Truss Through Tied Arch Bridge Building Challenge
Arch-itects
Macomb Mathematics, Science, and Technology Center
Matthew Butkowski, Jack Loring, Evan Tarian
Mr. McMillan
Table of Contents
Summary……………………………………………………………………………………….3
Introduction…………………………………………………………………………………….4
Bridge Creation………………………………………………………………………………..5
Scientific Principles of Truss Through Tied Arch Bridge…………………………………..5
Design……………………………………………………………………………………….….6
Data and Calculations………………………………………………………………………....7
ModelSmart Testing…....……………………………………………………………………...7
Sample Calculation……………………………………………………………………………10
Bentley Drawing………………………………………………………………………………..11
Drawings and Pictures…………………………………………………………………..…….12
Design Improvements, Testing, and Precautions………………………………………….16
1
Challenges……………………………………………………………………………………..16
Precaution……………………………………………………………………………………...17
Conclusion/Recommendations……………………………………………………………....18
Acknowledgements……………………………………………………………………....…...20
Bibliography…………………………………………………………………………………....21
Appendix…………………………………………………………………….………………….23
2
Summary
When first designing the bridge, we used ModelSmart 2D to create truss designs,
and to test the strengths of the trusses to choose what design we would use. After
testing them, the software gave us both the bridge weight, as well as how much the
bridge held. We repeated this a few times each with separate designs. We calculated
the strength to weight ratio of each design modeled. We then analyzed that data to see
which of the designs had the greatest ratio. The truss with the best ratio was then
recreated using the Bentley software, and the arch of the bridge was added to it. Once
each part had been designed in Bentley, they were then constructed to scale with the
balsa wood, string, and wood glue provided by the competition. The arches that we
created required additional work, forming and reforming so that they would be as
identical as possible. The actual trusses were two inches starting at the edge and were
decreased to a one inch width toward the middle. After each individual piece was made
they were connected to form our bridge.
3
Introduction
We are the Arch-itects. We chose this name because it incorporates arches
which are crucial part of this challenge and also names architects which is the role that
we are playing by designing this bridge. The first of the three team members is Matthew
Butkowski a 16 year old gamer, geek, nerd, and overall oddball. Jack Loring is 16 and
loves to play sports, including baseball, football, and golf. Evan, the team captain, is 17,
an avid sports fan, and aspires to attend the University of Michigan. We are all from the
St. Clair Shores area, with two of us attending Lake Shore High School (Evan and Matt)
in addition to the Macomb Mathematics, Science, and Technology Center (MMSTC),
and one of us attending Cousino High School (Jack), as well as MMSTC.
4
Bridge Creation
Scientific Principles of Truss Through Tied Arch Bridge
Truss through tied arch bridges are bridges that use an effective combination of
through trusses and tied arches. Truss through tied arch bridges use a continuous
beam design because of continuous beams great resistance to bending. The
continuous beam is the platform that is used to cross the bridge. The beam is often
reinforced with trusses. These trusses are designed with triangles, the strongest
geometrical shape, in order to maximize strength while minimizing the weight of the
bridge. The truss portion of the bridge either uses a Pratt webbing or a Warren webbing.
Pratt webbing is characterized by having diagonals slanted toward the middle of the
bridge. Warren webbing is characterized by a series of isosceles triangles or equilateral
triangles. Either of these two are chosen due to both providing the bridge with great
support. Lastly, the bridge is completed with a tied arch. The arch spans over the top of
the bridge and is tied down to the platform to provide tension when the bridge is being
stressed.
Figure 1. Force Diagram of Arches
5
Figure 1, above, shows how a load on the bridge is distributed from the deck to
the ties and then through the arch. With the forces being distributed throughout the arch
it is important to have arches that will be able to hold the weight of the load.
Design
When first creating the bridge, we took into account many different structural
bridge designs which were found online and first attempted to create bridges similar to
those designs. At first, there was some trouble understanding how the ModelSmart
program worked. Certain things we attempted to do did not work since we did not have
previous familiarity with the software. However, with more experience on the software,
this problem was solved quite easily within the first day of designing. Similar problems
occurred once the use of the MicroStation PowerDraft software started. The given video
tutorials were a large aid in completing the sheet. The videos did not happen to show
how to accurately design and create an arch. Due to this, creating the arch took longer
than expected. The arch ended up being somewhat easy to create once the software’s
features were fully understood. While attempting these designs, an altered version of a
Viga Howe type truss was created and, after testing, had the best strength to weight
ratio. The arch design is the same as that of the truss design (Viga Howe) only
formatted to fit into the arch.
6
Data and Calculations
ModelSmart Testing
Figure 2, Town Lattice Truss
Figure 2 illustrates another of our preliminary designs, a Town Lattice Truss. This
design worked very well, and was considered as our best design (and the one we would
go with) until our final design.
7
Figure 3, K Design Truss
The K Design Truss shown in Figure 3 performed much better than the X Design,
but was still not as good as the Town Lattice Truss (the best at the time).
Figure 4, Howe Truss
Figure 4 shows our final bridge design, and the one we went with when
constructing our bridge. It out-performed the Town Lattice Truss with a better ratio, and
was ultimately chosen as our final design.
8
Table 1. Truss Design Test Data
Kind of Height Distance Weight Breaking Ratio
Truss (inches) Between (grams) Load
Truss (pounds)
(inches)
Pratt
Webbing 2 2 4.188 6.163 668.10
Pratt
Webbing
with Vertical
Supports 2 2 4.976 7.06 644.14
Town
Lattice
Truss 4 2 5.458 10.112 841.12
X-Design 2 2 5.262 5.688 490.75
K Design 4 2 6.408 9.438 668.67
Howe 2 2 4.547 8.617 860.37
Table 1, above, displays the the results of our data calculations from the testing
of the trusses. The table shows the weight in grams of the test piece in grams, the
breaking weight of the test in pounds, and the strength to weight ratio of the resulting
trials. The truss design that performed the best was the Howe truss design having a
strength to weight ratio of 860.37. The strength to weight ratio is calculated by
converting the breaking weight of the bridge into grams and then dividing it by the
weight of the bridge in grams. The other truss designs that were given consideration
include the town lattice truss and the K design. Ultimately, the Howe truss was chosen
because it had the highest strength to weight ratio according to the ModelSmart
software and was believed to cause the fewest construction difficulties. The bridge that
9
we constructed held 23,872.3 grams and weighed 40.5 grams. This means that the
bridges strength to weight ratio is 589.44.
Sample Calculation
Weight held by bridge
=Strength to Weight Ratio
Weight of the bridge
23,872.3g
=589.44
40.5g
Figure 8. Sample Calculation
Figure 8, above, displays the calculation of the bridges strength. To calculate take the
weight held by the bridge, 23,872 grams, and divide it by the weight of the bridge, 40.5 grams,
to get the strength to weight ratio, 589.44. These are the results from the testing of our actual
bridge.
10
Bentley Drawing
Figure 555. MicroStation PowerDraft Bridge Design
The above figure depicts the preliminary and final design of the constructed truss
through tied arch bridge. Nothing was changed between the preliminary and final
designs, so the same sheet was used. The top left of the sheet shows a side view of the
bridge. Labeled are the dimensions of each different length and angle measurement.
The top right shows an end point view, as if looking inside the bridge, also showing
labeled lengths and angles. The bottom left shows an aerial view, as if looking down
from inside a plane. Dimensions on the sheet are done in inches and show the actual
measurements of the physical bridge. The sheet is dimensioned so for every labeled
five inches on the paper, if measured with a ruler, would equal one inch. The full length
of the bridge extends to 18 inches. The width was made out to be three inches. The
arches themselves were approximately four and three eighths inches tall and the height
of the truss portion was approximately two and 63 hundredths. With these
measurements, the bridge had a total height just slightly over seven inches.
11
Drawings and Pictures
Figure 6. Construction of trusses
Figure 6, above, shows part the piecing together of the trusses. The beams that
you see in the picture are going to be used to connect the two trusses. Once connected
that the truss will have been glued to the road.
Figure 7. Completed Road
12
Figure 7, above, shows the road in the process of drying and will later be flipped
over from the view now and connected to the truss, as stated in the previous picture. On
both sides of the sticks that run horizontal is are long sticks running vertically as well as
the diagonal pieces.
Figure 8. Bended Arches
Figure 8, above, shows the arches that were created as they are removed from
being pinned to the cardboard. These arches are not including one of our arches. These
arches will later be connected by trusses.
13
Figure 9. Completed Arches and Bottom Half of Bridge
Figure 9, above, shows the arches with trusses in between, but the arches are
not connected to the bridge road, and they are not connected together.
Figure 10. Bridge without Suspension
Figure 10, above, shows the arches and truss connected the arches are
connected to one another and are held by way of zip ties.
14
Figure 11. Tying the Arches to the Bridge
Figure 11, above, shows one of our group members, Jack, tying the arches to
the bridge for extra support. Also, the strings we were using were braided to add
strength to them.
15
Design Improvements, Testing, and Precautions
The designs that were used, both preliminary and final, were tested using the
ModelSmart software to approximate about how much weight they would hold. With
each test, we attempted to add or remove parts of the wood we thought would either
improve the bridge’s ratio and/or remove parts we thought were unnecessary.
Eventually, these improvements led to several designs which were modifications from
their originals but had the best strength to weight ratio. From these “final” designs, we
then chose the design with the best ratio to use and attempt to build. Additionally, when
designing the bridges on a computer, we attempted to make designs that were not
overly complex, so that the building of the bridge would be completed on schedule and
before the deadline.
Challenges
Once the final design was decided upon, the building of the bridge had begun,
which of course presented it’s own challenges. Among these problems, the two most
significant was when the bridge broke during early stages of construction, and that the
arches of the bridge were also uncooperative when trying to create them. The bridge
first broke while trying to undo part of the construction that wasn’t quite right.
Unfortunately, half of the truss broke while trying to fix this problem, and that truss had
to be redone. This was accomplished though within the same day, since it happened
early on during the time that had been scheduled to build. The arches were not as much
of a problem when building them, but more so as just time consuming to create, as they
first had to be soaked in water for nearly an hour to be able to bend the desired way,
and then to keep them in that shape they had to be pinned to cardboard in the position
16
that we wanted (so as to be stiff in that position), which took another length of time.
Additionally, one of the wood sticks used to form the arch did break during the process,
and that final part for the arch needed to be redone. Finally, a level fell on the bridge
during the final stages of construction and due to time constraints, the damage done to
the bridge was unable to be fully repaired other than the addition of more glue to the
damaged parts. This may have led to a worse strength to weight ratio than was
anticipated.
Precautions
While building the bridge, we had no safety precautions other than elementary
safety precautions. These included being careful when handling the equipment
(scissors to cut wood, being careful when gluing pieces of the bridge together etc.), as
well as the handling of the bridge itself, being sure not to accidentally destroy it by some
unintended means. Even with these precautions, there were times the bridge either
broke or did not stick well together. This is likely due to the continuation of work on the
bridge while parts of it which had been glued were still drying, thus those parts of the
bridge were weaker at the points the bridge was broken.
17
Conclusion/Recommendations
Conclusion
To conclude, we believe our project is successful due to the strength to weight
ratio of the bridge. The constructed model bridge being dimensioned properly, therefore,
should work in the same way that the digitally constructed bridge worked. With this in
mind, the constructed bridge should be able to hold as much weight, if not more, than
what was predicted using the ModelSmart software. By taking part in this experiment,
each of us learned a number of things. First, we learned how to use two new types of
software for bridge constructing purposes, those being ModelSmart 2D and the Bentley
MicroStation PowerDraft V8I (SELECTseries 4) software. Additionally, the group
learned the scientific and physics-related principles of bridge construction through the
research that was done in finding a proper design for the bridge and the actual
construction of the bridge. The group found out about the strengths of different truss
designs, and what type of supports the most weight.
Recommendations/Further Improvements
If given the chance to do the project over again, we would attempt to make all the
lengths of the bridge more precise and accurate but this may not be able to be
prevented, because of the imperfections in the wood. Furthermore, we would have
made the trusses on the bridge more compact, as this was a common feature among
the high performing bridges. We would also add to more trusses to the bottom, because
the support is increased and more stability will be provided. Four trusses would be best
because of optimal strength and stability. One more thing we might do to improve is
18
curve the bottom of the trusses slightly to prevent bending and added support to the
trusses.
19
Acknowledgements
We would like to thank our Statistics teacher, Mrs. Rose Cybulski for showing us
the ModelSmart software, since the software was very useful when digitally
constructing, designing, and testing our bridges. We would also like to thank Mr. Greg
McMillan, our Physics teacher, for providing us with the information we would need in
order to participate in the competition as well as giving us some hints as to how we
should construct the bridge. Finally, we would like to thank each other for sticking to the
plan and for supporting each other to complete the bridge and paper.
20
Bibliography
"Cantilever Bridge Facts, Design and History." Cantilever Bridge - Types, Facts and
Longest Cantilever Bridges. N.p., 2017. Web. 09 Jan. 2017.
<http://www.historyofbridges.com/facts-about-bridges/cantilever-bridge/>.
Cridlebaugh, Bruce S. "Bridge Basics - A Spotter's Guide to Bridge Design." Bridge
Basics - A Spotter's Guide to Bridge Design. N.p., 03 June 2008. Web. 07 Jan. 2017.
Distefano, Dorothy, and Michelle Arevalo. "What Is Continuous Beam?"
WiseGEEK. Conjecture Corporation, n.d. Web. 07 Jan. 2017.
"How Bridges Work." HowStuffWorks Science. HowStuffWorks, 2017. Web. 09 Jan.
2017. <http://science.howstuffworks.com/engineering/civil/bridge3.htm>.
"How Does a Suspension Bridge Work?" Wonderopolis. N.p., n.d. Web. 09 Jan. 2017.
<http://wonderopolis.org/wonder/how-does-a-suspension-bridge-work>.
"THE POINT & PITTSBURGH." Point Bridge. N.p., 17. Web. 9 Jan. 17. <http://point-
bridge.com/about-us/pittsburgh-the-point/>.
"File:Pride Rainbow - Lowry Avenue Bridge, Minneapolis (19218720442).jpg."
Wikimedia Common. N.p., 1 Oct. 16. Web. 9 Jan. 17.
<https://commons.wikimedia.org/wiki/File:Pride_Rainbow_-
_Lowry_Avenue_Bridge,_Minneapolis_(19218720442).jpg>.
"Tied-arch Bridge Facts, History and Examples." Tied-arch Bridge - Facts,
Design and Examples of Tied-arch Bridges. History of Bridges, 2017. Web. 07
Jan. 2017.
"Tied-arch Bridges." Steelconstruction.info. N.p., n.d. Web. 07 Jan. 2017.
21
Woodford, Chris. "How Bridges Work." Explain That Stuff. N.p., 26 Mar. 2016. Web.
09 Jan. 2017. <http://www.explainthatstuff.com/bridges.html>.
22
Appendix
Appendix A
Table 2. Daily Journal
Table 2, above, shows a daily log of each group member’s work on the project
throughout the days that it was being worked on.
23
Appendix B
Table 3. Daily Schedule
Task Day to be Completed Day Finished
Design Trusses 2-1-17 2-1-17
Construct Road 2-5-17 2-2-17
Construct Trusses 2-5-17 2-3-17
Design Arches 2-9-17 2-9-11
Construct Arches 2-10-17 2-11-17
Put Bridge Together 2-11-17 2-12-17
Complete Paper 2-13-17 2-13-17
Table 3, shown above, gives the day each task was to be finished, and the day
each task was completed. Most all of the tasks were completed on time. The arches
were not completed on time due to the need to wait for them to dry and one of them
breaking, which needed to be redone.
24