator with an
oxygen transfer rate of 1.8 kg O2/day.
Power needed

Oxygen needed per hour

O2 needed per hour / O2 transfer rate

112 .62

4.69

kg
1day

day
24 hr

kg
hr

102

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Thus, power needed

4.69 kg day

1.8 hr
kg

2.61 kW

An aerator unit provides 10kW of power. Thus, one unit is sufficient to provide
enough power for the activated sludge process.

6.4

SLUDGE TREATMENT
In this wastewater treatment plant, sludge is formed in the primary and

secondary sedimentation tank. This sludge needs to be treated and disposed. For
the MTBE plant, the following operations are used for the sludge treatment system:
i.

Sludge thickening by centrifugation

ii.

Condensation by using heat treatment

iii.

Dehydration by using vacuum filter

Wastes from the sludge treatment system, for example the filtrate from the
vacuum filter, are sent to the influent treatment plant to undergo further treatment.
Dehydrated sludge is sent to the sludge dump site. The flow chart for the sludge
treatment is shown in Figure 6.1. Although the treatment is expensive, it is
necessary for our plant.

103

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

S l udge P la nt

C EN TR IFU G ATIO N
TH IC K EN IN G

H EA T
TR E ATM EN T

T o influ ent plant

S l udge to dis pos al s ite

SL U D G E
STO R AG E

D ehy dr ated s lud ge

VAC U U M
FIL TE R

F iltrate to influen t pl an t

Figure 6.1 The Sludge Treatment System

6.5

WASTE TREATMENT PLANT LAYOUT


Generally, the layout of a waste treatment plant depends on the process

requirements. The treatment plant covers an area of 800m2. The plant layout is
shown in Figure 6.3. The waste treatment plant consists of the following units:
1.

1 holding tank

2.

1 primary sedimentation tank

3.

1 secondary sedimentation tank

4.

1 activated sludge reactor

5.

1 screening device

6.

1 power house

7.

4 pumps

8.

1 sludge store

9.

Units in the sludge treatment process


Table 6.2 Functions of Pumps in the Waste Treatment Plant
Pump

Function

104

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

To pump sludge from the sedimentation tank to the sludge


treatment tank.

To pump sludge from the secondary sedimentation tank to be


recycled to the activated sludge reactor.

To pump sludge from the secondary sedimentation tank to the


sludge treatment process.

To pump wastewater from the sludge treatment system to be


recycled to the influent plant.

U
LEG END
Pum p
P R IM A R Y
S E D IM E N T A T IO N T A N K

S lu d g e
f ro m
p r im a ry
s e d im e n t a t io n t a n k to b e
t re a t e d

S lu d g e
f ro m
s e c o n d a ry
s e d im e n t a t io n t a n k to b e
r e c y c le d

S lu d g e
f ro m
s e c o n d a ry
s e d im e n t a t io n t a n k to b e
t r e a te d
W a s t e w a te r f r o m s lu d g e
t r e a tm e n t s y s te m to in flu e n t
p la n t

F lo w
S lu d g e F lo w

S E T T L IN G T A N K

W a ste w a te r
F lo w

POW ER HOUSE
A E R A T IO N T A N K

S C R E E N IN G D E V IC E
2

S LU D G E TR EA TM E N T PR O C E SS

SECO NDARY
S E D IM E N T A T IO N T A N K
H O L D IN G T A N K

Figure 6.2 Waste Treatment Plant Layout


6.6

ABSORPTION TANK USING GRANULAR ACTIVATED CARBON

105

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

In the operation of absorption tank, granular activated carbon (GAC) is used


which has a diameter between 0.1-2.0 mm. The contact system for GAC consists of
cylindrical tanks, which contain a bed of the carbon material (refer the design
given). The water is passed through the bed with sufficient residence time allowed
for completion of the adsorption process. The system is operating in a fixed bed
mode. Fixed bed systems are batch operations that are taken off the line when the
adsorptive capacity of the carbon in used up.
Although fixed granular carbon beds can be cleaned in a place with
superheated steam, the most common practice is to remove the carbon for cleaning
in a furnace. The regeneration process is essentially the same as the original
activation process. The adsorbed organics are first burned at about 800 oC in the
absence of oxygen. An oxidizing agent, usually stream, is then applied at slightly
higher temperatures to remove the residue and reactivated carbon.

6.6.1 Analysis of the Absorption Process


The adsorption process takes place in the three steps, macrotransport,
microtransport and sorption. The quantities of adsorbate that can be taken up by an
adsorbent are function of both the characteristics and concentration of adsorbate
and the temperature. Generally, the amount of material absorbed is determined as
a function of the concentration at a constant temperature and the resulting function
is called an absorption isotherm. Equation that are often used to described the
experimental isotherm data where developed by Freundlich by Langmuir and by
Brunauer, Emmet and Teller (BET isotherm).
Freundlich Isotherm Equation:
x
= K f Ce1 n
m
Where x/m

= amount adsorbate absorbed per unit weight of absorbent (activated


carbon)

Ce

= equilibrium concentration of absorbed in solution after absorption


K f , n = empirical constant

106

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

The constants in the Freundlich isotherm can be determined by plotting (x/m)


versus C and making use of above equation rewritten as:
1
x
log = log K f + log Ce
n
m
6.6.2

Breakthrough Absorption Capacity


In the field, the breakthrough adsorption capacity, ( x m )b , of the GAC in a

full-scale column is some percentage of the theoretical absorption capacity found


from the isotherm. The

(x

m )b of a single column can be assumed to be

approximately 25 to 50 percent of the theoretical capacity ( x m ) o . Once ( x m )b is


known, time to breakthrough can be calculated by solving the following equation for
tb

X
C t
x

= b = Q Ci b b [8.34 lb Mgal .( mg L ) ]
2 Mc
m b M c

x
Where = field breakthrough adsorption capacity, lb/lb or g/g
m b
X b = mass of organic material absorbed in the GAC column at
breakthrough, lb or g
M c = mass of carbon in the column, lb or g

Q = flow rate, Mgal/d


Ci = influent organic concentration, mg/L
Cb = breakthrough organic concentration, mg/L
tb = time to breakthrough, day

Equation above was developed assuming that Ci is constant and that the effluent
concentration increases linearly with time from 0 to Cb value. The time breakthrough
can be calculated using the rearranging equation above. From the test data by
Freundlich adsorption isotherm plotted,

107

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

x
3.56
= 0.0015 Ce
m
x
= 0.0015(3.250)3.56
m 0

= 0.0996 mg/mg say 0.10 mg/mg = 0.10 Ib/Ib


Determination of breakthrough time,

tb =

( x / m) b M c
Q (Ci Cb / 2[8.34 Ib / Mgal .( mg / L)]

Following condition apply:

(x

m )b =50 percent of ( x m ) o =o.5 (0.10 lb/lb) = 0.050 lb/lb

Assuming from the data testing by Freundlich adsorption isotherm,


Surface area = 10 ft 2 = 0.929m2
M c = (10 ft 2 ) ( 5.0 ft ) 38 lb ft 3 = 1,900 lb
Q = 5.0 gal ft 2 . min 1440 min d 10 ft 2 = 72000 gal d = 0.072 Mgal d
Ci = 3.2 mg L
Cb = 0.75 mg L

the time to breakthrough is

tb =

( x / m) b M c
Q (Ci Cb / 2[8.34 Ib / Mgal .( mg / L)]

tb = 56 day

Therefore, results from our study based on Freundlich adsorption isotherm the
activated carbon in our design waste treatment column vessel can long lasting for
56 day. Therefore, our estimation is changing the activated carbon in the vessel
waste treatment in every 56 day to make sure the efficiency capacity of adsorption
carbon is in the maximum capacity.

REFERENCES

108

PRODUCTION OF 300,000 METRIC TON OF MTBE PER YEAR

Howard S. Peavy, Donald R. Rowe, George Tchobanoglous; Environmental


Engineering, McGraw-Hill, 1985.
David H. F. Liu, Bela G. Liptak, Wastewater Treatment, Lewis Publishers, 1999.

109

You might also like