Professional Documents
Culture Documents
Finish Predecessors Successors 25 Jul '16 01 Aug '16 08 Aug '16 15 Aug '16 22 Aug '16 29 Aug '16 05 Sep '16 12 Sep '16 19 Sep '16 26 Sep '16 03 Oct '16 10 Oct '16 17 Oct '16 24 Oct '16 31 Oct '16 07 Nov '16 14 Nov '16 21 Nov '16 28 Nov '16 05 Dec '16 12 Dec '16 19 Dec '16
Mode T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1 Peningkatan Saluran Drainase Kawasan Dalam Kota Tanjung Redeb
2 I. PEKERJAAN PENDAHULUAN
3 1. Mobilisasi dan Demobilisasi 4 days Wed 27/07/16 Sun 31/07/16 4SS;5SS
4 2. Perlindungan dan Keamanan Lalu lintas 148 days Wed 27/07/16 Fri 23/12/16 5SS 3SS
5 3. Pembersihan Lapangan / Lokasi 148 days Wed 27/07/16 Fri 23/12/16 4SS;6SS;7SS;8SS;3SS;12SS;22SS
6 4. Dewatering 148 days Wed 27/07/16 Fri 23/12/16 5SS
7 5. Utilitas dan Pelayanan PDAM 148 days Wed 27/07/16 Fri 23/12/16 5SS
8 6. Utilitas dan Pelayanan Telkom 148 days Wed 27/07/16 Fri 23/12/16 5SS
9 II. PEKERJAAN TANAH
10 A. JALAN DURIAN III (KANAN)
11 1. Penggalian Tanah Untuk Konstruksi Dengan Alat Berat 4 days Wed 27/07/16 Sun 31/07/16 12SS 13FS+1 day;14SS;17FS+1 day;52SS+5 days;53SS+12 days
12 2. Pembongkaran Pasangan Saluran Existing 11 days Wed 27/07/16 Sun 07/08/16 5SS 11SS;18FS+1 day;15FS+1 day
13 3. Pembongkaran jalan masuk pemukiman 6 days Mon 01/08/16 Sun 07/08/16 11FS+1 day 19FS+8 days;15FS+1 day
14 4. Pengangkutan Tanah Keluar Proyek 18 days Wed 27/07/16 Sun 14/08/16 11SS
15 5. Urugan Koral Sungai (Padat) 6 days Mon 08/08/16 Sun 14/08/16 12FS+1 day;13FS+1
43FS+1
day day;46SS
16 B. JALAN KAKABAN (KANAN)
17 1. Penggalian Tanah Untuk Konstruksi Dengan Alat Berat 13 days Mon 01/08/16 Sun 14/08/16 11FS+1 day 20SS;24SS+7 days;61FS+1 day
18 2. Pembongkaran Pasangan Saluran Existing 13 days Mon 08/08/16 Sun 21/08/16 12FS+1 day 25SS+7 days;21FS+1 day
19 3. Pembongkaran jalan masuk pemukiman 6 days Mon 15/08/16 Sun 21/08/16 13FS+8 days 26FS+1 day;21FS+1 day
20 4. Pengangkutan Tanah Keluar Proyek 27 days Mon 01/08/16 Sun 28/08/16 17SS
21 5. Urugan Koral Sungai (Padat) 6 days Mon 22/08/16 Sun 28/08/16 18FS+1 day;19FS+1 day
22 6. Pekerjaan Aspal Cutting 11 days Wed 27/07/16 Sun 07/08/16 5SS 29SS+5 days
23 C. JALAN PULAU PANJANG (KANAN)
24 1. Penggalian Tanah Untuk Konstruksi Dengan Alat Berat 13 days Mon 08/08/16 Sun 21/08/16 17SS+7 days 27SS+7 days;31FS+1 day;69FS+22 days
25 2. Pembongkaran Pasangan Saluran Existing 13 days Mon 15/08/16 Sun 28/08/16 18SS+7 days 28FS+1 day;32SS+7 days
26 3. Pembongkaran jalan masuk pemukiman 6 days Mon 22/08/16 Sun 28/08/16 19FS+1 day 28FS+1 day;33FS+1 day
27 4. Pengangkutan Tanah Keluar Proyek 20 days Mon 15/08/16 Sun 04/09/16 24SS+7 days 34SS+7 days
28 5. Urugan Koral Sungai (Padat) 6 days Mon 29/08/16 Sun 04/09/16 25FS+1 day;26FS+1 day
29 6. Pekerjaan Aspal Cutting 6 days Mon 01/08/16 Sun 07/08/16 22SS+5 days 36FS+8 days
30 D. PEMUDA (KIRI)
31 1. Penggalian Tanah Untuk Konstruksi Dengan Alat Berat 6 days Mon 22/08/16 Sun 28/08/16 24FS+1 day 38FS+1 day;77FS+43 days
32 2. Pembongkaran Pasangan Saluran Existing 13 days Mon 22/08/16 Sun 04/09/16 25SS+7 days 35FS+1 day
33 3. Pembongkaran jalan masuk pemukiman 6 days Mon 29/08/16 Sun 04/09/16 26FS+1 day 35FS+1 day
34 4. Pengangkutan Tanah Keluar Proyek 20 days Mon 22/08/16 Sun 11/09/16 27SS+7 days 39SS+7 days
35 5. Urugan Koral Sungai (Padat) 6 days Mon 05/09/16 Sun 11/09/16 32FS+1 day;33FS+1 day
36 6. Pekerjaan Aspal Cutting 6 days Mon 15/08/16 Sun 21/08/16 29FS+8 days
37 E. JALAN HRM. AYUB
38 1. Penggalian Tanah Untuk Konstruksi Dengan Alat Berat 6 days Mon 29/08/16 Sun 04/09/16 31FS+1 day 40FS+1 day;87FS+43 days
39 2. Pengangkutan Tanah Keluar Proyek 13 days Mon 29/08/16 Sun 11/09/16 34SS+7 days
40 3. Urugan Koral Sungai (Padat) 6 days Mon 05/09/16 Sun 11/09/16 38FS+1 day
41 III. PEKERJAAN SALURAN BETON PRECAST DAN
PENGEMBALIAN KONDISI
45 3. Pengadaan dan Pemasangan Box Culvert K-300 (150.150.100) 20 days Mon 19/09/16 Sun 09/10/16 44SS+21 days
(Precast)
46 4. Pengadaan dan Pemancangan Mini Pile (15x15x300) 6 days Mon 08/08/16 Sun 14/08/16 15SS
47 5. Pengadaan dan Pemasangan Grill Manhole besi UNP 13 days Mon 26/09/16 Sun 09/10/16 50FS+1 day;49SS;48SS+14 days
48 6. Beton K-250 27 days Mon 12/09/16 Sun 09/10/16 50SS+21 days 51FS+1 day;47SS+14 days
49 7. Beton K-350 13 days Mon 26/09/16 Sun 09/10/16 50FS+1 day 51FS+1 day;47SS
50 8. Besi Ulir U32 34 days Mon 22/08/16 Sun 25/09/16 43SS+7 days 48SS+21 days;49FS+1 day;47FS+1 day
51 9. Beton-175 13 days Mon 10/10/16 Sun 23/10/16 48FS+1 day;49FS+1 day
52 10. Perkuatan Sementara Penahan Tanah / Bangunan Dengan 27 days Mon 01/08/16 Sun 28/08/16 11SS+5 days
Steel Sheet Pile
53 11. Relokasi Tiang Listrik 6 days Mon 08/08/16 Sun 14/08/16 11SS+12 days
54 B. JALAN KAKABAN (KANAN)
55 1. Pengadaan danPemasangan U-Gutter K-300 (150.120.100) 34 days Mon 19/09/16 Sun 23/10/16 43SS+35 days 56SS+7
(Precast) days;59SS+14
56 2. Pengadaan dan Pemasangan Cover Slab Beton K-300 27 days Mon 26/09/16 Sun 23/10/16 55SS+7 days days;63SS+28
(20.180.100) Precast
57 3. Pengadaan dan Pemasangan Grill Manhole (Cover & Frame) 20 days Mon 10/10/16 Sun 30/10/16 59SS+7
Pabrikan days;58SS+7
58 4. Beton K-250 27 days days
Mon 03/10/16 Sun 30/10/16 59SS 57SS+7 days
59 5. Besi Ulir U32 27 days Mon 03/10/16 Sun 30/10/16 55SS+14 days 58SS;60SS+7 days;57SS+7 days
60 6. Beton-175 20 days Mon 10/10/16 Sun 30/10/16 59SS+7 days
61 7. Perkuatan Sementara Penahan Tanah / Bangunan Dengan 41 days Mon 15/08/16 Sun 25/09/16 17FS+1 day
Steel Sheet Pile
65 3. Pengadaan dan Pemasangan Grill Manhole (Cover & Frame) 13 days Mon 07/11/16 Sun 20/11/16 66SS+13 days
Pabrikan
66 4. Beton K-250 20 days Mon 24/10/16 Sun 13/11/16 67SS+7 days 68;65SS+13 days
67 5. Besi Ulir U32 27 days Mon 17/10/16 Sun 13/11/16 63SS 66SS+7 days;68
68 6. Beton-175 13 days Mon 14/11/16 Sun 27/11/16 66;67
69 7. Perkuatan Sementara Penahan Tanah / Bangunan Dengan 27 days Mon 12/09/16 Sun 09/10/16 24FS+22 days
Steel Sheet Pile
70 D. PEMUDA (KIRI)
71 1. Pengadaan danPemasangan U-Gutter K-300 (150.120.100) 20 days Mon 24/10/16 Sun 13/11/16 63SS+7 days 72SS+14
(Precast) days;75SS+7
72 2. Pengadaan dan Pemasangan Cover Slab Beton K-300 6 days Mon 07/11/16 Sun 13/11/16 71SS+14 days days;84SS+14
(15.180.100) Precast
73 3. Pengadaan dan Pemasangan Grill Manhole (Cover & Frame) 6 days Mon 07/11/16 Sun 13/11/16 75SS+7
Pabrikan days;74SS+7
74 4. Beton K-250 13 days Mon 31/10/16 Sun 13/11/16 days
75SS 73SS+7 days
75 5. Besi Ulir U32 6 days Mon 31/10/16 Sun 06/11/16 71SS+7 days 74SS;76FS+1 day;73SS+7 days
76 6. Beton-175 6 days Mon 07/11/16 Sun 13/11/16 75FS+1 day
77 7. Perkuatan Sementara Penahan Tanah / Bangunan Dengan 6 days Mon 10/10/16 Sun 16/10/16 31FS+43 days 78SS;79SS
Steel Sheet Pile
78 8. Relokasi Traffic light 6 days Mon 10/10/16 Sun 16/10/16 77SS 79SS
79 9. Relokasi Tiang Listrik 6 days Mon 10/10/16 Sun 16/10/16 77SS;78SS
80 10. Pasangan Kerb (20x30x50) cm K-250 pra cetak basah 18 days Mon 05/12/16 Fri 23/12/16 84;86
81 11. Pemasangan Lantai Keramik ( 40 cm x 40 cm ) 13 days Mon 05/12/16 Sun 18/12/16 84;86 82FS+1 day
82 12. Pemasangan Lantai Keramik ornamen ( 60 cm x 60 cm ) 4 days Mon 19/12/16 Fri 23/12/16 81FS+1 day
83 E. JALAN HRM. AYUB
84 1. Pengadaan danPemasangan U-Gutter K-300 (120.120.100) 26,81 days Mon 07/11/16 Sun 04/12/16 71SS+14 days 85SS+6
(Precast) days;80;81
85 2. Pengadaan dan Pemasangan Cover Slab Beton K-300 13 days Mon 14/11/16 Sun 27/11/16 84SS+6 days 86SS+7 days
(15.150.100) Precast
88 5. Relokasi Tiang Listrik 13 days Mon 24/10/16 Sun 06/11/16 87FS+1 day
Project: MICROSOFT PROJECT B Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Wed 13/07/16 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress
Page 1
Peningkatan Saluran Drainase Kawasan Dalam Kota Tanjung
I. PEKERJAAN
Redeb PENDAHULUAN 3. Pembersihan Lapangan / Lokasi 2. Perlindungan dan Keamanan Lalu lintas 1. Mobilisasi dan Demobilisasi
Start: ID: 1 Start: ID: 2 Start: 27/07/16 ID: 5 Start: 27/07/16 ID: 4 Start: 27/07/16 ID: 3
Finish: Dur: Finish: Dur: Finish: 23/12/16 Dur: 148 days Finish: 23/12/16 Dur: 148 days Finish: 31/07/16 Dur: 4 days
Comp: 0% Comp: 0% Res: Res: Res:
4. Dewatering
Start: 27/07/16 ID: 6
Finish: 23/12/16 Dur: 148 days
Res:
II. PEKERJAAN TANAH A. JALAN DURIAN III (KANAN) 2. Pembongkaran Pasangan Saluran Existing 1. Penggalian Tanah Untuk Konstruksi Dengan Alat Berat 3. Pembongkaran jalan masuk pemukiman
Start: ID: 9 Start: ID: 10 Start: 27/07/16 ID: 12 Start: 27/07/16 ID: 11 Start: 01/08/16 ID: 13
Finish: Dur: Finish: Dur: Finish: 07/08/16 Dur: 11 days Finish: 31/07/16 Dur: 4 days Finish: 07/08/16 Dur: 6 days
Comp: 0% Comp: 0% Res: Res: Res:
B. JALAN KAKABAN (KANAN) 1. Penggalian Tanah Untuk Konstruksi Dengan Alat Berat 4. Pengangkutan Tanah Keluar Proyek
Start: ID: 16 Start: 01/08/16 ID: 17 Start: 01/08/16 ID: 20
Finish: Dur: Finish: 14/08/16 Dur: 13 days Finish: 28/08/16 Dur: 27 days
Comp: 0% Res: Res:
C. JALAN PULAU PANJANG (KANAN) 1. Penggalian Tanah Untuk Konstruksi Dengan Alat Berat 4. Pengangkutan Tanah Keluar Proyek
Start: ID: 23 Start: 08/08/16 ID: 24 Start: 15/08/16 ID: 27
Finish: Dur: Finish: 21/08/16 Dur: 13 days Finish: 04/09/16 Dur: 20 days
Comp: 0% Res: Res:
E. JALAN HRM. AYUB 1. Penggalian Tanah Untuk Konstruksi Dengan Alat Berat 3. Urugan Koral Sungai (Padat)
Start: ID: 37 Start: 29/08/16 ID: 38 Start: 05/09/16 ID: 40
Finish: Dur: Finish: 04/09/16 Dur: 6 days Finish: 11/09/16 Dur: 6 days
Comp: 0% Res: Res:
7. Beton K-350
Start: 26/09/16 ID: 49
Finish: 09/10/16 Dur: 13 days
Res:
10. Perkuatan Sementara Penahan Tanah / Bangunan Dengan Steel Sheet Pile
Start: 01/08/16 ID: 52
Finish: 28/08/16 Dur: 27 days
Res:
6. Beton-175
Start: 10/10/16 ID: 60
Finish: 30/10/16 Dur: 20 days
Res:
5. Besi Ulir U32 4. Beton K-250 3. Pengadaan dan Pemasangan Grill Manhole (Cover & Frame) Pabrikan
Start: 17/10/16 ID: 67 Start: 24/10/16 ID: 66 Start: 07/11/16 ID: 65
Finish: 13/11/16 Dur: 27 days Finish: 13/11/16 Dur: 20 days Finish: 20/11/16 Dur: 13 days
Res: Res: Res:
6. Beton-175
Start: 14/11/16 ID: 68
Finish: 27/11/16 Dur: 13 days
Res:
6. Beton-175
Start: 07/11/16 ID: 76
Finish: 13/11/16 Dur: 6 days
Res:
Page 1