You are on page 1of 10

WHAT EVERY

ENGINEER
SHOULD KNOW
ABOUT WELDING
From amperage
W
ITHIN THE WELDING INDUS - primary variable in determining
TRY, THE TERM W E L D I N G heat input. Generally, an increase in
P ROCEDURE S PECIFICATION amperage means higher deposition
to preheat, (or WPS) is used to signify the com- rates, deeper penetration, and more
bination of variables used to make a admixture. The amperage flowing
theres more to certain weld. At a minimum the through an electrical circuit is the
WPS (or Welding Procedure or same, regardless of where it is mea-
welding simply Procedure) consists of:
process (Shielded Metal Arc Welding
sured. It may be measured with a
tong meter or with the use of an
procedures than [SMAW], Flux Cored Arc Welding
[FCAW], etc.); electrode specification
electrical shunt. The role of amper-
age is best understood in the context
meets the eye (AWS A5.1, A5.20, etc.); electrode
classification (E7018, E71T-1, etc.);
of heat input and current density
considerations. For CV welding, an
By Duane K. Miller, P.E. electrode diameter; electrical charac- increase in wire feed speed will
teristics ( (AC, DC+, DC-); base directly increase amperage. For
metal specification (A36, A572 Gr. SMAW on CC systems, the machine
50, etc.); minimum preheat and setting determines the basic amper-
interpass temperature; welding cur- age, although changes in the arc
rent (amperage)/wire feed speed; arc length (controlled by the welder) will
voltage; travel speed; position of further change amperage. Longer
welding; post weld heat treatment; arc lengths reduce amperage.
shielding gas type and flow rate; and Arc voltage is directly related to
joint design details. arc length. As the voltage increases,
The welding procedure is some- the arc length increases, as does the
what analogous to a cooks recipe: It demand for arc shielding. For CV
outlines the steps required to make welding, the voltage is determined
a quality weld under specific condi- primarily by the machine setting, so
tions. the arc length is relatively fixed in
CV welding. For SMAW on CC sys-
EFFECTS OF WELDING VARIABLES tems, however, the arc voltage is
The effects of the variables are determined by the arc length, which
somewhat dependent on the welding is manipulated by the welder. As arc
process being employed, but general lengths are increased with SMAW,
trends apply to all the processes. It the arc voltage will increase, and the
is important to distinguish the dif- amperage will decrease. Arc voltage
ference between constant current also controls the width of the weld
(CC) and constant voltage (CV) elec- bead, with higher voltages generat-
trical welding systems. Shielded ing wider beads. Arc voltage has a
metal arc welding is always done direct effect on the heat input com-
with a CC system, while flux cored putation.
welding and gas metal arc welding The voltage in a welding circuit
generally are performed with CV is not constant, but is composed of a
systems. Submerged arc may utilize series of voltage drops. Consider the
either. following example: assume the
Amperage is a measure of the power source delivers a total system
amount of current flowing through voltage of 40 volts. Between the
the electrode and the work. It is a power source and the welding head

Modern Steel Construction / May 1997


or gun, there is a voltage drop of per-
haps 3 volts associated with the
input cable resistance. From the
point of attachment of the work head
to the power source work terminal,
there is an additional voltage drop
of, say, 7 volts. Subtracting the 3
volts and the 7 volts from the origi-
nal 40 leaves 30 volts for the arc.
This example illustrates how impor-
tant it is to ensure that the voltages
used for monitoring welding proce-
dures properly recognize any losses
in the welding circuit. The most
accurate way to determine arc volt-
age is to measure the voltage drop
between the contact tip and the
work piece. However, this may not
be practical for semiautomatic weld-
ing, so voltage is typically read from
a point on the wire feeder (where the
gun and cable connection is made),
to the workpiece. For SMAW weld-
ing, voltage is not usually moni-
tored, since it is constantly changing
and cannot be controlled except by
the welder. Skilled welders hold
short arc lengths to deliver the best
weld quality.
Travel speed, measured in inch-
es per minute, is the rate at which
the electrode is moved relative to the
joint. All other variables being Wire feed speed is the preferred electrode extension is increased in a
equal, travel speed has an inverse method of maintaining welding pro- constant voltage system, the electri-
effect on the size of the weld beads. cedures for constant voltage wire cal resistance of the electrode
As the travel speed increases, the feed processes. The wire feed speed increases, causing the electrode to be
weld size will decrease. Extremely can be independently adjusted and heated. This is known as resistance
low travel speeds may result in measured directly, regardless of the heating or I2R heating. As the
reduced penetration, as the arc other welding conditions. It is possi- amount of heating increases, the arc
impinges on a thick layer of molten ble to utilize amperage as an alter- energy required to melt the electrode
metal and the weld puddle rolls native to wire feed speed although decreases. Longer electrode exten-
ahead of the arc. Travel speed is a the resultant amperage for a given sions may be employed to gain high-
key variable used in computing heat wire feed speed may vary, depending er deposition rates at a given amper-
input (reducing travel speed increas- on polarity, electrode diameter, elec- age. When the electrode extension is
es heat input). trode type and electrode extension. increased without any change in
Wire feed speed is a measure of Although equipment has been avail- wire feed speed, the amperage will
the rate at which the electrode is able for two decades that monitor decrease. This results in less pene-
passed through the welding gun and wire feed speed, many codes such as tration and less admixture. With the
delivered to the arc. Typically mea- AWS D1.1 continue to acknowledge increase in electrical stickout, it is
sured in inches per minute (ipm), amperage as the primary method for common to increase the machine
the deposition rates are directly pro- procedure documentation. D1.1 does voltage setting to compensate for the
portional to wire feed speed and permit the use of wire feed speed greater voltage drop across the elec-
directly related to amperage. When control instead of amperage, provid- trode.
all other welding conditions are ing a wire feed speed-amperage rela- In constant voltage systems, it is
maintained constant, an increase in tionship chart is available for com- possible to simultaneously increase
wire feed speed will directly lead to parison. Specification sheets both the ESO and the wire feed
an increase in amperage. For slower supplied by the filler metal manufac- speed in a balanced manner so that
wire feed speeds, the ratio of wire turer provide data that support the current remains constant. When
feed speed to amperage is relatively these relationships. this is done, higher deposition rates
constant and linear. For higher wire Electrode extension, also known are attained. Other welding vari-
feed speeds, this ratio may increase, as electrical stickout or ESO, is the ables, such as voltage and travel
resulting in a higher deposition rate distance from the contact tip to the speed, must be adjusted to maintain
per amp, but at the expense of pene- end of the electrode. It applies only a stable arc and to ensure quality
tration. to the wire fed processes. As the welding. The ESO variable should

Modern Steel Construction / May 1997


always be within the range recom- input. strength, the required level of pene-
mended by the manufacturer. Current density is determined tration is a function of the joint
Electrode diameter is another by dividing the welding amperage by design in the weld type. All welds
critical variable. Larger electrodes the cross sectional area of the elec- are required to deliver a certain
can carry higher welding currents. trode. For solid electrodes, the cur- yield and/or tensile strength,
For a fixed amperage, however, rent density is therefore proportion- although the exact level required is
smaller electrodes result in higher al to I/d 2. For tubular electrodes a function of the connection design.
deposition rates. This is because of where current is conducted by the Not all welds are required to deliver
the effect on current density dis- sheath, the current density is relat- minimum specified levels of notch
cussed below. ed to the area of the metallic cross toughness. Acceptable levels of
Polarity is a definition of the section. As the current density undercut and porosity are a function
direction of current flow. Positive increases, there will be an increase of the type of loading applied to the
polarity (reverse) is achieved when in deposition rates, as well as pene- weld. Determination of the most
the electrode lead is connected to the tration. The latter will increase the efficient means by which these con-
positive terminal of the direct cur- amount of admixture for a given ditions can be met cannot be left to
rent (DC) power supply. The work joint. Notice that this may be the welders, but is determined by
lead is connected to the negative ter- accomplished by either increasing knowledgeable welding technicians
minal. Negative polarity (straight) the amperage or decreasing the elec- and engineers who create written
occurs when the electrode is connect- trode size. Because the electrode welding procedure specifications and
ed to the negative terminal and the diameter is a squared function, a communicate those requirements to
work lead to the positive terminal. small decrease in diameter may welders by the means of these docu-
Alternating current (AC) is not a have a significant effect on deposi- ments. The WPS is the primary tool
polarity, but a current type. With tion rates and plate penetration. that is used to communicate to the
AC, the electrode is alternately posi- Preheat and interpass tempera- welder, supervisor, and the inspector
tive and negative. Submerged arc is ture are used to control cracking how a specific weld is to be made.
the only process that commonly uses tendencies, typically in the base The suitability of a weld made by a
either electrode positive and elec- materials. Regarding weld metal skilled welder in conformance with
trode negative polarity for the same properties, for most carbon-man- the requirements of a WPS can only
type of electrode. AC may also be ganese-silicon systems, a moderate be as good as the WPS itself.
used. For a fixed wire feed speed, a interpass temperature promotes Procedural variable values must be
submerged arc electrode will require good notch toughness. Preheat and properly selected in order to have a
more amperage on positive polarity interpass temperatures greater than WPS appropriate for the application.
than on negative. For a fixed 550 degrees F may negatively affect The ability of a welder to follow a
amperage, it is possible to utilize notch toughness. When the base written WPS is determined by
higher wire feed speeds and deposi- metal receives little or no preheat, welder qualification tests (D1.1-96,
tion rates with negative polarity the resultant rapid cooling may also paragraph C4.1.2). The welder may
than with positive. AC exhibits a lead to a deterioration of notch not know how or why each particu-
mix of both positive and negative toughness. Therefore, careful con- lar variable was selected, although
polarity characteristics. trol of preheat and interpass tem- these values must be used in produc-
The magnetic field that sur- peratures is critical. tion. The inspector is required to
rounds any DC conductor can cause ensure that all welding is done in
a phenomenon known as arc blow, PURPOSE OF WPSS accordance with the WPS, observing
where the arc is physically deflected The particular values for the vari- the technique of each welder on a
by the field. The strength of the ables discussed above have signifi- periodic basis (D1.1-96, paragraph
magnetic field is proportional to the cant affect on weld soundness, 6.5.4). Inspectors do not develop
square of the current value, so this mechanical properties, and produc- WPSs, but they must ensure the pro-
is a more significant potential prob- tivity. It is therefore critical that cedures exist and are followed (D1.1-
lem with higher currents. AC is less those procedural values used in the 96, paragraph 6.3.1).
prone to arc blow, and can some- actual fabrication and erection be The D1.1-96 Structural Welding
times be used to overcome this phe- appropriate for the specific require- Code - Steel requires written weld-
nomenon. ments of the applicable code and job ing procedures for all fabrication
Heat input is proportional to specifications. Welds that will be performed (D1.1-96, paragraph 5.5).
the welding amperage, times the arc architecturally exposed, for example, These WPSs are required to be writ-
voltage, divided by the travel speed. should be made with procedures ten, regardless of whether they are
Higher heat inputs relate to larger that minimize spatter, encourage prequalified or qualified by test.
weld cross sectional areas, and larg- exceptional surface finish, and have Each fabricator or erector is respon-
er heat affected zones, which may limited or no undercut. Welds that sible for the development of WPSs
negatively affect mechanical proper- will be covered with fireproofing, in (D1.1-96, paragraph 4.1.1.1, 4.6).
ties in that region. Higher heat contrast, would naturally have less Confusion about this issue apparent-
input generally results in slightly restrictive cosmetic requirements. ly still exists since there continue to
decreased yield and tensile strength Many issues must be considered be reports of fabrication being per-
in the weld metal, and generally when selecting welding procedure formed in the absence of written
lower notch toughness because of values. While all welds must welding procedure specifications.
the interaction of bead size and heat achieve fusion to ensure their One prevalent misconception is that

Modern Steel Construction / May 1997


if the actual parameters under rective measures to be taken may ment that they be written. The use
which welding will be performed necessitate weld removal and of prequalified WPSs still requires
meet all the conditions for prequali- replacement, an activity that rou- that the welders be appropriately
fied status, written WPSs are not tinely increases the cost of that par- qualified. All the workmanship pro-
required. This is not true. As has ticular weld tenfold. Avoiding these visions imposed in the fabrication
been shown in the cited code refer- types of unnecessary activities by section of the code apply to prequali-
ences, the requirement is clear. clear communication has obvious fied WPSs. The only code require-
The WPS is a communication quality and economic ramifications. ment exempted by prequalification
tool, and it is the primary means of There are other economic issues is the nondestructive testing and
communication to all the parties to be considered as well. In a most mechanical testing required for
involved regarding how the welding general way, the cost of welding is qualification testing of welding pro-
is to be performed. It must therefore inversely proportional to the deposi- cedures.
be readily available to foremen, tion rate. The deposition rate, in A host of restrictions and limita-
inspectors and the welders. The turn, is directly tied to the wire feed tions imposed on prequalified weld-
code is not prescriptive in its speed of the semiautomatic welding ing procedures do not apply to weld-
requirements regarding availability processes. If it is acceptable, for ing procedures that are qualified by
and distribution of WPSs. Some example, to make a given weld with test. Prequalified welding proce-
shop fabricators have issued each a wire feed speed of 200 ipm, then a dures must conform with all the pre-
welder employed in their organiza- weld made at 160 ipm (which may qualified requirements in the code.
tion with a set of welding procedures meet all the quality requirements) Failure to comply with a single pre-
that are typically retained in the would cost approximately 25% more qualified condition eliminates the
welders locker or tool box. Others than the weld made at the optimum opportunity for the welding proce-
have listed WPS parameters on shop procedure. Conformance with WPS dure to be prequalified (D1.1-96,
drawings. Some company bulletin values can help ensure that con- paragraph 3.1).
boards have listings of typical WPSs struction is performed at rates that In order for a WPS to be prequali-
used in the organization. Regardless are conducive to the required weld fied, the following conditions must
of the method used, WPSs must be quality and are economical as well. be met:
available to those authorized to use The code imposes minimum The welding process must be pre-
them. requirements for a given project. qualified. Only SMAW, SAW,
It is in the contractors best inter- Additional requirements may be GMAW (except GMAW-s), and
est to ensure that efficient communi- imposed by contract specifications. FCAW may be prequalified
cation is maintained with all parties The same would hold true regarding (D1.1-96, paragraph 3.2.1).
involved. Not only can quality be WPS values. Compliance with the The base metal/filler metal com-
compromised when WPSs are not minimum requirements of the code bination must be prequalified.
available, but productivity can suffer may not be adequate under all cir- Prequalified base metals, filler
as well. Regarding quality, the lim- cumstances. Additional require- metals, and combinations are
its of suitable operation of the par- ments can be communicated through shown in D1.1-96, paragraph 3.3,
ticular welding process and electrode the WPS. For example, the D1.1-96 Table 3.1.
The minimum preheat and inter-
for the steel, joint design and posi- code permits the use of an E71T-11
pass temperatures prescribed in
tion of welding must be understood. FCAW electrode for multiple pass
D1.1-96, paragraph 3.3, Table
Obviously, the particular electrode welding without any restriction on 3.2 must be employed (D1.1-96,
employed must be operated on the plate thickness. The Lincoln paragraph 3.5).
proper polarity, proper shielding Electric product, Innershield Specific requirements for the var-
gases must be used, and amperage NR211MP, has a maximum thick- ious weld types must be main-
levels must be appropriate for the ness restriction imposed by the man- tained. Fillet welds must be in
diameter of electrode, and for the ufacturer of 1/2 . This additional accordance with D1.1-96, para-
thickness of material on which weld- requirement can be incorporated graph 3.9, plug and slot welds in
ing is performed. Other issues may into the applicable WPS. Other rec- accordance with D1.1-96, para-
not be as obvious. For example, the ommendations that may be imposed graph 3.10, and groove welds in
required preheat for a particular by the steel producer, electrode man- accordance with D1.1-96, para-
application is a function of the ufacturer, or others can and should graph 3.11, 3.12, and 3.13 as
grade(s) of steel involved, the thick- be documented in the WPS. applicable. For the groove welds,
ness(es) of material, and the type of whether partial joint penetration
electrode employed (whether low PREQUALIFIED PROCEDURES or complete joint penetration, the
hydrogen or non-low hydrogen). All The AWS D1.1 code provides for required groove preparation
of this can be communicated by the use of prequalified WPSs. dimensions are shown in D1.1-96,
means of the written WPS. Prequalified WPSs are those that Figures 3.3 and 3.4.
Lack of conformance with the the AWS D1 Committee has deter- Even if prequalified joint details
parameters outlined in the WPS mined to have a history of accept- are employed, the welding procedure
may result in the deposition of a able performance, and so does not must be qualified by test if other
weld that does not meet the quality subject them to the qualification prequalified conditions are not met.
requirements imposed by the code or testing imposed on all other welding For example, if a prequalified detail
the job specifications. When an procedures. The use of prequalified is used on an unlisted steel, the
unacceptable weld is made, the cor- WPSs does not preclude the require- welding procedures must be quali-
fied by test.

Modern Steel Construction / May 1997


for the thickness of steel on which
the weld is being made is inappro-
priate. It would not meet the
requirements of D1.1-96, paragraph
5.3.1.2 in the section entitled
Fabrication, which requires that the
size of electrode and amperage be
suitable for the thickness of material
being welded. This illustration
demonstrates the fact that compli-
ance with all prequalified conditions
does not guarantee that the combi-
nation of selected variables will
always generate an acceptable weld.
Most contractors will determine
preliminary values for a prequalified
WPS based upon their experience,
recommendations from publications
such as Lincoln Electrics Procedure
Handbook of Arc Welding, industry
publications such as the AWS
Welding Handbooks, from AWS
Welding Procedure Specifications
(AWS B2.1), or other sources. It is
the responsibility of the contractor
to verify the suitability of the sug-
gested parameters prior to the appli-
cation of the actual procedure on a
project, although the verification
test need not be subject to the full
range of procedure qualification
tests imposed by the code. Typical
Prequalified status requires con- It is the contractors responsibili- tests will be made to determine
formance to a variety of procedural ty to ensure that the particular soundness of the weld deposit (e.g.,
parameters. These are largely con- parameters selected within the fusion, tie-in of weld beads, freedom
tained in D1.1-96, Table 3.7, and requirements of the prequalified from slag inclusions, etc.). The plate
include maximum electrode diame- WPS are suitable for the specific could be nondestructively tested or,
ters, maximum welding current, application. An extreme example as is more commonly done, cut, pol-
maximum root pass thickness, maxi- will serve as an illustration. ished, and etched. The latter opera-
mum fill pass thicknesses, maxi- Consider the following example of a tions allow for examination of pene-
mum single-pass fillet weld sizes, hypothetical proposed WPS for tration patterns, bead shapes, and
and maximum single pass weld lay- making a fillet weld on 3/8 A36 tie-in. Welds made with prequali-
ers (D1.1-96, Table 3.3). In addition steel in the flat position. The weld fied WPSs that meet the physical
to all the preceding requirements, type and steel are prequalified. dimensional requirements (fillet
welding performed with a prequali- SAW, a prequalified process, is weld size, maximum reinforcement
fied WPS must be in conformance selected. The filler metal selected is levels, and surface profile require-
with the other code provisions con- F7A2-EM12K, meeting the require- ments), and are sound (that is, hav-
tained in the fabrication section of ments of D1.1-96, Table 3.1. No pre- ing adequate fusion, tie-in and free-
AWS D1.1-96 Structural Welding heat is specified since it would not dom from excessive slag inclusions
Code. be required according to D1.1-96, and porosity) should meet the
The code does not imply that a Table 3.2. The electrode diameter strength and ductility requirements
WPS that is prequalified will auto- selected is 3/32, less than the max- imposed by the code for welding pro-
matically achieve the quality condi- imum specified in D1.1-96, Table cedures qualified by test. Weld
tions required by the code. The com- 3.7. The maximum single pass fillet soundness, however, cannot be
mentary language for paragraph weld size in the flat position, accord- assumed just because the WPS is
3.2.1 states the following: ing to D1.1-96, Table 3.7, is unlimit- prequalified.
The use of prequalified joints ed, so the fillet size can be pre-
and procedures does not necessarily qualified. The current level selected GUIDELINES
guarantee sound welds. Fabrication for making this particular fillet weld When developing prequalified
capability is still required, together is 800 amps, less than the 1000 amp WPSs, the starting point is a set of
with effective and knowledgeable maximum specified in D1.1-96, welding parameters appropriate for
supervision to consistently produce Table 3.7. the general application being consid-
sound welds. (AWS D1.1-96, para- However, the amperage level ered. Parameters for overhead weld-
graph C3.2.1) imposed on the electrode diameter ing will naturally vary from those

Modern Steel Construction / May 1997


required for down-hand welding. In the simplest case, the exact condi- type of tests required are defined in
The thickness of material involved tions that will be encountered in D1.1-96, Table 4.2 for complete joint
will dictate electrode sizes and corre- production will be replicated in the penetration groove welds, D1.1-96,
sponding current levels. The specific procedure qualification test. This Table 4.3 for partial joint penetra-
filler metals selected will reflect the would include the welding process, tion groove welds, and D1.1-96,
strength requirements of the connec- filler metal, grade of steel, joint Table 4.4 for fillet welds.
tion. Many other issues must be details, thicknesses of material, pre- Once the number of tests has
considered. heat values, minimum interpass been determined, the test plate is
Depending on the level of famil- temperature level, and the various sectioned and the specimens
iarity and comfort the contractor has welding parameters of amperage, machined for testing. The results of
with the particular values selected, voltage, and travel speed. The ini- the tests are recorded on the PQR.
welding a mock-up may be appropri- tial parameters used to make the According to D1.1-96, if the test
ate. Once the parameters that are procedure qualification test plate results meet all the prescribed
desired for use in production are beg for a name to define them, requirements, the testing is success-
established, it is essential to check although there is no standard indus- ful and welding procedures can be
each of the applicable parameters try term. It has been suggested that established based upon the success-
for compliance with the D1.1-96 TWPS be used where the T could ful PQR. If the test results are
code. alternately stand for temporary, unsuccessful, the PQR cannot be
To assist in this effort, Annex H test, or trial. In any case, it would used to establish the WPS. If any
has been provided in the D1.1-96 define the parameters to be used for one specimen of those tested fails to
code. This contains a check list that making the test plate since the meet the test requirements, two
identifies prequalified requirements. validity of the particular parameters retests of that particular type of test
If any single parameter deviates cannot be verified until they have may be performed with specimens
from these requirements, the con- successfully passed the required extracted from the same test plate.
tractor is left with two options: (1) test. The parameters for the test If both of the supplemental speci-
the preliminary procedure can be weld are recorded on a Procedure mens meet the requirements, the
adjusted to conform with the pre- Qualification Record (PQR). The D1.1-96 allows the tests to be
qualified constraints; or, (2) the actual values used should be record- deemed successful. If the test plate
WPS can be qualified by test. If the ed on this document. The target is over 11/2 thick, failure of a speci-
preliminary procedure is adjusted, it voltage, for example, may be 30 volts men necessitates retesting of all the
may be appropriate to reexamine its but, in actual fact, only 29 volts were specimens at the same time from
viability by another mock-up. used for making the test plate. The two additional locations in the test
The next step is to document, in 29 volts would be recorded. material (D1.1-96, paragraph 4.8.5).
writing, the prequalified WPS val- After the test plate has been It is wise to retain the PQRs
ues. A sample form is included in welded, it is allowed to cool and the from unsuccessful tests as they may
Annex E of the code. The fabricator plate is subjected to the visual and be valuable in the future when
may utilize any convenient format nondestructive testing as prescribed another similar welding procedure is
(D1.1-96, paragraph 3.6). Also con- by the code. The specific tests contemplated for testing.
tained in Annex E are a series of required are a function of the type of The acceptance criteria for the
examples of completed WPSs that weld being made and the particular various tests are prescribed in the
may be used as a pattern. welding consumables. The types of code. The reduced section tensile
qualification tests are described in tests are required to exceed the min-
QUALIFYING BY TEST D1.1-96, paragraph 4.4. imum specified tensile strength of
Conducting qualification tests In order to be acceptable, the test the steel being joined (D1.1-96, para-
There are two primary reasons why plates must first pass visual inspec- graph 4.8.3.5). Specific limits on the
welding procedures may be qualified tion followed by nondestructive test- size, location, distribution, and type
by test. First, it may be a contractu- ing (NDT) (D1.1-96, paragraphs of indication on bend specimens is
al requirement. Secondly, one or 4.8.1, 4.8.2). At the contractors prescribed in D1.1-96, paragraph
more of the specific conditions option, either RT or UT can be used 4.8.3.3.
encountered in production may devi- for NDT. The mechanical tests Writing WPSs from successful
ate from the prequalified require- required involve bend tests (for PQRs When a PQR records the
ments. In either case, a test weld soundness), macro etch tests (for successful completion of the required
must be made prior to the establish- soundness), and reduced section ten- tests, welding procedures may be
ment of the final WPS. The first sile tests (for strength). For qualifi- written from that PQR. At a mini-
step in qualifying a welding proce- cation of procedures on steels with mum, the values used for the test
dure by test is to determine the pro- significantly different mechanical weld will constitute a valid WPS.
cedure one wants to qualify. The properties, a longitudinal bend spec- The values recorded on the PQR are
same sources cited for the prequali- imen is possible (D1.1-96, paragraph simply transcribed to a separate
fied WPS starting points could be 4.8.3.2). All weld metal tensile tests form, now known as a WPS rather
used for WPSs qualified by test. are required for unlisted filler met- than a PQR.
These will typically be the parame- als. The nature of the bend speci- It is possible to write more than
ters used for fabrication of the test mens, whether side, face, or root, is one WPS from a successful PQR.
plate, although this is not always a function of the thickness of the Welding procedures that are suffi-
the case, as will be discussed later. steel involved. The number and ciently similar to those tested can be
a 5/16 fillet weld. The specific appli-
cation conditions, however, will
necessitate that a separate WPS be
developed for each situation. A sam-
ple WPS is included for each situa-
tion.
Situation One: The weld to be
made is a 5/16 fillet weld that con-
nects the shear tab to the column.
This weld will be made in the fabri-
cation shop with a column in the
horizontal position. The fillet weld
is applied to either side of a 1/2 shear
tab. It is welded to a W14x311 col-
umn with a flange thickness of 21/4 .
The shear tab is made of A36 steel,
while the column is of A572 Gr 50.
The welding engineer recognizes
that for the grades of steel involved,
and for the type of weld specified, a
prequalified WPS could be written.
The process of choice for this partic-
ular shop fabricator is gas shielded
flux cored arc welding, a prequali-
fied welding process. From Table
3.1 of the D1.1-96 code, a list of pre-
qualified filler metals is given.
Outershield 70, an E70T-1 electrode
is selected because, for semiauto-
matic welding, it is likely to be the
most economical process considering
deposition rate and cleanup time.
The electrode operates on DC+
supported by the same PQR. rather for planning qualification
polarity. From experience, the engi-
Significant deviations from those tests. For example, a test plate con-
neer knows that 3/32 diameter is
conditions, however, require addi- ducted in the 2G position qualifies
appropriate for the application, and
tional qualification testing. Changes the WPS for use in either the 1G or
specifies that the shielding gas
that are significant enough to war- 2G position. Even though the first
should be CO2 based upon the elec-
rant additional testing are consid- anticipated use of the WPS may be
trode manufacturers recommenda-
ered essential variables, and these for the 1G position, it may be advis-
tion and its low cost characteristics.
are listed in D1.1-96, Tables 4.5, 4.6, able to qualify in the 2G position so
From Table 3.2 of the D1.1-96 code,
and 4.7. For example, consider an that additional usage can be
the preheat is selected. It is con-
SMAW welding procedure that is obtained from this test plate.
trolled by the thicker steel, that is,
qualified by test using an E8018-C3 In a similar way, D1.1-96, Table
the column flange, and required to
electrode. From that test, it would 4.7 defines what changes can be
be a minimum of 150 degree F since
be possible to write a WPS that uti- made in the base metals used in pro-
the column flange thickness is 21/4.
lizes E7018 (since this is a decrease duction vs. qualification testing. An
From recommendations supplied by
in electrode strength) but it would alternate steel may be selected for
the electrode manufacturer, the
not be permissible to write a WPS the qualification testing simply
welding engineer selects a welding
that utilizes E9018-G electrode because it affords additional flexibil-
current of 460 amps, 31 volts, and
(because Table 4.5 lists an increase ity for future applications.
specifies that the welding speed
in filler metal classification strength If WPS qualification is performed
should be 15-17 ipm. The final vari-
as an essential variable). It is on a non-prequalified joint geometry,
able is determined based upon expe-
important to carefully review the and acceptable test results are
rience. If any doubts still exist, a
essential variables in order to deter- obtained, WPSs may be written from
simple fillet weld test could be made
mine whether a previously conduct- that PQR utilizing any of the pre-
to verify the travel speed for the
ed test may be used to substantiate qualified joint geometries (D1.1-96,
given amperage.
the new procedure being contemplat- Table 4.5, Item 32).
As a quick check, the engineer
ed.
EXAMPLES reviews Annex H to ensure that all
D1.1-96, Table 4.1 defines the
To provide some insight into the the prequalified conditions have
range of weld types and positions
thought process that a welding engi- been achieved. Finally, these are
qualified by various tests. This
neer may follow to develop a WPS, tabulated on the WPS.
table is best used, not as an after-
two examples will be given. In both Situation Two: The second weld
the-fact evaluation of the applicabili-
cases, the weld is the same, namely, to be made is also a 5/16 fillet weld,
ty of the test already conducted, but

Modern Steel Construction / May 1997


but in this case, the weld will be ments of this code (D1.1-96, para- arc), and flux cored arc WPSs in
made in the field. The weld will be graph 6.3.1). The D1.1-96 code does conjunction with certain related
made between the shear tab not require prequalified WPSs to be types of joints have been thor-
described above, and the beam web. submitted to the engineer for oughly tested and have a long
In this situation, the beam is a approval. Welding procedures that record of proven satisfactory per-
W36x150, specified to be of A36 have been qualified by test are formance. (D1.1-96, paragraph
steel. Under field conditions, the required to be reviewed by the engi- C3.2.1).
weld must be made in the vertical neer (D1.1-96, paragraph 4.1.1). The review required by the
position. However, the use of a prequalified inspector in D1.1-96, paragraph
The welding engineer again rec- joint does not exempt the engineer 6.3.1 does not specifically require a
ognizes that the WPS for this appli- from using engineering judgment in determination regarding the suit-
cation could be prequalified if all the determining the suitability of appli- ability of the procedure for the par-
applicable conditions are met. Self cation for these joints (D1.1-96, ticular application, but rather
shielded flux cored arc welding is paragraph 3.1). The code is not requires that the procedure conform
selected in order to ensure high explicit with respect to engineering to the requirements of the code. As
quality welds under windy condi- responsibility for the other aspects previously stated, the engineer is
tions. This is a prequalified process. of a prequalified WPS. not exempted from exercising engi-
In D1.1-96, Table 3.1, the engineer The code is clear that the inspec- neering judgment when prequalified
locates suitable filler metals and tor is required to review all WPSs. joint details are used.
selects Innershield NR232, an E71T- For a prequalified WPS, Annex H, The previously described respon-
8 self-shielded flux cored electrode Contents of a Prequalified WPS, is sibility of the inspector to review all
which operates on DC negative particularly helpful. This Annex WPSs applies equally to those quali-
polarity. Because the welding will provides a list of the various ele- fied by test. However, D1.1-96,
be made in the vertical position, a ments of a prequalified WPS, and paragraph 4.1.1 additionally
0.068 in. diameter electrode is speci- has a reference to the code para- requires the following:
fied. From technical literature sup- graph where these restrictions are Except for prequalified WPSs in
plied by Lincoln Electric, a middle- listed. In the reorganized D1.1-96 conformance with Section 3, a
of-the-range procedure suitable for code format, user-friendly tables and WPS for use in production weld-
vertical position welding is selected. figures summarize many of the pre- ing shall be qualified in confor-
The engineer specifies the current to qualified requirements. These mance with Section 4, Part B, and
shall be approved by the engi-
be 250 amps, 19-21 volts, with a include:
neer.
travel speed of 5.5-6.5 ipm. The con- Table 3.1 - Prequalified Base
The apparent logic behind the dif-
trolling variable is the thickness of Metal - Filler Metal Combinations
ferences in approval approaches is
the beam web, which is 5/8. In this for Matching Strength
that while prequalified WPSs are
situation, Table 3.2 of the D1.1-96 Table 3.2 - P r e q u a l i f i e d
based upon well established, time
code does not require any minimum Minimum Preheat and Interpass
proven, and documented welding
preheat. Temperatures
practices (see D1.1-96, paragraph
The two welds to be made are Table 3.3 - Filler Metal
C3.2.1), WPSs that have been quali-
remarkably similar, and yet the Requirements for Exposed Bare
fied by test may utilize new,
WPS values specified are significant- Applications of A588 Steel
unproven and sometimes controver-
ly different. In order to ensure that Table 3.7 - Prequalified WPS
sial concepts. WPSs that are quali-
quality welds are delivered at eco- Requirements
fied by test are not automatically
nomical rates, it is imperative that a Figure 3.3 - P r e q u a l i f i e d
subject to the same restrictions that
knowledgeable individual establish Groove Weld Joint Details
would apply to prequalified WPSs.
WPS values. These values must be Figure 3.4 - Prequalified CJP
Even though the required qualifica-
adhered to during fabrication and Groove Weld Details
tion tests have demonstrated the
erection in order to ensure quality In addition to the above tables,
adequacy of the particular WPS
welds in the final structure. Table 4.5 lists the essential variable
under test conditions, further scruti-
changes required for WPS requalifi-
REVIEW AND APPROVAL ny by the engineer is justified to
cation. The limitation of variables
After a WPS is developed by a ensure that it is applicable for the
prescribed in Table 4.5 also apply to
fabricator or erector, it is required to particular situation that will be
prequalified WPSs (D1.1-96, para-
be reviewed by the inspector (AWS encountered in production.
graph 3.6). Through the use of these
D1.1-96, paragraph 6.3.1). This Two examples will be cited to
tables, the majority of the prequali-
applies whether the WPS has been illustrate the philosophical differ-
fied conditions can be easily checked
qualified by test, or whether it is ences a welding engineer may take
by the inspector as part of the
prequalified. The code requires when evaluating a WPS qualified by
required review.
WPSs that are qualified by test to be test. In Situation One, the contrac-
The fundamental premise on
submitted to the engineer for tor wishes to use a WPS that would
which the suitability of prequalified
approval (D1.1-96, paragraph 4.1.1). otherwise be prequalified, except for
procedures stands is stated in the
Prequalified WPSs are required one change in the joint detail. Based
commentary as follows:
to be reviewed by the inspector who upon experience and some informal
Certain shielded metal arc, sub-
is required to make certain that the merged arc, gas metal arc tests, the contractor has determined
procedures conform to the require- (excluding the short circuiting that a modified groove detail will
mode of metal transfer across the reduce the required volume of weld

Modern Steel Construction / May 1997


not preheated prior to fabrication
(although the air temperature inside
the shop where the qualification
testing is being performed is at 70
degree F). After the first weld pass
is applied, the steel temperature
rises well above ambient due to the
thermal energy added by the weld-
ing process. A second weld pass is
applied to the first side. Next, the
plate is inverted and the root pass
made from the opposite side is
gouged out. While the interpass
temperature is still well above ambi-
ent, the second side of the joint is
welded. Finally, the plate is flipped
one more time, and the first side of
the joint is welded out to completion.
The test plate is subject to all of
the code-mandated tests, and suc-
cessfully meets the code require-
ments. With this information in
hand, the contractor submits the
procedure to the engineer for
approval, claiming that these tests
have proven the weldability of the
new steel, and that no preheat is
required. While it is true that the
code-mandated requirements have
been fulfilled, the suitability of this
welding procedure for actual fabrica-
tion has not been established. The
relatively small sizes associated
with the test plate (1 thick x 14
minimum wide x 30 minimum long,
according to D1.1-96, Figure 4.10) is
not sufficient to duplicate the
restraint or cooling rates that will be
seen in actual structures. These
issues will affect the resultant heat
metal without affecting quality. The lem with fusion problems associated affected zone microstructure, hydro-
joint detail is similar to a B-U2a-GF, with this technique. A successful gen diffusion rates, and residual
except that the root opening and PQR should satisfy the engineer who stress levels - all elements that
groove angles deviate from the pre- is required to approve this proce- affect the possibility of weld crack-
qualified requirements shown in dure. ing. In addition, except for the root
D1.1-96. Specifically, the combina- In Situation Two, the issue is pass, all of the weld passes had the
tion of a 1/8 root opening with a 45 more complex. A new steel is being benefit of the higher interpass tem-
degree included angle when applied contemplated for construction, and perature. Furthermore, the root
to plate 1/2 thick provides a near the claim of the steel producer is pass that was made without preheat
optimum configuration for this con- that it can be welded with reduced was gouged out when the second
tractors procedures that utilize preheat levels. It cannot be prequal- side was welded. Although no pre-
FCAW-g. Since these dimensional ified because (a) the steel is not heat was applied, the steel was at
changes are beyond the limits per- prequalified; and, (b) the preheat shop ambient temperature, qualify-
mitted by the as-detailed tolerances levels are below the prequalified lim- ing a 70 degrees F preheat tempera-
for the specific joint, they must be its. In order to qualify the procedure ture, not no preheat temperature.
qualified by test. If there were to be for unlimited thickness qualification, The engineer ought to view the
a problem associated with this D1.1-96, Table 4.2 requires the test second WPS with a greater degree of
approach, it would no doubt evi- plate be 1 in. or thicker. The con- scrutiny than first. It would be rea-
dence itself as a fusion-type prob- tractor qualifies the welding proce- sonable, for example, to require
lem. The required qualification test dure on 1 in. steel, although the weldability tests (such as: G-BOP,
as outlined in Table 4.2 require two actual application will utilize 4 in. TEKKEN, or CTS tests) in order to
Reduce Section Tension Tests, and thick steel. The actual joint configu- better understand the likely behav-
four Side Bend Tests. Both of these ration used for qualification testing ior of this proposed welding proce-
tests, and the Side Bend Test in par- is a double V groove butt joint, weld- dure. Larger scale, restrained mock-
ticular, will quickly reveal any prob- ed from two sides. The test plate is

Modern Steel Construction / May 1997


ups would be necessary to evaluate
actual restraint and cooling condi-
tions.
When WPSs that have been qual-
ified by test are reviewed, there are
three distinct elements of that
review: First, the procedure qualifi-
cation record should be evaluated to
ensure that all the required tests
have been performed, verifying that
the proper thicknesses of material,
positions of welding, and number of
required tests have all been per-
formed. Secondly, the results of the
testing must be examined to be cer-
tain that the code requirements
have been met. The final aspect of
the review is to compare the WPS to
the PQR. This will consist of a com-
parison of the requirements of AWS
D1.1-96, Table 4.5, as it relates to
any differences between the PQR
and the WPS. Requirements regard-
ing the steels used in testing versus
those listed on the WPS are
addressed in D1.1-96, Table 4.7.

The opinions and explanations


expressed above are the authors
alone and do not necessarily reflect
the opinions of the AWS or of the
AWS D1 Committee. Official inter-
pretations of the D1.1 code can only
be made by the D1 Committee. D1.1-
96, Annex F, provides information
detailing how an official interpreta-
tion can be obtained.

This article is based on a paper


presented at the 1997 National Stee
lConstruction Conference. Duane K.
Miller, P.E., is a senior project leader
and design consultant at The
Lincoln Electric Companys Welding
Technology Center.In that capacity,
he assists engineers and fabricators
in welding design and metallurgical
problems.

Modern Steel Construction / May 1997

You might also like