Professional Documents
Culture Documents
Reference to the stormwater strategy plan is required Task 3: Analyse Data and Prepare
when considering: Task 3: Analyse Data and Prepare
Forecasts
Forecasts
local network design parameters
opportunities and constraints for incorporation of Task 4: Formulate Alternatives
management components Task 4: Formulate Alternatives
determine the location and extent of any flooding measures in reducing post-development peak flows to
under major and minor system ARI design flows pre-development conditions or other required limits
determine the pollution loads for existing land uses determine the effectiveness of proposed water quality
within the catchment structures in reducing post-development pollutant
determine the performance of any existing water loads to pre-development levels or other agreed limits
quality control structures
(e) Tasks 5 & 6 : Compare Alternatives and Select
For proposed developments, models are required to: Recommended Plan
determine natural catchment flows within the Having formulated a set of possible alternative solutions
catchment which may be used as flow limits for for managing stormwater, the alternatives should be
development proposals compared and a subset selected to comprise a
determine natural pollutant loadings within the recommended plan. The essential features of each
catchment which may be used as pollutant load limits alternative such as size, costs, benefits, and positive and
for development proposals negative attributes should be compared in summary form
for presentation to decision-makers, and the community if
(d) Task 4 : Formulate Alternatives so required.
Formulation of alternatives is the most important part of Alternatives should be compared on the basis of how well
the stormwater master planning process because the they achieve the established objectives. An objective
substance of the recommended plan originates from this versus alternative matrix may be used to compare
step. Alternative formulation is a partly creative, partly alternatives. An example matrix is shown in Figure 9.2.
systematic effort where alternatives are conceptualised,
screened, and if promising, further developed. The range
of potential management practices presented in Table 8.2
ALTERNATIVES
may be used as a basis for selecting components for
alternative proposals.
Channel improvement
Community Retention
Community detention
On-site detention
Levees to protect
On-site retention
The essential conceptual, technical, economic,
residential area
management
environmental, financial, legal, administrative, political, and
Do nothing
Floodplain
other features of each alternative should be examined as
basins
basins
illustrated in Figure 8.3.
OBJECTIVES 1 2 3 4 5 6 7 8
In formulating alternative proposals, the water quantity
and quality characteristics must be determined, preferably Maximum prevention
of flood damages
by the use of an appropriate computer model (refer
Least disruptive to
Chapter 17). The objectives for modelling proposed physical environment
catchment conditions will depend on whether the Least harmful to
flora and fauna
catchment under consideration is an existing or a new
urban development. Ratio of benefits to NR NR
costs
Minimises NR NR
For existing developments, models are required to: construction costs
determine the effectiveness of the proposed As the positive and negative features of each alternative
conveyance systems and runoff quantity control are considered and compared with features of other
alternatives, the possibility of composite alternatives may
arise. Composite alternatives might achieve a technically private sectors will push for its implementation will depend
improved solution or might be a means of obtaining on the following factors:
support among decision-makers, and the community if so
the credibility of the plan as determined by the quality
required.
of the technical work and the thoroughness of the
community involvement program carried out during
(f) Task 7 : Prepare Plan Implementation Program
the planning process
The questions of when the plan elements are to be the frequency and severity of stormwater-related
implemented, who has the primary responsibility for problems and the level of concern that past problems
implementing them, and how the implementation is to be will occur again
carried out, including financing, should be addressed. For
plans prepared on a catchment basis, implementation may The ultimate test of a stormwater master plan is the
need to be carried out on a jurisdictional or sectoral basis degree to which stormwater problems have been mitigated
by a number of different Local Authorities. The number of and the degree to which potential stormwater problems
implementers can vary widely depending on the size and have been prevented from occurring. For community-
complexity of the stormwater master plan. funded projects, as step-by-step implementation proceeds,
each achievement should be strategically publicised. As
Responsibility for taking the lead in implementing elements these projects are paid for with public funds, the public
of a recommended plan can rest with government units should be informed about the return on their investment.
and agencies at all levels and with private entities.
9.3 MASTER PLAN COMPONENTS
The elements of the recommended plan should be
prioritised into relative order and the expected time for Master plans should consist of two major components,
implementation of each element stated. Prioritisation namely; a technical report, and supporting plans.
should be determined based on the following factors:
proposed drainage facilities, and downstream system topographic mapping and geological data (if available)
stability should be provided along with sufficient details to identify
method of conceptual design for maintaining existing systems elements. Plans should be of adequate scale and
flow regimes in any existing or proposed watercourses detail for accurate definition and location of all system
that may be altered by development elements and must provide support for hydrologic model
characterisation. In general, the following information is
method, conceptual design, and location of water
required:
quality control facilities
description of maintenance design features and delineation of sub-catchments of appropriate size and
provisions that will ensure reliable and long-term land use for computer model characterisation and
operation of facilities hydraulic analysis of all tributary flows
ecological analysis, including the physical and location and size of all existing and proposed
biological features of streams, ponds/wetlands, and hydrologic features and facilities in the catchment,
engineered waterways including ponds/wetlands, swales and floodways,
input and output files from hydrologic and/or hydraulic streams, channels, pipes, and culverts, etc
computer models included as an appendix an overall plan, and/or profile, and cross-sections of
a construction phasing plan that will ensure conveyance systems with frequency of flooding for
stormwater and erosion and sediment control during existing and developed conditions identified
development identification of existing areas of in-stream erosion,
sedimentation, and/or unstable slopes
9.3.2 Supporting Plans
identification of soils and preliminary analysis for
controlling erosion during construction and for use in
A conceptual or preliminary plan of the proposed
hydrologic modelling
stormwater conveyance, runoff quantity control, and water
quality control systems, based upon accurate field identification of upstream and downstream habitat
condition