Professional Documents
Culture Documents
Abstract
The goal of this project was to create an engine mount that would be able to
support a Lycoming O-300 engine, which weighs 250 lb. under normal gravity. We had to
use an already given template and create a frame that would be able to support such a
weight at large g forces like positive six and negative three. The pipe has to have been 1.5
inches in diameter, but we got to chose which material to make the pipe out of.
Burke and Kato 3
Table of Contents
Title Page 1
Abstract 2
Table of Contents 3
Problem Statement 4
Procedure 5
Design 6
Results 8
Conclusion 8
Burke and Kato 4
Problem Statement
The task that we had to complete was to create an engine mount frame that would
be able to hold a 250 lb engine under extreme requirements. The outline for the frame
itself was already made for us; we just had to download it from the pltw website. We had
to use piping that was 1.5 inches in diameter for the frame, although we could chose the
thickness of the pipe walls and the material that the pipes would be made of. The frame
also had to have 3 attachment points that the weight would be distributed through. We
then would have to run the frame through regular gravity, -3 Gs with the total weight of
the engine at this point being 750 lbs. up, and +6 Gs where the total weight of the engine
would be 1500 lbs. down. This task is important to Aerospace engineering because if the
engine is not supported well during flight, it has the capability to through off the fragile
Procedure
the different types of materials that may be used in aerospace engineering and some that
are not. We tested all the materials strength under tension and compression and got to
look at the weight and cost for each material to give us a better idea on the efficiency for
each material and what jobs the materials would be useful for.
2. The second project was done on Inventor and it taught us all of the frame testing and
modifications you can do on Inventor The project walked us through creating a 3D frame
from a 2D sketch along with how to use some new tools that help construct a proper
frame.
3. The third project we did taught us how to run the structural analysis on the frames once
we had finished a frame. It also showed us how to add forces to the frame and how to
change the angles. In addition, it taught us how to constrain the frame so that it wouldn't
made of steel.
5. Once we applied the pipes to the frame to create the struts, we had to cut them down
using mitering and trimming them to faces in order to make the struts fit nicely together,
and so that they didnt stick through the base of the engine mount or the three engine
attachment points.
6. We then restricted the movement of the frame by adding constraints, specifically the
fixed one, on all of the points where the struts touched the engine mount base.
7. Finally we added the forces to the different recreations. For the regular gravity, each
mount point received 83 lbs, for 3 Gs each point received 250 lbs, and for 6 Gs each point
Design Solution
Our design meets the constraints because the pipe was the right diameter, and we
used the correct base weight for the engine and the correct G levels for the other two
tests. We decided to go with the thicker walled steel pipes, as they would be able to hold
the weight up better than the thinner walled variants. We also chose steel as it is quite
cheap and easy to mold, while also having extremely high tension and compression
strengths. This is extremely important as we do not want the engine moving around in
larger increments like could be possible if we used a lighter metal like aluminum. The
solution worked very well, only moving .003 in at the highest force and the furthest from
the base.
negative 3 Gs.
Burke and Kato 7
Results
Kyle and I were able to finish the project, as we ran into no problems during the
creation of the frame, nor when we ran the structural analysis. I did make a few mistakes
as far as mis-clicks go when I was trimming the pipes, as if you click the face before the
pipe it will cut the face around the pipe instead of cutting the pipe to the face, which is
Burke and Kato 8
the ideal occurrence. If we did this project again and had more time to complete, I would
try to fix the lines that was the basis for the frame, as some of them did not go to the right
place as was designated by a little cross-hair looking thing showing where they should
have intersected the mount base plate. Since we did not build the frame outline, as we
downloaded it from PLTW, it would have been a long and time consuming process to
make those changes, time that we did not have. This would have probably increased the
strength of the frame as a whole because then the frame would have been in line with
itself, so the force would travel down straight struts. The redrawing of the lines would be
the main edit that would have to be made to make the frame perform better.
Conclusion
learned this in a separate assignment that was used for background for this project. We
also learned how to conduct stress analysis on a frame in inventor. This was also taught
outlines. In addition to this we also learned the properties of many common building
materials, like, steel, aluminum, and wood. This helped us when we decided on a material
to make our frame out of, as we needed something that would be able to sustain those
high forces that were tested. The final thing that we learned in this project was the
much easier to edit a frame, without having to edit each piece separately, as it is
proportional. This means that when one member is changed, the others change
Burke and Kato 9
proportionally. It also makes it easier to edit the frame to fit the constraints of different