Schedule Compression is a technique used to shorten the duration of the project
without changing the scope of the project. It is used when a project falls behind schedule and needs to catch up, or if the project wants to finish sooner than what was originally scheduled. There are basically two techniques used to shorten the project duration: Crashing and Fast Tracking Fast Tracking Activities are performed in parallel or worked on simultaneously instead of waiting for each piece to be completed separately. It does not involve any costs. It is simply a rearrangement of the activities in the original schedule. It may lead to a rework or rearrangement of the project.
But Why Fast Track or Crash?
1. Fast tracking involves the performance of activities in parallel, whereas crashing involves the addition of resources to a project. 2. In fast tracking, there is increased risk, whereas in crashing, there is increased cost. Crashing Crashing (or Compressing) is the term used to describe the process of accelerating an activity or multiple activities to shorten the overall duration of a project. By adding people or equipment or by working additional hours, an activitys duration can be shortened. The time required to complete a project is determined by the critical path, so to compress the schedule, one must focus on the critical path activities. To minimize the cost, those activities that are not on the critical path can be extended to minimize their costs without increasing the project completion time. Activities are crashed for different reasons: 1. An activity or a series of activities may need to be completed by a specific date for contractual reasons. 2. Some activities can be accomplished more economically during a certain time of the year encouraging the acceleration of activities. 3. The cost to accelerate an activity that shortens the projects duration may be less expensive than the cost of running the project for the same period. Normal time: Normal time is the time required to complete the activity at normal conditions and cost. Crash time: Crash time is the shortest possible activity time; crashing more than the normal time will increase the direct cost. Cost Slope Cost slope is the increase in cost per unit of time saved by crashing. A linear cost curve is shown in Figure 8.27.