STEP BY STEP

WITH PRIMAVERA (SAMPLE CASE)

Fery Safaria, MT

Training Program Hard Competency


PT Wijaya Karya (Persero) Tbk Juni 2010
STEP BY STEP WITH PRIMAVERA
Sample Case : Construction of Ordinary House (2.5 Months)
STEP BY STEP WITH PRIMAVERA
Sample Case : Construction of Ordinary House (2.5 Months)
STEP BY STEP WITH PRIMAVERA
Sample Case : Construction of Ordinary House (2.5 Months)
STEP BY STEP WITH PRIMAVERA
Sample Case : Construction of Ordinary House (2.5 Months)

- Commencement Date : 10 Agust 2010


- Working days : 6 days/week
- Unworking days : Sunday
- Working Hours : 8 hours/day (1 hour for rest time, incl lunch, and praying time)
- Lebaran Holiday : H-3 and H+3
STEP BY STEP WITH PRIMAVERA
1. Setting up EPS ;
STEP BY STEP WITH PRIMAVERA
2. Setting up OBS;
STEP BY STEP WITH PRIMAVERA
3. Setting up Currency;
4. Setting up Unit;
5. Setting up Calendars;
STEP BY STEP WITH PRIMAVERA
6. Creating New Project File;
File > New.
Choose EPS where the project will be
developed.
Determine ID and the New Project Name;
Determine Starting Date of Project;
Determine the Responsible Manager;
Choose rate type;
Choose No, do not run the Project Architect.
Finish.
STEP BY STEP WITH PRIMAVERA
7. Setting up Project Information;
STEP BY STEP WITH PRIMAVERA
7. Setting up Work Break Down Structure (WBS);
STEP BY STEP WITH PRIMAVERA
7. Setting up Work Break Down Structure (WBS);
STEP BY STEP WITH PRIMAVERA
8. Setting up Activity Code;
STEP BY STEP WITH PRIMAVERA
9. Adding Activities;
i.e. Activity name, activity code, duration, activity id
STEP BY STEP WITH PRIMAVERA
10. Setting Up Timescale;
STEP BY STEP WITH PRIMAVERA
11. Adding Milestone Activities;
STEP BY STEP WITH PRIMAVERA
12. Assign Activities Relationship;
STEP BY STEP WITH PRIMAVERA
13. Updating and Managing the Schedule ;
STEP BY STEP WITH PRIMAVERA
14. Schedule of Project Ready;
STEP BY STEP WITH PRIMAVERA
15. Resource;
Setting up : Resource Code and Roles
STEP BY STEP WITH PRIMAVERA
15.a Resource;
Adding the Resource Item, complete with the Detail Information
STEP BY STEP WITH PRIMAVERA
15.b Resource;
Modifying Resource Curve
STEP BY STEP WITH PRIMAVERA
15.c. Resource;
Assigning the resource to each Item using detail activity information
STEP BY STEP WITH PRIMAVERA
15.d. Resource;
Determining Production Rate of Each Resource per unit time

Determined by User/unit time

Automatic Process;
Remaining unit x duration
STEP BY STEP WITH PRIMAVERA
15.e. Resource Assignment Layout 1;
STEP BY STEP WITH PRIMAVERA
15.f. Resource Assignment Layout 2
STEP BY STEP WITH PRIMAVERA
16. Budgeting
Setting up Cost Account
STEP BY STEP WITH PRIMAVERA
16. a. Budgeting
Adding Activities Expenses
STEP BY STEP WITH PRIMAVERA
17. Tracking
STEP BY STEP WITH PRIMAVERA
18. Establishing a Project Base Line
STEP BY STEP WITH PRIMAVERA
19. Assigning a Project Base Line
STEP BY STEP WITH PRIMAVERA
20. Up-dating and Comparing Project Base Line
vs Current Schedule
STEP BY STEP WITH PRIMAVERA
21. Report
STEP BY STEP WITH PRIMAVERA
21. Report
STEP BY STEP WITH PRIMAVERA
21. Report
STEP BY STEP WITH PRIMAVERA
21. Report
STEP BY STEP WITH PRIMAVERA
22. S-Curve Development
Project Tracking (WBS)
CT-02 Monthly Project Cash Flow by WBS
Connecting with Pertmaster software

Exporting to Microsoft Project 2003


STEP BY STEP WITH PRIMAVERA
Connecting with Pertmaster software
STEP BY STEP WITH PRIMAVERA
Connecting with Pertmaster software
STEP BY STEP WITH PRIMAVERA
Exporting to Microsoft Project 2003
STEP BY STEP WITH PRIMAVERA
Exporting to Microsoft Project 2003
STEP BY STEP WITH PRIMAVERA
Exporting to Microsoft Project 2003
STEP BY STEP WITH PRIMAVERA
Exporting to Microsoft Project 2003
PRTS-1
Weeks 8/9/2010 8/16/2010 8/23/2010 8/30/2010 9/6/2010 9/13/2010 9/20/2010 9/27/2010 10/4/2010
Project Commencement
Cumulative Cost Rp0 Rp0 Rp0 Rp0 Rp0 Rp0 Rp0 Rp0 Rp0
Project Completion
Cumulative Cost Rp0 Rp0 Rp0 Rp0 Rp0 Rp0 Rp0 Rp0 Rp0
PEKERJAAN PERSIAPAN
Cumulative Cost
Engineering
Cumulative Cost Rp10,000,000 Rp10,000,000 Rp10,000,000 Rp10,000,000 Rp10,000,000 Rp10,000,000 Rp10,000,000 Rp10,000,000 Rp10,000,000
Mobilisasi
Cumulative Cost Rp8,000,000 Rp8,000,000 Rp8,000,000 Rp8,000,000 Rp8,000,000 Rp8,000,000 Rp8,000,000 Rp8,000,000 Rp8,000,000
Land Clearing
Cumulative Cost Rp800,000 Rp800,000 Rp800,000 Rp800,000 Rp800,000 Rp800,000 Rp800,000 Rp800,000 Rp800,000
Direksi Keet
Cumulative Cost Rp625,000 Rp2,500,000 Rp2,500,000 Rp2,500,000 Rp2,500,000 Rp2,500,000 Rp2,500,000 Rp2,500,000 Rp2,500,000
Bowplank / Pengukuran
Cumulative Cost Rp0 Rp900,000 Rp900,000 Rp900,000 Rp900,000 Rp900,000 Rp900,000 Rp900,000 Rp900,000
PEKERJAAN PONDASI
Cumulative Cost
Pemasangan Acuan Pondasi
Cumulative Cost Rp0 Rp0 Rp500,000 Rp500,000 Rp500,000 Rp500,000 Rp500,000 Rp500,000 Rp500,000
Pasangan batu kali
Cumulative Cost Rp0 Rp0 Rp8,000,000 Rp8,000,000 Rp8,000,000 Rp8,000,000 Rp8,000,000 Rp8,000,000 Rp8,000,000
Galian Tanah
Cumulative Cost Rp0 Rp400,000 Rp1,200,000 Rp1,200,000 Rp1,200,000 Rp1,200,000 Rp1,200,000 Rp1,200,000 Rp1,200,000
PEKERJAAN STRUKTUR
Cumulative Cost
Pemasangan Sloof
Cumulative Cost
Pembesian
Cumulative Cost Rp0 Rp0 Rp4,200,000 Rp8,400,000 Rp8,400,000 Rp8,400,000 Rp8,400,000 Rp8,400,000 Rp8,400,000
Pemasangan Formwork
Cumulative Cost Rp0 Rp0 Rp0 Rp0 Rp0 Rp0 Rp0 Rp0 Rp0
Pengecoran
Cumulative Cost Rp0 Rp0 Rp0 Rp8,250,000 Rp8,250,000 Rp8,250,000 Rp8,250,000 Rp8,250,000 Rp8,250,000
Pemasangan Kolom
FACEBOOK : PLANNING ENGINEERS " PRIMAVERA GUYS "