The survey works started in the mid of December 2014 after 4 months from the
stating date project (3/8/2014).
The approval of the shop drawing for the first area (Jafeer Jadeed) was on the mid of
Feb. 2015 after 5.5 months.
The ordering of the material should be start immediately based on the Contract
drawings but Toledo delayed the starting of the order about nine months.
The project manager mobilized after 3 months from the starting of the project.
Project engineer mobilized after 9 months. Toledo failed to appoint approved
quantity surveyor throughout the period of contact.
3-Finanical Difficulties
The worked stopped many times due to unavailability of cash at site to purchase
material like sand, electrode, petrol for transportation.
Two & half years passed & till date Toledo could not able to handover even single
area to AADC although the project consists of 9 areas.