Soal !!!

Figure 2.15 shows a schematic of the status of activities at a given point in time. The floors
are divided into four sections labeled A, B, C, and D.

Each of these sectios can be considered as units to be processed. At the time Illustrated, work
is proceeding as follows:

1. Erect forms section A, floor N + 5.


2. Place reinforcing steel, section D, floor N + 4.
3. Place concrete section C, floor N + 4
4. Dismantle forms section B, floor N + 1.
5. Place curtain wall section D, floor N.
6. Place windows section D, floor N 1.

Crews proceed from section A to B to C to D.

The diagram in Figure 2.16 shows the LOB objective chart for a 10-story building. The
program chart for a typical section is shown above the objective.

1
Hitung Line Of Balance pada Minggu ke 6 ?

Jawab

LOB ( I )=Section completed as for week 6+(slope)(lead time of control point I )

Jumlah sections yang selesai pada minggu ke 6 adalah 8 atau secara kumulatif sebanyak 32
sections (8 x 4), jadi

LOB ( 1 )=32

LOB ( 2 )=32+ ( 1/10 ) 2=32.2

LOB ( 3 )=32+ (1 /10 ) 8=32.8

LOB ( 4 )=32+ ( 1/10 ) 14=33.4

LOB ( 5 )=32+ (1 /10 ) 38=35.8

LOB ( 6 ) =32+ ( 1/10 ) 40=36

Control point 7 dan 8 berfungsi untuk menyeimbangan flatter portion dari objective. Slope
pada section 1 adalah 1/10 sections/hours. Jadi.

LOB ( 7 ) =36+ ( 1/10 ) ( 4240 )=36.2

2
LOB ( 8 ) =36+ ( 1/ 10 ) ( 4440 )=36.4

Diagram program dan objective dapat dilihat dibawah ini.

Line of Balance pada minggu ke 6 dapat dilihat pada graphic di bawah ini.

Line of Balance
37
36
35
34

Production in Section 33
32
31
30
29
8 7 6 5 4 3 2 1

Line of Balance for month 8