You are on page 1of 310

: 1.

2
: MOBILISASI

JENIS ALAT

PERALATAN

ASPHALT MIXING PLANT


ASPHALT FINISHER
ASPHALT SPRAYER
BULLDOZER 100-150 HP
COMPRESSOR 4000-6500 L/M
CONCRETE MIXER 0.3-0.6 M3
CRANE 10-15 TON
DUMP TRUCK 3.5 TON
DUMP TRUCK 10 TON
EXCAVATOR 80-140 HP
FLAT BED TRUCK 3-4 M3
GENERATOR SET
MOTOR GRADER >100 HP
TRACK LOADER 75-100 HP
WHEEL LOADER 1.0-1.6 M3
THREE WHEEL ROLLER 5-8 T
TANDEM ROLLER 6-8 T
TIRE ROLLER 8-10 T
VIBRATORY ROLLER 5-8 T
CONCRETE VIBRATOR
STONE CRUSHER
WATER PUMP 70-100 mm
WATER TANKER 3000-4500 L
PEDESTRIAN ROLLER
TAMPER
JACK HAMMER
FULVI MIXER
CONCRETE PUMP
TRAILER 20 TON
PILE DRIVER + HAMMER
CRANE ON TRACK 35 TON
WELDING SET
BORE PILE MACHINE
ASPHALT LIQUID MIXER
TRONTON
COLD MILLING MACHINE
ROCK DRILL BREAKER
COLD RECYCLER
HOT RECYCLER
AGGREGAT (CHIP) SPREADER
ASPHALT DISTRIBUTOR
SLIP FORM PAVER
CONCRETE PAN MIXER
CONCRETE BREAKER
ASPHALT TANKER
CEMENT TANKER
CONDRETE MIXER (350)
VIBRATING RAMMER
TRUK MIXER (AGITATOR)
BORE PILE MACHINE
CRANE ON TRACK 75-100 TON

Total untuk item B pada Lembar 1

: 1.2
: MOBILISASI

URAIAN

Sewa Tanah

PERALATAN
Periksa lembar 1.2-2

FASILITAS KONTRAKTOR
Base Camp
Kantor
Barak
Bengkel
Gudang, dan lain-lain
.......................................

FASILITAS LABORATORIUM
Ruang Laboratorium (sesuai Gambar)

Soil & Agregat Testing


Compaction Test
CBR Test
Specific Gravity
Atterberg Limits
Grain Size Analysis
Field Density Test by Sand Cone Meth
Moinsture Content
Abrasion of Aggregate by Los Angeles

Bituminous Testing
Marshall Asphalt Test
Extraction Test, Centrifuge/Refflux Me
Specific Gravity for Coarse Aggregate
Specific Gravity for Fine Aggregate
Mix Air Viod Content (Accurate Method
Core Drill
Metal Thermometer
Accessories and Tolls
Penetration Test
Softening Point
Refusal Density Compactor

Concrete Testing
Slump Cone
Cylinder/Cube Mould for Compressive
Beam Mould for Flexural Strength (RIG
Crushing Machine

Pendukun (Periksa Fasilitas Laboratorium)

Operasion (Periksa Fasilitas Laboratorium)

MOBILISASI LAINNYA
PEKERJAAN DARURAT
Perkuatan Jembatan Lama
Pemeriksaan Jalan Kerja/Samping
............................................................
............................................................
............................................................
............................................................

LAIN-LAIN
Komunikasi Lapangan Lengkap
...........................................................
...........................................................
...........................................................
...........................................................
...........................................................

DEMOBILISASI

Total Biaya Mobilisasi


Jumlah yang tercantum pada masing-masing item mobilisasi diatas dudah termasuk over-head dan
serta seluruh pajak dan bea cukai (kecuali PPn), dan pengeluaran lainnya.

SATUAN PENGUKURAN
HARGA SATUAN
No

II
2
3
4
5
6
7
8

III
1
2
3
4
5
6
7
8
9
10
11

IV
1
2
3
4

V
1
2
3
VI

VII

1.

2.
: 1.2
: MOBILISASI

KODE ALAT SATUAN VOL

E01 unit 1
E02 unit 1
E03 unit 1
E04 unit 1
E05 unit 1
E06 unit 1
E07 unit 1
E08 unit 18
E09 unit 5
E10 unit 3
E11 unit 1
E12 unit 1
E13 unit 1
E14 unit 1
E15 unit 1
E16 unit 2
E17 unit 1
E18 unit 1
E19 unit 1
E20 unit 5
E21 unit 1
E22 unit 2
E23 unit 1
E24 unit 1
E25 unit 1
E26 unit 2
E27 unit 1
E28 unit 2
E29 unit 2
E30 unit 2
E31 unit 2
E32 unit 2
E33 unit 1
E34 unit 1
E35 unit
E36 unit
E37 unit
E38 unit
E39 unit
E40 unit
E41 unit
E42 unit
E43 unit
E44 unit
E45 unit
E46 unit
E47 unit
E48 unit
E49 unit
E50 unit
E51 unit

Lembar 1

: 1.2
: MOBILISASI

SATUAN VOL.
HARGA SATUAN (Rp.)

M2 20,000

M2 150
M2 60
M2 60
M2 100
M2 100
..... 0

M2 108

Set 1
Set 1
Set 1
Set 1
Set 1
Set 2
Set 2
Bln 2

Set 1
Set 1
Set 1
Set 1
Set 1
Set 1
Set 1
Set 1
Bln 6
Set 1
Set 1

Set 1
Set 1
Set 1
Set 1

Laboratorium)

s Laboratorium)

LS 1
LS 1
.....
.....
.....
.....

Set 1
..... 0
..... 0
..... 0
..... 0
..... 0

LS 1
a masing-masing item mobilisasi diatas dudah termasuk over-head dan laba
cukai (kecuali PPn), dan pengeluaran lainnya.

: Lump Sum
: Rp.
URAIAN SATUAN VOLUME

Laboratory Building

Soil & Aggregate Testing


CBR Test Set 1.00
Specific Gravity Set 1.00
Atterberg Limits Set 1.00
Grain Size Analysis Set 1.00
Field Density Test by Sand Cone Methode Set 2.00
Moinsture Content Set 2.00
Abrasion of Aggregate by Los Angeles Machin Bln 2.00

Bituminos Testing
Marshall Asphalt Test Set 1.00
Extraction Test, Centrifuge/Reflux Method Set 1.00
Specific Gravity of Coarse Aggregate Set 1.00
Specific Gravity of Fine Aggregate Set 1.00
Mix Air Viod Content (Accurate Method) Set 1.00
Core Drill Set 1.00
Meta Thermometer Set 1.00
Accessories and Tolls Set 1.00
Penetration Test Bln 6.00
Softening Point Set 1.00
Refusal Density Compactor Set 1.00

Concrete Testing
Slump Cone Set 1.00
Cylinder/Cube Mould for Compreesive Strength Set 1.00
Beam Mould for Flexural Strength Set 1.00
Crushing Machine Set 1.00

Peralatan pendukung
Mobil Pick Up Unit 2.00
Komputer + Printer Set 1.00
Furniture Set 1.00
Operasional
Teknis Laboratorium Bln 12.00
Tenaga Kerja Terampil Bln 60.00

Test Luar
Test Luar, sesuai kebutuhan atau atas Ls 1.00
perintah Direksi

TOTAL HARGA ( I-VII )

Catatan :
Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termas
yang dibayar kontrak) dan biaya lain-lainnya.
Test luar adalah tes ke lembaga pengujian yang disetujui oleh Konsultan Pengawas.
Lembar 1.2-2

HARGA SATUAN (Rp.) JUMLAH HARGA (Rp.)


68.1225%

JUMLAH HARGA (Rp.)


779,940,000.00
HARGA TOTAL KET

SUB TOTAL

Beli
Beli
Beli
Beli
Beli
Beli
Sewa
SUB TOTAL

Beli
Beli
Beli
Beli
Beli
Beli
Beli
Beli
Beli
Beli
Beli
SUB TOTAL

Beli
Beli
Beli
Beli
SUB TOTAL

Beli
Beli
Beli
SUB TOTAL
SUB TOTAL

0.00 0.00
SUB TOTAL 0.00

Rp

g berkaitan (tetapi tidak termasuk PPN

ultan Pengawas.
URAIAN PEKERJAAN

I. PERSIAPAN
1.1 Pembersihan
1.2 Mobilisasi dan Demobilisasi Alat

II. PEKERJAAN TANAH


2.1 Galian biasa
2.2 Timbunan biasa

III. PEKERJAAN DRAINASE


3.1 Galian untuk Drainase
3.2 Pasangan Batu Dengan Mortar untuk Saluran
3.3 Pasangan Batu Bata untuk dinding drainase

IV. PEKERJAAN URUGAN


4.1 Pengangkutan Material
4.2 Penghamparan Material
4.2.A Lapis pondasi Agg kelas A
4.2.B Lapis pondasi Agg Kelas B
4.2.C Lapis pondasi Agg Kelas C
4.3 Pemadatan Material
4.4 Penyiapan Badan Jalan

V. PEKERJAAN ASPAL
5.1 Lapis Resap Pengikat
5.2 Lapis Perekat
5.3 Laston Lapis Aus (AC-WC)
5.4 Laston Lapis Antara (AC-BC)

VI. PEKERJAAN AKHIR ( FINISHING )


6.1 Dokumentasi dan pelaporan
6.2 Pembersihan akhir
KERJAAN

Mortar untuk Saluran


tuk dinding drainase
NO URAIAN PEKERJAAN

I PEMBERSIHAN

II PEKERJAAN TANAH

2.1 Galian Biasa

2.2 Timbunan Biasa

III PEKERJAAN DRAINASE

3.1 Galian Drainase

3.2 Pasangan Batu dengan Mortar

3.3 Pasangan Batu Bata

IV PEKERJAAN URUGAN

4.1 Pengankutan Material

4.2 Penghamparan Material


4.2.a Lapis Pondasi Agg kelas A
4.2.b Lapis Pondasi Agg Kelas B
4.2 .c Lapis Pondasi Agg Kelas C

4.3 Pemadatan Material


4.4 Penyiapan Badan Jalan

V PEKERJAAN ASPAL
5.1 Lapis Resap Pengikat
5.2 Lapis Perekat
5.3 Laston Lapis Aus (AC-WC)
5.4 Laston Lapis Antara (AC-BC)

VI PEKERJAAN AKHIR (FINISHING)


6.1 Dokumentasi dan Pelaporan
6.2 Pembersihan Akhir
SKET DAN PERHITUNGAN VOLUME PEKERJAAN QTT

Luas Lahan = 150M x 22 M = 3300 M^2 1

678,7 M^3 1

297,35 M^3 1

0,8 M * 1,40 M * 150 M = 168 M^3 1

0,8 M* 0,1 M * 150 M = 12 M^3 1

0,8 M * 0,1 M * 150 M * 2 = 24 M^3 1

0,15 M* 7 M* 150 M = 157,5 M^3 1


0,25 M* 7 M* 150 M = 262,5 M^3 1

0,04 M* 7 M* 150 M = 42 M^3 1
0,06 M* 7 M* 150 M = 63 M^3 1
TOTAL

3300

678.700

297.350

168

12

24

157.5
262.5

42
63
Daftar Harga Satuan Upah, Bahan Bangunan dan Peralatan Tahun 2010 Semester I
DAFTAR HARGA SATUAN UPAH, BAHAN BANGU
TAHUN 2010 SEMESTER

NO URAIAN SATUAN

A UPAH
1 Kepala Tukang Oh
2 Tukang Oh
3 Mandor Oh
4 Pekerja Oh
5 Masinis Oh
6 Operator Oh
7 Sopir Oh
8 Pembantu Masinis/Operator Oh
9 Supervisor Oh
10 Pemasak Aspal Oh
11 Penjaga Oh
12 Pembantu Sopir Oh
13 Mekanik Oh
14 Surveyor Oh

B BAHAN/MATERIAL
1 Agregat Halus m3
2 Agregat Kasar m3
3 Agregat Kelas A m3
4 Agregat Kelas B m3
5 Agregat Kelas C m3
6 Aluminium Foil m2
7 Alcubond m2
8 Amplas Biasa Lbr
9 Amplas Niken Lbr
10 Bambu dia. 6-8 cm/6m Btg
11 Batako buah
12 Batu Andesit hitam kecoklatan m2
13 Batu alam kecoklatan (Sangarong) m2
14 Batu Bata lobang m3
15 Batu Bata Kecil buah
16 Batu Bata Lobang buah
17 Batu Candi hitam m2
18 Batu Kali m3
19 Batu Kali tempel m2
20 Batu Karang Pilang m2
21 Batu Kerikil m3
22 Batu Koral beton m3
23 Batu Koral Jagung m3
24 Batu Krokos m3
25 Batu Palimanan kuning/hijau m2

- 24 -
Daftar Harga Satuan Upah, Bahan Bangunan dan Peralatan Tahun 2010 Semester I

NO URAIAN SATUAN
26 Batu Palimanan kuning/hijau + bevel m2
27 Batu Pecah 0.5 - 1 (screen) m3
28 Batu Abu 0.00 - 0.5 (filler) m3
29 Batu Pecah 1.3 - 1.9 (spilt) m3
30 Batu Pecah 2/3 m3
31 Batu Pecah 3/5 m3
32 Batu Pecah 5/7 m3
33 Batu Marmer m2
34 Batu Roster / Terawang keramik buah
35 Besi dia. 5 mm Batang
36 Besi dia. 6 mm KS Batang
37 Besi dia. 8 mm KS TI Batang
38 Besi dia. 10 mm KS TI Batang
39 Besi dia. 12 mm KS TI Batang
40 Besi dia. 14 mm KS TI Batang
41 Besi dia. 16 mm KS TI Batang
42 Besi dia. 19 mm KS TI Batang
43 Besi Beton Polos kg
44 Besi Baja Profil WF, I dan H kg
45 Besi Baja Konstruksi ( CNP, INP,dan besi L) kg
46 Besi Beam Clamp dan Plat Siku m2
47 Besi Hollow baja 20 X 40, tb. 2mm Batang
48 Besi Hollow baja 40 X 40, tb. 2mm Batang
49 Besi Hollow baja 30 X 60, tb. 2mm Batang
50 Besi Hollow Plafond 2 X 4 Batang
51 Besi Strip kg
52 Besi Strip 2 X 3 M'
53 Beton Ready Mix K - 125 m3
54 Beton Ready Mix K - 175 m3
55 Beton Ready Mix K - 225 m3
56 Beton Ready Mix K - 250 m3
57 Beton Ready Mix K - 275 m3
58 Beton Ready Mix K - 300 m3
59 Beton Ready Mix K - 350 m3
60 Beton Ready Mix K - 400 m4
61 Kabel NYA 1,5 mm m'
62 Kabel NYA 2,5 mm m'
63 Kabel NYA 4.0 mm m'
64 Kabel NYM 2 X 1,5 mm m'
65 Kabel NYM 2 X 2,5 mm m'
66 Kabel NYM 2 X 4,0 mm m'
67 Kawat Beton kg
68 Kawat Burung m2
69 Kawat Duri m'
70 Kawat Harmonika m2
71 Kawat Jaring pagar lbr

- 25 -
Daftar Harga Satuan Upah, Bahan Bangunan dan Peralatan Tahun 2010 Semester I

NO URAIAN SATUAN
72 Kawat Kassa m2
73 Kawat Las Dos
74 Kawat Nyamuk m2
75 Kawat Seng Polos kg
76 Kayu Gelam dia. 6-8 btg
77 Kayu Gelam dia. 10-12 btg
78 Kayu Hek btg
79 Kayu Lis 1/3 m'
80 Kayu Lis 1/4 m'
81 Kayu Lis Profil kecil m'
82 Kayu Lis Profil sedang m'
83 Kayu Lis Profil besar m'
84 Kayu Mosaik 30 x 30 cm Buah
85 Kayu Kaso 5/7 kelas III (Meranti dan sejenis) Btg
86 Kayu Kelas I (Unglen, Jati) m3
87 Kayu Kelas II (Petanang dan sejenis) m3
88 Kayu Kelas III (Meranti dan sejenis) m3
89 Kayu Papan 3/20 Kls. III m3
90 Kayu Kelas IV (Racuk dan sejenis) m3
91 Kayu Papan kelas IV keping
92 Kayu Racuk m3
93 Kayu Reng btg
94 Minyak solar untuk industri / Minyak aspal liter
95 Minyak Gardan liter
96 Minyak Hidrolik liter
97 Minyak Selinder liter
98 Mozaik kayu lantai Uk. 30 x 30 cm buah
99 Pagar BRC, uk. 240 cm X 120 cm, dia. 5,5 mm Unit
100 Pagar BRC, uk. 240 cm X 90 cm, dia. 6 mm Unit
101 Paku Biasa bermacam ukuran 2" - 5" kg
102 Paku Biasa 1/2" - 1" kg
103 Paku Sumbat buah
104 Paku Beton buah
105 Paku Asbes buah
106 Paku Sekrup 3,5" Kg
107 Paku Sekrup 3,5" buah
108 Parquet Jati m2
109 Pasir Beton / Pasang m3
110 Pasir Urug m3
111 Pewarna nat Bks
112 Plywood warna/Jabarwood Lbr
113 Plywood Jati 3 mm Lbr
114 Plywood Sungkay 3 mm/ megatick Lbr
115 Plywood 3 mm Lbr
116 Plywood 4 mm Lbr
117 Plywood 6 mm Lbr

- 26 -
Daftar Harga Satuan Upah, Bahan Bangunan dan Peralatan Tahun 2010 Semester I

NO URAIAN SATUAN
118 Plywood 9 mm Lbr
119 Plywood 12 mm Lbr
120 Plywood 20 mm Lbr
121 Politur dasar ltr
122 Politur Jadi ltr
123 Porselin Putih Uk. 10 x 10 cm buah
124 Porselin Warna Uk. 10 x 10 cm buah

C PERALATAN
1 Asphalt Finisher jam
2 Asphalt Mixing Plan jam
3 Asphalt Sprayer jam
4 Compresor jam
5 Concrete Mixer jam
6 Concrete Pump jam
7 Concrete Vibrator jam
8 Dump Truck jam
9 Excavator jam
10 Filter jam
11 Genset jam
12 Grader jam
13 Loader jam
14 Pneumatic Tired Roller jam
15 Tandem Roller jam
16 Flatbed Truck 3,5 ton jam
17 Water Tank Truck jam
18 Generator jam
19 Alat Bantu jam
20 Roller 3 roda jam
21 Sprayer, Selfprof jam
22 Buldozer jam
23 Scaffolding 177cm X 177 cm, Tg. 177 cm Set/Bulan
24 Stone Crusher (Pemecah batu) jam
25 Pengaduk beton jam
26 Stemper jam
27 Roller, Vibrator Pneu jam
28 Water Pump jam

Catatan : Harga satuan diatas belum termasuk PPn 10%.

- 27 -
Daftar Harga Satuan Upah, Bahan Bangunan dan Peralatan Tahun 2010 Semester I

NO URAIAN SATUAN

- 28 -
Daftar Harga Satuan Upah, Bahan Bangunan dan Peralatan Tahun 2010 Semester I
PAH, BAHAN BANGUNAN DAN PERALATAN
UN 2010 SEMESTER I

HRG SATUAN HARGA HARGA


(RUPIAH) Swakelola (Rp) DASAR (Rp)

100,153.90 91,049.00 91,049.00


78,153.90 71,049.00 71,049.00
138,653.90 126,049.00 126,049.00
67,153.90 61,049.00 61,049.00
82,500.00 75,000.00 75,000.00
83,653.90 76,049.00 76,049.00
61,653.90 56,049.00 56,049.00
67,153.90 61,049.00 61,049.00
83,653.90 76,049.00 76,049.00
50,653.90 46,049.00 46,049.00
45,153.90 41,049.00 41,049.00
56,153.90 51,049.00 51,049.00
89,153.90 81,049.00 81,049.00
83,653.90 76,049.00 76,049.00

305,250.00 310,800.00 277,500.00


298,650.00 304,080.00 271,500.00
287,650.00 292,880.00 261,500.00
254,650.00 259,280.00 231,500.00
243,650.00 248,080.00 221,500.00
23,650.00 24,080.00 21,500.00
1,382,150.00 1,407,280.00 1,256,500.00
10,450.00 10,640.00 9,500.00
13,750.00 14,000.00 12,500.00
51,150.00 52,080.00 46,500.00
9,900.00 10,080.00 9,000.00
282,150.00 287,280.00 256,500.00
202,400.00 206,080.00 184,000.00
479,050.00 487,760.00 435,500.00
7,667.00 7,806.40 6,970.00
7,755.00 7,896.00 7,050.00
238,150.00 242,480.00 216,500.00
315,150.00 320,880.00 286,500.00
75,900.00 77,280.00 69,000.00
309,650.00 315,280.00 281,500.00
254,650.00 259,280.00 231,500.00
227,150.00 231,280.00 206,500.00
304,150.00 309,680.00 276,500.00
243,650.00 248,080.00 221,500.00
205,150.00 208,880.00 186,500.00

- 29 -
Daftar Harga Satuan Upah, Bahan Bangunan dan Peralatan Tahun 2010 Semester I
HRG SATUAN HARGA HARGA
(RUPIAH) Swakelola (Rp) DASAR (Rp)
227,150.00 231,280.00 206,500.00
309,650.00 315,280.00 281,500.00
309,650.00 315,280.00 281,500.00
364,650.00 371,280.00 331,500.00
265,650.00 270,480.00 241,500.00
254,650.00 259,280.00 231,500.00
243,650.00 248,080.00 221,500.00
283,200.00 295,680.00 264,000.00
51,150.00 52,080.00 46,500.00
20,350.00 20,720.00 18,500.00
25,300.00 25,760.00 23,000.00
51,150.00 52,080.00 46,500.00
74,250.00 75,600.00 67,500.00
101,750.00 103,600.00 92,500.00
166,650.00 169,680.00 151,500.00
174,900.00 178,080.00 159,000.00
350,900.00 357,280.00 319,000.00
18,700.00 19,040.00 17,000.00
23,100.00 23,520.00 21,000.00
20,900.00 21,280.00 19,000.00
31,900.00 32,480.00 29,000.00
185,900.00 189,280.00 169,000.00
207,900.00 211,680.00 189,000.00
221,650.00 225,680.00 201,500.00
30,800.00 31,360.00 28,000.00
15,400.00 15,680.00 14,000.00
10,450.00 10,640.00 9,500.00
672,650.00 684,880.00 611,500.00
696,483.33 709,146.67 633,166.67
730,400.00 743,680.00 664,000.00
752,400.00 766,080.00 684,000.00
786,316.67 800,613.33 714,833.33
807,400.00 822,080.00 734,000.00
840,400.00 855,680.00 764,000.00
843,150.00 858,480.00 766,500.00
9,350.00 9,520.00 8,500.00
10,450.00 10,640.00 9,500.00
11,550.00 11,760.00 10,500.00
12,100.00 12,320.00 11,000.00
14,850.00 15,120.00 13,500.00
23,100.00 23,520.00 21,000.00
25,850.00 26,320.00 23,500.00
18,150.00 18,480.00 16,500.00
9,790.00 9,968.00 8,900.00
45,650.00 46,480.00 41,500.00
34,650.00 35,280.00 31,500.00

- 30 -
Daftar Harga Satuan Upah, Bahan Bangunan dan Peralatan Tahun 2010 Semester I
HRG SATUAN HARGA HARGA
(RUPIAH) Swakelola (Rp) DASAR (Rp)
18,150.00 18,480.00 16,500.00
64,900.00 66,080.00 59,000.00
25,850.00 26,320.00 23,500.00
24,200.00 24,640.00 22,000.00
12,650.00 12,880.00 11,500.00
14,300.00 14,560.00 13,000.00
16,500.00 16,800.00 15,000.00
8,387.50 8,540.00 7,625.00
8,662.50 8,820.00 7,875.00
8,800.00 8,960.00 8,000.00
10,450.00 10,640.00 9,500.00
14,300.00 14,560.00 13,000.00
13,200.00 13,440.00 12,000.00
61,050.00 62,160.00 55,500.00
6,057,150.00 6,167,280.00 5,506,500.00
4,297,150.00 4,375,280.00 3,906,500.00
3,252,150.00 3,311,280.00 2,956,500.00
2,069,650.00 2,107,280.00 1,881,500.00
1,217,150.00 1,239,280.00 1,106,500.00
23,650.00 24,080.00 21,500.00
942,150.00 959,280.00 856,500.00
20,350.00 20,720.00 18,500.00
11,770.00 11,984.00 10,700.00
24,200.00 24,640.00 22,000.00
33,000.00 33,600.00 30,000.00
24,200.00 24,640.00 22,000.00
15,400.00 15,680.00 14,000.00
348,150.00 354,480.00 316,500.00
381,150.00 388,080.00 346,500.00
25,300.00 25,760.00 23,000.00
25,300.00 25,760.00 23,000.00
7,672.50 7,812.00 6,975.00
7,755.00 7,896.00 7,050.00
7,672.50 7,812.00 6,975.00
48,400.00 49,280.00 44,000.00
7,562.50 7,700.00 6,875.00
430,650.00 438,480.00 391,500.00
89,650.00 91,280.00 81,500.00
78,650.00 80,080.00 71,500.00
8,800.00 8,960.00 8,000.00
75,900.00 77,280.00 69,000.00
128,150.00 130,480.00 116,500.00
128,150.00 130,480.00 116,500.00
52,250.00 53,200.00 47,500.00
68,750.00 70,000.00 62,500.00
89,650.00 91,280.00 81,500.00

- 31 -
Daftar Harga Satuan Upah, Bahan Bangunan dan Peralatan Tahun 2010 Semester I
HRG SATUAN HARGA HARGA
(RUPIAH) Swakelola (Rp) DASAR (Rp)
133,650.00 136,080.00 121,500.00
169,400.00 172,480.00 154,000.00
202,400.00 206,080.00 184,000.00
36,850.00 37,520.00 33,500.00
50,050.00 50,960.00 45,500.00
7,590.00 7,728.00 6,900.00
8,002.50 8,148.00 7,275.00

270,653.90 275,574.88 246,049.00


1,794,153.90 1,826,774.88 1,631,049.00
105,653.90 107,574.88 96,049.00
177,153.90 180,374.88 161,049.00
50,653.90 51,574.88 46,049.00
240,403.90 244,774.88 218,549.00
58,353.90 59,414.88 53,049.00
353,153.90 359,574.88 321,049.00
688,653.90 701,174.88 626,049.00
78,153.90 79,574.88 71,049.00
45,153.90 45,974.88 41,049.00
551,153.90 561,174.88 501,049.00
446,653.90 454,774.88 406,049.00
435,653.90 443,574.88 396,049.00
298,153.90 303,574.88 271,049.00
281,653.90 286,774.88 256,049.00
364,153.90 370,774.88 331,049.00
72,653.90 73,974.88 66,049.00
116,653.90 118,774.88 106,049.00
215,653.90 219,574.88 196,049.00
188,153.90 191,574.88 171,049.00
743,653.90 757,174.88 676,049.00
86,403.90 87,974.88 78,549.00
892,153.90 908,374.88 811,049.00
144,153.90 146,774.88 131,049.00
60,553.90 61,654.88 55,049.00
133,153.90 135,574.88 121,049.00
57,803.90 58,854.88 52,549.00

- 32 -
Daftar Harga Satuan Upah, Bahan Bangunan dan Peralatan Tahun 2010 Semester I
HRG SATUAN HARGA HARGA
(RUPIAH) Swakelola (Rp) DASAR (Rp)

- 33 -
0.00
0.00
67,153.90

SATUAN H
NO. Harga
URAIAN
Analisa Satuan
(Rp)
1 2 3

I PEKERJAAN PERSIAPAN
a. Tenaga Kerja
0.0298 oh Pekerja 67,153.90
0.0075 oh Mandor 870.78

Jumlah

II PEKERJAAN TANAH
2.1 Galian
a. Tenaga Kerja
0.0149 oh Pekerja 67,153.90
0.0075 oh Mandor 870.78

Jumlah

b. Peralatan
0.0075 oh Excavator 5,655.78
0.3064 oh Dump Truck (E10) 117,980.51
1 oh Alat Bantu (E08) 113,549.00

Jumlah

2.2 Timbunan
a. Tenaga Kerja
0.0298 oh Pekerja 67,153.90
0.0075 oh Mandor 870.78

Jumlah

b. Bahan
1.2 M^3 Bahan timbunan 161608.97

Jumlah
c. Peralatan
0.0075 oh Excaavator 5,655.78
0.4267 oh Dump Truck 164,302.50
0.119 oh Motor Grader 548,049.00
0.0109 oh Vibro Roller 130,049.00
1 oh Alat Bantu 113,549.00

Jumlah

2.3 Dinding Penahan Tanah


a. Tenaga Kerja
0.40 oh Mandor 46,627.33
1.20 oh Tukang 103,436.78
4.02 oh Pekerja 67,153.90

Jumlah

b. Bahan
1.08 oh Batu 314,500.00
0.4829 oh Pasir 89,000.00

c. Peralatan
0.4016 Concrete Mixer 21,005.25
1 Alat Bantu 113,549.00

PEKERJAAN DRAINASE
III 3.1 Galian Drainase
a. Tenaga Kerja
0.0298 oh Pekerja 67,153.90
0.0075 oh Mandor 870.78

Jumlah

b. Peralatan
0.007462 oh Excavator 5,627.22
0.1302 oh Dump Truck 50,134.02
Jumlah

3.2 Pasangan Batu dengan Mortar


a. Tenaga Kerja
0.40 oh Mandor 46,627.33
1.20 oh Tukang 103,436.78
4.02 oh Pekerja 67,153.90

Jumlah

b. Bahan
1.08 M^3 Batu 314,500.00
0.4829 M^3 Pasir 89,000.00

Jumlah

c. Peralatan
0.4016 jam Concrete Mixer 21,005.25
1 jam Alat Bantu 113,549.00

Jumlah

3.3 Pasangan Batu bata


a. Tenaga Kerja
0.40 oh Mandor 46,627.33
1.20 oh Tukang 103,436.78
4.02 oh Pekerja 67,153.90

Jumlah

b. Bahan
1.08 M^3 Batu 314,500.00
0.4829 M^3 Pasir 89,000.00

Jumlah

c. Peralatan
0.4016 jam Concrete Mixer 21,005.25
1 jam Alat Bantu 113,549.00
Jumlah

PEKERJAAN URUGAN
4.1 Pengangkutan Material

IV 4.2 Penghamparan Material

4.2 .A Lapis Pondasi Agg Kelas A


a. Tenaga Kerja
0.0595 oh Pekerja 67,153.90
0.0085 oh Mandor 986.88

Jumlah

b. Bahan
1.2586 M^3 Agg Kelas A 397,340.02

Jumlah

c. Peralatan
0.0085 oh Wheel Loader (E15) 443,549.00
0.5043 oh Dump Truck (E08) Err:522
0.0039 oh Motor Grader (E13) 548,049.00
0.0357 oh Tandem Roller (E17) Err:522
0.0141 oh Water Tanker (E23) Err:522
1 oh Alat Bantu 113,549.00

Jumlah

4.2.B Lapis Pondasi Agg Kelas B


a. Tenaga Kerja
0.0595 oh Pekerja 67,153.90
0.0085 oh Mandor 986.88

Jumlah

b. Bahan
1.2586 oh Agg Kelas B 385,639.95

Jumlah
c. Peralatan
0.0085 oh Wheel Loader (E15) 443,549.00
0.5043 oh Dump Truck (E08) Err:522
0.0039 oh Motor Grader (E13) 548,049.00
0.0357 oh Tandem Roller (E17) Err:522
0.0141 oh Water Tanker (E23) Err:522
1 oh Alat Bantu 113,549.00

Jumlah

4.2.C Lapis Pondasi Agg Kelas C


a. Tenaga Kerja
0.0595 oh Pekerja (L01) 67,153.90
0.0085 oh Mandor (L03) 986.88

Jumlah

4.3 Pemadatan Material

4.4 Penyiapan Badan Jalan


a. Tenaga Kerja
0.0012 oh Pekerja (E13) 67,153.90
0.0003 oh Mandor (E19) 138,653.90

Jumlah

b. Peralatan
0.0003 oh Motor Grader (E13) 548,049.00
0.0016 oh Vibro Roller (E19) 130,049.00
1 oh Alat Bantu 113,549.00

Jumlah

PEKERJAAN ASPAL
5.1 Lapis Resap Pengikat
a. Tenaga Kerja
V 0.0021 oh Pekerja 67,153.90
0.0004 oh Mandor 138,653.90

Jumlah
b. Bahan
0.679 oh Aspal 17,500.00
Jumlah

c. Peralatan
0.0002 oh Asp. Distributor 102,549.00
0.0002 oh Compressoe 174,049.00

Jumlah

5.2 Lapis Perekat


a. Tenaga Kerja
0.0021 oh Pekerja 67,153.90
0.0004 oh Mandor 138,653.90

Jumlah

b. Bahan
0.8487 oh Aspal 17,500.00
Jumlah

c. Peralatan
0.0002 oh Asp. Distrubutor 102,549.00
0.0002 oh Compressor 174,049.00

Jumlah

5.3 Laston Lapis Aus (AC-WC)


a. Tenaga Kerja
0.0186 oh Pekerja 67,153.90
0.0019 oh Mandor 138,653.90

Jumlah

b. Bahan
0.0307 oh Agr 5-10 & 1C 298,000.00
0.0298 oh Agr 0-5 304,600.00
5.1615 oh Aspal 17,500.00

Jumlah

c. Peralatan
0.0009 oh Wheel Loader 443,549.00
0.0019 oh AMP Err:522
0.0343 oh Dump Truck Err:522
0.0013 oh Asp. Finisher 270,653.90
0.0033 oh Tandem Roller Err:522
0.0015 oh P.Tyre Roller Err:522
1 oh Alat Bantu 113,549.00

Jumlah

5.4 Lapis Antara (AC-BC)


a. Bahan
0.9018 oh Agg 5-10 dan 1c 298,000.00
0.633 oh Agg 0-5 304,600.00
121.87 oh Aspal 17,500.00

Jumlah

b. Tenaga Kerja
0.0186 oh Pekerja 67,153.90
0.0019 oh Mandor 138,653.90

Jumlah

c. Peralatan
0.0218 oh WHEEL LOADER 443,549.00
0.0466 oh ASPHALT MIXING PLANT (AMP) 1,794,153.90
0.8579 oh DUMP TRUCK (DT) 353,153.90
0.0255 oh ASPHALT 270,653.90
0.0651 oh TANDEM ROLLER 298,153.90
0.0291 oh PNEUMATIC TIRE ROLLER 435,653.90
1 oh ALAT BANTU 113,549.00

Jumlah

PEKERJAAN AKHIR
6.1 Dokumentasi dan Pelaporan

6.2 Pembersihan Akhir


SATUAN HARGA
Jumlah Harga Jumlah Jumlah
Bahan Tenaga Bahan+Tenaga
(Rp) (Rp) (Rp)
4 5 6

2001.18622 2001.18622
791.6175 791.6175

2792.80372

1000.59311 1000.59311
791.62 791.62

1792.21061

5141.6175 5141.6175
107255.0136 107255.0136
113549 113549

225945.6311

227737.84171

2001.18622 2001.18622
791.6175 791.6175

2792.80372

193930.764 193930.764

193930.764
5141.6175 5141.6175
149365.9083 149365.9083
65217.831 65217.831
1417.5341 1417.5341
113549 113549

334691.8909

531415.45862

42388.4784 42388.4784
124620.631 94033.4352
269696.7778 269696.77779

406118.69139

339660 339660
42978.1 42978.1

382638.1

19095.6784 19095.6784
113549 113549

132644.6784

921401.46979

2001.18622 2001.18622
791.6175 791.6175

2792.80372

5115.655548 5115.655548093
45576.3798 45576.3798
50692.0353481

53484.8390681

42388.4784 42388.4784
94033.4352 94033.4352
269696.7778 269696.77779

406118.69139

339660 339660
42,978.10 42,978.10

382638.1

19095.6784 19095.6784
113549 113549

132644.6784

921401.4698

42388.4784 42388.4784
94033.4352 94033.4352
269696.7778 269696.77779

406118.69139

339660 339660
42978.1 42978.1

382638.1

19095.6784 19095.6784
113549 113549
132644.6784

921401.3698

3995.65705 3995.65705
897.1665 897.1665

4892.82355

361218.2 361218.2

361218.2

3770.1665 3770.1665
Err:522 Err:522
2137.3911 2137.3911
Err:522 Err:522
Err:522 Err:522
113549 113549

311610.3085

677721.33205

3995.65705 3995.65705
897.1665 897.1665

4892.82355

350581.7714 350581.7714

350581.7714
3770.1665 3770.1665
Err:522 Err:522
2,137.39 2,137.39
Err:522 Err:522
Err:522 Err:522
113549 113549

311610.3085

667084.90345

3995.65705 3995.65705
897.1665 897.1665

4892.82355

80.58468
41.59617 80.58468
41.59617

122.18085

164.4147
208.0784 164.4147
113549 208.0784
113549

113921.4931

114043.67395

141.02319
55.46156 141.02319
55.46156
196.48475

11882.5

11882.5

20.5098
34.8098 20.5098
34.8098

55.3196 12134.30435

141.02319
55.46156 141.02319
55.46156

196.48475

14852.25

14852.25

20.5098
34.8098 20.5098
34.8098

55.3196 15104.0543

1249.06254 1249.06254
263.44241 263.44241

1512.50495

9148.6 9148.6
9077.08 9077.08
90326.25 90326.25

108551.93

399.1941 399.1941
Err:522 Err:522
Err:522 Err:522
351.85007 351.85007
Err:522 Err:522
Err:522 Err:522
113549 113549

131460.3099

241524.74485

268736.4
192811.8 268736.4
2132725 192811.8
2132725

2594273.2

1249.06254 1249.06254
263.44241 263.44241

1512.50495

9669.3682 9669.3682
83607.5717 83607.5717
302970.7308 302970.73081
6901.67445 6901.67445
19409.81889 19409.81889
12677.52849 12677.52849
113549 113549

548785.69254

3144571.39749
RENCANA ANGGARAN BIAYA

NO URAIAN
1 2

I PEKERJAAN PERSIAPAN
1 Pembersihan

Jumlah

II PEKERJAAN TANAH
1 Galian tanah
2 Timbunan Tanah

Jumlah

III PEKERJAAN Drainase


1 Galian Drainase
2 Pasangan Batu dengan Mortar
,3 Pasangan Batu Bata

IV PEKERJAAN URUGAN
1 lapis pondasi Agg kelas A
2 Lapis Pondasi Agg Kelas B
3 Penyiapan Badan Jalan
Jumlah

V PEKERJAAN ASPAL
1 Lapis Resap Pengikat
2 Lapis Perekat
3 Laston Lapis Aus (AC-WC)
4 Lapis Antara (AC-BC)

RAB Gedung Balai KKT Kimpraswil Palembang


NO URAIAN
1 2

RAB Gedung Balai KKT Kimpraswil Palembang


NO URAIAN
1 2

RAB Gedung Balai KKT Kimpraswil Palembang


RENCANA ANGGARAN BIAYA

HARGA SATUAN VOLUME SATUAN


3 4 5

Rp 2,792.80 3,300.000 M'

Rp 227,737.84 678.700 M3
Rp 531,415.46 297.350 M3

M3

Rp 53,484.84 168.000 M3
Rp 921,401.47 12.000 M3
Rp 921,401.37 24.000

Rp 677,721.33 157.500 M^3


Rp 667,084.90 262.500 M^3
Rp 114,043.67

Rp 241,524.74 42.000
Rp 3,144,571.40 63.000

RAB Gedung Balai KKT Kimpraswil Palembang


HARGA SATUAN VOLUME SATUAN
3 4 5

RAB Gedung Balai KKT Kimpraswil Palembang


HARGA SATUAN VOLUME SATUAN
3 4 5

RAB Gedung Balai KKT Kimpraswil Palembang


BIAYA
6

Rp 9,216,252.28

Rp 9,216,252.28

Rp -
Rp 158,016,386.62

Rp -
Rp 312,582,059.79

Rp 8,985,452.96
Rp 11,056,817.64
Rp 22,113,632.88

Rp 39,803,665.88

Rp 106,741,109.80
Rp 175,109,787.16

Rp 281,850,896.95

Rp 10,144,039.28
Rp 198,107,998.04

Rp 208,652,129.38

RAB Gedung Balai KKT Kimpraswil Palembang


BIAYA
6

RAB Gedung Balai KKT Kimpraswil Palembang


BIAYA
6

RAB Gedung Balai KKT Kimpraswil Palembang


REKAPITULASI

No URAIAN PEKERJAAN

I PEKERJAAN PERSIAPAN

II PEKERJAAN TANAH

III PEKERJAAN Drainase

IV PEKERJAAN URUGAN

V PEKERJAAN ASPAL

JUMLAH BIAYA PEKERJAAN


PAJAK PERTAMBAHAN NILAI ( PPN ) = 10%
OVER HEAD = 10%
JUMLAH TOTAL BIAYA PEKERJAAN
DIBULATKAN
TERBILANG
SATU MILIYAR TIGA RATUS LIMA PULUH JUTA RUPIAH
BIAYA

Rp 9,216,252.28

Rp 312,582,059.79

Rp 39,803,665.88

Rp 281,850,896.95

Rp 208,652,129.38

Rp 852,102,362.50
Rp 85,210,236.25
Rp 85,210,236.25
Rp 1,022,522,835.01
Rp 1,350,000,000.00

JUTA RUPIAH
ITEM PEMBAYARAN NO. : 2.1
JENIS PEKERJAAN : Galian Utk Drainase, Saluran dan Saluran Air
SATUAN PEMBAYARAN : M3

No.
I.
1
2
3
4
5
6
II.
1

4
III.
1.

2.
2.a.

2.b.
ITEM PEMBAYARAN NO.: 2.1
JENIS PEKERJAAN : Galian Utk Drainase, Saluran dan Saluran Air
SATUAN PEMBAYARAN : M3

No.
2.d.

3.

4.

5.

6.

7.

ITEM PEMBAYARAN NO.: 2.2


JENIS PEKERJAAN : Pasangan Batu Dengan Mortar untuk Saluran
SATUAN PEMBAYARAN : M3

No.
I.
1
2

4
5
6

II.
1

III.

1
1.a.
1.b.

1.c.

2
2.a.
2.a.

ITEM PEMBAYARAN NO.: 2.2


JENIS PEKERJAAN : Pasangan Batu Dengan Mortar untuk Saluran
SATUAN PEMBAYARAN : M3

No.
3.

4.

5.

6.

7.

NO.PAKET KONTRAK :
NAMA PAKET :
PROV/KAB/KOTA :
ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN :
SATUAN PEMBAYARAN :

NO.

A
.

B.

C.

1
2
3

D.
E.
F.
Note. 1

2
PROYEK
No. PAKET KONTRAK
NAMA PAKET

PROP/ KAB/ KODYA


ITEM PEMBAYARAN NO.
JENIS PEKERJAAN
SATUAN PEMBAYARAN

NO

A.

1.
2.
3.

B.

1.
2.
3.

C.

1.
2.

D.
E.
F.
Note: 1
2

3
4

PROYEK
No. PAKET KONTRAK
NAMA PAKET
PROP/KAB/KOTA
ITEM PEMN=BAYRAN NO.
JENIS PEKERJAAN
SATUAN PEMBAYARAN

NO.

A.

1.
2.

B.

C.

1.
2.
3.
D.
E.
F.
Note: 1

3
4

No.
I.
1
2
3
4
5
6
II.
1
2

4
III.
1.

2.
2.a.

2.b.
2.d.

ITEM PEMBAYARAN NO. : 3.1 (1)


JENIS PEKERJAAN : Galian Biasa
SATUAN PEMBAYARAN : M3

NO.

6
7

PROYEK
No. PAKET KONTRAK
NAMA PAKET

PROP/ KAB/ KODYA


ITEM PEMBAYARAN NO.
JENIS PEKERJAAN
SATUAN PEMBAYARAN

NO
NO

A.

1.
2.

B.

1.

C.

1.
2.
3.
4.
5.

D.
E.
F.
Note: 1

3
4

PROYEK
No. PAKET KONTRAK
NAMA PAKET
PROP/ KAB/ KODYA
ITEM PEMBAYARAN NO.
JENIS PEKERJAAN
SATUAN PEMBAYARAN

No.

A.

1.
2.

B.

C.
1.
2.
3.

D.
E.
F.
Note : 1

2
3
4

ITEM PEMBAYARAN NO. : 3.3


JENIS PEKERJAAN : Penyiapan Badan Jalan
SATUAN PEMBAYARAN : M2

NO.
I
1
2
3
4
5

II
1
2

III
1.

2.
2.a.

2.b.
2.d.

3.

ITEM PEMBAYARAN NO. : 3.3


JENIS PEKERJAAN : Penyiapan Badan Jalan
SATUAN PEMBAYARAN : M2

NO.
4

7
PROYEK
No. PAKET KONTRAK
NAMA PAKET
PROP/ KAB/ KODYA
ITEM PEMBAYARAN NO.
JENIS PEKERJAAN
SATUAN PEMBAYARAN

NO.

A.

1.
2.

B.

1.

C.
1.
2.
3.
4.
5.
6.
7.

D.
E.
F.

Note : 1

3
4

ITEM PEMBAYARAN NO. : 5.1 (1)


JENIS PEKERJAAN : Lps. Pond. Agg. Kls. A
SATUAN PEMBAYARAN : M3

NO.
I
1
2
3
4
5
6
7
8

II
1

III
1

2
2.a.

2.b.
ITEM PEMBAYARAN NO. : 5.1 (1)
JENIS PEKERJAAN : Lps. Pond. Agg. Kls. A
SATUAN PEMBAYARAN : M3

NO.
2.c.

2.d.

2.e.
2.g.

ITEM PEMBAYARAN NO. : 5.1 (1)


JENIS PEKERJAAN : Lps. Pond. Agg. Kls. A
SATUAN PEMBAYARAN : M3

NO.
5

6
7
PROYEK
No.PAKET KONTRAK
NAMA PAKET
PROP/ KAB/ KODYA
ITEM PEMBAYARAN NO.
JENIS PEKERJAAN
SATUAN PEMBAYARAN

NO.

A.

1.
2.

B.

1.

C.
1.
2.
3.
4.
5.
6.
D.
E.
F.
Note: 1

3
4

PROYEK
No. PAKET KONTRAK
NAMA PAKET

PROP/ KAB/ KODYA


ITEM PEMBAYARAN NO.
JENIS PEKERJAAN
SATUAN PEMBAYARAN

NO

A.

1.
2.

B.

1.
C.

1.
2.
3.
4.
5.
6.

D.
E.
F.
Note: 1

3
4

PROYEK
No. PAKET KONTRAK
NAMA PAKET

PROP/ KAB/ KODYA


ITEM PEMBAYARAN NO.
JENIS PEKERJAAN
SATUAN PEMBAYARAN

NO

A.

1.
2.
B.

1.
2.

C.

1.
2.

D.
E.
F.
Note: 1

3
4

PROYEK
No. PAKET KONTRAK
NAMA PAKET

PROP/ KAB/ KODYA


ITEM PEMBAYARAN NO.
JENIS PEKERJAAN
SATUAN PEMBAYARAN

NO
A.

1.
2.

B.

1.
2.
3.
4.

C.
1.
2.
3.
4.
5.
6.
7.
8.

D.
E.
F.
Note: 1

3
4

PROYEK
No. PAKET KONTRAK
NAMA PAKET

PROP/ KAB/ KODYA


ITEM PEMBAYARAN NO.
JENIS PEKERJAAN
SATUAN PEMBAYARAN

NO

A.

1.
2.

B.

1.
2.

C.

1.
2.

D.
E.
F.
Note: 1

2
3
4

PROYEK
No. PAKET KONTRAK
NAMA PAKET

PROP/ KAB/ KODYA


ITEM PEMBAYARAN NO.
JENIS PEKERJAAN
SATUAN PEMBAYARAN

NO

A.

1.
2.

B.

1.
2.
3.
4.

C.
1.
2.
3.
4.
5.
6.
7.
8..
D.
E.
F.
Note: 1

3
4

ITEM PEMBAYARAN NO.


JENIS PEKERJAAN
SATUAN PEMBAYARAN

No

I.
1
2
3
4
5
6

II.
1

III.

A1
A1.a.
A1.b.

A2
A2.a.

A2.b.

A3

ITEM PEMBAYARAN NO.


JENIS PEKERJAAN
SATUAN PEMBAYARAN

No

4
5

7
ITEM PEMBAYARAN NO.
JENIS PEKERJAAN
SATUAN PEMBAYARAN

No

I.
1
2
3
4
5
6

II
1

III

1.a.
1.b.

2
2.1

2.b.

ITEM PEMBAYARAN NO.


JENIS PEKERJAAN
SATUAN PEMBAYARAN

No

6
7
ITEM PEMBAYARAN NO.
JENIS PEKERJAAN
SATUAN PEMBAYARAN

No

I.
1
2
3
4
5
6
7

8
9
10

11

12

II.

III.

1
1.a.
1.b.
1.c.
1.d.

2
2.a.

ITEM PEMBAYARAN NO.


JENIS PEKERJAAN
SATUAN PEMBAYARAN

No

2.b.

2.c.

2.d.
2.e.

2.f.

2.g.
URAIAN
ALAT BANTU
- Rambu = 2 buah
- kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah
- Tongkat Kontrol ketebalan hanparan

TENAGA
Produksi menentukan : A M P
Produksi AC-WC / hari = Tk x Q5
Kebutuhan tenaga :
- Pekerja
- Mandor

Koefisien Tenaga / M2 :
- Pekerja = (Tk x P) / Qt
- Mandor = (Tk x M) / Qt

HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran

ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Didapat Harga Satuan Pekerjaan :

Rp. 71846,43 / M2

WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelal............ Bulan

VOLUME PEKERJAAN YANG DIPERLUKAN


Volume Pel 1,00 M2
nase, Saluran dan Saluran Air

URAIAN KODE KOEF.


ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi pekerjaan : sepanjang jalan
Kondisi Jalan : baik
Jam kerja efektif per-hari Tk 7
Faktor pengembangann bahan Fk 1.2
Berat volume bahan D 1.6
URUTAN KERJA
Penggalian dilakukan dengan menggunakan excavator
Selanjutnya excavator menuangkan material hasil galian
kedalam truk

Dump Truck membuang material hasil galian keluar lokasi


L 2
jalan sejauh
Sekelompok pekerja akan merapikan hasil galian
PEMAKAIAN BAHAN, ALAT DAN TENAGA
BAHAN
Tidak ada bahan yang diperlukan
ALAT
Excavator (E10)
Kapasitas Bucket V 0.93
Faktor Bucket Fb 1
Faktor efisiensi alat Fa 0.83
Faktor Konversi (<40%) Fv 0.9
Waktu siklus = T1 x Fv Ts1 0.29
-Menggali, memuat dan berputar T1 0.3
Kap. Prod. Q1 134.01

Koefisien = 1 : Q1 0.00746213
DUMP TRUCK (E08)
Kapasitas bak V 3.5
Faktor efisiensi alat Fa 0.83
Kecepatan rata-rata bermuatan v1 20
Kecepatan rata-rata kosong v2 30
Waktu siklus : Ts2
- Muat + (V X 60)/ D X Q1 X Fk T1 0.82
- Waktu temouh isi + (L : v1) x 60 T2 6
- Waktu tempuh kosong + (L : v2) x 60 T3 4
- Lain-lain T4 1

Kapasitas Produksi / Jam = Q2 7.68

Koefisian = 1 : Q2 0.1302
ase, Saluran dan Saluran Air

URAIAN KODE KOEF.


ALAT BANTU
Diperlukan alat-alat bantu kecil 1
- Keranjang + Sapu

TENAGA
Produksi menentukan : EXCAVATOR Q1 134.01
Produksi Galian/hari = Tk x Q1 Qt 938.07
Kebutuhan tenaga :
- Pekerja P 4
- Mandor M 1

Koefisien tenaga / M3
- Pekerja = (Tk x P) : Qt (L01) 0.0298
- Mandor = (Tk x M) : Qt (L03) 0.0075

HARGA DASAR SATUAN UAH, BAHAN DAN ALAT


Lihat lampiran.

ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :
Rp. 26934,14 / M3

WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa pelal................. Bulan

VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pel 1,00 M3

Dengan Mortar untuk Saluran

URAIAN KODE KOEF.


Menggunakan alat (cara mekanik)
Lokasi pekerjaan : sepanjang jalan
Bahan dasar (batu, pasir dan semen) diterima seluruhnya di
lokasi pekerjaan
Jam kerja efektif per- hari L 8.7
Jam kerja efektif per- hari Tk 7
Perbandingan Pasir & Semen : -Volume Semen Sm 20
: - Volume Pasir Ps 80
Perbandingan Batu & Mortar :
- Batu Bt 60
- Mortar (campuran semen & pasir) Mr 40
Berat Jenis Bahan
- Pasangan Batu Dengan Mortar D1 2.4
- Batu D2 1.6
- Adukan (mortar) D3 1.8
- Pasir D4 1.67
- Semen Portland D5 1.44

URUTAN KERJA
Semen, pasir dan air dicampur dan diaduk menjadi
mortar deng menggunalan alat bantu
Batu dibersihkan dan dibasahi seluruh permukaannya
sebelum dipasang
Penyelesaian dan perapihan setelah pemasangan

PEMAKAIAN BAHAN, ALAT DAN TENAGA

BAHAN
Batu ---- {(Bt x D1 x 1 M3) : D2} x 1.2 (M02) 1.08
Semen -- Sm x {(Mr x d1 x 1 M3} : D3} x 1,05 0.112
x {D5 x (1000)} (M12) 161
Pasir ---- Ps x {(Mr x D1 x 1 M3) : D4} x 1,05 (M01) 0.4829

ALAT
CONCRETE MIXER (E60)
Kapasitas Alat V 500
Faktor efisiensi Alat Fa 0.83
Waktu siklus (T1 + T2 + T3 + T4)
- Memuat T1 5
- Mengaduk T2 3
- Menuang T3 1
- Menunggu, dll. T4 1
Ts1 10
Kap. Prod. Q1 2.49

Koefisien = 1 : Q1 (E06) 0.4016


ALAT BANTU
Diperlukan :
- Sekop = 4 buah
- Pacul = 4 buah
- Sendok S = 4 buah
-Ember = 8 buah
- Gerobak = 3 buah

Dengan Mortar untuk Saluran

URAIAN KODE KOEF.


TENAGA
Produksi Pas. Batu yang menentukan (Prod. C. Mixer) Q1 2.49
Produksi Pasangan Batu dalam 1 hari = Tk x Q1 Qt 17.43

Kebutuhan - Mandor M 1.00


- Tukang Batu Tb 3.00
- Pekerja P 10.00

Koefisien Tenaga / M3
- Mandor = (Tk x M) : Qt (L03) 0.40
- Tukang = (TkxTb) : Qt (L02) 1.20
- Pekerja = (Tk x P) : Qt (L01) 4.02

HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :
Rp. 437350,41

WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelal............ Bulan

VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pel.......... 1,00 M3

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MAS
PERKIRAAN
KOMPONEN SATUAN KUANTITAS

TENAGA

BAHAN

JUMLAH HARGA BAHAN

PERALATAN

Excavator (E10) jam 0.0075


Dump Truck (E08) jam 0.1302
Alat Bantu LS 1.0000

JUMLAH HARGA PERALATAN

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A+B+C)


OVERHEAD & PROFIT 10,0 % x D
HARGA SATUAN PEKERJAAN (D+E)
SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau
ukuran berat untuk bahan-bahan
Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu-satuan
pekerjaan dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dap
diubah kecuali

FORMULIR STANDAR UN
PEREKAMAN ANALISA MASING-M
: 2.2
: Pasangan Batu Dengan M
: M3

KOMPONEN

TENAGA

Pekerja (L01)
Tukang Batu (L02)
Mandor (L03)

JUMLAH HARGA TENAG

BAHAN

Batu (M02)
Semen (PC) (M12)
Pasir (M01)

JUMLAH HARGA BAHA

PERALATAN

Conc Mixer
Alat bantu

JUMLAH HARGA PERALATAN

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+ B + C)


OVERHEAD & PROFIT 10,0 % x D
HARGA SATUAN PEKERJAAN (D + E)
SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau u
berat untuk bahan-bahan
Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu-satuan pe
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah k
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam instruksi Kepada Peserta
Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
Biaya yang sudah masuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk P
yang dibayar dari kontrak) dan biaya-biaya lainnya

FORMULIR STANDAR UN
PEREKAMAN ANALISA MASING-M

:
:
:
:
: 3.1 (1)
: Galian Biasa
: M3

PERKIRAAN
KOMPONEN SATUAN KUANTITAS

TENAGA

Pekerja (L01) Jam 0.0149


Mandor (L03) Jam 0.0075

JUMLAH HARGA TENAGA

BAHAN

JUMLAH HARGA BAHAN

PERALATAN

Excavator Jam 0.0075


Dump Truck (E10) Jam 0.3064
Alat Bantu (E08) Ls 1.0000
JUMLAH HARGA PERALATAN

JUMLAH HARGA TENAGA, BAHAN DAN PERALTAN ( A + B + C )


OVERHEAD & PROFIT 10,0 % X D
HARGA SATUAN PEKERJAAN ( D + E )
SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau u
untuk bahan-bahan
Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pe
nomor mata pembayaran. Harga Satuan disampaikan Penyedia Jasa tidak dapat diubah kecuali terd
Penyesuaian Harga (Eskalasi/Deskalasi) sesuai Ketentuan dalam instruksi kepada Peserta Lelang
Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( trtapi tidak terma
dibayar dari kontrak) dan biaya-biaya lainnya

URAIAN KODE KOEF.


ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi pekerjaan : sepanjang jalan
Kondisi Jalan : baik
Jam kerja efektif per-hari Tk 7
Faktor pengembangann bahan Fk 1.2
Berat volume bahan (lepas) D 1.6
URUTAN KERJA
Tanah yang dipotong umumnya berada disisi jalan
Penggalian dilakukan dengan menggunakan excavator
Selanjutnya excavator menuangkan material hasil galian
kedalam truk
Dump Truck membuang material hasil galian keluar lokasi
L
jalan sejauh 5
PEMAKAIAN BAHAN, ALAT DAN TENAGA
BAHAN
Tidak ada bahan yang diperlukan
ALAT
Excavator (E10)
Kapasitas Bucket V 0.93
Faktor Bucket Fb 1
Faktor efisiensi alat Fa 0.83
Faktor Konversi (<40%) Fv 0.9
Waktu siklus Ts1
-Menggali, memuat (standar) T1 0.32
Waktu siklus = T1 x Fv Ts1 0.29
Kap. Prod. Q1 134.01

Koefisien = 1 : Q1 (E10) 0.0075


DUMP TRUCK (E08)
Kapasitas bak V 3.5
Faktor efisiensi alat Fa 0.83
Kecepatan rata-rata bermuatan v1 20
Kecepatan rata-rata kosong v2 30
Waktu siklus : Ts2
- Muat + (V X 60)/ D X Q1 X Fk T1 0.82
- Waktu tempuh isi + (L : v1) x 60 T2 15
- Waktu tempuh kosong + (L : v2) x 60 T3 10
- Lain-lain T4 2
Ts2 27.82

Kapasitas Produksi / Jam = Q2 3.26

Koefisian = 1 : Q2 (E08) 0.3064


ALAT BANTU
Diperlukan alat-alat bantu kecil
- Sekop
- Keranjang

URAIAN KODE KOEF.

TENAGA
Produksi menentukan : EXCAVATOR Q1 134.01
Produksi Galian / hari = Tk x Q1 Qt 938.07
Kebutuhan Tenaga :
- Pekerja P 2.00
- Mandor M 1.00

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0149
- Mandor = (Tk x M) : Qt (L03) 0.0075

HARGA DASAR SATUAN PEKERJAAN


Lihat lampiran

ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEKERJAAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelal . . . . . . . . . . Bulan

VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pel . . . . . . . . . 1,00 M3

FORMULIR STANDAR UN
PEREKAMAN ANALISA MASING-M

: 3.2 (1)
: Timbunan Biasa dari sela
: M3

KOMPONEN
KOMPONEN

TENAGA

Pekerja (L01)
Mandor (L03)

JUMLAH HARGA TENAG

BAHAN

Bahan timbunan (M08)

JUMLAH HARGA BAHA

PERALATAN

Excaavator (E15)
Dump Truck (E08)
Motor Grader (E13)
Vibro Roller (E19)
Alat Bantu

JUMLAH HARGA PERALATAN

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+ B + C)


OVERHEAD & PROFIT 10,0 % x D
HARGA SATUAN PEKERJAAN (D + E)
SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau u
berat untuk bahan-bahan
Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu-satuan pe
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah k
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam instruksi Kepada Peserta
Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
Biaya yang sudah masuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk P
yang dibayar dari kontrak) dan biaya-biaya lainnya

FORMULIR STANDAR UN
PEREKAMAN ANALISA MASING-M

:
:
:
:
: 3.3
: Penyiapan Badan Jalan
: M2

PERKIRAAN
KOMPONEN SATUAN KUANTITAS

TENAGA

Pekerja (E13) jam 0.0012


Mandor (E19) jam 0.0003

JUMLAH HARGA TENAGA

BAHAN

JUMLAH HARGA BAHAN

PERALATAN 0.0003
Motor Grader (E13) jam 0.0016
Vibro Roller (E19) jam 1.0000
Alat Bantu Ls

JUMLAH HARGA PERALATAN

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


OVERHEAD & PROFIT 10,0 % x D
HARGA SATUAN PEKERJAAN (D + E)
SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau u
untuk bahan-bahan
Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaiakan satu-satuan p
nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecua
Penyesuaian Harga ( Esakalasi/Deskalasi) sesuai kententuan dalam Instruksi Kepada Peserta Lelang
Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termas
dibayar dari kontrak) dan biaya-biaya lainnya

pan Badan Jalan

URAIAN KODE KOEF.


Asumsi
Pekerjaan dilaksanakan hanya pada tanah galian
Pekerjaan dilakukan secara mekanis
Lokasi pekerjaan : Sepanjang jalan
Kondisi Jalan : Jelek / belum padat
Jam kerja efektif per-hari Tk 7.00

URUTAN KERJA
Motor Grader meratakan permukaan hasil galian
Vibro Roller memadatkan permukaan yang telah
dipotong/diratakan oleh Motor Grader
Sekelompok pekerja akan membantu meratakan
badan jalan dengan alat bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA


BAHAN
Tidak diperlukan bahan / material

ALAT
MOTOR GRADER (E13)
Panjang operasi grader sekali jalan Lh 50.00
Lebar Efektif kerja Blade b 2.6
Lebar overlap bo 0.30
Faktor Efisiensi Alat Fa 0.80
Kecepatan rata-rata alat v 4.00
Jumlah lintasan n 4.00
Waktu siklus Ts1
Peralatan 1 kali lintasan = Lh : (v x 1000) x 60 T1 0.75
Lain-lain T2 1.00
Ts1 1.75

Kapasitas Produksi / Jam = Lh x (n*(bbo) x Fa x 60 Q1 3,257.14


n x Ts1
Koefisien = 1 : Q1 (E13) 0.0003

VIBRATOR ROLLER (E19)


kecepatan rata-rata alat v 4.00
Lebar efektif pemadatan Jumlah lintasan b 1.48
Faktor efisiensi alat n 8.00
Fa 0.83

Kapasitas Produksi / Jam = (v x 1000) x b x Fa Q2 614.2


n
Koefisien = 1 : Q2 (E19) 0.0016
ALAT BANTU
Diperlukan alat-alat bantu kecil
Sekop = 3 buah

TENAGA
Produksi menentukan : MOTOR GRADER Q1 3,257.14
Produksi pekerjaan / hari = Tk x Q1 Qt 22,800.00
Kebutuhan tenaga :
Pekerja P 4.00
Mandor M 1.00

Koefisien tenaga / M2
Pekerja = (Tk x P) : Qt (L01) 0.0012
mandor = (Tk x M) : Qt (L02) 0.0003

an Badan Jalan

URAIAN KODE KOEF.


HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran

ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelal . . . . . . . . . . Bulan

VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pel . . . . . . . . . 1,00 M2
FORMULIR STANDAR UN
PEREKAMAN ANALISA MASING M

:
:
:
:
: 5.1 (1)
: Lps. Pond. Agg. Kls. A
: M3

PERKIRAAN
KOMPONEN SATUAN KUANTITAS

TENAGA

Pekerja (L01) jam 0.0595


Mandor (L03) jam 0.0085

JUMLAH HARGA TENAGA


BAHAN

Aggregat A M26 M3 1.2586

JUMLAH HARGA BAHAN


PERALATAN
Wheel Loader (E15) jam 0.0085
Dump Truck (E08) jam 0.5043
Motor Grader (E13) jam 0.0039
Tandem Roller (E17) jam 0.0357
Water Tanker (E23) jam 0.0141
Alat Bantu Ls 1

JUMLAH HARGA PERALATAN

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+ B + C )


OVERHEAD & PROFIT 10,0 % x 10,0 % x D
HARGA SATUAN PEKERJAAN (D + E)

Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, volume dan/atau uk
berat untuk bahan- bahan.
Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan p
mata pembayaran. Harga satuan yang disampaikan Penyedia jasa tidak dapat diubah kecuali terd
Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam instruksi Kepada Peserta Lelang
Biaya satuan untuk peralatan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( te
Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak terma
kontrak) dan biaya-biaya lainnya.

d. Agg. Kls. A

URAIAN KODE KOEF.


Asumsi
Menggunakan alat berat ( Cara Mekanik )
Lokasi pekerjaan : Sepanjang jalan
Kondisi existing jalan : sedang
Jarak rata-rata Base Camp ke lokasi pekerjaan L 8.73
Tebal lapis agregat padat t 0.15
Berat isi padat Bip 1.81
Jam kerja efektif per-hari Tlk 7.00
Proporsi C Agregat Pecah Mesin 20 30 mm 20 30 28.00
Agregat Pecah Mesin 5 10 & 10 20 mm 510&1020 42.00
Pasir Urug PU 30.00
Berat Isi Agregat (lepas) Bil 1.51
Faktor kehi Agregat A Fh1 1.03

URUTAN KERJA
Wheel Loader memuat agregat campuran ke
dalam Dump Truck di Base Camp
Dump Truck mengangkut Agregat kelas A ke lokasi
pekerjaan dan dihampar dengan Motor Grader
Hamparan Agregat dibasahi dengan Water Tank Truck
sebelum dipadatkan dengan Tandem Roller
Selama Pemadatan, sekelompok pekerja akan
merapikan tapi hamparan dan level permukaan
dengan menggunakan Alat Bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA BAHAN


Agregat = 1 M3 x (Bip/Bil) x Fh (M26) 1.258860927

ALAT
WHEEL LOADER (E15)
Kapasitas bucket V 1.5
Faktor bucket Fb 0.85
Faktor Efisiensi alat Fa 0.83
Waktu siklus :
Memuat dan lain lain T1 0.45

Kap. Prod V x Fb x Fa x 60 Q1 117.71


(Bip/Bil) x T1
Koefisien = 1 : Q1

Dump Truck (E08)


kapasitas Bak V 3.5
Faktor Efisiensi alat Fa 0.8
Kecepatan rata-rata bermuatan v1 20.00
Kecepatan rata-rata kosong v2 30.00
Waktu Siklus :
Waktu memuat = V x 60/Q1 x Bil T1 1.18
Waktu tempuh isi = (L : v1) x 60 menit T2 26.18
Waktu tempuh kosong = (L : v2) x 60 menit T3 17.45
lain-lain T4 2.00
Ts2 46.81

kap. Prod. V x Fa x 60 Q2 1.98


Ts2 x Bip

Koefisien = 1 : Q2 (E08) 0.60

nd. Agg. Kls. A

URAIAN KODE KOEF.


MOTOR GRADER (E13)
Panjang hamparan Lh 50.00
Lebar efektif kerja blade b 2.4
Faktor Efisiensi alat Fa 0.83
Kecepatan rata-rata alat v 4.00
Jumlah lintasan n 2.00
Waktu siklus : Ts3
Perataan 1 lintasan = Lh : (v x 1000) x 60 T1 0.75
T2 1.00
Ts3 1.75

Kap. Prod. Lh x b x t x Fa x 60 Q3 256.11


n x Ts3
koefisien = 1 : Q3 (E13) 0.0039

TANDEM ROLLER (E17)


kecepatan rata-rata alat v 1.5
b 1.2
n 8.00
Fa 0.83

Kap. Prod. (v x 1000) x b x t x Fa Q4 28.01


n
koefisien = 1 : Q4 (E19) 0.0357

WATER TANK TRUCK (E23)


volume tanki air V 4.00
Kebutuhan air / M3 agregat padat Wc 0.07
Kapasitas pompa air pa 100.00
Faktor Efisiensi alat Fa 0.83

Kap. Prod. Pa x Fa x 60 Q5 71.14


1000 x Wc
Koefisien = 1 : Q5 (E23) 0.0141

ALAT BANTU
Diperlukan :
Kereta do = 2 buah
Sekop = 3 buah
Garpu = 2 buah

TENAGA
Produksi menentukan : WHEEL LOADER Q1 117.71
Produksi agregat / hari = Tk x Q1 Qt 823.99
Kebutuhan tenaga :
Pekerja P 7.00
Mandor M 1.00

Koefisisen tenaga / M3 :
Pekerja = (Tk x P) : Qt (L01) 0.0595
Mandor = (Tk x M) : Qt (L03) 0.0085

HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran

nd. Agg. Kls. A

URAIAN KODE KOEF.


ANALISA HARGA SATUAN PEKERJAAN
lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN
Didapat Harga Satuan Pekerjaan :

WAKTU PELAKSANAAN YANG DIPERLUKAN


masa Pelal . . . . . . . . . . . . . Bulan

VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pel . . . . . . . . . . . . 1,00 M3
PEREKAMAN ANALISA M

:
:
:
:
: 5.1 (2)
: Lps. Pond. Agg. Kls. B
: M3

PERKIRAAN
KOMPONEN SATUAN KUANTITAS

TENAGA

Pekerja (L01) jam 0.0595


Mandor (L03) jam 0.0085

JUMLAH HARGA TENAGA

BAHAN

Agregat B M27 M3 1.2586

JUMLAH HARGA BAHAN

PERALATAN
Wheel Loader (E15) jam
Dump Truck (E08) jam
Motor Grader (E13) jam
Tandem Roller (E17) jam
Water Tanker (E23) jam
Alat Bantu Ls

JUMLAH HARGA PERALATAN


JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
OVERHEAD & PROFIT 10,0 % X D
HARGA SATUAN PEKERJAAN ( D + E )
Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, volume dan/atau uk
berat untuk bahan- bahan.
Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan p
mata pembayaran. Harga satuan yang disampaikan Penyedia jasa tidak dapat diubah kecuali terd
Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam instruksi Kepada Peserta Lelang
Biaya satuan untuk peralatan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( te
Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak terma
kontrak) dan biaya-biaya lainnya.

FORMULIR STANDAR UN
PEREKAMAN ANALISA MASING-M

: 5.2 (1)
: Lapis Pondasi Agregat Ke
: M3

KOMPONEN

TENAGA

Pekerja (L01)
Mandor (L03)

JUMLAH HARGA TENAG

BAHAN

Agregat Kelas C1 (M28)

JUMLAH HARGA BAHA


PERALATAN

Wheel Loader (E15)


Alat bantu (E08)
Motor Grader (E13)
Tandem Roller (E17)
Water Tanker (E23)
Alat Bantu
JUMLAH HARGA PERALATAN

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+ B + C)


OVERHEAD & PROFIT 10,0 % x D
HARGA SATUAN PEKERJAAN (D + E)
SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau u
berat untuk bahan-bahan
Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu-satuan pe
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah k
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam instruksi Kepada Peserta
Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
Biaya yang sudah masuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk P
yang dibayar dari kontrak) dan biaya-biaya lainnya

FORMULIR STANDAR UN
PEREKAMAN ANALISA MASING-M

: 6.1 (1)
: Lapis Resap Pengikat
: Liter

KOMPONEN

TENAGA

Pekerja (L01)
Mandor (L03)

JUMLAH HARGA TENAG


BAHAN

Aspal (M10)
Kerosene (M11)

JUMLAH HARGA BAHA

PERALATAN

Asp. Distributor (E41)


Compressoe (E05)

JUMLAH HARGA PERALATAN

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+ B + C)


OVERHEAD & PROFIT 10,0 % x D
HARGA SATUAN PEKERJAAN (D + E)
SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau u
berat untuk bahan-bahan
Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu-satuan pe
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah k
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam instruksi Kepada Peserta
Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
Biaya yang sudah masuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk P
yang dibayar dari kontrak) dan biaya-biaya lainnya

FORMULIR STANDAR UN
PEREKAMAN ANALISA MASING-M

: 6.1 (1)
: Lapis Resap Pengikat
: Liter

KOMPONEN
TENAGA

Pekerja (L01)
Mandor (L03)

JUMLAH HARGA TENAG

BAHAN

Agr 5-10 & 1C (M29)


Agr 0-5 (M91)
Semen (M05)
Aspal (M10)

JUMLAH HARGA BAHA


PERALATAN
Wheel Loader (E15)
AMP (E01)
Genset (E12)
Dump Truck (E08)
Aspalt Finis (E02)
Tandem Roller (E17)
P.Tyre Roller (E18)
Alat Bantu
JUMLAH HARGA PERALATAN

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+ B + C)


OVERHEAD & PROFIT 10,0 % x D
HARGA SATUAN PEKERJAAN (D + E)
SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau u
berat untuk bahan-bahan
Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu-satuan pe
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah k
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam instruksi Kepada Peserta
Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
Biaya yang sudah masuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk P
yang dibayar dari kontrak) dan biaya-biaya lainnya

FORMULIR STANDAR UN
PEREKAMAN ANALISA MASING-M
: 6.1 (2)
: Lapis Perekat
: Liter

KOMPONEN

TENAGA

Pekerja (L01)
Mandor (L03)

JUMLAH HARGA TENAG

BAHAN

Aspal (M10)
Kerosene (M11)

JUMLAH HARGA BAHA

PERALATAN

Asp. Distrubutor (E41)


Compressor (E05)

JUMLAH HARGA PERALATAN

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+ B + C)


OVERHEAD & PROFIT 10,0 % x D
HARGA SATUAN PEKERJAAN (D + E)
SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau u
berat untuk bahan-bahan
Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu-satuan pe
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah k
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam instruksi Kepada Peserta
Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
Biaya yang sudah masuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk P
yang dibayar dari kontrak) dan biaya-biaya lainnya

FORMULIR STANDAR UN
PEREKAMAN ANALISA MASING-M

: 6..3 (5a)
: Laston Lapis Aus (AC-WC
: M2

KOMPONEN

TENAGA

Pekerja (L01)
Mandor (L03)

JUMLAH HARGA TENAG

BAHAN

Agr 5-10 & 1C (M29)


Agr 0-5 (M91)
Semen (M05)
Aspal (M10)

JUMLAH HARGA BAHA


PERALATAN
Wheel Loader (E15)
AMP (E01)
Genset (E12)
Dump Truck (E08)
Asp. Finisher (E02)
Tandem Roller (E17)
P.Tyre Roller (E18)
Alat Bantu
JUMLAH HARGA PERALATAN

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+ B + C)


OVERHEAD & PROFIT 10,0 % x D
HARGA SATUAN PEKERJAAN (D + E)
SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau u
berat untuk bahan-bahan
Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu-satuan pe
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah k
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam instruksi Kepada Peserta
Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
Biaya yang sudah masuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk P
yang dibayar dari kontrak) dan biaya-biaya lainnya

: 6.1 (1)
: Lapis Resap Pengikat
: Liter

Uraian

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi pekerjaan : sepanjang jalan
Jarak rata-rata Base Camp ke lokasi pekerjaan
Jam kerja efektif per-hari
Faktor kehilangan bahan
Komposisi campuran
- Aspal Pen 60 atau pen 80
- Kerosene
Berat isi bahan
- Aspal Pen 60 atau pen 80
- Kerosene
Bahan dasar (aspal & minyak pencair) semuanya diterim
di lokasi pekerjaan

URUTAN KERJA
Aspal dan Minyak Flux dicampur dan dipanaskan
sehingga menjadi campuran aspal cair
Permukaan yang akan dilapis dibersihkan dari debu
dan kotoran dengan Air Compressor
Campuran aspal cair disemprotkan dengan Asphalt
Distributor ke atas permukaan yang dilapis

PEMAKAIAN BAHAN, ALAT DAN TENAGA

BAHAN
Untuk mendapatkan 1 liter lapis Resap Pengikat
diperlukan ( 1 liter x Fh )

Aspal = As x PC x D1
Kerosene = Kx PC

ALAT
ASPALT DISTRIBUTOR
Lebar penyemprotan
Kecepatan penyemprotan
Kapasitas pompa aspal
Faktor effisiensi kerja

Kap. Prod.

Koefisien = 1 : Q1

AIR COMPRESSOR

Kap. Prod. / jam = Asphalt Distributor

Koefisien = 1 : Q2

TENAGA
Produksi menentukan : ASPHALT DISTRIBUTOR
Produksi Lapis Resep Pengikat/hari = Tk x Q4
Kebutuhan tenaga :
- Pekerja
- Mandor

: 6.1 (1)
: Lapis Resap Pengikat
: Liter

Uraian

Koefisien tenaga / liter :


- Pekerja
- Mandor

HARGA DASAR SATUN UPAH, BAHAN DAN ALAT


Lihat lampiran
ANALISA HARGA SATUAN PEKERJAAN
Lihat perhitungan dalam FORMULIS STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelal . . . . . . . . . . . . . Bulan

VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pel 1,00 Liter
: 6.1 (2)
: Lapis Perekat
: Liter

Uraian

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi pekerjaan : sepanjang jalan
Jarak rata-rata Base Camp ke lokasi pekerjaan
Jam kerja efektif per-hari
Faktor kehilangan bahan
Komposisi campuran
- Aspan Pen 60 atau Pen 80
- Kerosene
Berat isi Bahan
- Aspan Pen 60 atau Pen 80
- Kerosene
Bahan dasar (aspal & minyak pencair) semuanya
diterima dilokasi pekerjaan

URUTAN KERJA
Aspal dan Minyak flux dicampur dan dipanaskan
sehingga menjadi campuran aspal cair
Permukaan yang akan dilapis dibersihkan dari debu
dan kotoran dengan Air Compressor
Campuran aspal cair disemprotkan dengan Asphlat
Distributor ke atas permukaan yang akan dilapis

PEMAKAIAN, BAHAN, ALAT DAN TENAGA

BAHAN
Untuk mendapatkan 1 liter Lapis Resap Pengikat
diperlukan ( 1 liter x Fh )

Aspal = As x PC x D1
Kerosene = K x PC

ALAT
ASPHALT DISTIBUTOR
Lebar penyemprotan
Kecepatan penyemprotan
Kapasitas pompa aspal
Faktor effisiensi kerja

Kap. Prod.

Koefisien = 1 : Q1

AIR COMPRESSOR

Kap. Prod./jam = Asphalt Distributor

Koefisien = 1 : Q2

TENAGA
Produksi menentukan : ASPHALT SPRAYER
Produksi Lapis Resap Pengikat / hari = Tk x Q4
Kebutuhan tenaga :
- Pekerja
- Mandor

: 6.1 (2)
: Lapis Resap Pengikat
: Liter

Uraian

HARGA DASAR SATUN UPAH, BAHAN DAN ALAT


Lihat lampiran

ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIS STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelal . . . . . . . . . . . . . Bulan

VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pel 1,00 Liter
: 6.3 (5a)
: Laston Lapis Aus (AC-WC)
: M2

Uraian

ASUMSI
Menggunakan alat berat (cara mekanik)
Lokasi pekerjaan : sepanjang jalan
Kondisi existing jalan : sedang
Jarak rata-rata Base Camp ke lokasi pekerjaan
Tebal Lapis (AC-WC) padat
Jam kerja efektif per-hari
Faktpr kehilangan material

Berat isi Agregat (padat)


Berat isi Agregat (lepas)
Komposisi campuran AC-WC :
- Agr Pch Mesin 5 - 10 & 10 - 15 mm
- Agr Pch Mesin 0 - 5 mm
- Semen
- Asphalt
Berat isi bahan
- AC-WC
- Agr Pch Mesin 5 - 10 & 10 - 15 mm
- Agr Pch Mesin 0 - 5 mm
Jarak Stock pile ke Cold Bin

URUTAN KERJA

Wheel Loader memuat Agregat ke dalam


Cold Bin AMP
Agregat dan aspal dicampur dan dipanaskan dengan
AMP untuk dimuat langsung kedalam Dump Truck
dan diangkut ke lokasi pekerjaan.
Campurkan panas AC dihampar dengan Finisher dan
dipadatkan dengan Tandem & Pneumatic Tire Roller.
Selama pemadatan, sekelompok pekerja akan
merapikan tepi hamparan dengan menggunakan Alat
Bantu

PEMAKAIAN BAHAN, ALAT DAN TENAGA

BAHAN
Agr 5-10 & = ("5-10 & 10-15" x (D1 x tM3) x Fh1) :
Agr 0-5 = ("0-5" x (D1 x tM3) x Fh1) : D3
Semen = (FF x (D1 x tM3) x Fh1) x 1000
Aspal = (As x (D1 x tM3) x Fh2) x 1000

ALAT
WHEEL LOADER
Kapasitas bucket
Faktor bucket
Faktor effisiensi alat
Waktu siklus T1 + T2 + T3
- Kecepatan maju rata-rata
- Kecepatan mundur rata-rata
- Muat ke E (I x 60) / Vf
- Kembali ke Stock pile = (I x 60) / Vr
- Lain-lain (waktu pasti)

Kap. Prod. V
txT

Koefisien = 1 : Q1

: 6.3 (5a)
: Laston Lapis Aus (AC-WC)
: M2

Uraian

ASPHALT MIXING PLANT (AMP)


Kapasitas
Faktor Effisiensi alat

Kap. Prod. Vx Fa
D1 x t
Koefisien = 1 : Q2

GENERATORSET ( GENSET )
Kap. Prod. / Jam = SAMA DENGAN AMP
Koefisien = 1 : Q3

DUMP TRUCK (DT)


Kapasitas bak
Faktor Efisiensi alat
Kecepatan rata-rata bermuatan
Kecepatan rata-rata kosong
Kapasitas AMP / batch
Waktu menyiapkan 1 batck AC-BC
Waktu siklus
- Mengisi B = (V :Q2b) x Tb
- Angkut = (L : v1) x 60 menit
- Tunggu + dump + Putar
- Kembali = (L : v2) x 60 menit

Kap. Prod.

Koefisien = 1 : Q4

ASPHALT
Kecepatan menghampar
Faktor efisiensi alat
Lebar hampar
Kap. Prod. /

Koefisien = 1 : Q5

TANDEM ROLLER
Kecepatan rata-rata alat
Lebar efektif pemadatan
Jumlah lintasan
Faktor Efisiensi alat

Kap. Prod. (v

Koefisien = 1 : Q6

PNEUMATIC TIRE ROLLER


Kecepatan rata-rata
Lebar efektif pemadatan
Jumlah lintasan
Faktor Efisiensi alat

Kap. Prod./j (v

Koefisien = 1 : Q7

: 6.3 (5a)
: Laston Lapis Aus (AC-WC)
: M2
KODE

Q2
Qt

P
M

(L01)
(L03)
ITEM PEMBAYARAN NO. : 6.3 (6a)
JENIS PEKERJAAN : Laston Lapis Antara (AC-BC)
SATUAN PEMBAYARAN : M3

No. URAIAN KODE


I. ASUMSI
1. Menggunakan alat berat (cara mekanik)
2. Lokasi pekerjaan : sepanjang jalan
3. Kondisi existing jalan : sedang
4. Jarak rata-rata L
5. Tebal lapis (AC t
6. Jam kerja efekti Tk
7. Faktor kehilangan Fh1
Fh2
8. Berat isi Agreg Bip
9. Berat isi Agreg Bil
10. Komposisi campuran AC-BC
- Agr Pch Mesi 5 - 10 & 10 - 20

- Agregat Peca 0-5


- Semen FF
- Asphalt As
11. Berat isi bahan :
- AC-BC D1
- Agr Pch Mesi D2
- Agr Pch Mesi D3
12. Jarak Stock pil I

II. URUTAN KEDUA


1. Wheel Loader memuat Agregat ke dalam Cold Bin
2. Agregat dan aspal dicampur dan dipanaskan deng
kedalam Dump Truck dan diangkut ke lokasi peker
3. Campuran panas AC-BC dihampar dengan Finisher
& Pneumatic Tier Roller
4. Selama pemadatan, sekelompok pekerja akan mer
menggunakan Alat Bantu
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
1.a. Agr 5-10 & = ("5-10
(M92)
& 10-20" x (D1 x 1M3) x F
1.b. Agr 0-5 = ("0-5"
(M91)x (D1 x 1M3) x Fh1) : D3
1.c. Semen = (FF (M05)
x (D1 x 1M3) x Fh1) x 1000
1.d. Aspal = (As(M10)
x (D1 x 1M3) x Fh2) x 1000

2. ALAT
2.a WHEEL LOADE (E15)
Kapasitas buck V
Faktor bucket Fb
Faktor efisiensi Fa
Waktu Sikli T1 Ts1
- Kecepatan ma Vf
- Kecepatan ke Vr
- Muat ke E T1
- Kembali ke St T2
- Lain-lain (wa T3
Ts1

Kap. Prod. D2 x Q1
Ts1 x Fh1 x (Bip/Bil)

Koefisien = 1 : (E15)

ITEM PEMBAYAR
: 6.3 (6a)
JENIS PEKERJAA: Laston Lapis Antara (AC-BC)
SATUAN PEMBA: M3

No. URAIAN KODE


2.b. ASPHALT MIXIN (E01)
Kapasitas prod V
Faktor Efisiensi Fa

Kap. Prod ________V x Fa__________


Q2
D1
Koefisien = 1 : (E01)

2.c. GENERATORSET (E12)


Kap. Prod. / Q3
Koefisien = 1 : (E12)

2.d. DUMP TRUCK ( (E08)


Kapasitas bak V
Faktor Efisiensi Fa
Kecepatan rata v1
Kecepatan rata v2
Kapasitas AMP/ Q2b
Waktu menyiap Tb
Waktu Siklus Ts2
- Mengisi B = T1
- Angkut = (L T2
- Tunggu + du T3
- Kembali = (L T4
Ts2

Kap. Prod. V x Fa x 60__


Q4
D1 x Ts2

Koefisien = 1 : (E08)

2.e. ASPHALT (E02)


Kecepatan me V
Faktor efesiensi Fa
Lebar hampar b
Kap. Prod. Q5

Koefisien = 1 : (E02)

2.f. TANDEM ROLLE (E17)


Kecepatan rata- v
Lebar efektif b
Jumlah Lintasa n
Faktor Efesiensi Fa

Kap. Prod. __ (v x 1000)Q6


x b x t x Fa__
n

Koefisien (E17)

2. g. PNEUMATIC TIR (E18)


Kecepatan rata v
lebar efektif b
Jumlah Lintasa n
faktor Efisiensi Fa

Kap. Prod. __(v x 1000)Q7


x b x t x Fa__
n

Koefisien = 1 : (E18)

ITEM PEMBAYAR
: 6.3 (6a)
JENIS PEKERJAA: Laston Lapis Antara (AC-BC)
SATUAN PEMBA: M3

No. URAIAN KODE


2.h ALAT BANTU
diperlukan
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah
- Tongkat Kontrol ketebalan hanparan

3 TENAGA
Produksi menen Q2
Produksi AC-WC Qt
Kebutuhan tenaga :
- Pekerja P
- Mandor M

Koefisien Tenaga / M2 :
- Pekerja = (Tk (L01)
- Mandor = (Tk (L03)

4 HARGA DASAR SATUAN UPAH, BAHAN DAN AL


Lihat lampiran

5 ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNT
PEREKAMAN ANALISA MASING-MASING HARGA SAT
Didapat Harga Satuan Pekerjaan :

Rp.
1.734.269,48 / M3

6 WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelal............ Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN


Volume Pel 1,00 M3
Analisa EI-21

URAIAN ANALISA HARGA SATUAN


SATUAN KETERANGAN

jam
-
Ton/M3

Km

M3
-
-

menit
menit
M3

jam

ton
-
Km/Jam
Km/Jam

menit
menit
menit
menit

M3

Jam
Berlanjut ke hal. Berikut

Analisa EI-21

URAIAN ANALISA HARGA SATUAN

SATUAN KETERANGAN

M3/Jam
M3

orang
orang

Jam
Jam

Analisa EI-22

URAIAN ANALISA HARGA SATUAN


SATUAN KETERANGAN
KM
jam
%
%

%
%

ton/m3
ton/m3
ton/m3
ton/m3
ton/m3

M3
Lepas
Kg
M3

Liter
-

menit
menit
menit
menit
menit
M3

jam
Lump Sum

Analisa EI-22

URAIAN ANALISA HARGA SATUAN


SATUAN KETERANGAN

M3/Jam
M3

orang
orang
orang

jam
jam
jam

ANDAR UNTUK
ALISA MASING-MASING HARGA SATUAN
HARGA JUMLAH
SATUAN (Rp.) HARGA
(Rp.)

AN

ATAN

n, volume dan/atau

saikan satu-satuan
nyedia Jasa tidak dapat

MULIR STANDAR UNTUK


ANALISA MASING-MASING HARGA SATUAN
PERKIRAAN VOL. PEK
angan Batu Dengan Mortar untuk Saluran TOTAL HARGA (Rp.)
% THD. BIAYA PROYEK

PERKIRAAN HARGA JUMLAH


SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

Jam 4.0161
Jam 1.2048
Jam 0.4016

MLAH HARGA TENAGA

M3 1.0800
zak 161.0000
M3 0.4829

MLAH HARGA BAHAN

Jam 0.4016
Ls 1.0000

ERALATAN

n, volume dan/atau ukuran


saikan satu-satuan pekerjaan
a tidak dapat diubah kecuali
ruksi Kepada Peserta Lelang
kai dan operator
tapi tidak termasuk PPN

MULIR STANDAR UNTUK


ANALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL.PEK :
TOTAL HARGA (Rp.) :
% THD. BIAYA PROYEK :

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

GA

AN
ATAN

n, volume dan/atau ukuran berat

saikan satu satuan pekerjaan dari


pat diubah kecuali terdapat
ada Peserta Lelang
kai dan operator
n ( trtapi tidak termasuk PPN yang

SATUAN KETERANGAN

jam
-
Ton/M3 1.40-1.80

Km

M3
-
-
lihat panduan
menit
menit
menit
M3/jam

jam
ton
-
Km/Jam
Km/Jam

menit
menit
menit
menit
menit

M3

Jam
Lump Sump

SATUAN KETERANGAN

M3/jam
M3

orang
orang

Jam
Jam
MULIR STANDAR UNTUK
ANALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. PEK :


mbunan Biasa dari selain Sumber Galian TOTAL HARGA (Rp.) :
% THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


SATUAN
SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

Jam 0.0298
Jam 0.0075

MLAH HARGA TENAGA

M3 1.2000

MLAH HARGA BAHAN

Jam 0.0075
Jam 0.4267
Jam 0.1190
Jam 0.0109
Ls 1.0000

ERALATAN

n, volume dan/atau ukuran

saikan satu-satuan pekerjaan


a tidak dapat diubah kecuali
ruksi Kepada Peserta Lelang
kai dan operator
tapi tidak termasuk PPN

MULIR STANDAR UNTUK


ANALISA MASING-MASING HARGA SATUAN
PERKIRAAN VOL.PEK
enyiapan Badan Jalan TOTAL HARGA (Rp.)
% THD. BIAYA PROYEK

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

GA

AN

n, volume dan/atau ukuran berat

saiakan satu-satuan pekerjaan dari


ak dapat diubah kecuali terdapat
Kepada Peserta Lelang
kai dan operator
n (tetapi tidak termasuk PPN yang

SATUAN KETERANGAN

Jam

M
M


Km / Jam
lintasan

menit
menit
menit

M2

Jam

Km/Jam
M
lintasan

M2

Jam

Lump Sum

M2/Jam
M2

orang
orang

Jam
Jam

SATUAN KETERANGAN
MULIR STANDAR UNTUK
ANALISA MASING MASING HARGA SATUAN
PERKIRAAN VOL. PEK :
TOTAL HARGA :
% THD. BIAYA PROYEK :

HARGA JUMLAH
SATUAN HARGA
(Rp) (Rp)

GA

AN

ATAN

n, volume dan/atau ukuran

esaikan satu satuan pekerjaan dari nomor


at diubah kecuali terdapat Penyesuaian

ak yang berkaitan ( tetapi tidak termasuk PPN)


n ( tetapi tidak termasuk PPN yang dibayar dari

SATUAN KETERANGAN
KM
M

jam
% Gradasi harus
% memenuhi
% spec
ton/m3

M3

M3 (lepas)
kondisi sdg

menit panduan

M3

ton

KM/jam
KM/jam

menit
menit
menit
menit
menit

M3

jam

SATUAN KETERANGAN

M
M

KM/jam
lintasan 1 x pp

menit
menit
menit

M3

jam

KM/jam
M
lintasan

M3

jam

M3
M3
liter/mnt

M3

jam

Lump sum

M3/jam
M3

orang
orang

jam
jam

SATUAN KETERANGAN
FORMULIR STANDAR UNTUK
EKAMAN ANALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. PEK :


Pond. Agg. Kls. B TOTAL HARGA :
% THD. BIAYA PROYEK :

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

GA

AN
n, volume dan/atau ukuran

esaikan satu satuan pekerjaan dari nomor


at diubah kecuali terdapat Penyesuaian

ak yang berkaitan ( tetapi tidak termasuk PPN)


n ( tetapi tidak termasuk PPN yang dibayar dari

MULIR STANDAR UNTUK


ANALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. PEK :


pis Pondasi Agregat Kelas C TOTAL HARGA (Rp.) :
% THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

Jam 0.0898
Jam 0.0128

MLAH HARGA TENAGA

M3 1.2586

MLAH HARGA BAHAN


Jam 0.0128
Jam 0.4261
Jam 0.0039
Jam 0.0357
Jam 0.0141
Ls 1.0000
ERALATAN

n, volume dan/atau ukuran

saikan satu-satuan pekerjaan


a tidak dapat diubah kecuali
ruksi Kepada Peserta Lelang
kai dan operator
tapi tidak termasuk PPN

MULIR STANDAR UNTUK


ANALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. PEK :


pis Resap Pengikat TOTAL HARGA (Rp.) :
% THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

Jam 0.0021
Jam 0.0004

MLAH HARGA TENAGA


Kg 0.6790
liter 0.3708

MLAH HARGA BAHAN

Jam 0.0002
Jam 0.0002

ERALATAN

n, volume dan/atau ukuran

saikan satu-satuan pekerjaan


a tidak dapat diubah kecuali
ruksi Kepada Peserta Lelang
kai dan operator
tapi tidak termasuk PPN

MULIR STANDAR UNTUK


ANALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. PEK :


pis Resap Pengikat TOTAL HARGA (Rp.) :
% THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
Jam 0.3261
Jam 0.0466

MLAH HARGA TENAGA

M3 0.9018
M3 0.6330
Kg 46.2840
Kg 121.8696

MLAH HARGA BAHAN

Jam 0.0128
Jam 0.0466
Jam 0.0466
Jam 0.8579
Jam 0.0255
Jam 0.6510
Jam 0.0291
Ls 1.0000
ERALATAN

n, volume dan/atau ukuran

saikan satu-satuan pekerjaan


a tidak dapat diubah kecuali
ruksi Kepada Peserta Lelang
kai dan operator
tapi tidak termasuk PPN

MULIR STANDAR UNTUK


ANALISA MASING-MASING HARGA SATUAN
PERKIRAAN VOL. PEK :
pis Perekat TOTAL HARGA (Rp.) :
% THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

Jam 0.0021
Jam 0.0004

MLAH HARGA TENAGA

Kg 0.8487
liter 0.2060

MLAH HARGA BAHAN

Jam 0.0002 254201.2


Jam 0.0002 111049.4

ERALATAN

n, volume dan/atau ukuran

saikan satu-satuan pekerjaan


a tidak dapat diubah kecuali
ruksi Kepada Peserta Lelang
kai dan operator
tapi tidak termasuk PPN

MULIR STANDAR UNTUK


ANALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. PEK :


ton Lapis Aus (AC-WC) TOTAL HARGA (Rp.) :
% THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

Jam 0.0186
Jam 0.0019

MLAH HARGA TENAGA

M3 0.0307
M3 0.0298
Kg 1.8514
Kg 5.1615

MLAH HARGA BAHAN

Jam 0.0009
Jam 0.0019
Jam 0.0019
Jam 0.0343
Jam 0.0013
Jam 0.0033
Jam 0.0015
Ls 1.0000
ERALATAN

n, volume dan/atau ukuran

saikan satu-satuan pekerjaan


a tidak dapat diubah kecuali
ruksi Kepada Peserta Lelang
kai dan operator
tapi tidak termasuk PPN

Resap Pengikat

KODE

t (cara mekanik)
njang jalan
mp ke lokasi pekerjaan L
ri Tk
n Fh

n 80 As
K

n 80 D1
D2
inyak pencair) semuanya diterima

dicampur dan dipanaskan


uran aspal cair
dilapis dibersihkan dari debu
Compressor
semprotkan dengan Asphalt
ukaan yang dilapis

ALAT DAN TENAGA

ter lapis Resap Pengikat


) PC

(M10)
(M11)

(E41)
b
an V
pas
Fa

Pas x Fa x 60 Q1

(E41)

(E05)

alt Distributor Q2

(E05)

ASPHALT DISTRIBUTOR Q4
engikat/hari = Tk x Q4 Qt

P
M

Resap Pengikat

KODE

:
= (Tk x P) : Qt
= (Tk x M) : Qt

N UPAH, BAHAN DAN ALAT


UAN PEKERJAAN
FORMULIS STANDAR UNTUK
MASING-MASING HARGA

Pekerjaan :

N YANG DIPERLUKAN
... Bulan

YANG DIPERLUKAN
1,00 Liter
KODE

t (cara mekanik)

mp ke lokasi pekerjaan L
Tk
Fh

As
K

D1
D2
inyak pencair) semuanya

icampur dan dipanaskan


uran aspal cair
dilapis dibersihkan dari debu

semprotkan dengan Asphlat


ukaan yang akan dilapis

ALAT DAN TENAGA

ter Lapis Resap Pengikat


PC

(M10)
(M11)
(E41)
b
V
pas
Fa

pas x Fa x 60 Q1

(E41)

(E05)

Q2

(E05)

ASPHALT SPRAYER Q4
engikat / hari = Tk x Q4 Qt

= (Tk x P) :Qt P
= (Tk x M) :Qt M

Resap Pengikat

KODE

N UPAH, BAHAN DAN ALAT

UAN PEKERJAAN
FORMULIS STANDAR UNTUK
MASING-MASING HARGA

N YANG DIPERLUKAN
... Bulan

YANG DIPERLUKAN
1,00 Liter
n Lapis Aus (AC-WC)

KODE

t (cara mekanik)

mp ke lokasi pekerjaan L
t
Tk
- Agregat Fh1
- Aspal Fh2
Bip
Bil

5-10 & 10-5

0-5
FF
As

D1
D2
D3
I

Agregat ke dalam

mpur dan dipanaskan dengan


sung kedalam Dump Truck

ihampar dengan Finisher dan


dem & Pneumatic Tire Roller.
kelompok pekerja akan
an dengan menggunakan Alat

ALAT DAN TENAGA

0 & 10-15" x (D1 x tM3) x Fh1) : D2 (M92)


" x (D1 x tM3) x Fh1) : D3 (M91)
x (D1 x tM3) x Fh1) x 1000 (M05)
x (D1 x tM3) x Fh2) x 1000 (M10)

(E15)
V
Fb
Fa
Ts1
Vf
Vr
T1
= (I x 60) / Vr T2
T3
Ts1

V x Fb x Fa x 60 Q1
t x Ts1 x (Bip/Bil) x Fh1

(E15)

n Lapis Aus (AC-WC)

KODE

(E01)
v
Fa

Vx Fa Q2
D1 x t
(E01)

(E12)
A DENGAN AMP Q3
(E12)

(E08)
V
Fa
v1
v2
Q2b
Tb
Ts2
T1
T2
T3
T4
Ts2

V x Fa x 60 Q4
D1 x Ts2 x t

(E08)

(E02)
V
Fa
b
V x b x 60 x Fa Q5

(E02)

(E17)
v
b
n
Fa

(v x 1000) x b x Fa Q6
n
(E17)

(E18)
v
b
n
Fa

(v x 1000) x b x Fa Q7
n
(E18)

on Lapis Aus (AC-WC)


KOEF. SATUAN KETERANGAN

Lump Sum

536.64 M2
3756.47 M2

10.00 orang
1.00 orang

0.0186 Jam
0.0019 Jam
on Lapis Antara (AC-BC)

KOEF. SATUAN KETERANGAN

erat (cara mekanik)


panjang jalan

8.73 KM
0.05 M
7 Jam
1.05 -
1.03 -
1.81 ton/m3
1.51 ton/m3

52.2 % Gradasi harus-


40.8 % memenuhi -
1.9 % Spesifikasi
5.1 %

2.32 ton/M3
1.41 ton/M3
1.57 ton/M3
0.05 km

at Agregat ke dalam Cold Bin AMP


campur dan dipanaskan dengan AMP untuk dimuat langsung
dan diangkut ke lokasi pekerjaan
BC dihampar dengan Finisher dan dipadatkan dengan Tandem

sekelompok pekerja akan merapikan tepi hamparaan dengan


N, ALAT DAN TENAGA

0.9018 M3
0.633 M3
46.2824 Kg
121.87 Kg

1.5 M3 panduan
0.85 -
0.83 -
1.1 menit
15 km/jam panduan
20 km/jam panduan
0.2 menit
0.15 menit
0.75 menit
1.1 menit

45.86 ton

0.0218 jam

on Lapis Antara (AC-BC)

KOEF. SATUAN Keterangan

60 ton/ Jam
0.83 -

21.47 M3

0.0466 Jam

21.47 M3
0.0466 Jam

3.5 ton
0.80 -
20.00 Km / Jam
30.00 Km/ Jam
1.00 ton
1.00 menit

3.5 menit
26.18 menit
15.00 menit
17.45 menit
62.13 menit

1.17 M3

0.8579 Jam

5.00 m/menit
0.83 -
3.15 meter
39.22 M3

0.0255 Jam

1.50 Km/ Jam


1.48 M
6.00 Lintasan
0.83 -

15.36 M3

0.0651 Jam

2.50 Km / Jam
1.99 M
6.00 Lintasan
0.83 -

34.41 M3

0.0291 Jam
on Lapis Antara (AC-BC)

KOEF. SATUAN Keterangan

Lump Sum

ebalan hanparan

21.47 M3
150.26 M3

7.00 orang
1.00 orang

0.3261 Jam
0.0466 Jam

UAN UPAH, BAHAN DAN ALAT

ATUAN PEKERJAAN
am FORMULIR STANDAR UNTUK
MASING-MASING HARGA SATUAN

34.269,48 / M3

AAN YANG DIPERLUKAN


Bulan

N YANG DIPERLUKAN
1,00 M3
1.00
155108.97
0.01
1.00
71846.43
Analisa EI-611

URAIAN ANALISA HARGA SATUAN

KOEF. SATUAN KETERANGAN

8,73 KM
7,00 Jam
1,03 -

64 % Terhadap volume

36 % Terhadap volume

1,03 Kg/liter
0,80
1,03 liter

0,6790 Kg.
0,3708 Liter

3,00 M
30,00 m/menit Asumsi
100 liter/menit Panduan
0,80 Sedang

4.800,00 Liter

0,0002 Jam

4.800,00 Liter

0,0002 Jam

4.800,00 Liter
33.600,00 Jam

10,00 orang
2,00 orang

Berlanjut ke hal. Berikut

Analisa EI-611

URAIAN ANALISA HARGA SATUAN

Lanjutan

KOEF. SATUAN KETERANGAN

(L01) 0,0021 Jam


(L03) 0,0004 Jam
Analisa EI-612

URAIAN ANALISA HARGA SATUAN

KOEF. SATUAN KETERANGAN

8,73 KM
7,00 Jam
1,03 -

64 % Terhadap volume

36 % Terhadap volume

1,03 Kg/liter
0,80

1,03 liter

0,8487 Kg.
0,2060 Liter
3,00 M
30,00 m/menit Asumsi
100 liter/menit Panduan
0,80 Sedang

4.800,00 Liter

0,0002 Jam

4.800,00 Liter

0,0002 Jam

4.800,00 Liter
33.600,00 Jam

10,00 orang
2,00 orang

Berlanjut ke hal. Berikut

Analisa EI-612

URAIAN ANALISA HARGA SATUAN

Lanjutan

KOEF. SATUAN KETERANGAN


Analisa EI-635(a)

URAIAN ANALISA HARGA SATUAN

KOEF. SATUAN KETERANGAN

8,73 KM
0,04 M
7,00 Jam
1,05 -
1,03 -
1,81 ton/m3
1,51 ton/m3

44,70 %
48,00 %
1,90 %
5,40 %

2,32 ton/m3
1,42 ton/m3
1,57 ton/m3
0,05 km

0,0307 M3
0,0298 M3
1.8514 Kg
5.1615 Kg

1,50 M3
0,85 -
0,83 -
1,10 menit
15,00 km/jam
20,00 km/jam
0,20 menit
0,15 menit
0,75 menit
1,10 menit

1.146,56 M2

0,0009 Jam

Berlanjut ke hal. Berikut

Analisa EI-635(a)

URAIAN ANALISA HARGA SATUAN

Lanjutan

KOEF. SATUAN KETERANGAN

60,00 Ton / Jam


0,83 -

536,64 M2

0,0019 Jam

536,64 M2
0,0019 Jam

3,50 Ton
0,80 -
20,00 KM / Jam
30,00 KM / Jam
1,00 ton
1,00 menit

3,50 menit
26,18 menit
15,00 menit
17,45 menit
62,13 menit

29,14 M2

0,0343 Jam

5,00 m/menit
0,83 -
3,15 meter
784,35 M2

0,0013 Jam

1,50 Km / Jam
1,48 M
6,00 lintasan 2 Awal & 4 Akhir

0,83 -

307,10 M2

0,0033 Jam

2,50 KM / Jam
1,99 M
6,00 lintasan
0,83 -

688,21 M2

0,0015 Jam

Berlanjut ke hal. Berikut


ITEM PEMBAYAR
: 3.2 (1)
JENIS PEKERJAA: Timbunan Biasa dari selain Sumber Galian
SATUAN PEMBA: M3

No. URAIAN KODE KOEF.


I ASUMSI
1 Pekerjaan dilakukan secra mekanis
2 Lokasi pekerjaan: sepanjang jalan
3 Kondisi Jalan: baik
4 Jam kerja efektif per-hari Tk 7.00
5 Faktor pengembangan bahan Fk 1.20
6 Tebal hamparan padat t 0.15
7 Berat volume bahan (lepas) D 1.60

II URUTAN KERJA
1 Excavator menggali dan memuat ke dalam drump truck
2 Dump Truck mengangkut ke lapangan dengan L 8.70
3 Material diratakan dengan menggunakan Motor Grader
4 Material dipadatkan menggunakan Vibratory Roller
5 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III PEMAKAIAN BAHAN, ALAT DAN TENAGA


1 BAHAN
1.a. Bahan timb= 1 x Fk (M08) 1.20

2 ALAT
2.a. EXCAVATOR (E15)
Kapasitas Bucket V 0.93
Faktor Bucket Fb 1.00
Faktor Efisiensi Alat Fa 0.83
Faktor Konvensi Fv 0.90
Waktu siklus Ts1
- Muat T1 0.32
Waktu Siklus= T1 x Fv Ts1 0.29

Kapasitas ProdV x Fb x Fa x 60 Q1 134.01


Fkk x Ts 1

Koefisien = 1 : Q1 (E10) 0.0075

DUMP TRUCK (E08)


Kapasitas bak V 3.50
Faktor efisiensi alat Fa 0.83
Kecepatan rata-rata bermuatan v1 20.00
Kecepatan rata-rata kosong v2 30.00
Waktu siklus: Ts2
- Waktu = (V x 60) (D x Q1) T1 0.98
- Waktu tempuh isi = (L : v1) x 60 T2 26.10
- Waktu tempuh kosong = (L : v2) x 60 T3 17.40
- Lain-lain T4 2.00
Ts2 46.48

Kapasitas Produ V x Fa x 60 Q2 2.34


D x Ts2

Koefisien = 1 : Q2 (E08) 0.4267


ITEM PEMBAYAR
: 3.2 (1)
JENIS PEKERJAA: Timbunan Biasa dari selain Sumber Galian
SATUAN PEMBA: M3

SATUAN Keterangan No. URAIAN KODE KOEF. SATUAN


2.c. MOTOR GRADE (E13)
Panjang Hampa Lh 50.00 M
Lebar Overlap bo 0.30 M
Faktor Efisiensi Fa 0.80 -
Jam Kecepatan rata- v 4.00 Km / Jam
- Jumlah lintasan n 2 lintasan
M Lebar pisau efe bo 2.6 M
Ton/M3 Waktu siklus Ts3
- Perataan 1 kali lintasan
T1 __Lh x 60__0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit
Km
Kapasitas Prod/Jam =Q3__Lh x (n(b-bo)+bo
8.40
x t x Fa x
M360
Ts3 x n

Koefisien = 1 : Q3 (E13) 0.1190 Jam

2.d. VIBRATOR ROL (E19)


Kecepatan rata- v 4.00 Km / Jam
Lebar efektif b 1.48 M
M3 Jumlah lintasan n 8.00 lintasan
Faktor efisiensi Fa 0.83 -

Kapasitas = _________(v
Q4 x 1000) x b x 92.13
t x Fa_________
M3
M3 n
-
- Koefisien = 1 : Q4 (E19) 0.0109 Jam
Lihat panduan
2.e. ALAT BANTU
menit Diperlukan alat-alat bantu kecil
menit - Sekop = 3 buah

M3 3 TENAGA
Prooduksi men Q1 134.01 M3/Jam
Produksi Timbu Qt 938.07 M3
Jam Kebutuhan tenaga:
P 4.00 orang
M 1.00 orang
Ton
- Koefisien tenaga / M3 :
KM/Jam (L01) 0.0298 Jam
KM/Jam (L02) 0.0075 Jam

menit 4 HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


menit Lihat lampiran
menit
menit
menit

M3

Jam
ITEM PEMBAYAR
: 3.2 (1)
JENIS PEKERJAA: Timbunan Biasa dari selain Sumber Galian
SATUAN PEMBA: M3

KETERANGAN No. URAIAN KODE KOEF. SATUAN KETERANGAN

5 ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan:

Rp . 155.108,97
/ M3

6 WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelal .................... Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pel 1,00 M3

Lump Sump

You might also like