You are on page 1of 1

BUILDING 1 feburary march april may

S.no. Item 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4

1 Excavation in foundation

2 P.C.C. in foundation
Reinforcement in
3 foundation

4 Shuttering in foundation

5 Concreting in foundaton
Brickwork in foundation
6 upto tie beam lvl
Shuttering of coulmn to
7 plinth beam
Concreting of column to
8 plinth beam
Earthfilling on low laying
9 areas
Excavation for tie beam on
10 natural ground
P.C.C. under tie beam on
11 natural ground

12 Reinforcement of tie beam

13 shuttering of tie beam

14 Concreting of tie beam

15 Reinforcement in column
Anchor bolt layout in
16 column
Shuttering of column upto
17 plinth level
Concreting of anchor bolt
18 and column
Pouring of GP2 cement to
19 plinth level

20 Brickwork upto plinth level


DPC over brickwork at
21 plinth level.
Earth filling upto plinth
22 level.
Brickwork above plinth
23 level
Reinforcement of column
24 upto tie beam
Shuttering of column upto
25 tie beam level
Concreting of column to
26 top tie beam lvl
shuttering for sun shade
27 over openings
Reinforcement layout for
28 sun shades

28 Concreting of sun shades

29 Concreting in top tie beam

30 Plaster of internal walls

31 plaster of external walls

32 P.C.C. of internal Floor.


Reinforcement layout in
33 internal flooring.
concreting of internal
34 flooring

35 Trimix flooring .