You are on page 1of 4

1 997 AACE INTERNATIONAL TRANSACTIONS

C&C.07

How to Lose Money


Negotiating a Construction Claim

Michael R. Just, CCE, and Brian Tbrone

W
it clear toe contractor that ltS delay methodoIogy was wrong, the

delay anaIysIS WaS reVled during the trial

tenable arguments The most common mltakes made by owners and Losing Strategy(Contractor and Owner)-Ignore Resoce
COntraCtOrS include poor strategleS in defense of delay clalmS, I)Oorly Constraints
artioulated claims for additlOnal costand negotlat10n apProaches Both contractors and owners have used this losmg strategy and
that result m animoslty between the parties instead of effective reso- Suffered the consequences When contractors lgnOre reSOurCe re-
lution. These meifectlVe methods can make succeSful claims reOlu_
qulrementS m their scheduleshe result is a Chedule that shows
t10n muCh more difficult and adversarlal The resuIt can be delayed more float than if resources were taken into accountThis leads
resolutlOn Or, ln the worst case, eXPenSIVe lltlgation We haYe docu- to a classIC argument OVer Who owns the float in the schedule When
mented the most common loslng Strategies in three areas Schedule a contractor submlts a requeSt for a time extensIOn, lt is reeCted to

delay, COSt and damages, and negotiation approach In addlt10n, We the extent the lmPaCt Or Change uses available float The owners

have cited experiences from actual case hltOneS Where negotiations ClaSic (and technlCaIly correct) argument is that lfe change uti-

Were affected by poor strategy Hopefully, lessons will be leamed llZes float and the prQJeCt COmPletlOn date lS nOt lmPaCted, then the
at will be valuable to cost englneers and pro]eCt management prO- tlme eXtenSIOn requeSt lS denied The contracIor argues tha=) the
fessionals in achievmg more succeSclalmS and change-Order ne- float does not actually exlSt, Or 2) lf lt does exist, the float is required
godations. to maintaln SOme level of eclenCy These arguments, mOre Often

than not leave the owner unconvlnCed. When the parties cannot ne-

LOSING SCHEDULE STRATEGIES gotiate the changet oflen leads to a more serlOuS dispute later. The

reallty i that most schedules are created without consideron of re_

Losing Strategy #1 (Contractor)-LBlame the Owner for A SOurCeS. The obvIOuS Wmnlng Strategy lS tO Ioad schedules with re-
Delays SOurCe requlrementS When this has not been done, both partleS need
Contractors sometlmeS uSe a negOtlatlng Strategy Whereby all to consider the lmPllCation When evaluating requests for tlme.

PrQJeCt delays are blamed, by default, On the owner. When thlS Strat- CentlyVeI few contractors are sophlSticated enough to integrate

egy lS aPPllednO COnSideration lS glVen for how discrete changes or resource planmng wlth the schedug effort eifectively

events impac[ed the prqect completion date Usuallya lltany Of

OWner-CauSed impacts is identified, but the relatlOnShip of these im- Losing Strategyl (Contractor)-Ignore CPM

PactS and alleged delays to specific actlVities in the prQleCt SChedule Even if the contract does not requlre a Critical path method
is not specified. If specifro activities are idened, the criticallty Of (CPM) Chedule, a CPM is required to prove delay to the project

these activities is lgnOred. SChedule In the interest of saving time or money, many COntractOrS
try to assert owner.caused delay without the aid of a CPM schedule.
Loslng Straegyl (Conlractor)-Ignore Conrrency Owner Wi11 not generally granime extensions or entertain delay

Failure to consider concurrence of delays may result in an Claim Wlthout some fom of CPM analysl The CPM-based Ched-

analysis that greatly overstates total prQieCt delay. In fact, nOt COn- ule presentation should be ued at the changeOrder stage EYen if lt

Sidering conourrency may yield an analysIS that show a longer delay is not requlred by the contracCPM schedule i8 neCeSSary to P-OVe

than the actual preet delay that occurred. On a recent claim negoti- delay.
ationo additlon Of a11 delay days requested by the contractor ex-

Ceeded the actual prqiect delay by tee years. Put another way, the Losing Strategy rs (Contmctol. and Owner)-FIle `q3arly
requested time extension, if granted, WOuld have resulted in a con_ Schedulel) Claims
tract complefron 3 years after 'he actual proJeCt COmPletion date An early schedule is a schedule that shows prq)eCt COmPle

This inaccurate analysis reulted from the addltion of delays that all tion earlier than the contract completion dale. Thi is a loer for the

OurTed at the same lime. This led to a total breakdown of negotia- OWner Who usually refue tO alow legitimate early schedules. It lS

tien and to a lengthy and expenive triaL After the trial judge made also a loser fore contractor, Who artifroially shortens schedule to

Wm the claim game [5]. Becaue OWnerS are WOrried about the

CC.07. 1
1 997 AACE INTERNATIONAL TRANSACTIONS

tracts IS temPtlng. In addltlOn, 1t lS less tlme COnSum]ng and leS eX-


amiflCatlOnS Of approvmg early schedules they are frequently e-

pensiYe to PrePare ClalmS On this basIS Contractors often take the a


jected The reason owners are reluctat to approve early schedules is
titude, I bld X, and I spent X plus Y, I want to be paid Y also The
the fear that a delay claim will be filed even though the prueCt is

completed wlthin the specified contract tlme. Of course lt l nOW


reality is that ln mOSt CaSeS, the costs can be accumulated to mdlVld-
ual changes or lmPaCtS Aough the US Federal Coof ClalmS
well-eStabllShed that the contractor has the righ=o finish early The
has anowed this method, lt Placed llmits [4l on posslble abue by re-
coactor,s Iow bld prlCe may have been based on a plan that results

in ely completlOn and the associated cot SaVlngS. The on]y way qulng pOf tha

the owner knows for sure lS through the contract or contractor COOP- l the nature of the partlCular losses make -t imposslble or hlghly
eration when the bid lS PrOVided to the owner WhlCh proves it lS impractical to detemme them wlth a reasonable degree of accu-
raCy;
predlCated on an early completion Even O, an OWner could assert

that the plan lS unreasOnable In many cases the contractor does not 2the plalntlff, bld orestlmate WaS reallStlC,

provlde bld backup or provides ntradlCtOry backup to support the


3its actual costs were reaOnable; and
early complet10n SChedule. The wlming strategy for the contractor lS
4 1t WaS reSPOnSlble for the added expense
to be prepared to support early schedules with bid backup and a ra-
tionale for its reasonableness. The wlnnlng Strategy for the owner is These circumstances certalnly occur on construCtlOn ProeCtS

to approve early schedules that are supported by the bld and deter- but not nearly as often as thlS methodoIogy lS uSed In most crCum-

mined to be reaOnable stances, the cost can be attributed to specific events and estmated as

SuCh.
Lusing Strategy #6 (OwIler)-Ignore Possible Contractor Claim

Yet to Be Made Losing Strategy # (Contractor)-Ignore Overhead Recovery in


Owners and thelr COnSultants should not lgnOre ClalmS that have Change-Order MarkUps

not yet been made but could be made ln the futue When negotiatmg Frequently, the mark-uP On Changes IS lgnOred when extended
a claimt lS always helpful to put yourself ln yOur adversarys overhead (field and home oce overhead) clalmS are made Clearly

shoes Although it is up to the contractor to prove de[ay and lmPaCl some portion of the specified contract mark-uP IS lntended to cover
the wise owner recognlZeS When legltimate clains could be devel- field and home oce overhead Some contracts explicltly state that

oped wlthe expendlture Of addltlOnal money and outslde expertlSe. intent and go on to specify the allocatlOn Of the mark-P between

Inevltably, the contractor that has been damaged by legitlmate OWner home office overhead, field oce overhead, and profit Some con-

impacts wln tlme, hire the necessary consultants to prove it. Tlme tract clauses also mClude what the overhead lS lntended to cover [3]
and money can be saved lfese claims can be negotlated early m With or wiout clear contrac=anguage, many COntraCtOrS COm-

e resolution process. pletely lgnOre any reCOVery Of overhead that was lnCluded as part of
the mark-uP and request the total St for field and home oce over-

I,OSING COSTIDAMAGE STRATEGIES head (Eichleay) for period Of owner-CauSed delay However When

the overhead received through mark-uPS IS lgnOred SOme Or a11 of

Lusing Strategy(Contractor)-AIways Usee Eiceay the overhead lS double recovered Altemate contract recoverleS have
Fomula been suggested to reduce the double recovery and the resultlng dis-

Many clalmS uSe the EIChleay formula to calculate home o putes [1]. Unthe contracts are modified COactors need to con

overhead impacts. The Eichleay formula, howeverS aPPlicable ln


sider the overhead received in changes and avoid the double
recovery, Which can reduce the credlbility of an otherwISe me-itor
very linrited circumstances. The two key elements for the proper use
of the Eichleay fomula are ous claim

l. a distinct standby penod of uncertain durat10n Caued by the


Losing Strategy # (Ownerd Contractor)-Use Reservation of
PrQleCt OWner, and
Rigts
2. an economic impact on the absorption of the contractors home
Contractors and owners hould endeavor to negotlate all costs
Oce expese
associated with changes-rdlreCt, lndlreCt' lmPaCt Or Otherwise

In recent decl10nS in the US federal courts [2], contraCtorS have Currently, ln Order to kP their clalmS OPtlOnS OPen unti=he very
es[ablihed prima facie Eichleay damages (economic impact) by end of the prQject, COntraCtOrS nOW rOutinely mclude reservation-Of-
showing l)e existence of a govemmenimposed delay, and 2) that rights langunge ln their change orders. This statement uua11y indl-
the delay was for an unce-taln Period during which the contractor cates that the change orders covere direc=ime and costs of the
had to stand ready to compe the work. The burden then shs to changed work but do not include any effects or rlPPle costs, Or fur-
the govemment to show that the contractor could have reduced its ther extension of time These are to be reserved until such time as

overhead or laken on other wok to absorb the unabsoed overhead they can be finally ascertalned.'. Any reservation-Of-rights language
created by the impacted prQject Other recent case law (Ayer V. or other language that precludes thenal resolution of cost on a par-

JohoI1996) has focused on standbyrequirements ticular issue is gomg tO be construed as a failure to demonstrate
The blanket use of the Eichleay formula for most owner_CauSed gooduth negotiations. Contractors should have prQ]eCt COntrOl yS-
delay situations l Clearly a losing strategyl Contractors that use the tems, both Chedule and cost systems) to aCC`tely assess theI

Eichleay formula need to be prepared to prove standby and eco- impact of a change. PrQjects wchange orders contaimng reserva-

nomic effect. tlOn-Of-nghts lmguage are much more likely to end up ln PrOtraCted'
expensive litigation.
LuslngStrategy# (Contractor)Use Total Cost Clalms

Gratuitously
Applicability of the total cost recovery lS also rare' but [he
hopes of converting lump sum contracts into cosreimbursable con-

C&C.07.2
1 997 AACE INTERNATIONAL TRANSACTIONS

to t?e into account amounts already recovered ln Change orders, and


RECOMMENDED READING
fallure to agree on the reservation of nghts ln Changes Loslng negO- l. DrlSCOll, Thomas J,, et al Construction Schedulig:

tiation approaches are related to both the negotiators preparatlOn PrepaI.ation, Liability and Claims New York: Wlley Law
and his1er taCties during the negotlatlOn PrOCeSS. Preparation prob- bllCaons, 1991

lems mClude relylng On the frequently faulty or biased reco11ections 2. Fondahl, John W7he Developmen! f !he Cotruc10
of pcople who worked on the job, and negotiating without command Emeer Pas POgreSS CZndre Problem. Journa1 0f
of the facts. Problemat]C taCtics lnClude addlng emOtion to the nego- Construction Engineering and Management l 17, nO 3
tiatron sessIOnS, and inexibility on ceraln POlntS beyond what lS
(Septeber 1991) 380-392
warranted by the facts Owners, COntraCtorS, and nSultants can all

lean from these frequently used losmg strategleS tO PreSent thelr fu-
Michael R Just, CCE
ture cases well and achieYe equitable se.ttlements at the bargalIrng
OBnen Keitberg
ble.
200 West Madison, Sulte 2805
REERENCES ChlCagO, lL 60606

I Just, Michael, and James Murphy. New Jas m Ovehead

Recovery 1995 TI.anSaCtions of AACE International. Brian Torone

Morgantown, WV AACE Intemationa=995 OBrien KreltZberg

50 Fremont St.
2. ech-Con Co. v West61 S.3d 883 (Fed. Clr 1995)
San FrancISCO, CA 94105
3. Torone, Brlan, and MIChael Jus{ Avoiding Construction
Disputes With Eective Cost and Schedule Specications

Project Management Institute ReglOnal Symposlum, 1 993.


4. WB Co7PO oJ. V. UndSe, 183 Ct C1 409, 426 (1968)

(lS is theotal cost case)

5. Zack, Jame GClazmsh: C rrePtZCtice Journal

of Construction Engieerlng and Manngemen= 19 nO. 3

(Septembe 1 993)

C&C.07.4

You might also like