Professional Documents
Culture Documents
ABSTRACT
INTRODUCTION
TABLE 1
CLEAN-UP RESULTS AFTER SCON TREATMENT
Qg
(MMscfd)
Cumulative
Liquid (bbl)
Sand
37
0,9
6,3
Free
114,5
45
1,3
17,9
Free
20/64
114
45
1,8
20,7
Free
22/64
112,8
47
3,7
20,9
Free
WHFP
WHFT
Choke
(in)
(bar)
(C)
8/64
115,2
18/64
Figure 1 - Peciko Field Geological Markers illustrates 2 main intervals, Tunu Main Zone (MZ) and Shallow
(Sh). Shallow intervals made of two sub-intervals, Very Shallow (above Beta marker) and Fresh
Water Sands (between Beta marker and top Upper reservoirs layer 0a or flooding surface FS5).
Upper and Main Zone starts from Maximum Flooding (MF) 6 down to MF9. Upper and Shallow
are unconsolidated sands and Tunu Main Zone are consolidated sands.
Figure 2 - Sand Consolidation bonds the formation sand grains artificially into a consolidated mass. The resin
coats the sand grains and then hardens to hold sand in place (Total Techno Hub April 2011, page
32).
Figure 3 - Resin sand consolidation processes into the porous media (William and Joe 2003)
Figure 4 - Reservoir properties of the SCON pilot test. Good productivity with unconsolidated sand, therefore
the risk of sand production.
Figure 5 - Laboratory Test example during SCON design phase to adjust chemical composition for each
reservoir characteristics, (Left) Resin component before mixed, (Right) Resin after mixed and
cured.
Figure 6 - Equipment Schematic for Resin Injection Skid and CO2 Blanketing System. Transferred via
Transfer Tank to Tank A/B, SCON Chemical then mixed on the static mixer. CO2 blanketing
system was applied to reduce fire risk during transfer, mixing and pumping as the chemical is
flammable. The chemical is then injected into the well using High Pressure Pump through Coiled
Tubing Unit.
Figure 7 - Injection Chart during Resin Injection. Treating pressure indicates pumping pressure during the
job with maximum SCON chemical rate injection deduced from injectivity test prior to the job
execution.
Figure 8 - Production Performance of pilot SCON shows that the well can be produced in stable gas rate
between 2-3 MMscfd without sand production.
Figure 9 - Sand Monitoring after SCON Treatment. (Top) Average sand rate from Portable Acoustic Sand
Detection (ASD) illustrates no sand produced or low sand rate after SCON job. At the end of 2014
and with increasing of water production, sand rate showed a slight increase and reached 0.03 gr/s;
(Bottom) Visual choke inspection shows no trace of sand or no physical erosion.