Professional Documents
Culture Documents
CFL - First Batch of Cases
CFL - First Batch of Cases
CRUZ, J.:
This case involves the Proper interpretation of Article 28(1) of the Warsaw
Convention, reading as follows:
Art. 28. (1) An action for damage must be brought at the option of
the plaintiff, in the territory of one of the High Contracting Parties,
either before the court of the domicile of the carrier or of his
principal place of business, or where he has a place of business
through which the contract has been made, or before the court at
the place of destination.
The petitioner is a minor and a resident of the Philippines. Private respondent
Northwest Orient Airlines (NOA) is a foreign corporation with principal office in
Minnesota, U.S.A. and licensed to do business and maintain a branch office in the
Philippines.
On October 21, 1986, the petitioner purchased from NOA a round-trip ticket in San
Francisco. U.S.A., for his flight from San Francisco to Manila via Tokyo and back. The
scheduled departure date from Tokyo was December 20, 1986. No date was specified
for his return to San Francisco. 1
On December 19, 1986, the petitioner checked in at the NOA counter in the San
Francisco airport for his scheduled departure to Manila. Despite a previous
confirmation and re-confirmation, he was informed that he had no reservation for his
flight from Tokyo to Manila. He therefore had to be wait-listed.
On March 12, 1987, the petitioner sued NOA for damages in the Regional Trial Court
of Makati. On April 13, 1987, NOA moved to dismiss the complaint on the ground of
lack of jurisdiction. Citing the above-quoted article, it contended that the complaint
could be instituted only in the territory of one of the High Contracting Parties, before:
1. the court of the domicile of the carrier;
On February 1, 1988, the lower court granted the motion and dismissed the
case. 2 The petitioner appealed to the Court of Appeals, which affirmed the decision of
the lower court. 3 On June 26, 1991, the petitioner filed a motion for reconsideration,
but the same was denied. 4 The petitioner then came to this Court, raising
substantially the same issues it submitted in the Court of Appeals.
The assignment of errors may be grouped into two major issues, viz:
(1) the constitutionality of Article 28(1) of the Warsaw Convention; and
(2) the jurisdiction of Philippine courts over the case.
The petitioner also invokes Article 24 of the Civil Code on the protection of minors.
I
THE ISSUE OF CONSTITUTIONALITY
A. The petitioner claims that the lower court erred in not ruling that
Article 28(1) of the Warsaw Convention violates the constitutional
guarantees of due process and equal protection.
The Republic of the Philippines is a party to the Convention for the Unification of
Certain Rules Relating to International Transportation by Air, otherwise known as the
Warsaw Convention. It took effect on February 13, 1933. The Convention was
concurred in by the Senate, through its Resolution No. 19, on May 16, 1950. The
Philippine instrument of accession was signed by President Elpidio Quirino on
October 13, 1950, and was deposited with the Polish government on November 9,
1950. The Convention became applicable to the Philippines on February 9, 1951. On
September 23, 1955, President Ramon Magsaysay issued Proclamation No. 201,
declaring our formal adherence thereto. "to the end that the same and every article
and clause thereof may be observed and fulfilled in good faith by the Republic of the
Philippines and the citizens thereof." 5
The Convention is thus a treaty commitment voluntarily assumed by the Philippine
government and, as such, has the force and effect of law in this country.
The petitioner contends that Article 28(1) cannot be applied in the present case
because it is unconstitutional. He argues that there is no substantial distinction
between a person who purchases a ticket in Manila and a person who purchases his
ticket in San Francisco. The classification of the places in which actions for damages
may be brought is arbitrary and irrational and thus violates the due process and equal
protection clauses.
It is well-settled that courts will assume jurisdiction over a constitutional question only
if it is shown that the essential requisites of a judicial inquiry into such a question are
first satisfied. Thus, there must be an actual case or controversy involving a conflict of
legal rights susceptible of judicial determination; the constitutional question must have
been opportunely raised by the proper party; and the resolution of the question is
unavoidably necessary to the decision of the case itself. 6
Courts generally avoid having to decide a constitutional question. This attitude is
based on the doctrine of separation of powers, which enjoins upon the departments of
the government a becoming respect for each other's acts.
The treaty which is the subject matter of this petition was a joint legislative-executive
act. The presumption is that it was first carefully studied and determined to be
constitutional before it was adopted and given the force of law in this country.
The petitioner's allegations are not convincing enough to overcome this presumption.
Apparently, the Convention considered the four places designated in Article 28 the
most convenient forums for the litigation of any claim that may arise between the
airline and its passenger, as distinguished from all other places. At any rate, we agree
with the respondent court that this case can be decided on other grounds without the
necessity of resolving the constitutional issue.
B. The petitioner claims that the lower court erred in not ruling that
Art. 28(1) of the Warsaw Convention is inapplicable because of a
fundamental change in the circumstances that served as its basis.
The petitioner goes at great lengths to show that the provisions in the Convention
were intended to protect airline companies under "the conditions prevailing then and
which have long ceased to exist." He argues that in view of the significant
developments in the airline industry through the years, the treaty has become
irrelevant. Hence, to the extent that it has lost its basis for approval, it has become
unconstitutional.
The petitioner is invoking the doctrine of rebus sic stantibus. According to Jessup,
"this doctrine constitutes an attempt to formulate a legal principle which would justify
non-performance of a treaty obligation if the conditions with relation to which the
parties contracted have changed so materially and so unexpectedly as to create a
situation in which the exaction of performance would be unreasonable." 7 The key
element of this doctrine is the vital change in the condition of the contracting parties
that they could not have foreseen at the time the treaty was concluded.
The Court notes in this connection the following observation made in Day v. Trans
World Airlines, Inc.: 8
The Warsaw drafters wished to create a system of liability rules that
would cover all the hazards of air travel . . . The Warsaw delegates
knew that, in the years to come, civil aviation would change in ways
that they could not foresee. They wished to design a system of air
law that would be both durable and flexible enough to keep pace
with these changes . . . The ever-changing needs of the system of
civil aviation can be served within the framework they created.
It is true that at the time the Warsaw Convention was drafted, the airline industry was
still in its infancy. However, that circumstance alone is not sufficient justification for the
rejection of the treaty at this time. The changes recited by the petitioner were,
realistically, not entirely unforeseen although they were expected in a general sense
only. In fact, the Convention itself, anticipating such developments, contains the
following significant provision:
Article 41. Any High Contracting Party shall be entitled not earlier
than two years after the coming into force of this convention to call
for the assembling of a new international conference in order to
consider any improvements which may be made in this convention.
To this end, it will communicate with the Government of the French
Republic which will take the necessary measures to make
preparations for such conference.
But the more important consideration is that the treaty has not been rejected by the
Philippine government. The doctrine of rebus sic stantibus does not operate
automatically to render the treaty inoperative. There is a necessity for a formal act of
rejection, usually made by the head of State, with a statement of the reasons why
compliance with the treaty is no longer required.
In lieu thereof, the treaty may be denounced even without an expressed justification
for this action. Such denunciation is authorized under its Article 39, viz:
Article 39. (1) Any one of the High Contracting Parties may
denounce this convention by a notification addressed to the
Government of the Republic of Poland, which shall at once inform
the Government of each of the High Contracting Parties.
(2) Denunciation shall take effect six months after the notification of
denunciation, and shall operate only as regards the party which
shall have proceeded to denunciation.
Obviously. rejection of the treaty, whether on the ground of rebus sic stantibus or
pursuant to Article 39, is not a function of the courts but of the other branches of
government. This is a political act. The conclusion and renunciation of treaties is the
prerogative of the political departments and may not be usurped by the judiciary. The
courts are concerned only with the interpretation and application of laws and treaties
in force and not with their wisdom or efficacy.
C. The petitioner claims that the lower court erred in ruling that the
plaintiff must sue in the United States, because this would deny
him the right to access to our courts.
The petitioner alleges that the expenses and difficulties he will incur in filing a suit in
the United States would constitute a constructive denial of his right to access to our
courts for the protection of his rights. He would consequently be deprived of this vital
guaranty as embodied in the Bill of Rights.
Obviously, the constitutional guaranty of access to courts refers only to courts with
appropriate jurisdiction as defined by law. It does not mean that a person can go
to any court for redress of his grievances regardless of the nature or value of his
claim. If the petitioner is barred from filing his complaint before our courts, it is
because they are not vested with the appropriate jurisdiction under the Warsaw
Convention, which is part of the law of our land.
II
The private respondent for its part invokes the ruling in Butz v. British
Airways, 17 where the United States District Court (Eastern District of Pennsylvania)
said:
. . . Although the authorities which addressed this precise issue are
not extensive, both the cases and the commentators are almost
unanimous in concluding that the "place of destination" referred to
in the Warsaw Convention "in a trip consisting of several parts . . .
is the ultimate destination that is accorded treaty jurisdiction." . . .
But apart from that distinguishing feature, I cannot agree with the
Court's analysis in Aanestad; whether the return portion of the ticket
is characterized as an option or a contract, the carrier was legally
bound to transport the passenger back to the place of origin within
the prescribed time and. the passenger for her part agreed to pay
the fare and, in fact, did pay the fare. Thus there was mutuality of
obligation and a binding contract of carriage, The fact that the
passenger could forego her rights under the contract does not
make it any less a binding contract. Certainly, if the parties did not
contemplate the return leg of the journey, the passenger would not
have paid for it and the carrier would not have issued a round trip
ticket.
We agree with the latter case. The place of destination, within the meaning of the
Warsaw Convention, is determined by the terms of the contract of carriage or,
specifically in this case, the ticket between the passenger and the carrier.
Examination of the petitioner's ticket shows that his ultimate destination is San
Francisco. Although the date of the return flight was left open, the contract of carriage
between the parties indicates that NOA was bound to transport the petitioner to San
Francisco from Manila. Manila should therefore be considered merely an agreed
stopping place and not the destination.
The petitioner submits that the Butz case could not have overruled the Aanestad case
because these decisions are from different jurisdictions. But that is neither here nor
there. In fact, neither of these cases is controlling on this Court. If we have preferred
the Butz case, it is because, exercising our own freedom of choice, we have decided
that it represents the better, and correct, interpretation of Article 28(1).
Article 1(2) also draws a distinction between a "destination" and an "agreed stopping
place." It is the "destination" and not an "agreed stopping place" that controls for
purposes of ascertaining jurisdiction under the Convention.
The contract is a single undivided operation, beginning with the place of departure
and ending with the ultimate destination. The use of the singular in this expression
indicates the understanding of the parties to the Convention that every contract of
carriage has one place of departure and one place of destination. An intermediate
place where the carriage may be broken is not regarded as a "place of destination."
C. The petitioner claims that the lower court erred in not ruling that
under Art. 28(1) of the Warsaw Convention, this case was properly
filed in the Philippines because the defendant has its domicile in
the Philippines.
The petitioner argues that the Warsaw Convention was originally written in French
and that in interpreting its provisions, American courts have taken the broad view that
the French legal meaning must govern. 18 In French, he says, the "domicile" of the
carrier means every place where it has a branch office.
The private respondent notes, however, that in Compagnie Nationale Air France vs.
Giliberto, 19 it was held:
The plaintiffs' first contention is that Air France is domiciled in the
United States. They say that the domicile of a corporation includes
any country where the airline carries on its business on "a regular
and substantial basis," and that the United States qualifies under
such definition. The meaning of domicile cannot, however, be so
extended. The domicile of a corporation is customarily regarded as
the place where it is incorporated, and the courts have given the
meaning to the term as it is used in article 28(1) of the Convention.
(See Smith v. Canadian Pacific Airways, Ltd. (2d Cir. 1971), 452
F2d 798, 802; Nudo v. Societe Anonyme Belge d' Exploitation de la
Navigation Aerienne Sabena Belgian World Airlines (E.D. pa.
1962). 207 F. Supp, 191; Karfunkel v. Compagnie Nationale Air
France (S.D.N.Y. 1977), 427 F. Suppl. 971, 974). Moreover, the
structure of article 28(1), viewed as a whole, is also incompatible
with the plaintiffs' claim. The article, in stating that places of
business are among the bases of the jurisdiction, sets out two
places where an action for damages may be brought; the country
where the carrier's principal place of business is located, and the
country in which it has a place of business through which the
particular contract in question was made, that is, where the ticket
was bought, Adopting the plaintiffs' theory would at a minimum blur
these carefully drawn distinctions by creating a third intermediate
category. It would obviously introduce uncertainty into litigation
under the article because of the necessity of having to determine,
and without standards or criteria, whether the amount of business
done by a carrier in a particular country was "regular" and
"substantial." The plaintiff's request to adopt this basis of jurisdiction
reserved seat to someone who had no better right to it. In short. the private
respondent committed a tort.
Such allegation, he submits, removes the present case from the coverage of the
Warsaw Convention. He argues that in at least two American cases, 21 it was held that
Article 28(1) of the Warsaw Convention does not apply if the action is based on tort.
This position is negated by Husserl v. Swiss Air Transport Company, 22 where the
article in question was interpreted thus:
jurisdiction. Article 28(1) is the provision in the Convention which defines that
jurisdiction. Article 22 23 merely fixes the monetary ceiling for the liability of the carrier
in cases covered by the Convention. If the carrier is indeed guilty of willful
misconduct, it can avail itself of the limitations set forth in this article. But this can be
done only if the action has first been commenced properly under the rules on
jurisdiction set forth in Article 28(1).
III
THE ISSUE OF PROTECTION TO MINORS
The petitioner calls our attention to Article 24 of the Civil Code, which states:
Art. 24. In all contractual property or other relations, when one of
the parties is at a disadvantage on account of his moral
dependence, ignorance, indigence, mental weakness, tender age
or other handicap, the courts must be vigilant for his protection.
Application of this article to the present case is misplaced. The above provision
assumes that the court is vested with jurisdiction to rule in favor of the disadvantaged
minor, As already explained, such jurisdiction is absent in the case at bar.
CONCLUSION
A number of countries have signified their concern over the problem of citizens being
denied access to their own courts because of the restrictive provision of Article 28(1)
of the Warsaw Convention. Among these is the United States, which has proposed an
amendment that would enable the passenger to sue in his own domicile if the carrier
does business in that jurisdiction. The reason for this proposal is explained thus:
In the event a US citizen temporarily residing abroad purchases a
Rome to New York to Rome ticket on a foreign air carrier which is
generally subject to the jurisdiction of the US, Article 28 would
prevent that person from suing the carrier in the US in a "Warsaw
Case" even though such a suit could be brought in the absence of
the Convention.
The proposal was incorporated in the Guatemala Protocol amending the Warsaw
Convention, which was adopted at Guatemala City on March 8,
1971. 24 But it is still ineffective because it has not yet been ratified by the required
minimum number of contracting parties. Pending such ratification, the petitioner will
still have to file his complaint only in any of the four places designated by Article 28(1)
of the Warsaw Convention.
The proposed amendment bolsters the ruling of this Court that a citizen does not
necessarily have the right to sue in his own courts simply because the defendant
airline has a place of business in his country.
The Court can only sympathize with the petitioner, who must prosecute his claims in
the United States rather than in his own country at least inconvenience. But we are
unable to grant him the relief he seeks because we are limited by the provisions of
the Warsaw Convention which continues to bind us. It may not be amiss to observe at
this point that the mere fact that he will have to litigate in the American courts does
not necessarily mean he will litigate in vain. The judicial system of that country in
known for its sense of fairness and, generally, its strict adherence to the rule of law.
WHEREFORE, the petition is DENIED, with costs against the petitioner. It is so
ordered.
Narvasa, C.J., Gutierrez, Jr., Paras, Feliciano, Padilla, Bidin, Grio-Aquino,
Medialdea, Regalado, Davide, Jr., Romero, Nocon and Bellosillo, JJ., concur.
name.Thus, ASPAC Multi-Trade, Inc. became legally and publicly known as ASPACITEC (Philippines).
By virtue of said contracts, ASPAC sold electronic products, exported by ITEC,
to their sole customer, the Philippine Long Distance Telephone Company, (PLDT, for
brevity).
To facilitate their transactions, ASPAC, dealing under its new appellation, and
PLDT executed a document entitled PLDT-ASPAC/ITEC PROTOCOL[4] which defined
the project details for the supply of ITECs Interface Equipment in connection with the
Fifth Expansion Program of PLDT.
One year into the second term of the parties Representative Agreement, ITEC
decided to terminate the same, because petitioner ASPAC allegedly violated its
contractual commitment as stipulated in their agreements.[5]
Contested in this petition for review on Certiorari is the Decision of the Court of
Appeals on June 7, 1991, sustaining the RTC Order dated February 22, 1991,
denying the petitioners Motion to Dismiss, and directing the issuance of a writ of
preliminary injunction, and its companion Resolution of October 9, 1991, denying the
petitioners Motion for Reconsideration.
On January 31, 1991, the complaint[6] in Civil Case No. 91-294, was filed with
the Regional Trial Court of Makati, Branch 134 by ITEC, INC. Plaintiff sought to
enjoin, first, preliminarily and then, after trial, permanently; (1) defendants DIGITAL,
CMDI, and Francisco Aguirre and their agents and business associates, to cease and
desist from selling or attempting to sell to PLDT and to any other party, products
which have been copied or manufactured in like manner, similar or identical to the
products, wares and equipment of plaintiff, and (2) defendant ASPAC, to cease and
desist from using in its corporate name, letter heads, envelopes, sign boards and
business dealings, plaintiffs trademark, internationally known as ITEC; and the
recovery from defendants in solidum, damages of at least P500,000.00, attorneys
fees and litigation expenses.
On August 14, 1987, ITEC entered into a contract with petitioner ASPAC
referred to as Representative Agreement.[1] Pursuant to the contract, ITEC engaged
ASPAC as its exclusive representative in the Philippines for the sale of ITECs
products, in consideration of which, ASPAC was paid a stipulated commission. The
agreement was signed by G.A. Clark and Francisco S. Aguirre, presidents of ITEC
and ASPAC respectively, for and in behalf of their companies. [2] The said agreement
was initially for a term of twenty-four months. After the lapse of the agreed period, the
agreement was renewed for another twenty-four months.
Through a License Agreement[3] entered into by the same parties on November
10, 1988, ASPAC was able to incorporate and use the name ITEC in its own
In due time, defendants filed a motion to dismiss[7] the complaint on the following
grounds: (1) That plaintiff has no legal capacity to sue as it is a foreign corporation
doing business in the Philippines without the required BOI authority and SEC license,
and (2) that plaintiff is simply engaged in forum shopping which justifies the
application against it of the principle of forum non conveniens.
On February 8, 1991, the complaint was amended by virtue of which ITEC
INTERNATIONAL, INC. was substituted as plaintiff instead of ITEC, INC.[8]
from the Board of Investments and the Securities and Exchange Commission, and
thus, disqualified from instituting the present action in our courts. It is their contention
that the provisions of the Representative Agreement, petitioner ASPAC executed with
private respondent ITEC, are similarly highly restrictive in nature as those found in the
agreements which confronted the Court in the case of Top-Weld Manufacturing,
Inc. vs. ECED S.A. et al.,[16] as to reduce petitioner ASPAC to a mere conduit or
extension of private respondents in the Philippines.
In that case, we ruled that respondent foreign corporations are doing business in
the Philippines because when the respondents entered into the disputed contracts
with the petitioner, they were carrying out the purposes for which they were created,
i.e., to manufacture and market welding products and equipment. The terms and
conditions of the contracts as well as the respondents conduct indicate that they
established within our country a continuous business, and not merely one of a
temporary character. The respondents could be exempted from the requirements of
Republic Act 5455 if the petitioner is an independent entity which buys and distributes
products not only of the petitioner, but also of other manufacturers or transacts
business in its name and for its account and not in the name or for the account of the
foreign principal. A reading of the agreements between the petitioner and the
respondents shows that they are highly restrictive in nature, thus making the
petitioner a mere conduit or extension of the respondents.
It is alleged that certain provisions of the Representative Agreement executed
by the parties are similar to those found in the License Agreement of the parties in the
Top-Weld case which were considered as highly restrictive by this Court. The
provisions in point are:
2.0 Terms and Conditions of Sales.
2.1 Sale of ITEC products shall be at the purchase price set by ITEC from time to
time. Unless otherwise expressly agreed to in writing by ITEC the purchase price is
net to ITEC and does not include any transportation charges, import charges or taxes
into or within the Territory. All orders from customers are subject to formal acceptance
by ITEC at its Huntsville, Alabama U.S.A. facility.
xxx xxx xxx
SO ORDERED."[14]
Petitioners are now before us via Petition for Review on Certiorari[15] under Rule
45 of the Revised Rules of Court.
3.1.1. Not represent or offer for sale within the Territory any product which competes
with an existing ITEC product or any product which ITEC has under active
development.
3.1.2. Actively solicit all potential customers within the Territory in a systematic and
businesslike manner.
3.1.3. Inform ITEC of all request for proposals, requests for bids, invitations to bid and
the like within the Territory.
3.1.4. Attain the Annual Sales Goal for the Territory established by ITEC. The Sales
Goals for the first 24 months is set forth on Attachment two (2) hereto. The Sales
Goal for additional twelve month periods, if any, shall be sent to the Sales Agent by
ITEC at the beginning of each period. These Sales Goals shall be incorporated into
this Agreement and made a part hereof.
xxx xxx xxx
6.0. Representative as Independent Contractor
xxx xxx xxx
6.2. When acting under this Agreement REPRESENTATIVE is authorized to solicit
sales within the Territory on ITECs behalf but is authorized to bind ITEC only in its
capacity as Representative and no other, and then only to specific customers and on
terms and conditions expressly authorized by ITEC in writing.[17]
Aside from the abovestated provisions, petitioners point out the following
matters of record, which allegedly witness to the respondents' activities within the
Philippines in pursuit of their business dealings:
a. While petitioner ASPAC was the authorized exclusive representative for three (3)
years, it solicited from and closed several sales for and on behalf of private
respondents as to their products only and no other, to PLDT, worth no less than US
$15 Million (p. 20, tsn, Feb. 18, 1991);
b. Contract No. 1 (Exhibit for Petitioners) which covered these sales and identified by
private respondents sole witness, Mr. Clarence Long, is not in the name of petitioner
ASPAC as such representative, but in the name of private respondent ITEC, INC. (p.
20, tsn, Feb. 18, 1991);
c. The document denominated as PLDT-ASPAC/ITEC PROTOCOL (Annex C of the
original and amended complaints) which defined the responsibilities of the parties
thereto as to the supply, installation and maintenance of the ITEC equipment sold
under said Contract No. 1 is, as its very title indicates, in the names jointly of the
petitioner ASPAC and private respondents;
Generally, a foreign corporation has no legal existence within the state in which
it is foreign. This proceeds from the principle that juridical existence of a corporation is
confined within the territory of the state under whose laws it was incorporated and
organized, and it has no legal status beyond such territory. Such foreign corporation
may be excluded by any other state from doing business within its limits, or conditions
may be imposed on the exercise of such privileges. [25] Before a foreign corporation
can transact business in this country, it must first obtain a license to transact business
in the Philippines, and a certificate from the appropriate government agency. If it
transacts business in the Philippines without such a license, it shall not be permitted
to maintain or intervene in any action, suit, or proceeding in any court or
administrative agency of the Philippines, but it may be sued on any valid cause of
action recognized under Philippine laws.[26]
In a long line of decisions, this Court has not altogether prohibited a foreign
corporation not licensed to do business in the Philippines from suing or maintaining
an action in Philippine Courts. What it seeks to prevent is a foreign corporation doing
business in the Philippines without a license from gaining access to Philippine Courts.
[27]
The purpose of the law in requiring that foreign corporations doing business in
the Philippines be licensed to do so and that they appoint an agent for service of
process is to subject the foreign corporation doing business in the Philippines to the
jurisdiction of its courts. The object is not to prevent the foreign corporation from
performing single acts, but to prevent it from acquiring a domicile for the purpose of
business without taking steps necessary to render it amenable to suit in the local
courts.[28] The implication of the law is that it was never the purpose of the legislature
to exclude a foreign corporation which happens to obtain an isolated order for
business from the Philippines, and thus, in effect, to permit persons to avoid their
contracts made with such foreign corporations.[29]
There is no exact rule or governing principle as to what constitutes doing or
engaging or transacting business. Indeed, such case must be judged in the light of its
peculiar circumstances, upon its peculiar facts and upon the language of the statute
applicable. The true test, however, seems to be whether the foreign corporation is
continuing the body or substance of the business or enterprise for which it was
organized.[30]
Article 44 of the Omnibus Investments Code of 1987 defines the phrase to
include:
soliciting orders, purchases, service contracts, opening offices, whether called liaison
offices or branches; appointing representatives or distributors who are domiciled in
the Philippines or who in any calendar year stay in the Philippines for a period or
periods totaling one hundred eighty (180) days or more; participating in the
The same rule was observed relating to a foreign corporation with an exclusive
distributing agent in the Philippines, and which has been selling its products here
since 1929,[33] and a foreign corporation engaged in the business of manufacturing
and selling computers worldwide, and had installed at least 26 different products in
several corporations in the Philippines, and allowed its registered logo and trademark
to be used and made it known that there exists a designated distributor in the
Philippines.[34]
In its Master Service Agreement [39] with TESSI, private respondents required its
local technical representative to provide the employees of the technical and service
center with ITEC identification cards and business cards, and to correspond only on
ITEC, Inc., letterhead. TESSI personnel are instructed to answer the telephone with
ITEC Technical Assistance Center., such telephone being listed in the telephone book
under the heading of ITEC Technical Assistance Center, and all calls being recorded
and forwarded to ITEC on a weekly basis.
In Georg Grotjahn GMBH and Co. vs. Isnani,[35] it was held that the
uninterrupted performance by a foreign corporation of acts pursuant to its primary
purposes and functions as a regional area headquarters for its home office, qualifies
such corporation as one doing business in the country.
What is more, TESSI was obliged to provide ITEC with a monthly report
detailing the failure and repair of ITEC products, and to requisition monthly the
materials and components needed to replace stock consumed in the warranty repairs
of the prior month.
very purpose of the law was circumvented and evaded when the petitioner entered
into said agreements despite the prohibition of R.A. No. 5455. The parties in this case
being equally guilty of violating R.A. No. 5455, they are in pari delicto, in which case it
follows as a consequence that petitioner is not entitled to the relief prayed for in this
case.
The doctrine of lack of capacity to sue based on the failure to acquire a local
license is based on considerations of sound public policy. The license requirement
was imposed to subject the foreign corporation doing business in the Philippines to
the jurisdiction of its courts. It was never intended to favor domestic corporations who
enter into solitary transactions with unwary foreign firms and then repudiate their
obligations simply because the latter are not licensed to do business in this country.[45]
In Antam Consolidated Inc. vs. Court of Appeals, et al.[46] we expressed our
chagrin over this commonly used scheme of defaulting local companies which are
being sued by unlicensed foreign companies not engaged in business in the
Philippines to invoke the lack of capacity to sue of such foreign
companies. Obviously, the same ploy is resorted to by ASPAC to prevent the
injunctive action filed by ITEC to enjoin petitioner from using knowledge possibly
acquired in violation of fiduciary arrangements between the parties.
By entering into the Representative Agreement with ITEC, Petitioner is charged
with knowledge that ITEC was not licensed to engage in business activities in the
country, and is thus estopped from raising in defense such incapacity of ITEC, having
chosen to ignore or even presumptively take advantage of the same.
In Top-Weld, we ruled that a foreign corporation may be exempted from the
license requirement in order to institute an action in our courts if its representative in
the country maintained an independent status during the existence of the disputed
contract. Petitioner is deemed to have acceded to such independent character when
it entered into the Representative Agreement with ITEC, particularly, provision 6.2
(supra).
Petitioners insistence on the dismissal of this action due to the application, or
non application, of the private international law rule of forum non conveniens defies
well-settled rules of fair play. According to petitioner, the Philippine Court has no
venue to apply its discretion whether to give cognizance or not to the present action,
because it has not acquired jurisdiction over the person of the plaintiff in the case, the
latter allegedly having no personality to sue before Philippine Courts. This argument
is misplaced because the court has already acquired jurisdiction over the plaintiff in
the suit, by virtue of his filing the original complaint. And as we have already
observed, petitioner are not at liberty to question plaintiffs standing to sue, having
already acceded to the same by virtue of its entry into the Representative Agreement
referred to earlier.
Thus, having acquired jurisdiction, it is now for the Philippine Court, based on
the facts of the case, whether to give due course to the suit or dismiss it, on the
principle of forum non conveniens.[47] Hence, the Philippine Court may refuse to
assume jurisdiction in spite of its having acquired jurisdiction. Conversely, the court
may assume jurisdiction over the case if it chooses to do so; provided, that the
following requisites are met: 1) That the Philippine Court is one to which the parties
may conveniently resort to; 2) That the Philippine Court is in a position to make an
intelligent decision as to the law and the facts; and, 3) That the Philippine Court has
or is likely to have power to enforce its decision.[48]
The aforesaid requirements having been met, and in view of the courts
disposition to give due course to the questioned action, the matter of the present
forum not being the most convenient as a ground for the suits dismissal, deserves
scant consideration.
IN VIEW OF THE FOREGOING PREMISES, the instant Petition is hereby
DISMISSED. The decision of the Court of Appeals dated June 7, 1991, upholding the
RTC Order dated February 22, 1991, denying the petitioners Motion to Dismiss, and
ordering the issuance of the Writ of Preliminary Injunction is hereby affirmed in toto.
SO ORDERED.
1. Declaring the existence of a perfected contract to buy and sell over the six
(6) parcels of land situated at Don Jose, Sta. Rosa, Laguna with an area of
101 hectares, more or less, covered by and embraced in Transfer
Certificates of Title Nos. T-106932 to T-106937, inclusive, of the Land
Records of Laguna, between the plaintiffs as buyers and the defendant
Producers Bank for an agreed price of Five and One Half Million
(P5,500,000.00) Pesos;
2. Ordering defendant Producers Bank of the Philippines, upon finality of this
decision and receipt from the plaintiffs the amount of P5.5 Million, to execute
in favor of said plaintiffs a deed of absolute sale over the aforementioned six
(6) parcels of land, and to immediately deliver to the plaintiffs the owner's
copies of T.C.T. Nos. T-106932 to T- 106937, inclusive, for purposes of
registration of the same deed and transfer of the six (6) titles in the names of
the plaintiffs;
3. Ordering the defendants, jointly and severally, to pay plaintiffs Jose A.
Janolo and Demetrio Demetria the sums of P200,000.00 each in moral
damages;
4. Ordering the defendants, jointly and severally, to pay plaintiffs the sum of
P100,000.00 as exemplary damages ;
5. Ordering the defendants, jointly and severally, to pay the plaintiffs the
amount of P400,000.00 for and by way of attorney's fees;
6. Ordering the defendants to pay the plaintiffs, jointly and severally, actual
and moderate damages in the amount of P20,000.00;
With costs against the defendants.
After the parties filed their comment, reply, rejoinder, sur-rejoinder and reply to surrejoinder, the petition was given due course in a Resolution dated January 18, 1995.
Thence, the parties filed their respective memoranda and reply memoranda. The First
Division transferred this case to the Third Division per resolution dated October 23,
1995. After carefully deliberating on the aforesaid submissions, the Court assigned
the case to the undersigned ponentefor the writing of this Decision.
The Parties
Petitioner First Philippine International Bank (formerly Producers Bank of the
Philippines; petitioner Bank, for brevity) is a banking institution organized and existing
under the laws of the Republic of the Philippines. Petitioner Mercurio Rivera
(petitioner Rivera, for brevity) is of legal age and was, at all times material to this
case, Head-Manager of the Property Management Department of the petitioner Bank.
Respondent Carlos Ejercito (respondent Ejercito, for brevity) is of legal age and is the
assignee of original plaintiffs-appellees Demetrio Demetria and Jose Janolo.
T-106932
113,580 sq. m.
T-106933
70,899 sq. m.
T-106934
52,246 sq. m.
T-106935
96,768 sq. m.
T-106936
187,114 sq. m.
T-106937
481,481 sq. m.
Respondent Court of Appeals is the court which issued the Decision and Resolution
sought to be set aside through this petition.
The Facts
The facts of this case are summarized in the respondent Court's Decision3 as follows:
(1) In the course of its banking operations, the defendant Producer Bank of
the Philippines acquired six parcels of land with a total area of 101 hectares
located at Don Jose, Sta. Rose, Laguna, and covered by Transfer
Certificates of Title Nos. T-106932 to T-106937. The property used to be
owned by BYME Investment and Development Corporation which had them
mortgaged with the bank as collateral for a loan. The original plaintiffs,
Demetrio Demetria and Jose O. Janolo, wanted to purchase the property
and thus initiated negotiations for that purpose.
(2) In the early part of August 1987 said plaintiffs, upon the suggestion of
BYME investment's legal counsel, Jose Fajardo, met with defendant
Mercurio Rivera, Manager of the Property Management Department of the
defendant bank. The meeting was held pursuant to plaintiffs' plan to buy the
property (TSN of Jan. 16, 1990, pp. 7-10). After the meeting, plaintiff Janolo,
following the advice of defendant Rivera, made a formal purchase offer to
the bank through a letter dated August 30, 1987 (Exh. "B"), as follows:
September 1, 1987
TCT NO.
AREA
Thank you for your letter-offer to buy our six (6) parcels of acquired lots at
Sta. Rosa, Laguna (formerly owned by Byme Industrial Corp.). Please be
informed however that the bank's counter-offer is at P5.5 million for more
than 101 hectares on lot basis.
We shall be very glad to hear your position on the on the matter.
Best regards.
Thank you.
(6) On October 12, 1987, the conservator of the bank (which has been
placed under conservatorship by the Central Bank since 1984) was replaced
by an Acting Conservator in the person of defendant Leonida T.
Encarnacion. On November 4, 1987, defendant Rivera wrote plaintiff
Demetria the following letter (Exh. "F"):
Dear Sir:
Your proposal to buy the properties the bank foreclosed from Byme
investment Corp. located at Sta. Rosa, Laguna is under study yet as of this
time by the newly created committee for submission to the newly designated
Acting Conservator of the bank.
For your information.
(7) What thereafter transpired was a series of demands by the plaintiffs for
compliance by the bank with what plaintiff considered as a perfected
contract of sale, which demands were in one form or another refused by the
bank. As detailed by the trial court in its decision, on November 17, 1987,
plaintiffs through a letter to defendant Rivera (Exhibit "G") tendered payment
of the amount of P5.5 million "pursuant to (our) perfected sale agreement."
Defendants refused to receive both the payment and the letter. Instead, the
parcels of land involved in the transaction were advertised by the bank for
sale to any interested buyer (Exh, "H" and "H-1"). Plaintiffs demanded the
execution by the bank of the documents on what was considered as a
"perfected agreement." Thus:
This is in connection with the offer of our client, Mr. Jose O. Janolo, to
purchase your 101-hectare lot located in Sta. Rosa, Laguna, and which are
covered by TCT No. T-106932 to 106937.
(9) The foregoing letter drew no response for more than four months. Then,
on May 3, 1988, plaintiff, through counsel, made a final demand for
compliance by the bank with its obligations under the considered perfected
contract of sale (Exhibit "N"). As recounted by the trial court (Original
Record, p. 656), in a reply letter dated May 12, 1988 (Annex "4" of
defendant's answer to amended complaint), the defendants through Acting
Conservator Encarnacion repudiated the authority of defendant Rivera and
claimed that his dealings with the plaintiffs, particularly his counter-offer of
P5.5 Million are unauthorized or illegal. On that basis, the defendants
justified the refusal of the tenders of payment and the non-compliance with
the obligations under what the plaintiffs considered to be a perfected
contract of sale.
(10) On May 16, 1988, plaintiffs filed a suit for specific performance with
damages against the bank, its Manager Rivers and Acting Conservator
Encarnacion. The basis of the suit was that the transaction had with the
bank resulted in a perfected contract of sale, The defendants took the
position that there was no such perfected sale because the defendant Rivera
is not authorized to sell the property, and that there was no meeting of the
minds as to the price.
On March 14, 1991, Henry L. Co (the brother of Luis Co), through counsel
Sycip Salazar Hernandez and Gatmaitan, filed a motion to intervene in the
trial court, alleging that as owner of 80% of the Bank's outstanding shares of
stock, he had a substantial interest in resisting the complaint. On July 8,
1991, the trial court issued an order denying the motion to intervene on the
ground that it was filed after trial had already been concluded. It also denied
a motion for reconsideration filed thereafter. From the trial court's decision,
the Bank, petitioner Rivera and conservator Encarnacion appealed to the
Court of Appeals which subsequently affirmed with modification the said
judgment. Henry Co did not appeal the denial of his motion for intervention.
In the course of the proceedings in the respondent Court, Carlos Ejercito was
substituted in place of Demetria and Janolo, in view of the assignment of the latters'
rights in the matter in litigation to said private respondent.
On July 11, 1992, during the pendency of the proceedings in the Court of Appeals,
Henry Co and several other stockholders of the Bank, through counsel Angara Abello
Concepcion Regala and Cruz, filed an action (hereafter, the "Second Case")
purportedly a "derivative suit" with the Regional Trial Court of Makati, Branch 134,
docketed as Civil Case No. 92-1606, against Encarnacion, Demetria and Janolo "to
declare any perfected sale of the property as unenforceable and to stop Ejercito from
enforcing or implementing the sale"4 In his answer, Janolo argued that the Second
Case was barred by litis pendentia by virtue of the case then pending in the Court of
Appeals. During the pre-trial conference in the Second Case, plaintiffs filed a Motion
for Leave of Court to Dismiss the Case Without Prejudice. "Private respondent
opposed this motion on the ground, among others, that plaintiff's act of forum
shopping justifies the dismissal of both cases, with prejudice."5 Private respondent, in
his memorandum, averred that this motion is still pending in the Makati RTC.
The Issues
From the foregoing positions of the parties, the issues in this case may be summed
up as follows:
1) Was there forum-shopping on the part of petitioner Bank?
2) Was there a perfected contract of sale between the parties?
3) Assuming there was, was the said contract enforceable under the statute
of frauds?
4) Did the bank conservator have the unilateral power to repudiate the
authority of the bank officers and/or to revoke the said contract?
5) Did the respondent Court commit any reversible error in its findings of
facts?
IV.
The First Issue: Was There Forum-Shopping?
The findings and conclusions of the Court of Appeals do not conform to the
evidence on record.
On the other hand, petitioners prayed for dismissal of the instant suit on the
ground8 that:
I.
Petitioners have engaged in forum shopping.
II.
The factual findings and conclusions of the Court of Appeals are supported
by the evidence on record and may no longer be questioned in this case.
III.
The Court of Appeals correctly held that there was a perfected contract
between Demetria and Janolo (substituted by; respondent Ejercito) and the
bank.
IV.
The Court of Appeals has correctly held that the conservator, apart from
being estopped from repudiating the agency and the contract, has no
authority to revoke the contract of sale.
In order to prevent the vexations of multiple petitions and actions, the Supreme Court
promulgated Revised Circular No. 28-91 requiring that a party "must certify under
oath . . . [that] (a) he has not (t)heretofore commenced any other action or proceeding
involving the same issues in the Supreme Court, the Court of Appeals, or any other
tribunal or agency; (b) to the best of his knowledge, no such action or proceeding is
pending" in said courts or agencies. A violation of the said circular entails sanctions
that include the summary dismissal of the multiple petitions or complaints. To be sure,
petitioners have included a VERIFICATION/CERTIFICATION in their Petition stating
"for the record(,) the pendency of Civil Case No. 92-1606 before the Regional Trial
Court of Makati, Branch 134, involving aderivative suit filed by stockholders of
petitioner Bank against the conservator and other defendants but which is the subject
of a pending Motion to Dismiss Without Prejudice.9
Private respondent Ejercito vigorously argues that in spite of this verification,
petitioners are guilty of actual forum shopping because the instant petition pending
before this Court involves "identical parties or interests represented, rights asserted
and reliefs sought (as that) currently pending before the Regional Trial Court, Makati
Branch 134 in the Second Case. In fact, the issues in the two cases are so interwined
that a judgement or resolution in either case will constitute res judicata in the other." 10
On the other hand, petitioners explain 11 that there is no forum-shopping because:
1) In the earlier or "First Case" from which this proceeding arose, the Bank
was impleaded as a defendant, whereas in the "Second Case" (assuming
the Bank is the real party in interest in a derivative suit), it wasplaintiff;
2) "The derivative suit is not properly a suit for and in behalf of the
corporation under the circumstances";
3) Although the CERTIFICATION/VERIFICATION (supra) signed by the
Bank president and attached to the Petition identifies the action as a
"derivative suit," it "does not mean that it is one" and "(t)hat is a legal
question for the courts to decide";
4) Petitioners did not hide the Second Case at they mentioned it in the said
VERIFICATION/CERTIFICATION.
We rule for private respondent.
To begin with, forum-shopping originated as a concept in private international law.12,
where non-resident litigants are given the option to choose the forum or place
wherein to bring their suit for various reasons or excuses, including to secure
procedural advantages, to annoy and harass the defendant, to avoid overcrowded
dockets, or to select a more friendly venue. To combat these less than honorable
excuses, the principle of forum non convenienswas developed whereby a court, in
conflicts of law cases, may refuse impositions on its jurisdiction where it is not the
most "convenient" or available forum and the parties are not precluded from seeking
remedies elsewhere.
In this light, Black's Law Dictionary 13 says that forum shopping "occurs when a party
attempts to have his action tried in a particular court or jurisdiction where he feels he
will receive the most favorable judgment or verdict." Hence, according to Words and
Phrases14, "a litigant is open to the charge of "forum shopping" whenever he chooses
a forum with slight connection to factual circumstances surrounding his suit, and
litigants should be encouraged to attempt to settle their differences without imposing
undue expenses and vexatious situations on the courts".
In the Philippines, forum shopping has acquired a connotation encompassing not only
a choice of venues, as it was originally understood in conflicts of laws, but also to a
choice of remedies. As to the first (choice of venues), the Rules of Court, for example,
allow a plaintiff to commence personal actions "where the defendant or any of the
defendants resides or may be found, or where the plaintiff or any of the plaintiffs
resides, at the election of the plaintiff" (Rule 4, Sec, 2 [b]). As to remedies, aggrieved
parties, for example, are given a choice of pursuing civil liabilities independently of the
criminal, arising from the same set of facts. A passenger of a public utility vehicle
involved in a vehicular accident may sue on culpa contractual, culpa aquiliana or
culpa criminal each remedy being available independently of the others
although he cannot recover more than once.
In either of these situations (choice of venue or choice of remedy), the
litigant actually shops for a forum of his action, This was the original concept
of the term forum shopping.
Eventually, however, instead of actually making a choice of the forum of their
actions, litigants, through the encouragement of their lawyers, file their
xxx
xxx
As already observed, there is between the action at bar and RTC Case No.
86-36563, an identity as regards parties, or interests represented, rights
asserted and relief sought, as well as basis thereof, to a degree sufficient to
give rise to the ground for dismissal known as auter action pendant or lis
pendens. That same identity puts into operation the sanction of twin
dismissals just mentioned. The application of this sanction will prevent any
further delay in the settlement of the controversy which might ensue from
attempts to seek reconsideration of or to appeal from the Order of the
Regional Trial Court in Civil Case No. 86-36563 promulgated on July 15,
1986, which dismissed the petition upon grounds which appear persuasive.
Consequently, where a litigant (or one representing the same interest or person) sues
the same party against whom another action or actions for the alleged violation of the
same right and the enforcement of the same relief is/are still pending, the defense
of litis pendencia in one case is bar to the others; and, a final judgment in one would
constituteres judicata and thus would cause the dismissal of the rest. In either case,
forum shopping could be cited by the other party as a ground to ask for summary
dismissal of the two 20 (or more) complaints or petitions, and for imposition of the
other sanctions, which are direct contempt of court, criminal prosecution, and
disciplinary action against the erring lawyer.
Applying the foregoing principles in the case before us and comparing it with the
Second Case, it is obvious that there exist identity of parties or interests represented,
identity of rights or causes and identity of reliefs sought.
Very simply stated, the original complaint in the court a quo which gave rise to the
instant petition was filed by the buyer (herein private respondent and his
predecessors-in-interest) against the seller (herein petitioners) to enforce the alleged
perfected sale of real estate. On the other hand, the complaint 21 in the Second Case
seeks to declare such purported sale involving the same real property "as
unenforceable as against the Bank", which is the petitioner herein. In other words, in
the Second Case, the majority stockholders, in representation of the Bank, are
seeking to accomplish what the Bank itself failed to do in the original case in the trial
court. In brief, the objective or the relief being sought, though worded differently, is the
same, namely, to enable the petitioner Bank to escape from the obligation to sell the
property to respondent. In Danville Maritime, Inc. vs. Commission on Audit. 22, this
Court ruled that the filing by a party of two apparently different actions, but with
the same objective, constituted forum shopping:
In the attempt to make the two actions appear to be different, petitioner
impleaded different respondents therein PNOC in the case before the
lower court and the COA in the case before this Court and sought what
seems to be different reliefs. Petitioner asks this Court to set aside the
questioned letter-directive of the COA dated October 10, 1988 and to direct
said body to approve the Memorandum of Agreement entered into by and
between the PNOC and petitioner, while in the complaint before the lower
court petitioner seeks to enjoin the PNOC from conducting a rebidding and
from selling to other parties the vessel "T/T Andres Bonifacio", and for an
extension of time for it to comply with the paragraph 1 of the memorandum
of agreement and damages. One can see that although the relief prayed for
in the two (2) actions are ostensibly different, the ultimate objective in both
actions is the same, that is, approval of the sale of vessel in favor of
petitioner and to overturn the letter-directive of the COA of October 10, 1988
disapproving the sale. (emphasis supplied).
In an earlier case 23 but with the same logic and vigor, we held:
In other words, the filing by the petitioners of the instant special civil action
for certiorari and prohibition in this Court despite the pendency of their action
in the Makati Regional Trial Court, is a species of forum-shopping. Both
actions unquestionably involve the same transactions, the same essential
facts and circumstances. The petitioners' claim of absence of identity simply
because the PCGG had not been impleaded in the RTC suit, and the suit did
not involve certain acts which transpired after its commencement, is
specious. In the RTC action, as in the action before this Court, the validity of
the contract to purchase and sell of September 1, 1986, i.e., whether or not it
had been efficaciously rescinded, and the propriety of implementing the
same (by paying the pledgee banks the amount of their loans, obtaining the
release of the pledged shares, etc.) were the basic issues. So, too, the relief
was the same: the prevention of such implementation and/or the restoration
of the status quo ante. When the acts sought to be restrained took place
anyway despite the issuance by the Trial Court of a temporary restraining
order, the RTC suit did not become functus oficio. It remained an effective
vehicle for obtention of relief; and petitioners' remedy in the premises was
plain and patent: the filing of an amended and supplemental pleading in the
RTC suit, so as to include the PCGG as defendant and seek nullification of
the acts sought to be enjoined but nonetheless done. The remedy was
certainly not the institution of another action in another forum based on
essentially the same facts, The adoption of this latter recourse renders the
petitioners amenable to disciplinary action and both their actions, in this
Court as well as in the Court a quo, dismissible.
In the instant case before us, there is also identity of parties, or at least, of interests
represented. Although the plaintiffs in the Second Case (Henry L. Co. et al.) are not
name parties in the First Case, they represent the same interest and entity, namely,
petitioner Bank, because:
Firstly, they are not suing in their personal capacities, for they have no direct personal
interest in the matter in controversy. They are not principally or even subsidiarily
liable; much less are they direct parties in the assailed contract of sale; and
Secondly, the allegations of the complaint in the Second Case show that the
stockholders are bringing a "derivative suit". In the caption itself, petitioners claim to
have brought suit "for and in behalf of the Producers Bank of the Philippines" 24.
Indeed, this is the very essence of a derivative suit:
An individual stockholder is permitted to institute a derivative suit on behalf
of the corporation wherein he holdsstock in order to protect or vindicate
corporate rights, whenever the officials of the corporation refuse to sue, or
are the ones to be sued or hold the control of the corporation. In such
Respondent, on the other hand, replied that there is a difference in factual setting
between Victronics and the present suit. In the former, as underscored in the abovequoted Court ruling, the defendants did not file anyresponsive pleading in the first
case. In other words, they did not make any denial or raise any defense or counterclaim therein In the case before us however, petitioners filed a responsive pleading to
the complaint as a result of which, the issues were joined.
Indeed, by praying for affirmative reliefs and interposing counterclaims in their
responsive pleadings, the petitioners became plaintiffs themselves in the original
case, giving unto themselves the very remedies they repeated in the Second Case.
Ultimately, what is truly important to consider in determining whether forum-shopping
exists or not is the vexation caused the courts and parties-litigant by a party who asks
different courts and/or administrative agencies to rule on the same or related causes
and/or to grant the same or substantially the same reliefs, in the process creating the
possibility of conflicting decisions being rendered by the different fora upon the same
issue. In this case, this is exactly the problem: a decision recognizing the perfection
and directing the enforcement of the contract of sale will directly conflict with a
possible decision in the Second Case barring the parties front enforcing or
implementing the said sale. Indeed, a final decision in one would constitute res
judicata in the other 28.
The foregoing conclusion finding the existence of forum-shopping notwithstanding,
the only sanction possible now is the dismissal of both cases with prejudice, as the
other sanctions cannot be imposed because petitioners' present counsel entered their
appearance only during the proceedings in this Court, and the Petition's
VERIFICATION/CERTIFICATION contained sufficient allegations as to the pendency
of the Second Case to show good faith in observing Circular 28-91. The Lawyers who
filed the Second Case are not before us; thus the rudiments of due process prevent
us from motu propio imposing disciplinary measures against them in this Decision.
However, petitioners themselves (and particularly Henry Co, et al.) as litigants are
admonished to strictly follow the rules against forum-shopping and not to trifle with
court proceedings and processes They are warned that a repetition of the same will
be dealt with more severely.
Having said that, let it be emphasized that this petition should be dismissed not
merely because of forum-shopping but also because of the substantive issues raised,
as will be discussed shortly.
The Second Issue: Was The Contract Perfected?
The respondent Court correctly treated the question of whether or not there was, on
the basis of the facts established, a perfected contract of sale as the ultimate issue.
Holding that a valid contract has been established, respondent Court stated:
There is no dispute that the object of the transaction is that property owned
by the defendant bank as acquired assets consisting of six (6) parcels of
land specifically identified under Transfer Certificates of Title Nos. T-106932
to T-106937. It is likewise beyond cavil that the bank intended to sell the
sale by having the offer officially acted upon by the bank. The bank cannot
turn around and later say, as it now does, that what Rivera states as the
bank's action on the matter is not in fact so. It is a familiar doctrine, the
doctrine of ostensible authority, that if a corporation knowingly permits one of
its officers, or any other agent, to do acts within the scope of an apparent
authority, and thus holds him out to the public as possessing power to do
those acts, the corporation will, as against any one who has in good faith
dealt with the corporation through such agent, he estopped from denying his
authority (Francisco v. GSIS, 7 SCRA 577, 583-584; PNB v. Court of
Appeals, 94 SCRA 357, 369-370; Prudential Bank v. Court of Appeals, G.R.
No. 103957, June 14, 1993). 29
Article 1318 of the Civil Code enumerates the requisites of a valid and perfected
contract as follows: "(1) Consent of the contracting parties; (2) Object certain which is
the subject matter of the contract; (3) Cause of the obligation which is established."
There is no dispute on requisite no. 2. The object of the questioned contract consists
of the six (6) parcels of land in Sta. Rosa, Laguna with an aggregate area of about
101 hectares, more or less, and covered by Transfer Certificates of Title Nos. T106932 to T-106937. There is, however, a dispute on the first and third requisites.
Petitioners allege that "there is no counter-offer made by the Bank, and any supposed
counter-offer which Rivera (or Co) may have made is unauthorized. Since there was
no counter-offer by the Bank, there was nothing for Ejercito (in substitution of
Demetria and Janolo) to accept." 30 They disputed the factual basis of the respondent
Court's findings that there was an offer made by Janolo for P3.5 million, to which the
Bank counter-offered P5.5 million. We have perused the evidence but cannot find
fault with the said Court's findings of fact. Verily, in a petition under Rule 45 such as
this, errors of fact if there be any - are, as a rule, not reviewable. The mere fact
that respondent Court (and the trial court as well) chose to believe the evidence
presented by respondent more than that presented by petitioners is not by itself a
reversible error. In fact, such findings merit serious consideration by this Court,
particularly where, as in this case, said courts carefully and meticulously discussed
their findings. This is basic.
Be that as it may, and in addition to the foregoing disquisitions by the Court of
Appeals, let us review the question of Rivera's authority to act and petitioner's
allegations that the P5.5 million counter-offer was extinguished by the P4.25 million
revised offer of Janolo. Here, there are questions of law which could be drawn from
the factual findings of the respondent Court. They also delve into the contractual
elements of consent and cause.
The authority of a corporate officer in dealing with third persons may be actual or
apparent. The doctrine of "apparent authority", with special reference to banks, was
laid out in Prudential Bank vs. Court of Appeals31, where it was held that:
Conformably, we have declared in countless decisions that the principal is
liable for obligations contracted by the agent. The agent's apparent
representation yields to the principal's true representation and the contract is
considered as entered into between the principal and the third person
(citing National Food Authority vs. Intermediate Appellate Court, 184 SCRA
166).
A bank is liable for wrongful acts of its officers done in the interests
of the bank or in the course of dealings of the officers in their
representative capacity but not for acts outside the scape of their
authority (9 C.J.S., p. 417). A bank holding out its officers and
agents as worthy of confidence will not be permitted to profit by the
frauds they may thus be enabled to perpetrate in the apparent
scope of their employment; nor will it be permitted to shirk its
responsibility for such frauds even though no benefit may accrue to
the bank therefrom (10 Am Jur 2d, p. 114). Accordingly, a banking
corporation is liable to innocent third persons where the
representation is made in the course of its business by an agent
acting within the general scope of his authority even though, in the
particular case, the agent is secretly abusing his authority and
attempting to perpetrate a fraud upon his principal or some other
person, for his own ultimate benefit (McIntosh v. Dakota Trust Co.,
52 ND 752, 204 NW 818, 40 ALR 1021).
Application of these principles is especially necessary because banks have
a fiduciary relationship with the public and their stability depends on the
confidence of the people in their honesty and efficiency. Such faith will be
eroded where banks do not exercise strict care in the selection and
supervision of its employees, resulting in prejudice to their depositors.
From the evidence found by respondent Court, it is obvious that petitioner Rivera has
apparent or implied authority to act for the Bank in the matter of selling its acquired
assets. This evidence includes the following:
(a) The petition itself in par. II-i (p. 3) states that Rivera was "at all times
material to this case, Manager of the Property Management Department of
the Bank". By his own admission, Rivera was already the person in charge
of the Bank's acquired assets (TSN, August 6, 1990, pp. 8-9);
(b) As observed by respondent Court, the land was definitely being sold by
the Bank. And during the initial meeting between the buyers and Rivera, the
latter suggested that the buyers' offer should be no less than P3.3 million
(TSN, April 26, 1990, pp. 16-17);
(c) Rivera received the buyers' letter dated August 30, 1987 offering P3.5
million (TSN, 30 July 1990, p.11);
(d) Rivera signed the letter dated September 1, 1987 offering to sell the
property for P5.5 million (TSN, July 30, p. 11);
(e) Rivera received the letter dated September 17, 1987 containing the
buyers' proposal to buy the property for P4.25 million (TSN, July 30, 1990, p.
12);
(f) Rivera, in a telephone conversation, confirmed that the P5.5 million was
the final price of the Bank (TSN, January 16, 1990, p. 18);
(g) Rivera arranged the meeting between the buyers and Luis Co on
September 28, 1994, during which the Bank's offer of P5.5 million was
confirmed by Rivera (TSN, April 26, 1990, pp. 34-35). At said meeting, Co, a
major shareholder and officer of the Bank, confirmed Rivera's statement as
to the finality of the Bank's counter-offer of P5.5 million (TSN, January 16,
1990, p. 21; TSN, April 26, 1990, p. 35);
(h) In its newspaper advertisements and announcements, the Bank referred
to Rivera as the officer acting for the Bank in relation to parties interested in
buying assets owned/acquired by the Bank. In fact, Rivera was the officer
mentioned in the Bank's advertisements offering for sale the property in
question (cf. Exhs. "S" and "S-1").
In the very recent case of Limketkai Sons Milling, Inc. vs. Court of Appeals, et. al.32,
the Court, through Justice Jose A. R. Melo, affirmed the doctrine of apparent authority
as it held that the apparent authority of the officer of the Bank of P.I. in charge of
acquired assets is borne out by similar circumstances surrounding his dealings with
buyers.
To be sure, petitioners attempted to repudiate Rivera's apparent authority through
documents and testimony which seek to establish Rivera's actual authority. These
pieces of evidence, however, are inherently weak as they consist of Rivera's selfserving testimony and various inter-office memoranda that purport to show his limited
actual authority, of which private respondent cannot be charged with knowledge. In
any event, since the issue is apparent authority, the existence of which is borne out
by the respondent Court's findings, the evidence of actual authority is immaterial
insofar as the liability of a corporation is concerned 33.
Petitioners also argued that since Demetria and Janolo were experienced lawyers
and their "law firm" had once acted for the Bank in three criminal cases, they should
be charged with actual knowledge of Rivera's limited authority. But the Court of
Appeals in its Decision (p. 12) had already made a factual finding that the buyers had
no notice of Rivera's actual authority prior to the sale. In fact, the Bank has not shown
that they acted as its counsel in respect to any acquired assets; on the other hand,
respondent has proven that Demetria and Janolo merely associated with a loose
aggrupation of lawyers (not a professional partnership), one of whose members (Atty.
Susana Parker) acted in said criminal cases.
Petitioners also alleged that Demetria's and Janolo's P4.25 million counter-offer in the
letter dated September 17, 1987 extinguished the Bank's offer of P5.5 million 34 .They
disputed the respondent Court's finding that "there was a meeting of minds when on
30 September 1987 Demetria and Janolo through Annex "L" (letter dated September
30, 1987) "accepted" Rivera's counter offer of P5.5 million under Annex "J" (letter
dated September 17, 1987)", citingthe late Justice Paras35, Art. 1319 of the Civil
Code 36 and related Supreme Court rulings starting with Beaumont vs. Prieto 37.
However, the above-cited authorities and precedents cannot apply in the instant case
because, as found by the respondent Court which reviewed the testimonies on this
point, what was "accepted" by Janolo in his letter dated September 30, 1987 was the
Bank's offer of P5.5 million as confirmed and reiterated to Demetria and Atty. Jose
Fajardo by Rivera and Co during their meeting on September 28, 1987. Note that the
said letter of September 30, 1987 begins with"(p)ursuant to our discussion last 28
September 1987 . . .
Petitioners insist that the respondent Court should have believed the testimonies of
Rivera and Co that the September 28, 1987 meeting "was meant to have the offerors
improve on their position of P5.5. million."38 However, both the trial court and the
Court of Appeals found petitioners' testimonial evidence "not credible", and we find no
basis for changing this finding of fact.
Indeed, we see no reason to disturb the lower courts' (both the RTC and the CA)
common finding that private respondents' evidence is more in keeping with truth and
logic that during the meeting on September 28, 1987, Luis Co and Rivera
"confirmed that the P5.5 million price has been passed upon by the Committee and
could no longer be lowered (TSN of April 27, 1990, pp. 34-35)"39. Hence,
assuming arguendo that the counter-offer of P4.25 million extinguished the offer of
P5.5 million, Luis Co's reiteration of the said P5.5 million price during the September
28, 1987 meeting revived the said offer. And by virtue of the September 30, 1987
letter accepting this revived offer, there was a meeting of the minds, as the
acceptance in said letter was absolute and unqualified.
We note that the Bank's repudiation, through Conservator Encarnacion, of Rivera's
authority and action, particularly the latter's counter-offer of P5.5 million, as being
"unauthorized and illegal" came only on May 12, 1988 or more than seven (7) months
after Janolo' acceptance. Such delay, and the absence of any circumstance which
might have justifiably prevented the Bank from acting earlier, clearly characterizes the
repudiation as nothing more than a last-minute attempt on the Bank's part to get out
of a binding contractual obligation.
Taken together, the factual findings of the respondent Court point to an implied
admission on the part of the petitioners that the written offer made on September 1,
1987 was carried through during the meeting of September 28, 1987. This is the
conclusion consistent with human experience, truth and good faith.
It also bears noting that this issue of extinguishment of the Bank's offer of P5.5 million
was raised for the first time on appeal and should thus be disregarded.
This Court in several decisions has repeatedly adhered to the principle that
points of law, theories, issues of fact and arguments not adequately brought
to the attention of the trial court need not be, and ordinarily will not be,
considered by a reviewing court, as they cannot be raised for the first time
on appeal (Santos vs. IAC, No. 74243, November 14, 1986, 145 SCRA
592).40
waived any defects of the contract under the statute of frauds, pursuant to Article
1405 of the Civil Code:
Art. 1405. Contracts infringing the Statute of Frauds, referred to in No. 2 of
article 1403, are ratified by the failure to object to the presentation of oral
evidence to prove the same, or by the acceptance of benefits under them.
As private respondent pointed out in his Memorandum, oral testimony on the
reaffirmation of the counter-offer of P5.5 million is a plenty and the silence of
petitioners all throughout the presentation makes the evidence binding on them thus;
A Yes, sir, I think it was September 28, 1987 and I was again present
because Atty. Demetria told me to accompany him we were able to meet
Luis Co at the Bank.
xxx
xxx
xxx
Q Now, what transpired during this meeting with Luis Co of the Producers
Bank?
A Atty. Demetria asked Mr. Luis Co whether the price could be reduced, sir.
Q What price?
A The 5.5 million pesos and Mr. Luis Co said that the amount cited by Mr.
Mercurio Rivera is the final price and that is the price they intends (sic) to
have, sir.
Q What do you mean?.
A That is the amount they want, sir.
Q What is the reaction of the plaintiff Demetria to Luis Co's statement (sic)
that the defendant Rivera's counter-offer of 5.5 million was the defendant's
bank (sic) final offer?
A He said in a day or two, he will make final acceptance, sir.
Q What is the response of Mr. Luis Co?.
A He said he will wait for the position of Atty. Demetria, sir.
[Direct testimony of Atty. Jose Fajardo, TSN, January 16, 1990, at pp. 18-21.]
Q What transpired during that meeting between you and Mr. Luis Co of the
defendant Bank?
A We went straight to the point because he being a busy person, I told him if
the amount of P5.5 million could still be reduced and he said that was
already passed upon by the committee. What the bank expects which was
contrary to what Mr. Rivera stated. And he told me that is the final offer of the
bank P5.5 million and we should indicate our position as soon as possible.
Q What was your response to the answer of Mr. Luis Co?
A I said that we are going to give him our answer in a few days and he said
that was it. Atty. Fajardo and I and Mr. Mercurio [Rivera] was with us at the
time at his office.
Q For the record, your Honor please, will you tell this Court who was with Mr.
Co in his Office in Producers Bank Building during this meeting?
A Mr. Co himself, Mr. Rivera, Atty. Fajardo and I.
Q By Mr. Co you are referring to?
A Mr. Luis Co.
Q After this meeting with Mr. Luis Co, did you and your partner accede on
(sic) the counter offer by the bank?
A Yes, sir, we did.? Two days thereafter we sent our acceptance to the bank
which offer we accepted, the offer of the bank which is P5.5 million.
[Direct testimony of Atty. Demetria, TSN, 26 April 1990, at pp. 34-36.]
Q According to Atty. Demetrio Demetria, the amount of P5.5 million was
reached by the Committee and it is not within his power to reduce this
amount. What can you say to that statement that the amount of P5.5 million
was reached by the Committee?
board of directors of a bank, under Section 28-A of Republic Act No. 265 (otherwise
known as the Central Bank Act) as follows:
Whenever, on the basis of a report submitted by the appropriate supervising
or examining department, the Monetary Board finds that a bank or a nonbank financial intermediary performing quasi-banking functions is in a state
of continuing inability or unwillingness to maintain a state of liquidity deemed
adequate to protect the interest of depositors and creditors, the Monetary
Board may appoint a conservator to take charge of the assets, liabilities, and
the management of that institution, collect all monies and debts due said
institution and exercise all powers necessary to preserve the assets of the
institution, reorganize the management thereof, and restore its viability. He
shall have the power to overrule or revoke the actions of the previous
management and board of directors of the bank or non-bank financial
intermediary performing quasi-banking functions, any provision of law to the
contrary notwithstanding, and such other powers as the Monetary Board
shall deem necessary.
In the first place, this issue of the Conservator's alleged authority to revoke or
repudiate the perfected contract of sale was raised for the first time in this Petition
as this was not litigated in the trial court or Court of Appeals. As already stated earlier,
issues not raised and/or ventilated in the trial court, let alone in the Court of Appeals,
"cannot be raised for the first time on appeal as it would be offensive to the basic
rules of fair play, justice and due process."43
In the second place, there is absolutely no evidence that the Conservator, at the time
the contract was perfected, actually repudiated or overruled said contract of sale. The
Bank's acting conservator at the time, Rodolfo Romey, never objected to the sale of
the property to Demetria and Janolo. What petitioners are really referring to is the
letter of Conservator Encarnacion, who took over from Romey after the sale was
perfected on September 30, 1987 (Annex V, petition) which unilaterally repudiated
not the contract but the authority of Rivera to make a binding offer and which
unarguably came months after the perfection of the contract. Said letter dated May
12, 1988 is reproduced hereunder:
A It was not discussed by the Committee but it was discussed initially by Luis
Co and the group of Atty. Demetrio Demetria and Atty. Pajardo (sic) in that
September 28, 1987 meeting, sir.
[Direct testimony of Mercurio Rivera, TSN, 30 July 1990, pp. 14-15.]
The Fourth Issue: May the Conservator Revoke
the Perfected and Enforceable Contract.
It is not disputed that the petitioner Bank was under a conservator placed by the
Central Bank of the Philippines during the time that the negotiation and perfection of
the contract of sale took place. Petitioners energetically contended that the
conservator has the power to revoke or overrule actions of the management or the
We deny that Producers Bank has ever made a legal counter-offer to any of
your clients nor perfected a "contract to sell and buy" with any of them for
the following reasons.
In the "Inter-Office Memorandum" dated April 25, 1986 addressed to and
approved by former Acting Conservator Mr. Andres I. Rustia, Producers
Bank Senior Manager Perfecto M. Pascua detailed the functions of Property
Management Department (PMD) staff and officers (Annex A.), you will
immediately read that Manager Mr. Mercurio Rivera or any of his
subordinates has no authority, power or right to make any alleged counteroffer. In short, your lawyer-clients did not deal with the authorized officers of
the bank.
Moreover, under Sec. 23 and 36 of the Corporation Code of the Philippines
(Bates Pambansa Blg. 68.) and Sec. 28-A of the Central Bank Act (Rep. Act
No. 265, as amended), only the Board of Directors/Conservator may
authorize the sale of any property of the corportion/bank..
Our records do not show that Mr. Rivera was authorized by the old board or
by any of the bank conservators (starting January, 1984) to sell the aforesaid
property to any of your clients. Apparently, what took place were just
preliminary discussions/consultations between him and your clients, which
everyone knows cannot bind the Bank's Board or Conservator.
can it delegate such non-existent powers to the conservator under Section 28-A of
said law?
Obviously, therefore, Section 28-A merely gives the conservator power to revoke
contracts that are, under existing law, deemed to be defective i.e., void, voidable,
unenforceable or rescissible. Hence, the conservator merely takes the place of a
bank's board of directors. What the said board cannot do such as repudiating a
contract validly entered into under the doctrine of implied authority the conservator
cannot do either. Ineluctably, his power is not unilateral and he cannot simply
repudiate valid obligations of the Bank. His authority would be only to bring court
actions to assail such contracts as he has already done so in the instant case. A
contrary understanding of the law would simply not be permitted by the Constitution.
Neither by common sense. To rule otherwise would be to enable a failing bank to
become solvent, at the expense of third parties, by simply getting the conservator to
unilaterally revoke all previous dealings which had one way or another or come to be
considered unfavorable to the Bank, yielding nothing to perfected contractual rights
nor vested interests of the third parties who had dealt with the Bank.
The Fifth Issue: Were There Reversible Errors of Facts?
Basic is the doctrine that in petitions for review under Rule 45 of the Rules of Court,
findings of fact by the Court of Appeals are not reviewable by the Supreme Court.
In Andres vs. Manufacturers Hanover & Trust Corporation, 45, we held:
. . . The rule regarding questions of fact being raised with this Court in a
petition for certiorari under Rule 45 of the Revised Rules of Court has been
stated in Remalante vs. Tibe, G.R. No. 59514, February 25, 1988, 158
SCRA 138, thus:
Rest assured that we have nothing personal against your clients. All our acts
are official, legal and in accordance with law. We also have no personal
interest in any of the properties of the Bank.
The rule in this jurisdiction is that only questions of law may be raised in a
petition for certiorari under Rule 45 of the Revised Rules of Court. "The
jurisdiction of the Supreme Court in cases brought to it from the Court of
Appeals is limited to reviewing and revising the errors of law imputed to it, its
findings of the fact being conclusive " [Chan vs. Court of Appeals, G.R. No.
L-27488, June 30, 1970, 33 SCRA 737, reiterating a long line of decisions].
This Court has emphatically declared that "it is not the function of the
Supreme Court to analyze or weigh such evidence all over again, its
jurisdiction being limited to reviewing errors of law that might have been
committed by the lower court" (Tiongco v. De la Merced, G. R. No. L-24426,
July 25, 1974, 58 SCRA 89; Corona vs. Court of Appeals, G.R. No. L-62482,
April 28, 1983, 121 SCRA 865; Baniqued vs. Court of Appeals, G. R. No. L47531, February 20, 1984, 127 SCRA 596). "Barring, therefore, a showing
that the findings complained of are totally devoid of support in the record, or
that they are so glaringly erroneous as to constitute serious abuse of
discretion, such findings must stand, for this Court is not expected or
required to examine or contrast the oral and documentary evidence
submitted by the parties" [Santa Ana, Jr. vs. Hernandez, G. R. No. L-16394,
December 17, 1966, 18 SCRA 973] [at pp. 144-145.]
The resolution of this petition invites us to closely scrutinize the facts of the
case, relating to the sufficiency of evidence and the credibility of witnesses
presented. This Court so held that it is not the function of the Supreme Court
to analyze or weigh such evidence all over again. The Supreme Court's
jurisdiction is limited to reviewing errors of law that may have been
committed by the lower court. The Supreme Court is not a trier of facts. . . .
Conservator after Rivera had duly presented plaintiffs' offer for discussion by
the Committee . . . Tersely put, under the established fact, the price of P5.5
Million was, as clearly worded in Rivera's letter (Exh. "E"), the official and
definitive price at which the bank was selling the property. (p. 11, CA
Decision)
xxx
As held in the recent case of Chua Tiong Tay vs. Court of Appeals and Goldrock
Construction and Development Corp. 47:
The Court has consistently held that the factual findings of the trial court, as
well as the Court of Appeals, are final and conclusive and may not be
reviewed on appeal. Among the exceptional circumstances where a
reassessment of facts found by the lower courts is allowed are when the
conclusion is a finding grounded entirely on speculation, surmises or
conjectures; when the inference made is manifestly absurd, mistaken or
impossible; when there is grave abuse of discretion in the appreciation of
facts; when the judgment is premised on a misapprehension of facts; when
the findings went beyond the issues of the case and the same are contrary
to the admissions of both appellant and appellee. After a careful study of the
case at bench, we find none of the above grounds present to justify the reevaluation of the findings of fact made by the courts below.
In the same vein, the ruling of this Court in the recent case of South Sea Surety and
Insurance Company Inc. vs.Hon. Court of Appeals, et al. 48 is equally applicable to the
present case:
We see no valid reason to discard the factual conclusions of the appellate
court, . . . (I)t is not the function of this Court to assess and evaluate all over
again the evidence, testimonial and documentary, adduced by the parties,
particularly where, such as here, the findings of both the trial court and the
appellate court on the matter coincide. (emphasis supplied)
Petitioners, however, assailed the respondent Court's Decision as "fraught with
findings and conclusions which were not only contrary to the evidence on record but
have no bases at all," specifically the findings that (1) the "Bank's counter-offer price
of P5.5 million had been determined by the past due committee and approved by
conservator Romey, after Rivera presented the same for discussion" and (2) "the
meeting with Co was not to scale down the price and start negotiations anew, but a
meeting on the already determined price of P5.5 million" Hence, citingPhilippine
National Bank vs. Court of Appeals 49, petitioners are asking us to review and reverse
such factual findings.
The first point was clearly passed upon by the Court of Appeals 50, thus:
There can be no other logical conclusion than that when, on September 1,
1987, Rivera informed plaintiffs by letter that "the bank's counter-offer is at
P5.5 Million for more than 101 hectares on lot basis, "such counter-offer
price had been determined by the Past Due Committee and approved by the
xxx
xxx
serious abuse or evident lack of basis or capriciousness of any kind, because the trial
court is in a better position to observe the demeanor of the witnesses and their
courtroom manner as well as to examine the real evidence presented.
Epilogue.
In summary, there are two procedural issues involved forum-shopping and the raising
of issues for the first time on appeal [viz., the extinguishment of the Bank's offer of
P5.5 million and the conservator's powers to repudiate contracts entered into by the
Bank's officers] which per se could justify the dismissal of the present case. We did
not limit ourselves thereto, but delved as well into the substantive issues the
perfection of the contract of sale and its enforceability, which required the
determination of questions of fact. While the Supreme Court is not a trier of facts and
as a rule we are not required to look into the factual bases of respondent Court's
decisions and resolutions, we did so just the same, if only to find out whether there is
reason to disturb any of its factual findings, for we are only too aware of the depth,
magnitude and vigor by which the parties through their respective eloquent counsel,
argued their positions before this Court.
We are not unmindful of the tenacious plea that the petitioner Bank is operating
abnormally under a government-appointed conservator and "there is need to
rehabilitate the Bank in order to get it back on its feet . . . as many people depend on
(it) for investments, deposits and well as employment. As of June 1987, the Bank's
overdraft with the Central Bank had already reached P1.023 billion . . . and there
were (other) offers to buy the subject properties for a substantial amount of money." 53
While we do not deny our sympathy for this distressed bank, at the same time, the
Court cannot emotionally close its eyes to overriding considerations of substantive
and procedural law, like respect for perfected contracts, non-impairment of obligations
and sanctions against forum-shopping, which must be upheld under the rule of law
and blind justice.
This Court cannot just gloss over private respondent's submission that, while the
subject properties may currently command a much higher price, it is equally true that
at the time of the transaction in 1987, the price agreed upon of P5.5 million was
reasonable, considering that the Bank acquired these properties at a foreclosure sale
for no more than P3.5 million 54. That the Bank procrastinated and refused to honor its
commitment to sell cannot now be used by it to promote its own advantage, to enable
it to escape its binding obligation and to reap the benefits of the increase in land
values. To rule in favor of the Bank simply because the property in question has
algebraically accelerated in price during the long period of litigation is to reward
lawlessness and delays in the fulfillment of binding contracts. Certainly, the Court
cannot stamp its imprimatur on such outrageous proposition.
WHEREFORE, finding no reversible error in the questioned Decision and Resolution,
the Court hereby DENIES the petition. The assailed Decision is AFFIRMED.
Moreover, petitioner Bank is REPRIMANDED for engaging in forum-shopping and
WARNED that a repetition of the same or similar acts will be dealt with more severely.
Costs against petitioners.
SO ORDERED.
BANK
percent (10%) of the acquisition cost of the four vessels and were left with the unpaid
balance of their loans with defendant banks. [11] The Litonjuas prayed for the
accounting of the revenues derived in the operation of the six vessels and of the
proceeds of the sale thereof at the foreclosure proceedings instituted by petitioners;
damages for breach of trust; exemplary damages and attorneys fees.[12]
DECISION
AUSTRIA-MARTINEZ, J.:
This is a petition for review on certiorari under Rule 45 of the Rules of Court
assailing the November 29, 1994 decision of the Court of Appeals [1] and the April 28,
1995 resolution denying petitioners motion for reconsideration.
The factual background of the case is as follows:
On May 10, 1993, Eduardo K. Litonjua, Sr. and Aurelio J. Litonjua (Litonjuas, for
brevity) filed a Complaint[2] before the Regional Trial Court of Pasig against the Bank
of America NT&SA and Bank of America International, Ltd. (defendant banks for
brevity) alleging that: they were engaged in the shipping business; they owned two
vessels: Don Aurelio and El Champion, through their wholly-owned corporations; they
deposited their revenues from said business together with other funds with the
branches of said banks in the United Kingdom and Hongkong up to 1979; with their
business doing well, the defendant banks induced them to increase the number of
their ships in operation, offering them easy loans to acquire said vessels; [3] thereafter,
the defendant banks acquired, through their (Litonjuas) corporations as the
borrowers: (a) El Carrier[4]; (b) El General[5]; (c) El Challenger[6]; and (d) El
Conqueror[7]; the vessels were registered in the names of their corporations; the
operation and the funds derived therefrom were placed under the complete and
exclusive control and disposition of the petitioners; [8] and the possession the vessels
was also placed by defendant banks in the hands of persons selected and designated
by them (defendant banks).[9]
The Litonjuas claimed that defendant banks as trustees did not fully render an
account of all the income derived from the operation of the vessels as well as of the
proceeds of the subsequent foreclosure sale;[10] because of the breach of their
fiduciary duties and/or negligence of the petitioners and/or the persons designated by
them in the operation of private respondents six vessels, the revenues derived from
the operation of all the vessels declined drastically; the loans acquired for the
purchase of the four additional vessels then matured and remained unpaid, prompting
defendant banks to have all the six vessels, including the two vessels originally
owned by the private respondents, foreclosed and sold at public auction to answer for
the obligations incurred for and in behalf of the operation of the vessels; they
(Litonjuas) lost sizeable amounts of their own personal funds equivalent to ten
iii) The monies were advanced outside the Philippines. Furthermore, the mortgaged
vessels were part of an offshore fleet, not based in the Philippines;
iv) All the loans involved were granted to the Private Respondents
foreign CORPORATIONS;
v) The Restructuring Agreements were ALL governed by the laws of England;
vi) The subsequent sales of the mortgaged vessels and the application of the sales
proceeds occurred and transpired outside the Philippines, and the deliveries of the
sold mortgaged vessels were likewise made outside the Philippines;
vii) The revenues of the vessels and the proceeds of the sales of these vessels
were ALL deposited to the Accounts of the foreign CORPORATIONS abroad; and
viii) Bank of America International Ltd. is not licensed nor engaged in trade or
business in the Philippines.[24]
Petitioners argue further that the loan agreements, security documentation and
all subsequent restructuring agreements uniformly, unconditionally and expressly
provided that they will be governed by the laws of England; [25] that Philippine Courts
would then have to apply English law in resolving whatever issues may be presented
to it in the event it recognizes and accepts herein case; that it would then be imposing
a significant and unnecessary expense and burden not only upon the parties to the
transaction but also to the local court. Petitioners insist that the inconvenience and
difficulty of applying English law with respect to a wholly foreign transaction in a case
pending in the Philippines may be avoided by its dismissal on the ground of forum
non conveniens. [26]
Finally, petitioners claim that private respondents have already waived their
alleged causes of action in the case at bar for their refusal to contest the foreign civil
cases earlier filed by the petitioners against them in Hongkong and England, to wit:
1.) Civil action in England in its High Court of Justice, Queens Bench Division
Commercial Court (1992-Folio No. 2098) against (a) LIBERIAN TRANSPORT
NAVIGATION. SA.; (b) ESHLEY COMPANIA NAVIERA SA., (c) EL CHALLENGER
SA; (d) ESPRIONA SHIPPING CO. SA; (e) PACIFIC NAVIGATOS CORP. SA; (f)
EDDIE NAVIGATION CORP. SA; (g) EDUARDO K. LITONJUA & (h) AURELIO K.
LITONJUA.
2.) Civil action in England in its High Court of Justice, Queens Bench Division,
Commercial Court (1992-Folio No. 2245) against (a) EL CHALLENGER S.A., (b)
It is a well-settled rule that the order denying the motion to dismiss cannot be
the subject of petition for certiorari. Petitioners should have filed an answer to the
complaint, proceed to trial and await judgment before making an appeal. As
repeatedly held by this Court:
An order denying a motion to dismiss is interlocutory and cannot be the subject of the
extraordinary petition for certiorari or mandamus. The remedy of the aggrieved party
is to file an answer and to interpose as defenses the objections raised in his motion to
dismiss, proceed to trial, and in case of an adverse decision, to elevate the entire
case by appeal in due course. xxx Under certain situations, recourse to certiorari or
mandamus is considered appropriate, i.e., (a) when the trial court issued the order
without or in excess of jurisdiction; (b) where there is patent grave abuse of discretion
by the trial court; or (c) appeal would not prove to be a speedy and adequate remedy
as when an appeal would not promptly relieve a defendant from the injurious effects
of the patently mistaken order maintaining the plaintiffs baseless action and
compelling the defendant needlessly to go through a protracted trial and clogging the
court dockets by another futile case.[34]
Records show that the trial court acted within its jurisdiction when it issued the
assailed Order denying petitioners motion to dismiss. Does the denial of the motion to
dismiss constitute a patent grave abuse of discretion? Would appeal, under the
circumstances, not prove to be a speedy and adequate remedy? We will resolve said
questions in conjunction with the issues raised by the parties.
First issue. Did the trial court commit grave abuse of discretion in refusing to
dismiss the complaint on the ground that plaintiffs have no cause of action against
defendants since plaintiffs are merely stockholders of the corporations which are the
registered owners of the vessels and the borrowers of petitioners?
No. Petitioners argument that private respondents, being mere stockholders of
the foreign corporations, have no personalities to sue, and therefore, the complaint
should be dismissed, is untenable. A case is dismissible for lack of personality to sue
upon proof that the plaintiff is not the real party-in-interest. Lack of personality to sue
can be used as a ground for a Motion to Dismiss based on the fact that the complaint,
on the face thereof, evidently states no cause of action.[35] In San Lorenzo Village
Association, Inc. vs. Court of Appeals, [36] this Court clarified that a complaint states a
cause of action where it contains three essential elements of a cause of action,
namely: (1) the legal right of the plaintiff, (2) the correlative obligation of the
defendant, and (3) the act or omission of the defendant in violation of said legal
right. If these elements are absent, the complaint becomes vulnerable to a motion to
dismiss on the ground of failure to state a cause of action. [37] To emphasize, it is not
the lack or absence of cause of action that is a ground for dismissal of the complaint
but rather the fact that the complaint states no cause of action. [38] Failure to state a
cause of action refers to the insufficiency of allegation in the pleading, unlike lack of
cause of action which refers to the insufficiency of factual basis for the action. Failure
to state a cause of action may be raised at the earliest stages of an action through a
motion to dismiss the complaint, while lack of cause of action may be raised any time
after the questions of fact have been resolved on the basis of stipulations, admissions
or evidence presented.[39]
In the case at bar, the complaint contains the three elements of a cause of
action. It alleges that: (1) plaintiffs, herein private respondents, have the right to
demand for an accounting from defendants (herein petitioners), as trustees by reason
of the fiduciary relationship that was created between the parties involving the vessels
in question; (2) petitioners have the obligation, as trustees, to render such an
accounting; and (3) petitioners failed to do the same.
Petitioners insist that they do not have any obligation to the private respondents
as they are mere stockholders of the corporation; that the corporate entities have
juridical personalities separate and distinct from those of the private respondents.
Private respondents maintain that the corporations are wholly owned by them and
prior to the incorporation of such entities, they were clients of petitioners which
induced them to acquire loans from said petitioners to invest on the additional ships.
We agree with private respondents. As held in the San Lorenzo case,[40]
xxx assuming that the allegation of facts constituting plaintiffs cause of action is not
as clear and categorical as would otherwise be desired, any uncertainty thereby
arising should be so resolved as to enable a full inquiry into the merits of the action.
As this Court has explained in the San Lorenzo case, such a course, would preclude
multiplicity of suits which the law abhors, and conduce to the definitive determination
and termination of the dispute. To do otherwise, that is, to abort the action on account
of the alleged fatal flaws of the complaint would obviously be indecisive and would not
end the controversy, since the institution of another action upon a revised complaint
would not be foreclosed.[41]
convenient or available forum and the parties are not precluded from seeking
remedies elsewhere.[43]
Whether a suit should be entertained or dismissed on the basis of said doctrine
depends largely upon the facts of the particular case and is addressed to the sound
discretion of the trial court.[44] In the case of Communication Materials and Design,
Inc. vs. Court of Appeals,[45] this Court held that xxx [a] Philippine Court may assume
jurisdiction over the case if it chooses to do so; provided, that the following requisites
are met: (1) that the Philippine Court is one to which the parties may conveniently
resort to; (2) that the Philippine Court is in a position to make an intelligent decision
as to the law and the facts; and, (3) that the Philippine Court has or is likely to have
power to enforce its decision. [46] Evidently, all these requisites are present in the
instant case.
Moreover, this Court enunciated in Philsec. Investment Corporation vs. Court of
Appeals,[47] that the doctrine of forum non conveniens should not be used as a ground
for a motion to dismiss because Sec. 1, Rule 16 of the Rules of Court does not
include said doctrine as a ground. This Court further ruled that while it is within the
discretion of the trial court to abstain from assuming jurisdiction on this ground, it
should do so only after vital facts are established, to determine whether special
circumstances require the courts desistance; and that the propriety of dismissing a
case based on this principle of forum non conveniens requires a factual
determination, hence it is more properly considered a matter of defense.[48]
Third issue. Are private respondents guilty of forum shopping because of the
pendency of foreign action?
Second Issue. Should the complaint be dismissed on the ground of forum nonconveniens?
No. Forum shopping exists where the elements of litis pendentia are present
and where a final judgment in one case will amount to res judicata in the other.
[49]
Parenthetically, for litis pendentia to be a ground for the dismissal of an action there
must be: (a) identity of the parties or at least such as to represent the same interest in
both actions; (b) identity of rights asserted and relief prayed for, the relief being
founded on the same acts; and (c) the identity in the two cases should be such that
the judgment which may be rendered in one would, regardless of which party is
successful, amount to res judicata in the other.[50]
In case at bar, not all the requirements for litis pendentia are present. While
there may be identity of parties, notwithstanding the presence of other respondents,
[51]
as well as the reversal in positions of plaintiffs and defendants[52], still the other
requirements necessary for litis pendentia were not shown by petitioner. It merely
mentioned that civil cases were filed in Hongkong and England without however
showing the identity of rights asserted and the reliefs sought for as well as the
presence of the elements of res judicata should one of the cases be adjudged.
DECISION
respondent 3-Plex, not being accredited by or registered with the Philippine Overseas
Construction Board (POCB), assigned and transferred all its rights and interests
under the joint venture agreement to VPECI, a construction and engineering firm duly
registered with the POCB.4 However, on 2 May 1981, 3-Plex and VPECI entered into
an agreement that the execution of the Project would be under their joint
management.5
The SOB required the contractors to submit (1) a performance bond of ID271,808/610
representing 5% of the total contract price and (2) an advance payment bond of
ID541,608/901 representing 10% of the advance payment to be released upon
signing of the contract.6 To comply with these requirements, respondents 3-Plex and
VPECI applied for the issuance of a guarantee with petitioner Philguarantee, a
government financial institution empowered to issue guarantees for qualified Filipino
contractors to secure the performance of approved service contracts abroad.7
Petitioner Philguarantee approved respondents' application. Subsequently, letters of
guarantee8 were issued by Philguarantee to the Rafidain Bank of Baghdad covering
100% of the performance and advance payment bonds, but they were not accepted
by SOB. What SOB required was a letter-guarantee from Rafidain Bank, the
government bank of Iraq. Rafidain Bank then issued a performance bond in favor of
SOB on the condition that another foreign bank, not Philguarantee, would issue a
counter-guarantee to cover its exposure. Al Ahli Bank of Kuwait was, therefore,
engaged to provide a counter-guarantee to Rafidain Bank, but it required a similar
counter-guarantee in its favor from the petitioner. Thus, three layers of guarantees
had to be arranged.9
Upon the application of respondents 3-Plex and VPECI, petitioner Philguarantee
issued in favor of Al Ahli Bank of Kuwait Letter of Guarantee No. 81-194F 10 (Performance Bond Guarantee) in the amount of ID271,808/610 and Letter of
Guarantee No. 81-195-F11 (Advance Payment Guarantee) in the amount of
ID541,608/901, both for a term of eighteen months from 25 May 1981. These letters
of guarantee were secured by (1) a Deed of Undertaking12executed by respondents
VPECI, Spouses Vicente P. Eusebio and Soledad C. Eusebio, 3-Plex, and Spouses
Eduardo E. Santos and Iluminada Santos; and (2) a surety bond13 issued by
respondent First Integrated Bonding and Insurance Company, Inc. (FIBICI). The
Surety Bond was later amended on 23 June 1981 to increase the amount of coverage
from P6.4 million to P6.967 million and to change the bank in whose favor the
petitioner's guarantee was issued, from Rafidain Bank to Al Ahli Bank of Kuwait. 14
On 11 June 1981, SOB and the joint venture VPECI and Ajyal executed the service
contract15 for the construction of the Institute of Physical Therapy Medical
Rehabilitation Center, Phase II, in Baghdad, Iraq, wherein the joint venture contractor
undertook to complete the Project within a period of 547 days or 18 months. Under
the Contract, the Joint Venture would supply manpower and materials, and SOB
would refund to the former 25% of the project cost in Iraqi Dinar and the 75% in US
dollars at the exchange rate of 1 Dinar to 3.37777 US Dollars.16
The construction, which was supposed to start on 2 June 1981, commenced only on
the last week of August 1981. Because of this delay and the slow progress of the
construction work due to some setbacks and difficulties, the Project was not
completed on 15 November 1982 as scheduled. But in October 1982, upon
foreseeing the impossibility of meeting the deadline and upon the request of Al Ahli
Bank, the joint venture contractor worked for the renewal or extension of the
Performance Bond and Advance Payment Guarantee. Petitioner's Letters of
Guarantee Nos. 81-194-F (Performance Bond) and 81-195-F (Advance Payment
Bond) with expiry date of 25 November 1982 were then renewed or extended to 9
February 1983 and 9 March 1983, respectively.17 The surety bond was also extended
for another period of one year, from 12 May 1982 to 12 May 1983.18 The Performance
Bond was further extended twelve times with validity of up to 8 December
1986,19 while the Advance Payment Guarantee was extended three times more up to
24 May 1984 when the latter was cancelled after full refund or reimbursement by the
joint venture contractor.20 The surety bond was likewise extended to 8 May 1987.21
On 27 August 1987, the Central Bank authorized the remittance for its account of the
amount of US$876,564 (equivalent to ID271, 808/610) to Al Ahli Bank representing
full payment of the performance counter-guarantee for VPECI's project in Iraq. 28
As of March 1986, the status of the Project was 51% accomplished, meaning the
structures were already finished. The remaining 47% consisted in electro-mechanical
works and the 2%, sanitary works, which both required importation of equipment and
materials.22
On 19 June 1991, the petitioner sent to the respondents separate letters demanding
full payment of the amount ofP47,872,373.98 plus accruing interest, penalty charges,
and 10% attorney's fees pursuant to their joint and solidary obligations under the
deed of undertaking and surety bond.32 When the respondents failed to pay, the
petitioner filed on 9 July 1991 a civil case for collection of a sum of money against the
respondents before the RTC of Makati City.
On 26 October 1986, Al Ahli Bank of Kuwait sent a telex call to the petitioner
demanding full payment of its performance bond counter-guarantee.
Upon receiving a copy of that telex message on 27 October 1986, respondent VPECI
requested Iraq Trade and Economic Development Minister Mohammad Fadhi
Hussein to recall the telex call on the performance guarantee for being a drastic
action in contravention of its mutual agreement with the latter that (1) the imposition of
penalty would be held in abeyance until the completion of the project; and (2) the time
extension would be open, depending on the developments on the negotiations for a
foreign loan to finance the completion of the project.23 It also wrote SOB protesting
the call for lack of factual or legal basis, since the failure to complete the Project was
due to (1) the Iraqi government's lack of foreign exchange with which to pay its
(VPECI's) accomplishments and (2) SOB's noncompliance for the past several years
with the provision in the contract that 75% of the billings would be paid in US
dollars.24 Subsequently, or on 19 November 1986, respondent VPECI advised the
petitioner not to pay yet Al Ahli Bank because efforts were being exerted for the
amicable settlement of the Project.25
On 14 April 1987, the petitioner received another telex message from Al Ahli Bank
stating that it had already paid to Rafidain Bank the sum of US$876,564 under its
letter of guarantee, and demanding reimbursement by the petitioner of what it paid to
the latter bank plus interest thereon and related expenses.26
Both petitioner Philguarantee and respondent VPECI sought the assistance of some
government agencies of the Philippines. On 10 August 1987, VPECI requested the
Central Bank to hold in abeyance the payment by the petitioner "to allow the
diplomatic machinery to take its course, for otherwise, the Philippine government ,
through the Philguarantee and the Central Bank, would become instruments of the
Iraqi Government in consummating a clear act of injustice and inequity committed
against a Filipino contractor."27
After due trial, the trial court ruled against Philguarantee and held that the latter had
no valid cause of action against the respondents. It opined that at the time the call
was made on the guarantee which was executed for a specific period, the guarantee
had already lapsed or expired. There was no valid renewal or extension of the
guarantee for failure of the petitioner to secure respondents' express consent thereto.
The trial court also found that the joint venture contractor incurred no delay in the
execution of the Project. Considering the Project owner's violations of the contract
which rendered impossible the joint venture contractor's performance of its
undertaking, no valid call on the guarantee could be made. Furthermore, the trial
court held that no valid notice was first made by the Project owner SOB to the joint
venture contractor before the call on the guarantee. Accordingly, it dismissed the
complaint, as well as the counterclaims and cross-claim, and ordered the petitioner to
pay attorney's fees of P100,000 to respondents VPECI and Eusebio Spouses
and P100,000 to 3-Plex and the Santos Spouses, plus costs. 33
In its 14 June 1999 Decision,34 the Court of Appeals affirmed the trial court's decision,
ratiocinating as follows:
First, appellant cannot deny the fact that it was fully aware of the status of
project implementation as well as the problems besetting the contractors,
between 1982 to 1985, having sent some of its people to Baghdad during
that period. The successive renewals/extensions of the guarantees in fact,
was prompted by delays, not solely attributable to the contractors, and such
extension understandably allowed by the SOB (project owner) which had not
anyway complied with its contractual commitment to tender 75% of payment
in US Dollars, and which still retained overdue amounts collectible by
VPECI.
Second, appellant was very much aware of the violations committed by the
SOB of its contractual undertakings with VPECI, principally, the payment of
foreign currency (US$) for 75% of the total contract price, as well as of the
complications and injustice that will result from its payment of the full amount
of the performance guarantee, as evident in PHILGUARANTEE's letter
dated 13 May 1987 .
Third, appellant was fully aware that SOB was in fact still obligated to the
Joint Venture and there was still an amount collectible from and still being
retained by the project owner, which amount can be set-off with the sum
covered by the performance guarantee.
The petitioner asserts that since the guarantee it issued was absolute, unconditional,
and irrevocable the nature and extent of its liability are analogous to those of
suretyship. Its liability accrued upon the failure of the respondents to finish the
construction of the Institute of Physical Therapy Buildings in Baghdad.
By guaranty a person, called the guarantor, binds himself to the creditor to fulfill the
obligation of the principal debtor in case the latter should fail to do so. If a person
binds himself solidarily with the principal debtor, the contract is called suretyship. 37
Strictly speaking, guaranty and surety are nearly related, and many of the principles
are common to both. In both contracts, there is a promise to answer for the debt or
default of another. However, in this jurisdiction, they may be distinguished thus:
1. A surety is usually bound with his principal by the same instrument
executed at the same time and on the same consideration. On the other
hand, the contract of guaranty is the guarantor's own separate undertaking
often supported by a consideration separate from that supporting the
contract of the principal; the original contract of his principal is not his
contract.
2. A surety assumes liability as a regular party to the undertaking; while the
liability of a guarantor is conditional depending on the failure of the primary
debtor to pay the obligation.
3. The obligation of a surety is primary, while that of a guarantor is
secondary.
I
RESPONDENTS ARE NOT LIABLE UNDER THE DEED OF
UNDERTAKING THEY EXECUTED IN FAVOR OF PETITIONER IN
CONSIDERATION FOR THE ISSUANCE OF ITS COUNTER-GUARANTEE
AND THAT PETITIONER CANNOT PASS ON TO RESPONDENTS WHAT
IT HAD PAID UNDER THE SAID COUNTER-GUARANTEE.
II
PETITIONER CANNOT CLAIM SUBROGATION.
III
IT IS INIQUITOUS AND UNJUST FOR PETITIONER TO HOLD
RESPONDENTS LIABLE UNDER THEIR DEED OF UNDERTAKING.36
The main issue in this case is whether the petitioner is entitled to reimbursement of
what it paid under Letter of Guarantee No. 81-194-F it issued to Al Ahli Bank of
Kuwait based on the deed of undertaking and surety bond from the respondents.
bond required of V.P. EUSEBIO for the construction of the Physical Therapy
Institute, Phase II, Baghdad, Iraq, plus interest and other incidental
expenses related thereto.
In the event of default by V.P. EUSEBIO, we shall pay you 100% of the
obligation unpaid but in no case shall such amount exceed Iraq Dinars (ID)
271,808/610 plus interest and other incidental expenses. (Emphasis
supplied)39
Guided by the abovementioned distinctions between a surety and a guaranty, as well
as the factual milieu of this case, we find that the Court of Appeals and the trial court
were correct in ruling that the petitioner is a guarantor and not a surety. That the
guarantee issued by the petitioner is unconditional and irrevocable does not make the
petitioner a surety. As a guaranty, it is still characterized by its subsidiary and
conditional quality because it does not take effect until the fulfillment of the condition,
namely, that the principal obligor should fail in his obligation at the time and in the
form he bound himself.40 In other words, an unconditional guarantee is still subject to
the condition that the principal debtor should default in his obligation first before resort
to the guarantor could be had. A conditional guaranty, as opposed to an unconditional
guaranty, is one which depends upon some extraneous event, beyond the mere
default of the principal, and generally upon notice of the principal's default and
reasonable diligence in exhausting proper remedies against the principal.41
It appearing that Letter of Guarantee No. 81-194-F merely stated that in the event of
default by respondent VPECI the petitioner shall pay, the obligation assumed by the
petitioner was simply that of an unconditional guaranty, not conditional guaranty. But
as earlier ruled the fact that petitioner's guaranty is unconditional does not make it a
surety. Besides, surety is never presumed. A party should not be considered a surety
where the contract itself stipulates that he is acting only as a guarantor. It is only
when the guarantor binds himself solidarily with the principal debtor that the contract
becomes one of suretyship.42
Having determined petitioner's liability as guarantor, the next question we have to
grapple with is whether the respondent contractor has defaulted in its obligations that
would justify resort to the guaranty. This is a mixed question of fact and law that is
better addressed by the lower courts, since this Court is not a trier of facts.
It is a fundamental and settled rule that the findings of fact of the trial court and the
Court of Appeals are binding or conclusive upon this Court unless they are not
supported by the evidence or unless strong and cogent reasons dictate
otherwise.43 The factual findings of the Court of Appeals are normally not reviewable
by us under Rule 45 of the Rules of Court except when they are at variance with
those of the trial court. 44 The trial court and the Court of Appeals were in unison that
the respondent contractor cannot be considered to have defaulted in its obligations
because the cause of the delay was not primarily attributable to it.
A corollary issue is what law should be applied in determining whether the respondent
contractor has defaulted in the performance of its obligations under the service
contract. The question of whether there is a breach of an agreement, which
includes default or mora,45 pertains to the essential or intrinsic validity of a contract. 46
No conflicts rule on essential validity of contracts is expressly provided for in our laws.
The rule followed by most legal systems, however, is that the intrinsic validity of a
contract must be governed by the lex contractus or "proper law of the contract." This
is the law voluntarily agreed upon by the parties (the lex loci voluntatis) or the law
intended by them either expressly or implicitly (the lex loci intentionis). The law
selected may be implied from such factors as substantial connection with the
transaction, or the nationality or domicile of the parties.47 Philippine courts would do
well to adopt the first and most basic rule in most legal systems, namely, to allow the
parties to select the law applicable to their contract, subject to the limitation that it is
not against the law, morals, or public policy of the forum and that the chosen law
must bear a substantive relationship to the transaction. 48
It must be noted that the service contract between SOB and VPECI contains no
express choice of the law that would govern it. In the United States and Europe, the
two rules that now seem to have emerged as "kings of the hill" are (1) the parties may
choose the governing law; and (2) in the absence of such a choice, the applicable law
is that of the State that "has the most significant relationship to the transaction and
the parties."49 Another authority proposed that all matters relating to the time, place,
and manner of performance and valid excuses for non-performance are determined
by the law of the place of performance or lex loci solutionis, which is useful because it
is undoubtedly always connected to the contract in a significant way.50
In this case, the laws of Iraq bear substantial connection to the transaction, since one
of the parties is the Iraqi Government and the place of performance is in Iraq. Hence,
the issue of whether respondent VPECI defaulted in its obligations may be
determined by the laws of Iraq. However, since that foreign law was not properly
pleaded or proved, the presumption of identity or similarity, otherwise known as
the processual presumption, comes into play. Where foreign law is not pleaded or,
even if pleaded, is not proved, the presumption is that foreign law is the same as
ours.51
Our law, specifically Article 1169, last paragraph, of the Civil Code, provides: "In
reciprocal obligations, neither party incurs in delay if the other party does not comply
or is not ready to comply in a proper manner with what is incumbent upon him."
Default or mora on the part of the debtor is the delay in the fulfillment of the prestation
by reason of a cause imputable to the former. 52 It is the non-fulfillment of an
obligation with respect to time.53
It is undisputed that only 51.7% of the total work had been accomplished. The 48.3%
unfinished portion consisted in the purchase and installation of electro-mechanical
equipment and materials, which were available from foreign suppliers, thus requiring
US Dollars for their importation. The monthly billings and payments made by
SOB54 reveal that the agreement between the parties was a periodic payment by the
Project owner to the contractor depending on the percentage of accomplishment
within the period. 55 The payments were, in turn, to be used by the contractor to
finance the subsequent phase of the work. 56 However, as explained by VPECI in its
letter to the Department of Foreign Affairs (DFA), the payment by SOB purely in
Dinars adversely affected the completion of the project; thus:
5.2 That Plaintiff is a foreign contractor in Iraq and as such, would need
foreign currency (US$), to finance the purchase of various equipment,
materials, supplies, tools and to pay for the cost of project management,
supervision and skilled labor not available in Iraq and therefore have to be
imported and or obtained from the Philippines and other sources outside
Iraq.
5.3 That the Ministry of Labor and Employment of the Philippines requires
the remittance into the Philippines of 70% of the salaries of Filipino workers
working abroad in US Dollars;
5.5 That the Iraqi Dinar is not a freely convertible currency such that the
same cannot be used to purchase equipment, materials, supplies, etc.
outside of Iraq;
5.6 That most of the materials specified by SOB in the CONTRACT are not
available in Iraq and therefore have to be imported;
5.7 That the government of Iraq prohibits the bringing of local currency
(Iraqui Dinars) out of Iraq and hence, imported materials, equipment, etc.,
cannot be purchased or obtained using Iraqui Dinars as medium of
acquisition.
10. Due to the lack of Foreign currency in Iraq for this purpose, and if only to
assist the Iraqi government in completing the PROJECT, the Contractor
without any obligation on its part to do so but with the knowledge and
consent of SOB and the Ministry of Housing & Construction of Iraq, offered
to arrange on behalf of SOB, a foreign currency loan, through the facilities of
Circle International S.A., the Contractor's Sub-contractor and SACE MEDIO
CREDITO which will act as the guarantor for this foreign currency loan.
Arrangements were first made with Banco di Roma. Negotiation started in
June 1985. SOB is informed of the developments of this negotiation,
attached is a copy of the draft of the loan Agreement between SOB as the
Borrower and Agent. The Several Banks, as Lender, and counterguaranteed by Istituto Centrale Per II Credito A Medio Termine
(Mediocredito) Sezione Speciale Per L'Assicurazione Del Credito
All'Exportazione (Sace). Negotiations went on and continued until it suddenly
collapsed due to the reported default by Iraq in the payment of its obligations
with Italian government, copy of the news clipping dated June 18, 1986 is
hereto attached as Annex "D" to form an integral part hereof;
15. On September 15, 1986, Contractor received information from Circle
International S.A. that because of the news report that Iraq defaulted in its
obligations with European banks, the approval by Banco di Roma of the loan
to SOB shall be deferred indefinitely, a copy of the letter of Circle
International together with the news clippings are hereto attached as
Annexes "F" and "F-1", respectively.57
As found by both the Court of Appeals and the trial court, the delay or the noncompletion of the Project was caused by factors not imputable to the respondent
contractor. It was rather due mainly to the persistent violations by SOB of the terms
and conditions of the contract, particularly its failure to pay 75% of the accomplished
work in US Dollars. Indeed, where one of the parties to a contract does not perform
in a proper manner the prestation which he is bound to perform under the contract, he
is not entitled to demand the performance of the other party. A party does not incur in
delay if the other party fails to perform the obligation incumbent upon him.
The petitioner, however, maintains that the payments by SOB of the monthly billings
in purely Iraqi Dinars did not render impossible the performance of the Project by
VPECI. Such posture is quite contrary to its previous representations. In his 26 March
1987 letter to the Office of the Middle Eastern and African Affairs (OMEAA), DFA,
Manila, petitioner's Executive Vice-President Jesus M. Taedo stated that while
VPECI had taken every possible measure to complete the Project, the war situation in
Iraq, particularly the lack of foreign exchange, was proving to be a great obstacle;
thus:
VPECI has taken every possible measure for the completion of the project
but the war situation in Iraq particularly the lack of foreign exchange is
proving to be a great obstacle. Our performance counterguarantee was
called last 26 October 1986 when the negotiations for a foreign currency
loan with the Italian government through Banco de Roma bogged down
following news report that Iraq has defaulted in its obligation with major
European banks. Unless the situation in Iraq is improved as to allay the
SOB, which are fully supported by evidence and which have been meritoriously set
up against the paying guarantor, the petitioner in this case. And even if the deed of
undertaking and the surety bond secured petitioner's guaranty, the petitioner is
precluded from enforcing the same by reason of the petitioner's undue payment on
the guaranty. Rights under the deed of undertaking and the surety bond do not arise
because these contracts depend on the validity of the enforcement of the guaranty.
The petitioner guarantor should have waited for the natural course of guaranty: the
debtor VPECI should have, in the first place, defaulted in its obligation and that the
creditor SOB should have first made a demand from the principal debtor. It is only
when the debtor does not or cannot pay, in whole or in part, that the guarantor should
pay.71 When the petitioner guarantor in this case paid against the will of the debtor
VPECI, the debtor VPECI may set up against it defenses available against the
creditor SOB at the time of payment. This is the hard lesson that the petitioner must
learn.
As the government arm in pursuing its objective of providing "the necessary support
and assistance in order to enable [Filipino exporters and contractors to operate
viably under the prevailing economic and business conditions,"72 the petitioner should
have exercised prudence and caution under the circumstances. As aptly put by the
Court of Appeals, it would be the height of inequity to allow the petitioner to pass on
its losses to the Filipino contractor VPECI which had sternly warned against paying
the Al Ahli Bank and constantly apprised it of the developments in the Project
implementation.
WHEREFORE, the petition for review on certiorari is hereby DENIED for lack of merit,
and the decision of the Court of appeals in CA-G.R. CV No. 39302 is AFFIRMED.
No pronouncement as to costs.
SO ORDERED.
It then concluded that the service of summons effected in Manila or beyond the
territorial boundaries of Japan was null and did not confer jurisdiction upon the Tokyo
District Court over the person of SHARP; hence, its decision was void.
A foreign judgment is presumed to be valid and binding in the country from which it
comes, until the contrary is shown. It is also proper to presume the regularity of the
proceedings and the giving of due notice therein. 6
Under Section 50, Rule 39 of the Rules of Court, a judgment in an action in
personam of a tribunal of a foreign country having jurisdiction to pronounce the same
is presumptive evidence of a right as between the parties and their successors-ininterest by a subsequent title. The judgment may, however, be assailed by evidence
of want of jurisdiction, want of notice to the party, collusion, fraud, or clear mistake of
law or fact. Also, under Section 3 of Rule 131, a court, whether of the Philippines or
elsewhere, enjoys the presumption that it was acting in the lawful exercise of
jurisdiction and has regularly performed its official duty.
Consequently, the party attacking a foreign judgment has the burden of overcoming
the presumption of its validity. 7Being the party challenging the judgment rendered by
the Japanese court, SHARP had the duty to demonstrate the invalidity of such
judgment. In an attempt to discharge that burden, it contends that the extraterritorial
service of summons effected at its home office in the Philippines was not only
ineffectual but also void, and the Japanese Court did not, therefore acquire
jurisdiction over it.
It is settled that matters of remedy and procedure such as those relating to the
service of process upon a defendant are governed by the lex fori or the internal law of
the forum. 8 In this case, it is the procedural law of Japan where the judgment was
rendered that determines the validity of the extraterritorial service of process on
SHARP. As to what this law is is a question of fact, not of law. It may not be taken
judicial notice of and must be pleaded and proved like any other fact. 9Sections 24
and 25, Rule 132 of the Rules of Court provide that it may be evidenced by an official
publication or by a duly attested or authenticated copy thereof. It was then incumbent
upon SHARP to present evidence as to what that Japanese procedural law is and to
show that under it, the assailed extraterritorial service is invalid. It did not.
Accordingly, the presumption of validity and regularity of the service of summons and
the decision thereafter rendered by the Japanese court must stand.
present, but to accept the summons because, according to him, he was no longer an
employee of SHARP. While it may be true that service could have been made upon
any of the officers or agents of SHARP at its three other branches in Japan, the
availability of such a recourse would not preclude service upon the proper
government official, as stated above.
As found by the Court of Appeals, it was the Tokyo District Court which ordered that
summons for SHARP be served at its head office in the Philippine's after the two
attempts of service had failed. 16 The Tokyo District Court requested the Supreme
Court of Japan to cause the delivery of the summons and other legal documents to
the Philippines. Acting on that request, the Supreme Court of Japan sent the
summons together with the other legal documents to the Ministry of Foreign Affairs of
Japan which, in turn, forwarded the same to the Japanese Embassy in Manila .
Thereafter, the court processes were delivered to the Ministry (now Department) of
Foreign Affairs of the Philippines, then to the Executive Judge of the Court of First
Instance (now Regional Trial Court) of Manila, who forthwith ordered Deputy Sheriff
Rolando Balingit to serve the same on SHARP at its principal office in Manila. This
service is equivalent to service on the proper government official under Section 14,
Rule 14 of the Rules of Court, in relation to Section 128 of the Corporation Code.
Hence, SHARP's contention that such manner of service is not valid under Philippine
laws holds no water. 17
In deciding against the petitioner, the respondent court sustained the trial court's
reliance on Boudard vs. Tait 18where this Court held:
The fundamental rule is that jurisdiction in personam over
nonresidents, so as to sustain a money judgment, must be based
upon personal service within the state which renders the judgment.
xxx xxx xxx
The process of a court, has no extraterritorial effect, and no
jurisdiction is acquired over the person of the defendant by serving
him beyond the boundaries of the state. Nor has a judgment of a
court of a foreign country against a resident of this country having
no property in such foreign country based on process served here,
any effect here against either the defendant personally or his
property situated here.
Process issuing from the courts of one state or country cannot run
into another, and although a nonresident defendant may have been
personally served with such process in the state or country of his
domicile, it will not give such jurisdiction as to authorize a personal
judgment against him.
It further availed of the ruling in Magdalena Estate, Inc. vs. Nieto 19 and Dial
Corp. vs. Soriano, 20 as well as the principle laid down by the Iowa Supreme Court in
the 1911 case of Raher vs. Raher. 21
The first three cases are, however, inapplicable. Boudard involved the enforcement of
a judgment of the civil division of the Court of First Instance of Hanoi, French IndoChina. The trial court dismissed the case because the Hanoi court never acquired
jurisdiction over the person of the defendant considering that "[t]he, evidence
adduced at the trial conclusively proves that neither the appellee [the defendant] nor
his agent or employees were ever in Hanoi, French Indo-China; and that the
deceased Marie Theodore Jerome Boudard had never, at any time, been his
employee." In Magdalena Estate, what was declared invalid resulting in the failure of
the court to acquire jurisdiction over the person of the defendants in an action in
personam was the service of summons through publication against non-appearing
resident defendants. It was claimed that the latter concealed themselves to avoid
personal service of summons upon them. In Dial, the defendants were foreign
corporations which were not, domiciled and licensed to engage in business in the
Philippines and which did not have officers or agents, places of business, or
properties here. On the other hand, in the instant case, SHARP was doing business
in Japan and was maintaining four branches therein.
Insofar as to the Philippines is concerned, Raher is a thing of the past. In that case, a
divided Supreme Court of Iowa declared that the principle that there can be no
jurisdiction in a court of a territory to render a personal judgment against anyone upon
service made outside its limits was applicable alike to cases of residents and nonresidents. The principle was put at rest by the United States Supreme Court when it
ruled in the 1940 case ofMilliken vs. Meyer 22 that domicile in the state is alone
sufficient to bring an absent defendant within the reach of the state's jurisdiction for
purposes of a personal judgment by means of appropriate substituted service or
personal service without the state. This principle is embodied in section 18, Rule 14 of
the Rules of Court which allows service of summons on residents temporarily out of
the Philippines to be made out of the country. The rationale for this rule was explained
in Milliken as follows:
[T]he authority of a state over one of its citizens is not terminated by
the mere fact of his absence from the state. The state which
accords him privileges and affords protection to him and his
property by virtue of his domicile may also exact reciprocal duties.
"Enjoyment of the privileges of residence within the state, and the
attendant right to invoke the protection of its laws, are inseparable"
from the various incidences of state citizenship. The responsibilities
of that citizenship arise out of the relationship to the state which
domicile creates. That relationship is not dissolved by mere
absence from the state. The attendant duties, like the rights and
rural banks, stock savings and loan associations" (which have been
formed and organized under Philippine laws), making no distinction
between the former and the latter in so far as the terms "banking
institutions" and "bank" are used in the Act [Sec. 2], declaring on
the contrary that in "all matters not specifically covered by special
provisions applicable only to foreign banks, or their branches and
agencies in the Philippines, said foreign banks or their branches
and agencies lawfully doing business in the Philippines "shall be
bound by all laws, rules, and regulations applicable to domestic
banking corporations of the same class, except such laws, rules
and regulations as provided for the creation, formation,
organization, or dissolution of corporations or as fix the relation,
liabilities, responsibilities, or duties of members, stockholders or
officers of corporation. [Sec. 18].
This court itself has already had occasion to hold [Claude Neon
Lights, Fed. Inc. vs. Philippine Advertising Corp., 57 Phil. 607] that
a foreign corporation licitly doing business in the Philippines, which
is a defendant in a civil suit, may not be considered a nonresident within the scope of the legal provision authorizing
attachment against a defendant not residing in the Philippine
Islands; [Sec. 424, in relation to Sec. 412 of Act No. 190, the Code
of Civil Procedure; Sec. 1(f), Rule 59 of the Rules of 1940, Sec.
1(f), Rule 57, Rules of 1964] in other words, a preliminary
attachment may not be applied for and granted solely on the
asserted fact that the defendant is a foreign corporation authorized
to do business in the Philippines and is consequently and
necessarily, "a party who resides out of the Philippines."
Parenthetically, if it may not be considered as a party not residing in
the Philippines, or as a party who resides out of the country, then,
logically, it must be considered a party who does reside in the
Philippines, who is a resident of the country. Be this as it may, this
Court pointed out that:
. . . Our laws and jurisprudence indicate a
purpose to assimilate foreign corporations, duly
licensed to do business here, to the status of
domestic corporations. (Cf. Section 73, Act No.
1459, and Marshall Wells Co. vs. Henry W. Elser
& Co., 46 Phil. 70, 76; Yu Cong Eng vs. Trinidad,
47 Phil. 385, 411) We think it would be entirely
out of line with this policy should we make a
discrimination against a foreign corporation, like
the petitioner, and subject its property to the
harsh writ of seizure by attachment when it has
expenses, and exemplary damages but REVERSED insofar as in sustained the trial
court's dismissal of NORTHWEST's complaint in Civil Case No. 83-17637 of Branch
54 of the Regional Trial Court of Manila, and another in its stead is hereby rendered
ORDERING private respondent C.F. SHARP L COMPANY, INC. to pay to
NORTHWEST the amounts adjudged in the foreign judgment subject of said case,
with interest thereon at the legal rate from the filing of the complaint therein until the
said foreign judgment is fully satisfied.
Costs against the private respondent.
SO ORDERED.
QUISUMBING, J.:
This petition for certiorari pursuant to Rule 45 of the Rules of Court seeks to annul
and set aside the Resolution 1dated September 27, 1995 and the Decision 2 dated
April 10, 1996 of the Court of Appeals 3 in CA-G.R. SP No. 36533, 4 and the
Orders 5 dated August 29, 1994 6 and February 2, 1995 7 that were issued by the trial
court in Civil Case No. Q-93-18394. 8
The pertinent antecedent facts which gave rise to the instant petition, as stated in the
questioned Decision 9, are as follows:
On January 21, 1988 defendant SAUDIA hired plaintiff as a Flight
Attendant for its airlines based in Jeddah, Saudi Arabia. . . .
On April 27, 1990, while on a lay-over in Jakarta, Indonesia, plaintiff
went to a disco dance with fellow crew members Thamer AlGazzawi and Allah Al-Gazzawi, both Saudi nationals. Because it
was almost morning when they returned to their hotels, they agreed
to have breakfast together at the room of Thamer. When they were
in te (sic) room, Allah left on some pretext. Shortly after he did,
Thamer attempted to rape plaintiff. Fortunately, a roomboy and
several security personnel heard her cries for help and rescued her.
Later, the Indonesian police came and arrested Thamer and Allah
Al-Gazzawi, the latter as an accomplice.
When plaintiff returned to Jeddah a few days later, several SAUDIA
officials interrogated her about the Jakarta incident. They then
requested her to go back to Jakarta to help arrange the release of
Thamer and Allah. In Jakarta, SAUDIA Legal Officer Sirah Akkad
and base manager Baharini negotiated with the police for the
immediate release of the detained crew members but did not
succeed because plaintiff refused to cooperate. She was afraid that
she might be tricked into something she did not want because of
her inability to understand the local dialect. She also declined to
take flight. At the Inflight Service Office where she was told to go,
the secretary of Mr. Yahya Saddick took away her passport and told
her to remain in Jeddah, at the crew quarters, until further orders.
On July 3, 1993 a SAUDIA legal officer again escorted plaintiff to
the same court where the judge, to her astonishment and shock,
rendered a decision, translated to her in English, sentencing her to
five months imprisonment and to 286 lashes. Only then did she
realize that the Saudi court had tried her, together with Thamer and
Allah, for what happened in Jakarta. The court found plaintiff guilty
of (1) adultery; (2) going to a disco, dancing and listening to the
music in violation of Islamic laws; and (3) socializing with the male
crew, in contravention of Islamic tradition. 10
Facing conviction, private respondent sought the help of her employer, petitioner
SAUDIA. Unfortunately, she was denied any assistance. She then asked the
Philippine Embassy in Jeddah to help her while her case is on appeal. Meanwhile, to
pay for her upkeep, she worked on the domestic flight of SAUDIA, while Thamer and
Allah continued to serve in the international
flights. 11
Because she was wrongfully convicted, the Prince of Makkah dismissed the case
against her and allowed her to leave Saudi Arabia. Shortly before her return to
Manila, 12 she was terminated from the service by SAUDIA, without her being
informed of the cause.
On November 23, 1993, Morada filed a Complaint 13 for damages against SAUDIA,
and Khaled Al-Balawi ("Al-Balawi"), its country manager.
On January 19, 1994, SAUDIA filed an Omnibus Motion To Dismiss 14 which raised
the following grounds, to wit: (1) that the Complaint states no cause of action against
Saudia; (2) that defendant Al-Balawi is not a real party in interest; (3) that the claim or
demand set forth in the Complaint has been waived, abandoned or otherwise
extinguished; and (4) that the trial court has no jurisdiction to try the case.
From the Order of respondent Judge 20 denying the Motion to Dismiss, SAUDIA filed
on September 20, 1994, its Motion for Reconsideration 21 of the Order dated August
29, 1994. It alleged that the trial court has no jurisdiction to hear and try the case on
the basis of Article 21 of the Civil Code, since the proper law applicable is the law of
the Kingdom of Saudi Arabia. On October 14, 1994, Morada filed her
Opposition 22 (To Defendant's Motion for Reconsideration).
In the Reply 23 filed with the trial court on October 24, 1994, SAUDIA alleged that
since its Motion for Reconsideration raised lack of jurisdiction as its cause of action,
the Omnibus Motion Rule does not apply, even if that ground is raised for the first
time on appeal. Additionally, SAUDIA alleged that the Philippines does not have any
substantial interest in the prosecution of the instant case, and hence, without
jurisdiction to adjudicate the same.
Respondent Judge subsequently issued another Order 24 dated February 2, 1995,
denying SAUDIA's Motion for Reconsideration. The pertinent portion of the assailed
Order reads as follows:
Acting on the Motion for Reconsideration of defendant Saudi
Arabian Airlines filed, thru counsel, on September 20, 1994, and the
Opposition thereto of the plaintiff filed, thru counsel, on October 14,
1994, as well as the Reply therewith of defendant Saudi Arabian
Airlines filed, thru counsel, on October 24, 1994, considering that a
perusal of the plaintiffs Amended Complaint, which is one for the
recovery of actual, moral and exemplary damages plus attorney's
fees, upon the basis of the applicable Philippine law, Article 21 of
the New Civil Code of the Philippines, is, clearly, within the
jurisdiction of this Court as regards the subject matter, and there
being nothing new of substance which might cause the reversal or
modification of the order sought to be reconsidered, the motion for
reconsideration of the defendant, is DENIED.
SO ORDERED. 25
On February 10, 1994, Morada filed her Opposition (To Motion to Dismiss) . Saudia
filed a reply 16 thereto on March 3, 1994.
Consequently, on February 20, 1995, SAUDIA filed its Petition for Certiorari and
Prohibition with Prayer for Issuance of Writ of Preliminary Injunction and/or Temporary
Restraining Order 26 with the Court of Appeals.
On June 23, 1994, Morada filed an Amended Complaint 17 wherein Al-Balawi was
dropped as party defendant. On August 11, 1994, Saudia filed its Manifestation and
Motion to Dismiss Amended Complaint 18.
15
The trial court issued an Order 19 dated August 29, 1994 denying the Motion to
Dismiss Amended Complaint filed by Saudia.
On May 7, 1996, SAUDIA filed its Supplemental Petition for Review with Prayer for
Temporary Restraining Order 31dated April 30, 1996, given due course by this Court.
After both parties submitted their Memoranda, 32 the instant case is now deemed
submitted for decision.
Petitioner SAUDIA raised the following issues:
I
The trial court has no jurisdiction to hear and try Civil Case No. Q93-18394 based on Article 21 of the New Civil Code since the
proper law applicable is the law of the Kingdom of Saudi Arabia
inasmuch as this case involves what is known in private
international law as a "conflicts problem". Otherwise, the Republic
of the Philippines will sit in judgment of the acts done by another
sovereign state which is abhorred.
II
On the other hand, private respondent contends that since her Amended Complaint is
based on Articles 19 35 and 21 36 of the Civil Code, then the instant case is properly a
matter of domestic law. 37
Under the factual antecedents obtaining in this case, there is no dispute that the
interplay of events occurred in two states, the Philippines and Saudi Arabia.
As stated by private respondent in her Amended Complaint
38
The forms in which this foreign element may appear are many. 41 The foreign element
may simply consist in the fact that one of the parties to a contract is an alien or has a
foreign domicile, or that a contract between nationals of one State involves properties
situated in another State. In other cases, the foreign element may assume a complex
form. 42
In the instant case, the foreign element consisted in the fact that private respondent
Morada is a resident Philippine national, and that petitioner SAUDIA is a resident
foreign corporation. Also, by virtue of the employment of Morada with the petitioner
Saudia as a flight stewardess, events did transpire during her many occasions of
travel across national borders, particularly from Manila, Philippines to Jeddah, Saudi
Arabia, and vice versa, that caused a "conflicts" situation to arise.
We thus find private respondent's assertion that the case is purely domestic,
imprecise. A conflicts problem presents itself here, and the question of
jurisdiction 43 confronts the court a quo.
After a careful study of the private respondent's Amended Complaint, 44 and the
Comment thereon, we note that she aptly predicated her cause of action on Articles
19 and 21 of the New Civil Code.
Before a choice can be made, it is necessary for us to determine under what category
a certain set of facts or rules fall. This process is known as "characterization", or the
"doctrine of qualification". It is the "process of deciding whether or not the facts relate
to the kind of question specified in a conflicts rule." 55 The purpose of
"characterization" is to enable the forum to select the proper law. 56
Our starting point of analysis here is not a legal relation, but a factual situation, event,
or operative fact. 57 An essential element of conflict rules is the indication of a "test" or
"connecting factor" or "point of contact". Choice-of-law rules invariably consist of a
factual relationship (such as property right, contract claim) and a connecting factor or
point of contact, such as the situs of the res, the place of celebration, the place of
performance, or the place of wrongdoing. 58
Note that one or more circumstances may be present to serve as the possible test for
the determination of the applicable law. 59 These "test factors" or "points of contact" or
"connecting factors" could be any of the following:
(1) The nationality of a person, his domicile, his residence, his
place of sojourn, or his origin;
(2) the seat of a legal or juridical person, such as a corporation;
(3) the situs of a thing, that is, the place where a thing is, or is
deemed to be situated. In particular, thelex situs is decisive when
real rights are involved;
(4) the place where an act has been done, the locus actus, such as
the place where a contract has been made, a marriage celebrated,
a will signed or a tort committed. The lex loci actus is particularly
important in contracts and torts;
(5) the place where an act is intended to come into effect, e.g., the
place of performance of contractual duties, or the place where a
power of attorney is to be exercised;
(6) the intention of the contracting parties as to the law that should
govern their agreement, the lex loci intentionis;
(7) the place where judicial or administrative proceedings are
instituted or done. The lex fori the law of the forum is
particularly important because, as we have seen earlier, matters of
"procedure" not going to the substance of the claim involved are
governed by it; and because the lex fori applies whenever the
content of the otherwise applicable foreign law is excluded from
application in a given case for the reason that it falls under one of
the exceptions to the applications of foreign law; and
(8) the flag of a ship, which in many cases is decisive of practically
all legal relationships of the ship and of its master or owner as
such. It also covers contractual relationships particularly contracts
of affreightment. 60 (Emphasis ours.)
After a careful study of the pleadings on record, including allegations in the Amended
Complaint deemed admitted for purposes of the motion to dismiss, we are convinced
that there is reasonable basis for private respondent's assertion that although she
was already working in Manila, petitioner brought her to Jeddah on the pretense that
she would merely testify in an investigation of the charges she made against the two
SAUDIA crew members for the attack on her person while they were in Jakarta. As it
turned out, she was the one made to face trial for very serious charges, including
adultery and violation of Islamic laws and tradition.
There is likewise logical basis on record for the claim that the "handing over" or
"turning over" of the person of private respondent to Jeddah officials, petitioner may
have acted beyond its duties as employer. Petitioner's purported act contributed to
and amplified or even proximately caused additional humiliation, misery and suffering
of private respondent. Petitioner thereby allegedly facilitated the arrest, detention and
prosecution of private respondent under the guise of petitioner's authority as
employer, taking advantage of the trust, confidence and faith she reposed upon it. As
purportedly found by the Prince of Makkah, the alleged conviction and imprisonment
of private respondent was wrongful. But these capped the injury or harm allegedly
inflicted upon her person and reputation, for which petitioner could be liable as
claimed, to provide compensation or redress for the wrongs done, once duly proven.
Considering that the complaint in the court a quo is one involving torts, the
"connecting factor" or "point of contact" could be the place or places where the
tortious conduct or lex loci actus occurred. And applying the torts principle in a
conflicts case, we find that the Philippines could be said as a situs of the tort (the
place where the alleged tortious conduct took place). This is because it is in the
Philippines where petitioner allegedly deceived private respondent, a Filipina residing
and working here. According to her, she had honestly believed that petitioner would,
in the exercise of its rights and in the performance of its duties, "act with justice, give
her due and observe honesty and good faith." Instead, petitioner failed to protect her,
she claimed. That certain acts or parts of the injury allegedly occurred in another
country is of no moment. For in our view what is important here is the place where the
over-all harm or the totality of the alleged injury to the person, reputation, social
standing and human rights of complainant, had lodged, according to the plaintiff
below (herein private respondent). All told, it is not without basis to identify the
Philippines as the situs of the alleged tort.
Moreover, with the widespread criticism of the traditional rule of lex loci delicti
commissi, modern theories and rules on tort liability 61 have been advanced to offer
fresh judicial approaches to arrive at just results. In keeping abreast with the modern
theories on tort liability, we find here an occasion to apply the "State of the most
significant relationship" rule, which in our view should be appropriate to apply now,
given the factual context of this case.
In applying said principle to determine the State which has the most significant
relationship, the following contacts are to be taken into account and evaluated
according to their relative importance with respect to the particular issue: (a) the place
where the injury occurred; (b) the place where the conduct causing the injury
occurred; (c) the domicile, residence, nationality, place of incorporation and place of
business of the parties, and (d) the place where the relationship, if any, between the
parties is centered. 62
As already discussed, there is basis for the claim that over-all injury occurred and
lodged in the Philippines. There is likewise no question that private respondent is a
resident Filipina national, working with petitioner, a resident foreign corporation
engaged here in the business of international air carriage. Thus, the "relationship"
between the parties was centered here, although it should be stressed that this suit is
not based on mere labor law violations. From the record, the claim that the
Philippines has the most significant contact with the matter in this dispute, 63 raised by
private respondent as plaintiff below against defendant (herein petitioner), in our view,
has been properly established.
Prescinding from this premise that the Philippines is the situs of the tort complained of
and the place "having the most interest in the problem", we find, by way of
recapitulation, that the Philippine law on tort liability should have paramount
application to and control in the resolution of the legal issues arising out of this case.
Further, we hold that the respondent Regional Trial Court has jurisdiction over the
parties and the subject matter of the complaint; the appropriate venue is in Quezon
City, which could properly apply Philippine law. Moreover, we find untenable
petitioner's insistence that "[s]ince private respondent instituted this suit, she has the
burden of pleading and proving the applicable Saudi law on the matter." 64 As aptly
said by private respondent, she has "no obligation to plead and prove the law of the
Kingdom of Saudi Arabia since her cause of action is based on Articles 19 and 21" of
the Civil Code of the Philippines. In her Amended Complaint and subsequent
pleadings, she never alleged that Saudi law should govern this case.65 And as
correctly held by the respondent appellate court, "considering that it was the petitioner
who was invoking the applicability of the law of Saudi Arabia, then the burden was on
it [petitioner] to plead and to establish what the law of Saudi Arabia is". 66
Lastly, no error could be imputed to the respondent appellate court in upholding the
trial court's denial of defendant's (herein petitioner's) motion to dismiss the case. Not
only was jurisdiction in order and venue properly laid, but appeal after trial was
obviously available, and expeditious trial itself indicated by the nature of the case at
hand. Indubitably, the Philippines is the state intimately concerned with the ultimate
outcome of the case below, not just for the benefit of all the litigants, but also for the
vindication of the country's system of law and justice in a transnational setting. With
these guidelines in mind, the trial court must proceed to try and adjudge the case in
the light of relevant Philippine law, with due consideration of the foreign element or
elements involved. Nothing said herein, of course, should be construed as prejudging
the results of the case in any manner whatsoever.
WHEREFORE, the instant petition for certiorari is hereby DISMISSED. Civil Case No.
Q-93-18394 entitled "Milagros P. Morada vs. Saudi Arabia Airlines" is hereby
REMANDED to Regional Trial Court of Quezon City, Branch 89 for further
proceedings.
SO ORDERED.
Romulo, Mabanta, Sayoc, Buenaventura, De los Angeles Law Offices for BRII/AIBC.
Florante M. De Castro for private respondents in 105029-32.
The petition in G.R. Nos. 105029-32, entitled "Asia International Builders Corporation,
et. al., v. National Labor Relations Commission, et. al." was filed under Rule 65 of the
Revised Rules of Court:
(1) to reverse the Resolution dated September 2, 1991 of NLRC in
POEA Cases Nos. L-84-06-555, L-85-10-777, L-85-10-779 and
L-86-05-460, insofar as it granted the claims of 149 claimants; and
QUIASON, J.:
The petition in G.R. No. 104776, entitled "Bienvenido M. Cadalin, et. al. v. Philippine
Overseas Employment Administration's Administrator, et. al.," was filed under Rule 65
of the Revised Rules of Court:
(1) to modify the Resolution dated September 2, 1991 of the
National Labor Relations Commission (NLRC) in POEA Cases Nos.
L-84-06-555, L-85-10-777, L-85-10-779 and L-86-05-460; (2) to
render a new decision: (i) declaring private respondents as in
default; (ii) declaring the said labor cases as a class suit; (iii)
ordering Asia International Builders Corporation (AIBC) and Brown
and Root International Inc. (BRII) to pay the claims of the 1,767
claimants in said labor cases; (iv) declaring Atty. Florante M. de
Castro guilty of forum-shopping; and (v) dismissing POEA Case No.
L-86-05-460; and
(3) to reverse the Resolution dated March 24, 1992 of NLRC,
denying the motion for reconsideration of its Resolution dated
September 2, 1991 (Rollo, pp. 8-288).
The petition in G.R. Nos. 104911-14, entitled "Bienvenido M. Cadalin, et. al., v. Hon.
National Labor Relations Commission, et. al.," was filed under Rule 65 of the Revised
Rules of Court:
(1) to reverse the Resolution dated September 2, 1991 of NLRC in
POEA Cases Nos. L-84-06-555, L-85-10-777, L-85-10-799 and
L-86-05-460 insofar as it: (i) applied the three-year prescriptive
period under the Labor Code of the Philippines instead of the tenyear prescriptive period under the Civil Code of the Philippines; and
Florante de Castro filed another complaint for the same money claims and benefits in
behalf of several claimants, some of whom were also claimants in POEA Case No. L84-06-555 (POEA Case No. 85-10-779).
On October 19, 1984, claimants filed their "Compliance" with the Order dated October
2, 1984 and an "Urgent Manifestation," praying that the POEA direct the parties to
submit simultaneously their position papers after which the case would be deemed
submitted for decision. On the same day, AIBC asked for time to file its comment on
the "Compliance" and "Urgent Manifestation" of claimants. On November 6, 1984, it
filed a second motion for extension of time to file the comment.
On November 8, 1984, the POEA Administrator informed AIBC that its motion for
extension of time was granted.
On November 14, 1984, claimants filed an opposition to the motions for extension of
time and asked that AIBC and BRII be declared in default for failure to file their
answers.
On November 20, 1984, AIBC and BRII filed a "Comment" praying, among other
reliefs, that claimants should be ordered to amend their complaint.
On December 27, 1984, the POEA Administrator issued an order directing AIBC and
BRII to file their answers within ten days from receipt of the order.
On February 27, 1985, AIBC and BRII appealed to NLRC seeking the reversal of the
said order of the POEA Administrator. Claimants opposed the appeal, claiming that it
was dilatory and praying that AIBC and BRII be declared in default.
On July 13, 1984, the claimants submitted their "Compliance and Manifestation." On
July 23, 1984, AIBC filed a "Motion to Strike Out of the Records", the "Complaint" and
the "Compliance and Manifestation." On July 25, 1984, the claimants filed their
"Rejoinder and Comments," averring, among other matters, the failure of AIBC and
BRII to file their answers and to attend the pre-trial conference on July 25, 1984. The
claimants alleged that AIBC and BRII had waived their right to present evidence and
had defaulted by failing to file their answers and to attend the pre-trial conference.
On April 2, 1985, the original claimants filed an "Amended Complaint and/or Position
Paper" dated March 24, 1985, adding new demands: namely, the payment of
overtime pay, extra night work pay, annual leave differential pay, leave indemnity pay,
retirement and savings benefits and their share of forfeitures (G.R. No. 104776, Rollo,
pp. 14-16). On April 15, 1985, the POEA Administrator directed AIBC to file its answer
to the amended complaint (G.R. No. 104776, Rollo, p. 20).
On October 2, 1984, the POEA Administrator denied the "Motion to Strike Out of the
Records" filed by AIBC but required the claimants to correct the deficiencies in the
complaint pointed out in the order.
On May 28, 1985, claimants filed an "Urgent Motion for Summary Judgment." On the
same day, the POEA issued an order directing AIBC and BRII to file their answers to
the "Amended Complaint," otherwise, they would be deemed to have waived their
right to present evidence and the case would be resolved on the basis of
complainant's evidence.
On October 10, 1984, claimants asked for time within which to comply with the Order
of October 2, 1984 and filed an "Urgent Manifestation," praying that the POEA
Administrator direct the parties to submit simultaneously their position papers, after
which the case should be deemed submitted for decision. On the same day, Atty.
On June 5, 1985, AIBC countered with a "Motion to Dismiss as Improper Class Suit
and Motion for Bill of Particulars Re: Amended Complaint dated March 24, 1985."
Claimants opposed the motions.
On September 4, 1985, the POEA Administrator reiterated his directive to AIBC and
BRII to file their answers in POEA Case No. L-84-06-555.
On September 18, 1985, AIBC filed its second appeal to the NLRC, together with a
petition for the issuance of a writ of injunction. On September 19, 1985, NLRC
enjoined the POEA Administrator from hearing the labor cases and suspended the
period for the filing of the answers of AIBC and BRII.
On September 19, 1985, claimants asked the POEA Administrator to include
additional claimants in the case and to investigate alleged wrongdoings of BRII, AIBC
and their respective lawyers.
On October 10, 1985, Romeo Patag and two co-claimants filed a complaint (POEA
Case No. L-85-10-777) against AIBC and BRII with the POEA, demanding monetary
claims similar to those subject of POEA Case No. L-84-06-555. In the same month,
Solomon Reyes also filed his own complaint (POEA Case No. L-85-10-779) against
AIBC and BRII.
On October 17, 1985, the law firm of Florante M. de Castro & Associates asked for
the substitution of the original counsel of record and the cancellation of the special
powers of attorney given the original counsel.
On December 12, 1985, Atty. Del Mundo filed in NLRC a notice of the claim to
enforce attorney's lien.
On May 29, 1986, Atty. De Castro filed a complaint for money claims (POEA Case
No. 86-05-460) in behalf of 11 claimants including Bienvenido Cadalin, a claimant in
POEA Case No. 84-06-555.
On December 12, 1986, the NLRC dismissed the two appeals filed on February 27,
1985 and September 18, 1985 by AIBC and BRII.
In narrating the proceedings of the labor cases before the POEA Administrator, it is
not amiss to mention that two cases were filed in the Supreme Court by the
claimants, namely G.R. No. 72132 on September 26, 1985 and Administrative
Case No. 2858 on March 18, 1986. On May 13, 1987, the Supreme Court issued a
resolution in Administrative Case No. 2858 directing the POEA Administrator to
resolve the issues raised in the motions and oppositions filed in POEA Cases Nos. L84-06-555 and L-86-05-460 and to decide the labor cases with deliberate dispatch.
AIBC also filed a petition in the Supreme Court (G.R. No. 78489), questioning the
Order dated September 4, 1985 of the POEA Administrator. Said order required BRII
and AIBC to answer the amended complaint in POEA Case No. L-84-06-555. In a
resolution dated November 9, 1987, we dismissed the petition by informing AIBC that
all its technical objections may properly be resolved in the hearings before the POEA.
Complaints were also filed before the Ombudsman. The first was filed on September
22, 1988 by claimant Hermie Arguelles and 18 co-claimants against the POEA
Administrator and several NLRC Commissioners. The Ombudsman merely referred
the complaint to the Secretary of Labor and Employment with a request for the early
disposition of POEA Case No. L-84-06-555. The second was filed on April 28, 1989
by claimants Emigdio P. Bautista and Rolando R. Lobeta charging AIBC and BRII for
violation of labor and social legislations. The third was filed by Jose R. Santos,
Maximino N. Talibsao and Amado B. Bruce denouncing AIBC and BRII of violations of
labor laws.
On January 13, 1987, AIBC filed a motion for reconsideration of the NLRC Resolution
dated December 12, 1986.
On January 14, 1987, AIBC reiterated before the POEA Administrator its motion for
suspension of the period for filing an answer or motion for extension of time to file the
same until the resolution of its motion for reconsideration of the order of the NLRC
dismissing the two appeals. On April 28, 1987, NLRC en banc denied the motion for
reconsideration.
At the hearing on June 19, 1987, AIBC submitted its answer to the complaint. At the
same hearing, the parties were given a period of 15 days from said date within which
to submit their respective position papers. On June 24, 1987 claimants filed their
"Urgent Motion to Strike Out Answer," alleging that the answer was filed out of time.
On June 29, 1987, claimants filed their "Supplement to Urgent Manifestational
Motion" to comply with the POEA Order of June 19, 1987. On February 24, 1988,
AIBC and BRII submitted their position paper. On March 4, 1988, claimants filed their
"Ex-Parte Motion to Expunge from the Records" the position paper of AIBC and BRII,
claiming that it was filed out of time.
On September 1, 1988, the claimants represented by Atty. De Castro filed their
memorandum in POEA Case No. L-86-05-460. On September 6, 1988, AIBC and
BRII submitted their Supplemental Memorandum. On September 12, 1988, BRII filed
its "Reply to Complainant's Memorandum." On October 26, 1988, claimants submitted
their "Ex-Parte Manifestational Motion and Counter-Supplemental Motion," together
with 446 individual contracts of employments and service records. On October 27,
1988, AIBC and BRII filed a "Consolidated Reply."
On January 30, 1989, the POEA Administrator rendered his decision in POEA Case
No. L-84-06-555 and the other consolidated cases, which awarded the amount of
$824,652.44 in favor of only 324 complainants.
On February 10, 1989, claimants submitted their "Appeal Memorandum For Partial
Appeal" from the decision of the POEA. On the same day, AIBC also filed its motion
for reconsideration and/or appeal in addition to the "Notice of Appeal" filed earlier on
February 6, 1989 by another counsel for AIBC.
On February 17, 1989, claimants filed their "Answer to Appeal," praying for the
dismissal of the appeal of AIBC and BRII.
On March 15, 1989, claimants filed their "Supplement to Complainants' Appeal
Memorandum," together with their "newly discovered evidence" consisting of payroll
records.
On April 5, 1989, AIBC and BRII submitted to NLRC their "Manifestation," stating
among other matters that there were only 728 named claimants. On April 20, 1989,
the claimants filed their "Counter-Manifestation," alleging that there were 1,767 of
them.
On July 27, 1989, claimants filed their "Urgent Motion for Execution" of the Decision
dated January 30, 1989 on the grounds that BRII had failed to appeal on time and
AIBC had not posted the supersedeas bond in the amount of $824,652.44.
On December 23, 1989, claimants filed another motion to resolve the labor cases.
On August 21, 1990, claimants filed their "Manifestational Motion," praying that all the
1,767 claimants be awarded their monetary claims for failure of private respondents
to file their answers within the reglamentary period required by law.
On September 2, 1991, NLRC promulgated its Resolution, disposing as follows:
WHEREFORE, premises considered, the Decision of the POEA in
these consolidated cases is modified to the extent and in
accordance with the following dispositions:
1. The claims of the 94 complainants identified
and listed in Annex "A" hereof are dismissed for
having prescribed;
2. Respondents AIBC and Brown & Root are
hereby ordered, jointly and severally, to pay the
for certiorari with the Supreme Court (G.R. Nos. 120741-44). The petition was
dismissed in a resolution dated January 27, 1992.
Three motions for reconsideration of the September 2, 1991 Resolution of the NLRC
were filed. The first, by the claimants represented by Atty. Del Mundo; the second, by
the claimants represented by Atty. De Castro; and the third, by AIBC and BRII.
In its Resolution dated March 24, 1992, NLRC denied all the motions for
reconsideration.
Hence, these petitions filed by the claimants represented by Atty. Del Mundo (G.R.
No. 104776), the claimants represented by Atty. De Castro (G.R. Nos. 104911-14)
and by AIBC and BRII (G.R. Nos. 105029-32).
II
Compromise Agreements
Before this Court, the claimants represented by Atty. De Castro and AIBC and BRII
have submitted, from time to time, compromise agreements for our approval and
jointly moved for the dismissal of their respective petitions insofar as the claimantsparties to the compromise agreements were concerned (See Annex A for list of
claimants who signed quitclaims).
Thus the following manifestations that the parties had arrived at a compromise
agreement and the corresponding motions for the approval of the agreements were
filed by the parties and approved by the Court:
b) The hours of work shall be those set forth by the Employer, and
Employer may, at his sole option, change or adjust such hours as
maybe deemed necessary from time to time.
4. TERMINATION
a) Notwithstanding any other terms and conditions of this
agreement, the Employer may, at his sole discretion, terminate
employee's service with cause, under this agreement at any time. If
the Employer terminates the services of the Employee under this
Agreement because of the completion or termination, or
suspension of the work on which the Employee's services were
being utilized, or because of a reduction in force due to a decrease
in scope of such work, or by change in the type of construction of
such work. The Employer will be responsible for his return
transportation to his country of origin. Normally on the most
expeditious air route, economy class accommodation.
xxx xxx xxx
PART B
11. BONUS
A bonus of 20% (for offshore work) of gross income will be accrued
and payable only upon satisfactory completion of this contract.
12. OFFDAY PAY
The seventh day of the week shall be observed as a day of rest
with 8 hours regular pay. If work is performed on this day, all hours
work shall be paid at the premium rate. However, this offday pay
provision is applicable only when the laws of the Host Country
require payments for rest day.
In the State of Bahrain, where some of the individual complainants
were deployed, His Majesty Isa Bin Salman Al Kaifa, Amir of
Bahrain, issued his Amiri Decree No. 23 on June 16, 1976,
otherwise known as the Labour Law for the Private Sector
(Records, Vol. 18). This decree took effect on August 16, 1976.
Some of the provisions of Amiri Decree No. 23 that are relevant to
the claims of the complainants-appellants are as follows (italics
supplied only for emphasis):
Art. 79: . . . A worker shall receive payment for
each extra hour equivalent to his wage
entitlement increased by a minimum of twentyfive per centum thereof for hours worked during
the day; and by a minimum of fifty per centum
thereof for hours worked during the night which
shall be deemed to being from seven o'clock in
the evening until seven o'clock in the
morning. . . .
Art. 80: Friday shall be deemed to be a weekly
day of rest on full pay.
IV
The issues raised before and resolved by the NLRC were:
First: Whether or not complainants are entitled to the benefits
provided by Amiri Decree No. 23 of Bahrain;
(a) Whether or not the complainants who have
worked in Bahrain are entitled to the abovementioned benefits.
(b) Whether or not Art. 44 of the same Decree
(allegedly prescribing a more favorable treatment
of alien employees) bars complainants from
enjoying its benefits.
Second: Assuming that Amiri Decree No. 23 of Bahrain is
applicable in these cases, whether or not complainants' claim for
the benefits provided therein have prescribed.
Third: Whether or not the instant cases qualify as a class suit.
Fourth: Whether or not the proceedings conducted by the POEA,
as well as the decision that is the subject of these appeals,
conformed with the requirements of due process;
(a) Whether or not the respondent-appellant was
denied its right to due process;
NLRC, however, held that the Amiri Decree No. 23 applied only to the claimants, who
worked in Bahrain, and set aside awards of the POEA Administrator in favor of the
claimants, who worked elsewhere.
On the second issue, NLRC ruled that the prescriptive period for the filing of the
claims of the complainants was three years, as provided in Article 291 of the Labor
Code of the Philippines, and not ten years as provided in Article 1144 of the Civil
Code of the Philippines nor one year as provided in the Amiri Decree No. 23 of 1976.
On the third issue, NLRC agreed with the POEA Administrator that the labor cases
cannot be treated as a class suit for the simple reason that not all the complainants
worked in Bahrain and therefore, the subject matter of the action, the claims arising
from the Bahrain law, is not of common or general interest to all the complainants.
On the fourth issue, NLRC found at least three infractions of the cardinal rules of
administrative due process: namely, (1) the failure of the POEA Administrator to
consider the evidence presented by AIBC and BRII; (2) some findings of fact were not
supported by substantial evidence; and (3) some of the evidence upon which the
decision was based were not disclosed to AIBC and BRII during the hearing.
On the fifth issue, NLRC sustained the ruling of the POEA Administrator that BRII and
AIBC are solidarily liable for the claims of the complainants and held that BRII was
the actual employer of the complainants, or at the very least, the indirect employer,
with AIBC as the labor contractor.
NLRC also held that jurisdiction over BRII was acquired by the POEA Administrator
through the summons served on AIBC, its local agent.
On the sixth issue, NLRC held that the POEA Administrator was correct in denying
the Motion to Declare AIBC in default.
On the seventh issue, which involved other money claims not based on the Amiri
Decree No. 23, NLRC ruled:
(1) that the POEA Administrator has no jurisdiction over the claims
for refund of the SSS premiums and refund of withholding taxes
and the claimants should file their claims for said refund with the
appropriate government agencies;
(2) the claimants failed to establish that they are entitled to the
claims which are not based on the overseas employment contracts
nor the Amiri Decree No. 23 of 1976;
(3) that the POEA Administrator has no jurisdiction over claims for
moral and exemplary damages and nonetheless, the basis for
granting said damages was not established;
(3) the NLRC and POEA Administrator erred in not holding that the
labor cases filed by AIBC and BRII cannot be considered a class
suit;
(4) that the prescriptive period for the filing of the claims is ten
years; and
(5) that NLRC and the POEA Administrator should have dismissed
POEA Case No. L-86-05-460, the case filed by Atty. Florante de
Castro (Rollo, pp. 31-40).
AIBC and BRII, commenting on the petition in G.R. No. 104776, argued:
(1) that they were not responsible for the delay in the disposition of
the labor cases, considering the great difficulty of getting all the
records of the more than 1,500 claimants, the piece-meal filing of
the complaints and the addition of hundreds of new claimants by
petitioners;
(2) that considering the number of complaints and claimants, it was
impossible to prepare the answers within the ten-day period
provided in the NLRC Rules, that when the motion to declare AIBC
in default was filed on July 19, 1987, said party had already filed its
answer, and that considering the staggering amount of the claims
(more than US$50,000,000.00) and the complicated issues raised
by the parties, the ten-day rule to answer was not fair and
reasonable;
(3) that the claimants failed to refute NLRC's finding that
there was no common or general interest in the subject matter of
the controversy which was the applicability of the Amiri Decree
No. 23. Likewise, the nature of the claims varied, some being
based on salaries pertaining to the unexpired portion of the
contracts while others being for pure money claims. Each claimant
demanded separate claims peculiar only to himself and depending
upon the particular circumstances obtaining in his case;
(4) that the prescriptive period for filing the claims is that prescribed
by Article 291 of the Labor Code of the Philippines (three years)
and not the one prescribed by Article 1144 of the Civil Code of the
Philippines (ten years); and
(5) that they are not concerned with the issue of whether POEA
Case No. L-86-05-460 should be dismissed, this being a private
quarrel between the two labor lawyers (Rollo, pp. 292-305).
Attorney's Lien
On November 12, 1992, Atty. Gerardo A. del Mundo moved to strike out the joint
manifestations and motions of AIBC and BRII dated September 2 and 11, 1992,
claiming that all the claimants who entered into the compromise agreements subject
of said manifestations and motions were his clients and that Atty. Florante M. de
Castro had no right to represent them in said agreements. He also claimed that the
claimants were paid less than the award given them by NLRC; that Atty. De Castro
collected additional attorney's fees on top of the 25% which he was entitled to
receive; and that the consent of the claimants to the compromise agreements and
quitclaims were procured by fraud (G.R. No. 104776, Rollo, pp. 838-810). In the
Resolution dated November 23, 1992, the Court denied the motion to strike out the
Joint Manifestations and Motions dated September 2 and 11, 1992 (G.R. Nos.
104911-14, Rollo, pp. 608-609).
On December 14, 1992, Atty. Del Mundo filed a "Notice and Claim to Enforce
Attorney's Lien," alleging that the claimants who entered into compromise
agreements with AIBC and BRII with the assistance of Atty. De Castro, had all signed
a retainer agreement with his law firm (G.R. No. 104776, Rollo, pp. 623-624; 8381535).
The claimants in G.R. Nos. 104911-14 based their petition for certiorari on the
grounds that NLRC gravely abused its discretion when it: (1) applied the three-year
prescriptive period under the Labor Code of the Philippines; and (2) it denied the
claimant's formula based on an average overtime pay of three hours a day (Rollo, pp.
18-22).
The claimants argue that said method was proposed by BRII itself during the
negotiation for an amicable settlement of their money claims in Bahrain as shown in
the Memorandum dated April 16, 1983 of the Ministry of Labor of Bahrain (Rollo, pp.
21-22).
BRII and AIBC, in their Comment, reiterated their contention in G.R. No. 104776 that
the prescriptive period in the Labor Code of the Philippines, a special law, prevails
over that provided in the Civil Code of the Philippines, a general law.
As to the memorandum of the Ministry of Labor of Bahrain on the method of
computing the overtime pay, BRII and AIBC claimed that they were not bound by what
appeared therein, because such memorandum was proposed by a subordinate
Bahrain official and there was no showing that it was approved by the Bahrain
Minister of Labor. Likewise, they claimed that the averaging method was discussed in
the course of the negotiation for the amicable settlement of the dispute and any offer
made by a party therein could not be used as an admission by him (Rollo, pp. 228236).
G.R. Nos. 105029-32
Contempt of Court
On February 18, 1993, an omnibus motion was filed by Atty. Del Mundo to cite Atty.
De Castro and Atty. Katz Tierra for contempt of court and for violation of Canons 1, 15
and 16 of the Code of Professional Responsibility. The said lawyers allegedly misled
this Court, by making it appear that the claimants who entered into the compromise
agreements were represented by Atty. De Castro, when in fact they were represented
by Atty. Del Mundo (G.R. No. 104776, Rollo, pp. 1560-1614).
On September 23, 1994, Atty. Del Mundo reiterated his charges against Atty. De
Castro for unethical practices and moved for the voiding of the quitclaims submitted
by some of the claimants.
In G.R. Nos. 105029-32, BRII and AIBC claim that NLRC gravely abused its
discretion when it: (1) enforced the provisions of the Amiri Decree No. 23 of 1976 and
not the terms of the employment contracts; (2) granted claims for holiday, overtime
and leave indemnity pay and other benefits, on evidence admitted in contravention of
petitioner's constitutional right to due process; and (3) ordered the POEA
Administrator to hold new hearings for the 683 claimants whose claims had been
dismissed for lack of proof by the POEA Administrator or NLRC itself. Lastly, they
allege that assuming that the Amiri Decree No. 23 of 1976 was applicable, NLRC
erred when it did not apply the one-year prescription provided in said law (Rollo, pp.
29-30).
VI
To the POEA Administrator, the prescriptive period was ten years, applying Article
1144 of the Civil Code of the Philippines. NLRC believed otherwise, fixing the
prescriptive period at three years as provided in Article 291 of the Labor Code of the
Philippines.
The claimants in G.R. No. 104776 and G.R. Nos. 104911-14, invoking different
grounds, insisted that NLRC erred in ruling that the prescriptive period applicable to
the claims was three years, instead of ten years, as found by the POEA Administrator.
The Solicitor General expressed his personal view that the prescriptive period was
one year as prescribed by the Amiri Decree No. 23 of 1976 but he deferred to the
ruling of NLRC that Article 291 of the Labor Code of the Philippines was the operative
law.
The POEA Administrator held the view that:
These money claims (under Article 291 of the Labor Code) refer to
those arising from the employer's violation of the employee's right
as provided by the Labor Code.
In the instant case, what the respondents violated are not the rights
of the workers as provided by the Labor Code, but the provisions of
the Amiri Decree No. 23 issued in Bahrain, which ipso
factoamended the worker's contracts of employment. Respondents
consciously failed to conform to these provisions which specifically
provide for the increase of the worker's rate. It was only after June
30, 1983, four months after the brown builders brought a suit
against B & R in Bahrain for this same claim, when respondent
AIBC's contracts have undergone amendments in Bahrain for the
new hires/renewals (Respondent's Exhibit 7).
Hence, premises considered, the applicable law of prescription to
this instant case is Article 1144 of the Civil Code of the Philippines,
which provides:
Art. 1144. The following actions may be brought
within ten years from the time the cause of action
accrues:
(1) Upon a written contract;
(2) Upon an obligation created by law;
whether that was the purpose this test is the most satisfactory one.
It does not lead American courts into the necessity of examining
into the unfamiliar peculiarities and refinements of different foreign
legal systems. . .
AIBC and BRII, insisting that the actions on the claims have prescribed under the
Amiri Decree No. 23 of 1976, argue that there is in force in the Philippines a
"borrowing law," which is Section 48 of the Code of Civil Procedure and that where
such kind of law exists, it takes precedence over the common-law conflicts rule (G.R.
No. 104776,Rollo, pp. 45-46).
The following actions must be brought within ten years from the
time the right of action accrues:
(1) Upon a written contract;
Section 48 has not been repealed or amended by the Civil Code of the Philippines.
Article 2270 of said Code repealed only those provisions of the Code of Civil
Procedures as to which were inconsistent with it. There is no provision in the Civil
Code of the Philippines, which is inconsistent with or contradictory to Section 48 of
the Code of Civil Procedure (Paras, Philippine Conflict of Laws 104 [7th ed.]).
In the light of the 1987 Constitution, however, Section 48 cannot be enforced ex
proprio vigore insofar as it ordains the application in this jurisdiction of Section 156 of
the Amiri Decree No. 23 of 1976.
The courts of the forum will not enforce any foreign claim obnoxious to the forum's
public policy (Canadian Northern Railway Co. v. Eggen, 252 U.S. 553, 40 S. Ct. 402,
64 L. ed. 713 [1920]). To enforce the one-year prescriptive period of the Amiri Decree
No. 23 of 1976 as regards the claims in question would contravene the public policy
on the protection to labor.
In the Declaration of Principles and State Policies, the 1987 Constitution emphasized
that:
The state shall promote social justice in all phases of national
development. (Sec. 10).
The state affirms labor as a primary social economic force. It shall
protect the rights of workers and promote their welfare (Sec. 18).
In article XIII on Social Justice and Human Rights, the 1987 Constitution provides:
Sec. 3. The State shall afford full protection to labor, local and
overseas, organized and unorganized, and promote full
employment and equality of employment opportunities for all.
Having determined that the applicable law on prescription is the Philippine law, the
next question is whether the prescriptive period governing the filing of the claims is
three years, as provided by the Labor Code or ten years, as provided by the Civil
Code of the Philippines.
The claimants are of the view that the applicable provision is Article 1144 of the Civil
Code of the Philippines, which provides:
civil and administrative cases, and in all proceedings, including judicial and quasijudicial hearings. Hence, under the Constitution, any party to a case may demand
expeditious action on all officials who are tasked with the administration of justice.
However, as held in Caballero v. Alfonso, Jr., 153 SCRA 153 (1987), "speedy
disposition of cases" is a relative term. Just like the constitutional guarantee of
"speedy trial" accorded to the accused in all criminal proceedings, "speedy disposition
of cases" is a flexible concept. It is consistent with delays and depends upon the
circumstances of each case. What the Constitution prohibits are unreasonable,
arbitrary and oppressive delays which render rights nugatory.
Caballero laid down the factors that may be taken into consideration in determining
whether or not the right to a "speedy disposition of cases" has been violated, thus:
In the determination of whether or not the right to a "speedy trial"
has been violated, certain factors may be considered and balanced
against each other. These are length of delay, reason for the delay,
assertion of the right or failure to assert it, and prejudice caused by
the delay. The same factors may also be considered in answering
judicial inquiry whether or not a person officially charged with the
administration of justice has violated the speedy disposition of
cases.
Likewise, in Gonzales v. Sandiganbayan, 199 SCRA 298, (1991), we held:
It must be here emphasized that the right to a speedy disposition of
a case, like the right to speedy trial, is deemed violated only when
the proceeding is attended by vexatious, capricious, and
oppressive delays; or when unjustified postponements of the trial
are asked for and secured, or when without cause or justified
motive a long period of time is allowed to elapse without the party
having his case tried.
Since July 25, 1984 or a month after AIBC and BRII were served with a copy of the
amended complaint, claimants had been asking that AIBC and BRII be declared in
default for failure to file their answers within the ten-day period provided in Section 1,
Rule III of Book VI of the Rules and Regulations of the POEA. At that time, there was
a pending motion of AIBC and BRII to strike out of the records the amended
complaint and the "Compliance" of claimants to the order of the POEA, requiring them
to submit a bill of particulars.
The cases at bench are not of the run-of-the-mill variety, such that their final
disposition in the administrative level after seven years from their inception, cannot be
NLRC and the POEA Administrator are correct in their stance that inasmuch as the
first requirement of a class suit is not present (common or general interest based on
the Amiri Decree of the State of Bahrain), it is only logical that only those who worked
in Bahrain shall be entitled to file their claims in a class suit.
Adding to the confusion in the proceedings before NLRC, is the listing of some of the
complainants in both petitions filed by the two lawyers. As noted by NLRC, "the
problem created by this situation is that if one of the two petitions is dismissed, then
the parties and the public respondents would not know which claim of which petitioner
was dismissed and which was not."
The Court is extra-cautious in allowing class suits because they are the exceptions to
the condition sine qua non, requiring the joinder of all indispensable parties.
B. Claimants insist that all their claims could properly be consolidated in a "class suit"
because "all the named complainants have similar money claims and similar rights
sought irrespective of whether they worked in Bahrain, United Arab Emirates or in
Abu Dhabi, Libya or in any part of the Middle East" (Rollo, pp. 35-38).
A class suit is proper where the subject matter of the controversy is one of common or
general interest to many and the parties are so numerous that it is impracticable to
bring them all before the court (Revised Rules of Court, Rule 3, Sec. 12).
While all the claims are for benefits granted under the Bahrain Law, many of the
claimants worked outside Bahrain. Some of the claimants were deployed in Indonesia
and Malaysia under different terms and conditions of employment.
While there are common defendants (AIBC and BRII) and the nature of the claims is
the same (for employee's benefits), there is no common question of law or fact. While
some claims are based on the Amiri Law of Bahrain, many of the claimants never
worked in that country, but were deployed elsewhere. Thus, each claimant is
interested only in his own demand and not in the claims of the other employees of
defendants. The named claimants have a special or particular interest in specific
benefits completely different from the benefits in which the other named claimants
and those included as members of a "class" are claiming (Berses v. Villanueva, 25
Phil. 473 [1913]). It appears that each claimant is only interested in collecting his own
claims. A claimants has no concern in protecting the interests of the other claimants
as shown by the fact, that hundreds of them have abandoned their co-claimants and
have entered into separate compromise settlements of their respective claims. A
principle basic to the concept of "class suit" is that plaintiffs brought on the record
must fairly represent and protect the interests of the others (Dimayuga v. Court of
Industrial Relations, 101 Phil. 590 [1957]). For this matter, the claimants who worked
in Bahrain can not be allowed to sue in a class suit in a judicial proceeding. The most
that can be accorded to them under the Rules of Court is to be allowed to join as
plaintiffs in one complaint (Revised Rules of Court, Rule 3, Sec. 6).
Filing of Petitioners and Complainants." The first sentence of the circular expressly
states that said circular applies to an governs the filing of petitions in the Supreme
Court and the Court of Appeals.
While Administrative Circular No. 04-94 extended the application of the anti-forum
shopping rule to the lower courts and administrative agencies, said circular took effect
only on April 1, 1994.
POEA and NLRC could not have entertained the complaint for unethical conduct
against Atty. De Castro because NLRC and POEA have no jurisdiction to investigate
charges of unethical conduct of lawyers.
Attorney's Lien
The "Notice and Claim to Enforce Attorney's Lien" dated December 14, 1992 was filed
by Atty. Gerardo A. Del Mundo to protect his claim for attorney's fees for legal
services rendered in favor of the claimants (G.R. No. 104776,Rollo, pp. 841-844).
A statement of a claim for a charging lien shall be filed with the court or administrative
agency which renders and executes the money judgment secured by the lawyer for
his clients. The lawyer shall cause written notice thereof to be delivered to his clients
and to the adverse party (Revised Rules of Court, Rule 138, Sec. 37). The statement
of the claim for the charging lien of Atty. Del Mundo should have been filed with the
administrative agency that rendered and executed the judgment.
Contempt of Court
The complaint of Atty. Gerardo A. Del Mundo to cite Atty. Florante De Castro and Atty.
Katz Tierra for violation of the Code of Professional Responsibility should be filed in a
separate and appropriate proceeding.
G.R. No. 104911-14
Claimants charge NLRC with grave abuse of discretion in not accepting their formula
of "Three Hours Average Daily Overtime" in computing the overtime payments. They
claim that it was BRII itself which proposed the formula during the negotiations for the
settlement of their claims in Bahrain and therefore it is in estoppel to disclaim said
offer (Rollo, pp. 21-22).
Claimants presented a Memorandum of the Ministry of Labor of Bahrain dated April
16, 1983, which in pertinent part states:
After the perusal of the memorandum of the Vice President and the
Area Manager, Middle East, of Brown & Root Co. and the Summary
of the compensation offered by the Company to the employees in
respect of the difference of pay of the wages of the overtime and
the difference of vacation leave and the perusal of the documents
attached thereto i.e., minutes of the meetings between the
Representative of the employees and the management of the
Company, the complaint filed by the employees on 14/2/83 where
they have claimed as hereinabove stated, sample of the Service
Contract executed between one of the employees and the company
through its agent in (sic) Philippines, Asia International Builders
Corporation where it has been provided for 48 hours of work per
week and an annual leave of 12 days and an overtime wage of 1 &
1/4 of the normal hourly wage.
xxx xxx xxx
The Company in its computation reached the following averages:
A. 1. The average duration of the actual service of the employee is
35 months for the Philippino (sic) employees . . . .
2. The average wage per hour for the Philippino (sic) employee is
US$2.69 . . . .
3. The average hours for the overtime is 3 hours plus in all public
holidays and weekends.
4. Payment of US$8.72 per months (sic) of service as
compensation for the difference of the wages of the overtime done
for each Philippino (sic) employee . . . (Rollo, p.22).
BRII and AIBC countered: (1) that the Memorandum was not prepared by them but by
a subordinate official in the Bahrain Department of Labor; (2) that there was no
showing that the Bahrain Minister of Labor had approved said memorandum; and (3)
that the offer was made in the course of the negotiation for an amicable settlement of
the claims and therefore it was not admissible in evidence to prove that anything is
due to the claimants.
While said document was presented to the POEA without observing the rule on
presenting official documents of a foreign government as provided in Section 24, Rule
132 of the 1989 Revised Rules on Evidence, it can be admitted in evidence in
proceedings before an administrative body. The opposing parties have a copy of the
said memorandum, and they could easily verify its authenticity and accuracy.
differential, annual-leave differential and leave indemnity pay to the claimants listed in
Annex B of the Resolution. At first, NLRC reversed the resolution of the POEA
Administrator granting these benefits on a finding that the POEA Administrator failed
to consider the evidence presented by AIBC and BRII, that some findings of fact of
the POEA Administrator were not supported by the evidence, and that some of the
evidence were not disclosed to AIBC and BRII (Rollo, pp. 35-36; 106-107). But
instead of remanding the case to the POEA Administrator for a new hearing, which
means further delay in the termination of the case, NLRC decided to pass upon the
validity of the claims itself. It is this procedure that AIBC and BRII complain of as
being irregular and a "reversible error."
They pointed out that NLRC took into consideration evidence submitted on appeal,
the same evidence which NLRC found to have been "unilaterally submitted by the
claimants and not disclosed to the adverse parties" (Rollo, pp. 37-39).
NLRC noted that so many pieces of evidentiary matters were submitted to the POEA
administrator by the claimants after the cases were deemed submitted for resolution
and which were taken cognizance of by the POEA Administrator in resolving the
cases. While AIBC and BRII had no opportunity to refute said evidence of the
claimants before the POEA Administrator, they had all the opportunity to rebut said
evidence and to present their
counter-evidence before NLRC. As a matter of fact, AIBC and BRII themselves were
able to present before NLRC additional evidence which they failed to present before
the POEA Administrator.
Under Article 221 of the Labor Code of the Philippines, NLRC is enjoined to "use
every and all reasonable means to ascertain the facts in each case speedily and
objectively and without regard to technicalities of law or procedure, all in the interest
of due process."
In deciding to resolve the validity of certain claims on the basis of the evidence of
both parties submitted before the POEA Administrator and NLRC, the latter
considered that it was not expedient to remand the cases to the POEA Administrator
for that would only prolong the already protracted legal controversies.
Even the Supreme Court has decided appealed cases on the merits instead of
remanding them to the trial court for the reception of evidence, where the same can
be readily determined from the uncontroverted facts on record (Development Bank of
the Philippines v. Intermediate Appellate Court, 190 SCRA 653 [1990]; Pagdonsalan
v. National Labor Relations Commission, 127 SCRA 463 [1984]).
C. AIBC and BRII charge NLRC with grave abuse of discretion when it ordered the
POEA Administrator to hold new hearings for 683 claimants listed in Annex D of the
Resolution dated September 2, 1991 whose claims had been denied by the POEA
Administrator "for lack of proof" and for 69 claimants listed in Annex E of the same
Resolution, whose claims had been found by NLRC itself as not "supported by
evidence" (Rollo, pp. 41-45).
NLRC based its ruling on Article 218(c) of the Labor Code of the Philippines, which
empowers it "[to] conduct investigation for the determination of a question, matter or
controversy, within its jurisdiction, . . . ."
It is the posture of AIBC and BRII that NLRC has no authority under Article 218(c) to
remand a case involving claims which had already been dismissed because such
provision contemplates only situations where there is still a question or controversy to
be resolved (Rollo, pp. 41-42).
A principle well embedded in Administrative Law is that the technical rules of
procedure and evidence do not apply to the proceedings conducted by administrative
agencies (First Asian Transport & Shipping Agency, Inc. v. Ople, 142 SCRA 542
[1986]; Asiaworld Publishing House, Inc. v. Ople, 152 SCRA 219 [1987]). This
principle is enshrined in Article 221 of the Labor Code of the Philippines and is now
the bedrock of proceedings before NLRC.
Notwithstanding the non-applicability of technical rules of procedure and evidence in
administrative proceedings, there are cardinal rules which must be observed by the
hearing officers in order to comply with the due process requirements of the
Constitution. These cardinal rules are collated in Ang Tibay v. Court of Industrial
Relations, 69 Phil. 635 (1940).
VIII
The three petitions were filed under Rule 65 of the Revised Rules of Court on the
grounds that NLRC had committed grave abuse of discretion amounting to lack of
jurisdiction in issuing the questioned orders. We find no such abuse of discretion.
WHEREFORE, all the three petitions are DISMISSED.
SO ORDERED.
Padilla, Davide, Jr., Bellosillo and Kapunan, JJ., concur.
THIRD DIVISION
KAZUHIRO HASEGAWA and NIPPON ENGINEERING
CONSULTANTS CO., LTD.,
Petitioners,
- versus -
MINORU KITAMURA,
Promulgated:
Respondent.
November 23, 2007
x------------------------------------------------------------------------------------x
DECISION
NACHURA, J.:
On February 28, 2000, petitioner Kazuhiro Hasegawa, Nippon's general manager for
its International Division, informed respondent that the company had no more
intention of automatically renewing his ICA. His services would be engaged by the
company only up to the substantial completion of the STAR Project onMarch 31,
2000, just in time for the ICA's expiry.[9]
Threatened with impending unemployment, respondent, through his lawyer,
requested a negotiation conference and demanded that he be assigned to the BBRI
project. Nippon insisted that respondents contract was for a fixed term that had
already expired, and refused to negotiate for the renewal of the ICA.[10]
As he was not able to generate a positive response from the petitioners, respondent
consequently initiated on June 1, 2000 Civil Case No. 00-0264 for specific
performance and damages with the Regional Trial Court of Lipa City.[11]
For their part, petitioners, contending that the ICA had been perfected in Japan and
executed by and between Japanese nationals, moved to dismiss the complaint for
lack of jurisdiction. They asserted that the claim for improper pre-termination of
respondent's ICA could only be heard and ventilated in the proper courts
ofJapan following the principles of lex loci celebrationis and lex contractus.[12]
Before the Court is a petition for review on certiorari under Rule 45 of the Rules of
Court assailing the April 18, 2001 Decision[1] of the Court of Appeals (CA) in CA-G.R.
SP No. 60827, and the July 25, 2001 Resolution [2] denying the motion for
reconsideration thereof.
In the meantime, on June 20, 2000, the DPWH approved Nippon's request for the
replacement of Kitamura by a certain Y. Kotake as project manager of the BBRI
Project.[13]
On March 30, 1999, petitioner Nippon Engineering Consultants Co., Ltd. (Nippon), a
Japanese consultancy firm providing technical and management support in the
infrastructure projects of foreign governments, [3] entered into an Independent
Contractor Agreement (ICA) with respondent Minoru Kitamura, a Japanese national
permanently residing in the Philippines.[4] The agreement provides that respondent
was to extend professional services to Nippon for a year starting onApril 1, 1999.
[5]
Nippon then assigned respondent to work as the project manager of the Southern
Tagalog Access Road (STAR) Project in the Philippines, following the company's
consultancy contract with the Philippine Government.[6]
On June 29, 2000, the RTC, invoking our ruling in Insular Government v. Frank[14] that
matters connected with the performance of contracts are regulated by the law
prevailing at the place of performance,[15] denied the motion to dismiss. [16] The trial
court subsequently denied petitioners' motion for reconsideration, [17] prompting them
to file with the appellate court, on August 14, 2000, their first Petition
for Certiorari under Rule 65 [docketed as CA-G.R. SP No. 60205]. [18] On August 23,
2000, the CA resolved to dismiss the petition on procedural groundsfor lack of
statement of material dates and for insufficient verification and certification against
forum shopping.[19] An Entry of Judgment was later issued by the appellate court
on September 20, 2000.[20]
When the STAR Project was near completion, the Department of Public Works and
Highways (DPWH) engaged the consultancy services of Nippon, on January 28,
2000, this time for the detailed engineering and construction supervision of the
Aggrieved by this development, petitioners filed with the CA, on September 19, 2000,
still within the reglementary period, a second Petition for Certiorari under Rule 65
already stating therein the material dates and attaching thereto the proper verification
and certification. This second petition, which substantially raised the same issues as
those in the first, was docketed as CA-G.R. SP No. 60827.[21]
No. 60827 (fundamentally raising the same issues as those in the first one) and the
instant petition for review thereof.
Ruling on the merits of the second petition, the appellate court rendered the
assailed April 18, 2001 Decision[22] finding no grave abuse of discretion in the trial
court's denial of the motion to dismiss. The CA ruled, among others, that the principle
of lex loci celebrationis was not applicable to the case, because nowhere in the
pleadings was the validity of the written agreement put in issue. The CA thus declared
that the trial court was correct in applying instead the principle of lex loci solutionis.[23]
We do not agree. When the CA dismissed CA-G.R. SP No. 60205 on account of the
petition's defective certification of non-forum shopping, it was a dismissal without
prejudice.[27] The same holds true in the CA's dismissal of the said case due to
defects in the formal requirement of verification[28] and in the other requirement in
Rule 46 of the Rules of Court on the statement of the material dates. [29] The dismissal
being without prejudice, petitioners can re-file the petition, or file a second petition
attaching thereto the appropriate verification and certificationas they, in fact didand
stating therein the material dates, within the prescribed period [30] in Section 4, Rule 65
of the said Rules.[31]
The dismissal of a case without prejudice signifies the absence of a decision on the
merits and leaves the parties free to litigate the matter in a subsequent action as
though the dismissed action had not been commenced. In other words, the
termination of a case not on the merits does not bar another action involving the
same parties, on the same subject matter and theory.[32]
Necessarily, because the said dismissal is without prejudice and has no res
judicata effect, and even if petitioners still indicated in the verification and certification
of the second certiorari petition that the first had already been dismissed on
procedural grounds,[33] petitioners are no longer required by the Rules to indicate in
their certification of non-forum shopping in the instant petition for review of the
second certiorari petition, the status of the aforesaid first petition before the CA. In
any case, an omission in the certificate of non-forum shopping about any event that
will not constitute res judicata and litis pendentia, as in the present case, is not a fatal
defect. It will not warrant the dismissal and nullification of the entire proceedings,
The pivotal question that this Court is called upon to resolve is whether the subject
matter jurisdiction of Philippine courts in civil cases for specific performance and
damages involving contracts executed outside the country by foreign nationals may
be assailed on the principles of lex loci celebrationis, lex contractus, the state of the
most significant relationship rule, or forum non conveniens.
However, before ruling on this issue, we must first dispose of the procedural matters
raised by the respondent.
Kitamura contends that the finality of the appellate court's decision in CA-G.R. SP No.
60205 has already barred the filing of the second petition docketed as CA-G.R. SP
considering that the evils sought to be prevented by the said certificate are no longer
present.[34]
The Court also finds no merit in respondent's contention that petitioner Hasegawa is
only authorized to verify and certify, on behalf of Nippon, the certioraripetition filed
with the CA and not the instant petition. True, the Authorization[35] dated September 4,
2000, which is attached to the second certiorari petition and which is also attached to
the instant petition for review, is limited in scopeits wordings indicate that Hasegawa
is given the authority to sign for and act on behalf of the company only in the petition
filed with the appellate court, and that authority cannot extend to the instant petition
for review.[36] In a plethora of cases, however, this Court has liberally applied the
language. Thus, petitioners posit that local courts have no substantial relationship to
subsequent fulfillment of the requirements have been made. [37] Given that petitioners
the parties[46] following the [state of the] most significant relationship rule in Private
herein sufficiently explained their misgivings on this point and appended to their
International Law.[47]
The Court notes that petitioners adopted an additional but different theory when they
elevated the case to the appellate court. In the Motion to Dismiss[48] filed with the trial
However, the Court cannot extend the same liberal treatment to the defect in the
court, petitioners never contended that the RTC is an inconvenient forum. They
merely argued that the applicable law which will determine the validity or invalidity of
Hasegawa is truly not authorized to act on behalf of Nippon in this case. The
respondent's
claim
is
that
of Japan,
[49]
following
the
principles
of lex
loci
aforesaid September 4, 2000 Authorization and even the subsequent August 17, 2001
Authorization were issued only by Nippon's president and chief executive officer, not
before the appellate court, petitioners on certiorari significantly invoked the defense
by the company's board of directors. In not a few cases, we have ruled that corporate
of forum non conveniens.[50] On petition for review before this Court, petitioners
powers are exercised by the board of directors; thus, no person, not even its officers,
dropped their other arguments, maintained the forum non conveniens defense, and
can bind the corporation, in the absence of authority from the board.[40] Considering
introduced their new argument that the applicable principle is the [state of the] most
that Hasegawa verified and certified the petition only on his behalf and not on behalf
of the other petitioner, the petition has to be denied pursuant to Loquias v. Office of
the Ombudsman.[41] Substantial compliance will not suffice in a matter that demands
Be that as it may, this Court is not inclined to deny this petition merely on the basis of
strict observance of the Rules.[42] While technical rules of procedure are designed not
to frustrate the ends of justice, nonetheless, they are intended to effect the proper and
orderly disposition of cases and effectively prevent the clogging of court dockets.
[43]
Further, the Court has observed that petitioners incorrectly filed a Rule 65 petition to
question the trial court's denial of their motion to dismiss. It is a well-established rule
that
judgments. Corresponding to these phases are the following questions: (1) Where
an
order
denying
a motion to dismiss
is
interlocutory,
and cannot be the subject of the extraordinary petition for certiorari or mandamus.
can or should litigation be initiated? (2) Which law will the court apply? and (3) Where
Analytically, jurisdiction and choice of law are two distinct concepts. [54] Jurisdiction
recognized exceptions to this rule,[45] petitioners' case does not fall among them.
considers whether it is fair to cause a defendant to travel to this state; choice of law
asks the further question whether the application of a substantive law which will
determine the merits of the case is fair to both parties. The power to exercise
jurisdiction does not automatically give a state constitutional authority to apply forum
Asserting that the RTC of Lipa City is an inconvenient forum, petitioners question its
law. While jurisdiction and the choice of the lex fori will often coincide, the minimum
jurisdiction to hear and resolve the civil case for specific performance and damages
contacts for one do not always provide the necessary significant contacts for the
filed by the respondent. The ICA subject of the litigation was entered into and
other.[55] The question of whether the law of a state can be applied to a transaction is
perfected in Tokyo, Japan, by Japanese nationals, and written wholly in the Japanese
different from the question of whether the courts of that state have jurisdiction to enter
determine which state has the most substantial connection to the occurrence and the
a judgment.[56]
parties. In a case involving a contract, the court should consider where the contract
was made, was negotiated, was to be performed, and the domicile, place of business,
In this case, only the first phase is at issuejurisdiction. Jurisdiction, however, has
or place of incorporation of the parties.[68] This rule takes into account several contacts
various aspects. For a court to validly exercise its power to adjudicate a controversy,
and evaluates them according to their relative importance with respect to the
it must have jurisdiction over the plaintiff or the petitioner, over the defendant or the
respondent, over the subject matter, over the issues of the case and, in cases
involving property, over the res or the thing which is the subject of the litigation. [57] In
Since these three principles in conflict of laws make reference to the law applicable to
assailing the trial court's jurisdiction herein, petitioners are actually referring to subject
a dispute, they are rules proper for the second phase, the choice of law.[70]They
matter jurisdiction.
choice-of-law rules are not only inapplicable but also not yet called for.
sovereign authority which establishes and organizes the court. It is given only by law
and in the manner prescribed by law.[58] It is further determined by the allegations of
the complaint irrespective of whether the plaintiff is entitled to all or some of the
that they have not yet pointed out any conflict between the laws of Japanand ours.
[59]
Before determining which law should apply, first there should exist a conflict of laws
[60]
situation requiring the application of the conflict of laws rules. [72] Also, when the law of
the court or tribunal cannot act on the matter submitted to it because no law grants it
a foreign country is invoked to provide the proper rules for the solution of a case, the
[61]
In the instant case, petitioners, in their motion to dismiss, do not claim that the trial
It should be noted that when a conflicts case, one involving a foreign element, is
court is not properly vested by law with jurisdiction to hear the subject controversy for,
brought before a court or administrative agency, there are three alternatives open to
indeed, Civil Case No. 00-0264 for specific performance and damages is one not
the latter in disposing of it: (1) dismiss the case, either because of lack of jurisdiction
capable of pecuniary estimation and is properly cognizable by the RTC of Lipa City.
or refusal to assume jurisdiction over the case; (2) assume jurisdiction over the case
[62]
What they rather raise as grounds to question subject matter jurisdiction are the
and apply the internal law of the forum; or (3) assume jurisdiction over the case and
principles of lex loci celebrationis and lex contractus,and the state of the most
take into account or apply the law of some other State or States. [74] The courts power
to hear cases and controversies is derived from the Constitution and the laws. While it
may choose to recognize laws of foreign nations, the court is not limited by foreign
sovereign law short of treaties or other formal agreements, even in matters regarding
Lex loci celebrationis relates to the law of the place of the ceremony [63] or the law of
the place where a contract is made.[64] The doctrine of lex contractus orlex loci
contractus means the law of the place where a contract is executed or to be
performed.[65] It controls the nature, construction, and validity of the contract [66] and it
may pertain to the law voluntarily agreed upon by the parties or the law intended by
them either expressly or implicitly.[67] Under the state of the most significant
relationship rule, to ascertain what state law to apply to a dispute, the court should
Neither can the other ground raised, forum non conveniens,[76] be used to
deprive the trial court of its jurisdiction herein. First, it is not a proper basis for a
motion to dismiss because Section 1, Rule 16 of the Rules of Court does not include
it as a ground.[77] Second, whether a suit should be entertained or dismissed on the
basis of the said doctrine depends largely upon the facts of the particular case and is
addressed to the sound discretion of the trial court.[78] In this case, the RTC decided to
assume jurisdiction. Third, the propriety of dismissing a case based on this principle
requires a factual determination; hence, this conflicts principle is more properly
considered a matter of defense.[79]
Accordingly, since the RTC is vested by law with the power to entertain and hear the
civil case filed by respondent and the grounds raised by petitioners to assail that
jurisdiction are inappropriate, the trial and appellate courts correctly denied the
petitioners motion to dismiss.
WHEREFORE, premises
on certiorari is DENIED.
SO ORDERED.
considered,
the
petition
for
review