Professional Documents
Culture Documents
How To Lose Money Negotiating A Construction Claim
How To Lose Money Negotiating A Construction Claim
C&C.07
W
it clear toe contractor that ltS delay methodoIogy was wrong, the
tenable arguments The most common mltakes made by owners and Losing Strategy(Contractor and Owner)-Ignore Resoce
COntraCtOrS include poor strategleS in defense of delay clalmS, I)Oorly Constraints
artioulated claims for additlOnal costand negotlat10n apProaches Both contractors and owners have used this losmg strategy and
that result m animoslty between the parties instead of effective reso- Suffered the consequences When contractors lgnOre reSOurCe re-
lution. These meifectlVe methods can make succeSful claims reOlu_
qulrementS m their scheduleshe result is a Chedule that shows
t10n muCh more difficult and adversarlal The resuIt can be delayed more float than if resources were taken into accountThis leads
resolutlOn Or, ln the worst case, eXPenSIVe lltlgation We haYe docu- to a classIC argument OVer Who owns the float in the schedule When
mented the most common loslng Strategies in three areas Schedule a contractor submlts a requeSt for a time extensIOn, lt is reeCted to
delay, COSt and damages, and negotiation approach In addlt10n, We the extent the lmPaCt Or Change uses available float The owners
have cited experiences from actual case hltOneS Where negotiations ClaSic (and technlCaIly correct) argument is that lfe change uti-
Were affected by poor strategy Hopefully, lessons will be leamed llZes float and the prQJeCt COmPletlOn date lS nOt lmPaCted, then the
at will be valuable to cost englneers and pro]eCt management prO- tlme eXtenSIOn requeSt lS denied The contracIor argues tha=) the
fessionals in achievmg more succeSclalmS and change-Order ne- float does not actually exlSt, Or 2) lf lt does exist, the float is required
godations. to maintaln SOme level of eclenCy These arguments, mOre Often
than not leave the owner unconvlnCed. When the parties cannot ne-
LOSING SCHEDULE STRATEGIES gotiate the changet oflen leads to a more serlOuS dispute later. The
Losing Strategy #1 (Contractor)-LBlame the Owner for A SOurCeS. The obvIOuS Wmnlng Strategy lS tO Ioad schedules with re-
Delays SOurCe requlrementS When this has not been done, both partleS need
Contractors sometlmeS uSe a negOtlatlng Strategy Whereby all to consider the lmPllCation When evaluating requests for tlme.
PrQJeCt delays are blamed, by default, On the owner. When thlS Strat- CentlyVeI few contractors are sophlSticated enough to integrate
egy lS aPPllednO COnSideration lS glVen for how discrete changes or resource planmng wlth the schedug effort eifectively
OWner-CauSed impacts is identified, but the relatlOnShip of these im- Losing Strategyl (Contractor)-Ignore CPM
PactS and alleged delays to specific actlVities in the prQleCt SChedule Even if the contract does not requlre a Critical path method
is not specified. If specifro activities are idened, the criticallty Of (CPM) Chedule, a CPM is required to prove delay to the project
these activities is lgnOred. SChedule In the interest of saving time or money, many COntractOrS
try to assert owner.caused delay without the aid of a CPM schedule.
Loslng Straegyl (Conlractor)-Ignore Conrrency Owner Wi11 not generally granime extensions or entertain delay
Failure to consider concurrence of delays may result in an Claim Wlthout some fom of CPM analysl The CPM-based Ched-
analysis that greatly overstates total prQieCt delay. In fact, nOt COn- ule presentation should be ued at the changeOrder stage EYen if lt
Sidering conourrency may yield an analysIS that show a longer delay is not requlred by the contracCPM schedule i8 neCeSSary to P-OVe
than the actual preet delay that occurred. On a recent claim negoti- delay.
ationo additlon Of a11 delay days requested by the contractor ex-
Ceeded the actual prqiect delay by tee years. Put another way, the Losing Strategy rs (Contmctol. and Owner)-FIle `q3arly
requested time extension, if granted, WOuld have resulted in a con_ Schedulel) Claims
tract complefron 3 years after 'he actual proJeCt COmPletion date An early schedule is a schedule that shows prq)eCt COmPle
This inaccurate analysis reulted from the addltion of delays that all tion earlier than the contract completion dale. Thi is a loer for the
OurTed at the same lime. This led to a total breakdown of negotia- OWner Who usually refue tO alow legitimate early schedules. It lS
tien and to a lengthy and expenive triaL After the trial judge made also a loser fore contractor, Who artifroially shortens schedule to
Wm the claim game [5]. Becaue OWnerS are WOrried about the
CC.07. 1
1 997 AACE INTERNATIONAL TRANSACTIONS
in ely completlOn and the associated cot SaVlngS. The on]y way qulng pOf tha
the owner knows for sure lS through the contract or contractor COOP- l the nature of the partlCular losses make -t imposslble or hlghly
eration when the bid lS PrOVided to the owner WhlCh proves it lS impractical to detemme them wlth a reasonable degree of accu-
raCy;
predlCated on an early completion Even O, an OWner could assert
that the plan lS unreasOnable In many cases the contractor does not 2the plalntlff, bld orestlmate WaS reallStlC,
to approve early schedules that are supported by the bld and deter- but not nearly as often as thlS methodoIogy lS uSed In most crCum-
mined to be reaOnable stances, the cost can be attributed to specific events and estmated as
SuCh.
Lusing Strategy #6 (OwIler)-Ignore Possible Contractor Claim
not yet been made but could be made ln the futue When negotiatmg Frequently, the mark-uP On Changes IS lgnOred when extended
a claimt lS always helpful to put yourself ln yOur adversarys overhead (field and home oce overhead) clalmS are made Clearly
shoes Although it is up to the contractor to prove de[ay and lmPaCl some portion of the specified contract mark-uP IS lntended to cover
the wise owner recognlZeS When legltimate clains could be devel- field and home oce overhead Some contracts explicltly state that
oped wlthe expendlture Of addltlOnal money and outslde expertlSe. intent and go on to specify the allocatlOn Of the mark-P between
Inevltably, the contractor that has been damaged by legitlmate OWner home office overhead, field oce overhead, and profit Some con-
impacts wln tlme, hire the necessary consultants to prove it. Tlme tract clauses also mClude what the overhead lS lntended to cover [3]
and money can be saved lfese claims can be negotlated early m With or wiout clear contrac=anguage, many COntraCtOrS COm-
e resolution process. pletely lgnOre any reCOVery Of overhead that was lnCluded as part of
the mark-uP and request the total St for field and home oce over-
I,OSING COSTIDAMAGE STRATEGIES head (Eichleay) for period Of owner-CauSed delay However When
Lusing Strategy(Contractor)-AIways Usee Eiceay the overhead lS double recovered Altemate contract recoverleS have
Fomula been suggested to reduce the double recovery and the resultlng dis-
Many clalmS uSe the EIChleay formula to calculate home o putes [1]. Unthe contracts are modified COactors need to con
In recent decl10nS in the US federal courts [2], contraCtorS have Currently, ln Order to kP their clalmS OPtlOnS OPen unti=he very
es[ablihed prima facie Eichleay damages (economic impact) by end of the prQject, COntraCtOrS nOW rOutinely mclude reservation-Of-
showing l)e existence of a govemmenimposed delay, and 2) that rights langunge ln their change orders. This statement uua11y indl-
the delay was for an unce-taln Period during which the contractor cates that the change orders covere direc=ime and costs of the
had to stand ready to compe the work. The burden then shs to changed work but do not include any effects or rlPPle costs, Or fur-
the govemment to show that the contractor could have reduced its ther extension of time These are to be reserved until such time as
overhead or laken on other wok to absorb the unabsoed overhead they can be finally ascertalned.'. Any reservation-Of-rights language
created by the impacted prQject Other recent case law (Ayer V. or other language that precludes thenal resolution of cost on a par-
JohoI1996) has focused on standbyrequirements ticular issue is gomg tO be construed as a failure to demonstrate
The blanket use of the Eichleay formula for most owner_CauSed gooduth negotiations. Contractors should have prQ]eCt COntrOl yS-
delay situations l Clearly a losing strategyl Contractors that use the tems, both Chedule and cost systems) to aCC`tely assess theI
Eichleay formula need to be prepared to prove standby and eco- impact of a change. PrQjects wchange orders contaimng reserva-
nomic effect. tlOn-Of-nghts lmguage are much more likely to end up ln PrOtraCted'
expensive litigation.
LuslngStrategy# (Contractor)Use Total Cost Clalms
Gratuitously
Applicability of the total cost recovery lS also rare' but [he
hopes of converting lump sum contracts into cosreimbursable con-
C&C.07.2
1 997 AACE INTERNATIONAL TRANSACTIONS
tiation approaches are related to both the negotiators preparatlOn PrepaI.ation, Liability and Claims New York: Wlley Law
and his1er taCties during the negotlatlOn PrOCeSS. Preparation prob- bllCaons, 1991
lems mClude relylng On the frequently faulty or biased reco11ections 2. Fondahl, John W7he Developmen! f !he Cotruc10
of pcople who worked on the job, and negotiating without command Emeer Pas POgreSS CZndre Problem. Journa1 0f
of the facts. Problemat]C taCtics lnClude addlng emOtion to the nego- Construction Engineering and Management l 17, nO 3
tiatron sessIOnS, and inexibility on ceraln POlntS beyond what lS
(Septeber 1991) 380-392
warranted by the facts Owners, COntraCtorS, and nSultants can all
lean from these frequently used losmg strategleS tO PreSent thelr fu-
Michael R Just, CCE
ture cases well and achieYe equitable se.ttlements at the bargalIrng
OBnen Keitberg
ble.
200 West Madison, Sulte 2805
REERENCES ChlCagO, lL 60606
50 Fremont St.
2. ech-Con Co. v West61 S.3d 883 (Fed. Clr 1995)
San FrancISCO, CA 94105
3. Torone, Brlan, and MIChael Jus{ Avoiding Construction
Disputes With Eective Cost and Schedule Specications
(Septembe 1 993)
C&C.07.4