Figure 2.15 shows a schematic of the status of activities at a given point in time. The floors
are divided into four sections labeled A, B, C, and D.
Each of these sectios can be considered as units to be processed. At the time Illustrated, work
is proceeding as follows:
The diagram in Figure 2.16 shows the LOB objective chart for a 10-story building. The
program chart for a typical section is shown above the objective.
1
Hitung Line Of Balance pada Minggu ke 6 ?
Jawab
Jumlah sections yang selesai pada minggu ke 6 adalah 8 atau secara kumulatif sebanyak 32
sections (8 x 4), jadi
LOB ( 1 )=32
Control point 7 dan 8 berfungsi untuk menyeimbangan flatter portion dari objective. Slope
pada section 1 adalah 1/10 sections/hours. Jadi.
2
LOB ( 8 ) =36+ ( 1/ 10 ) ( 4440 )=36.4
Line of Balance pada minggu ke 6 dapat dilihat pada graphic di bawah ini.
Line of Balance
37
36
35
34
Production in Section 33
32
31
30
29
8 7 6 5 4 3 2 1