You are on page 1of 6

THE COLLAPSE OF I-35W HIGHWAY BRIDGE IN MINNEAPOLIS

Hazwal, Saidatina Aishah, Khairul Hafizi


Faculty of Electrical Engineering
University Teknikal Malaysia Melaka (UTeM)
Durian Tunggal, Melaka
hazwal_ngadeni@yahoo.com.my, saida.aishah_007@yahoo.com, khairul_hafizi91@yahoo.com

Abstract This paper present the case study I. INTRODUCTION


on the Collapse of I-35W Highway Bridge in
Minneapolis. 1st of August 2007, the eight-lane, About 6:05 p.m. central daylight time on
1,907 foot long I-35W Highway Bridge over the Wednesday, 1st of August 2007, the eight-lane, 1,907
Mississippi River in Minneapolis, Minnesota had foot long I-35W Highway Bridge over the
collapsed and resulting in 13 people died and 145 Mississippi River in Minneapolis, Minnesota,
people were injured. On the day of the collapse, experienced a catastrophic failure in the main span of
the bridge was under construction and all the the deck truss.[1,2] As a result, 1,000 feet of the deck
equipment and construction aggregates were truss collapsed, with about 456 feet of the main span
delivered on the road and increase the weight of falling 108 feet into the 15 foot deep river. A total of
the bridge itself. It is investigated that one of the 111 vehicles were on the portion of the bridge that
reasons was due to the faulty gusset plate due to collapsed. Of these, 17 were recovered from the
the error in the original design. Corrosion damage water. As a result of the bridge collapse, 13 people
in gusset plates, fracture of a floor truss, died and 145 people were injured. [1] On the day of the
preexisting cracking, temperature effects, and pier collapse, roadway work was underway on the I-35W
movement were also identified. This accident is Highway Bridge and four of the eight travel lanes,
considered as engineered accident that caused by two outside lanes northbound and two inside lanes
flaws of the design. In this report, Code of southbound, were closed to traffic. In the early
Conduct was discussed in order to make other afternoon, construction equipment and construction
engineers aware about the safety of the public as it aggregates were delivered and positioned in the two
is an important thing to look at during designing. closed inside southbound lanes. The equipment and
Besides, line drawing and flow chart are used in aggregates, which were being staged for a concrete
order to identify the cause and problems occur in pour of the southbound lanes that was to begin about
the bridge. In line drawing, the positive and 7:00 p.m., were positioned toward the south end of
negative paradigm are listed and flow chart shows the center section of the deck truss portion of the
the process of constructing the bridge and bridge and were in place by about 2:30 p.m. [1] About
supposedly, there should not be any design flaws 6:05 p.m., a motion-activated surveillance video
in constructing the I-35W Highway Bridge if the camera just west of the I-35W Highway Bridge,
original design is reviewed and checked recorded a portion of the collapse sequence. This
thoroughly by the party in charged. Last but not tragedy instantly captured national attention. Since
least, the main cause of this accident is due to the safety of bridges and other public infrastructure is
design flaws of Sverdrup & Parcels quality taken for granted, catastrophic failures like this
control procedures to ensure that the appropriate directly threaten the credibility of the government,
main truss gusset plate calculations were and can easily turn into widespread panic and public
performed for the I-35W Highway Bridge and the outrage.
inadequate design review by Federal and State
transportation officials. II. DESCRIPTION OF THE LITERATURE

Engineering consulting firm of Sverdrup &


Parcel and Associates, Inc., of St. Louis, Missouri, a
Index Terms Bridge tragedy, type of predecessor company of Sverdrup Corporation
accident, ethical theories, flaws of design, code of designed the I-35W Highway Bridge which was
conduct. acquired in 1999 by Jacobs Engineering Group, Inc.
The bridge design was developed over several years,
with plans for the foundation approved in 1964 and
final design plans certified by the Sverdrup & Parcel Figure 1: Chronology of Incident
project manager cum Professional Engineer on 4th of
March 1965. The bridge design plans were approved III. ETHICAL ISSUES
by Minnesota Department of Transportation
(Mn/DOT) on 18th of June 18, 1965. A. Type of Accident

A. Causes of Tragedy There are many ways to categorized accidents.


One of the methods is to group accidents into three
One of the probable reasons was due to the types; which are procedural, engineered, and
faulty gusset plate (48 metal plate used to connect systemic. Procedural accidents are the result of
and secure multiple beams). This plate was half as someone making a bad choice or not following
thick as it should have been, the result of an error in established procedures. Engineered accidents are
the original design by Sverdrup & Parcel and caused by flaws of the design. Supposedly,
Associates in 1961 that somehow made its way engineered failures should be corrected during
through the quality control process within the firm, testing. As for systemic accidents, it is harder to
and the many rounds of design reviews by federal control and harder to understand. The perfect
and state transportation officials. Due to the example of systemic accident is the airline industry.
construction activity that was ongoing on that time,
concentrated construction weight were placed The collapse of the I-35W Bridge in
directly on the weakest link of the bridge. Meaning Minneapolis is considered as engineered accident.
that it is directly on the point where the faulty gusset From the investigation, it is noted that these are the
plate located. failures of materials, devices that do not perform well
under all conditions encountered or devices that do
Other than gusset plate, the Safety Board also not perform as expected. From this accident, the main
considered a number of potential explanations that factor is related to gusset plates that used to connect
lead to this accident. The following factors were the steel beams in the truss. The investigators
considered, but not totally taken into considerations determined that the original design for these gusset
as it was only a minor reasons as being causal to the plates was insufficient and unsatisfactory. It is been
collapse; corrosion damage in gusset plates, fracture found that the gusset plates installed on the bridge
of a floor truss, preexisting cracking, temperature were only half the thickness that should have been to
effects, and pier movement were also identified support the structure. [3] 16 of these gusset plates had
during the investigations. fractured when the bridge collapsed. [4] Besides, the
design of the bridge was also found to be fracture-
critical, meaning that there were no redundant load-
bearing paths designed into the structure, thus a
failure of any one of several critical structural
elements would lead to a collapse of the entire
structure. By referring to the definition of engineered
accidents, the engineered failures should be
anticipated in the design stage and should be caught
and corrected during testing. However, the original
design firm did not detect the design error when the
plans were originally created and approved. Even
though there were numerous subsequent
recalculations for maintenance, load rating, or
inspections, these calculations are not necessarily
expected to uncover original mistakes in the gusset
plate designs or calculations.

Last but not least, a serious design error that


leads to undersized gusset plates and structure that
was too weak to safely support the bridge led to this
accident.

B. Ethical Theory
The codes of ethics of the professional The I-35W Bridge was designed by the
engineering societies make it clear that safety is of
paramount importance to the engineer. Engineers engineering consulting firm of Sverdrup & Parcel and
have the responsibility to society to produce
products, structures, and process that are safe. Associates, Inc., of St. Louis, Missouri. The design
Clearly, nothing can be 100% safe, but engineers are
required to make their designs as safe as possible. was based on the 1961 American Association of State

National Transportation Safety Board (NTSB) Highway Officials (AASHO) Standard Specifications
received sets of design documents from both the
Minnesota Department of Transportation (Mn/DOT) for Highway Bridges and 1961 and 1962 Interim
and Jacobs Engineering Group, Inc. (Jacobs) after the
bridge collapse. In addition to the design drawings, Specifications, and on the 1964 Minnesota Highway
both entities provided the same collections of several
hundred pages of consecutively indexed and Department Standard Specifications for Highway
numbered compilations of checked computation
sheets showing calculations performed for the final Construction. The bridge design was developed over
design of the bridge. [3,4] The computation sheets for
the deck truss superstructure contained design numerous years. In 1964, plans for the foundation
calculations for the welded gusset plates used in the
floor trusses, but none of the records from Mn/DOT were approved and construction of some piers began
or Jacobs Engineering showed any calculations for
the gusset plates on the main trusses. during that time. The final design plans for the bridge

were certified by the Sverdrup & Parcel project

manager (a registered professional engineer) on

March 4, 1965. The bridge design plans were

approved by the Minnesota Highway Department on

June 18, 1965. [4]

Project manager of Sverdrup & Parcel (a registered


professional engineer) that certified the final design
plans for the bridge should check carefully about the
calculations and design of the bridge. None of the
records from Mn/DOT or Jacobs Engineering showed
any calculations for the gusset plates on the main
trusses. The project manager should realize this
design error before he certified it as safety design.
This is the first aspect to be taken into consideration
as a registered engineer.

Besides that, he can be regard as irresponsible


person for the actions taken as a project manager.
Although he allowed the project to be carried out and
give convenience to the public, the action actually
threatens the safety of people where the main fault is
placed on the design structure. From this accident,
the action of the project manager can be categorized
in virtue ethics. In engineering career, virtue ethics
concern about the action of the engineer itself.
Whether their action is honest, responsible and loyal
to the community and employer or not. In general things may be overlooked despite very through
view, it can be seen that the bridge has flaws in the inspections. Thus in order to maintain sustainability
design and might cause danger to the people. as well as ensure the lives, safety, health and welfare
However, the project manager still certified the final of the general public, engineers must accompany
design plans without knowingly the purpose of his traditional methods of bridge inspections with
action. advanced procedures utilizing technology that
includes the use of sensors, infrared and radar
C. Code of Conduct equipment. One mistake in engineering causes
people to die. These advanced technological methods
It is believe that engineers hold a great moral will allow engineers to prevent disaster, as well as
responsibility when it comes to the safety of the follow ethical codes within their profession.[3]
countrys bridges. The Board of Engineers lists in its
fundamental codes that engineers should hold The codes of professional conduct also
paramount the safety, health, and welfare of the states that, A Registered Engineer shall at all-time
public. Moreover, large numbers of the bridges have hold paramount the safety, health, and welfare of the
been deemed unsafe or structurally deficient. This public goes directly with the technology. This
problem has been resulted from poor bridge design technology will prevent disaster if being used with
and maintenance. One of the United States greatest correct. For example, the engineers are trying to
disasters was the collapse of the I-35W Highway install sensors on the bridges for the safety of the
Bridge back in 2007. An investigation was launched public, so there is no chance for incidents in the
to determine the cause of the accident. The Minneapolis of I-35W Bridge. Thirteen people died
investigations found that I-35W Bridge lacked and many were injured and with these sensors, these
sufficient quality control of the gusset plates design things can be prevented.
by the engineers.[4] The original design of gusset
plates was insufficient and the gusset plates installed Furthermore, A Registered Engineer shall
were only half the thickness that they should installed conduct himself honorably, responsibly, ethically, and
to support the structure. However, the investigators lawfully so as to enhance the honor, reputation, and
also were unable to verify when and by whom this usefulness of the profession. By letting the public
mistake were made. know that they can build these sensors and use them
in bridges, the public will go along with it because of
If one person dies as a result of engineering the safety reasons. The engineers reputation will rise
failure, not only does it negatively reflect the in the eyes of the public due to the giving this type of
profession, but also it is certainly a tragedy. All information to them. Besides that, another code of
engineering disciplines have a broad code of ethics professional conduct states that A Registered
that must be followed by all engineers. For instance, Engineer shall undertake assignments only if he is
section 1.1 of the 1st rule of practice in the code of qualified by education and experience in the specific
professional conduct states that, A Professional technical fields in which he is involved. This code
Engineers shall approve and sign only those explain that engineers should have knowledge of
engineering documents that he has prepared or are developments in the area of professional engineering
prepared under his direct supervision. The relevant to any services that are undertaken and being
documents that accompany a bridge inspection competence in the performance. The design of the I-
should only be approved if the inspection applies 35W Bridge structure should be develop by the
sufficient applicable methods. I-35W Bridge passed knowledgeable engineers.
inspection to the extent that it was safe to drive on.
The engineers performing the inspection most The maintenance and improvement of
certainly applied applicable standards to the process. technical competence should be done by seek, accept,
Nonetheless, the standards were not enough applied and offer honest criticism of technical work, correct
as the guidance in identifying the weak areas and errors, and to credit properly the contributions of
preventing the collapse.[3] The engineers remain others. Moreover, all persons regardless of such
ethical in this context. However, advanced factors as race, religion, gender, disability, age, or
technological inspection procedures would lead to national origin must to treat fairly. The maintenance
higher standards. In turn, society would obtain a and improvement must avoid injuring others and
greater degree of sustainability. raise the reputation. The engineers should be
maintain to assist others engineers and co-workers in
When inspecting bridges, all the aspects of their professional development and to support them
the codes apply for engineers. Furthermore, some in following this code of ethics.
The engineers must accept responsibility in
making engineering decisions consistent with the
safety, health and welfare of the public, and to
disclose promptly factors that might endanger the
public or the environment. The first one is to avoid
real or perceived conflicts of interest whenever
possible. Besides that, the engineers should be honest
and realistic in stating claims or estimates based on Figure 2: Line Drawing Analysis
available data, reject bribery in all its forms, and
improve the understanding of technology, its According to the line drawing analysis, the approach
appropriate application, and potential consequences. taken by the authority in this case wasnt the best
ethical choice.
Lastly, the code A Registered Engineer
shall act for each employer or clients as faithful agent B. Flowchart
or trustee is the code that all engineers must fulfill it.
The engineers shall have a fairness and loyalty to One possible flow chart that should been gone on
associates, clients, and employer. They also should constructing this bridge is illustrated in Figure 3.
have fidelity to public needs and have devotion to
high ideals of personal honor and professional
integrity.

IV. ANALYSIS

A. Line Drawing

Problem: Authority want to build a bridge located in


Minnesota that connecting the Minneapolis
neighborhoods of Downtown East and Marcy-
Holmes. The bridge was build in 1967 and in 2007,
the bridge was collapsed. The investigation team Figure 3: Flowchart Analysis
found out that there are flaws in the original design
by Sverdrup & Parcel and Associates. The gusset According to the above flow chart, the
plate used is half as thick as it should have been. The original design of the bridge should have gone
flaws only detected after the bridge collapsed because through several inspection processes before it is
of poor maintenance and inspection. permitted to construct. However, the design
somehow made its way through the quality
Positive Paradigm: Bridge Safe check process within the firm and authority
although there is error in the original design.
Negative Paradigm: Bridge Collapse
V. CONCLUSION
Hypothetical examples for consideration:
The National Transportation Safety Board
1. Replace the old gusset with new gusset according determines that the probable cause of the collapse of
to correct specification the I-35W bridge in Minneapolis, Minnesota, was the
inadequate load capacity, due to a design error by
2. Combine the existing gusset with another gusset Sverdrup & Parcel and Associates, Inc., of the gusset
that has the same size plates at the U10 nodes, which failed under a
combination of substantial increases in the weight of
3. Construct additional structure to support the bridge the bridge, which resulted from previous bridge
tension modifications and the traffic and concentrated
construction loads on the bridge on the day of the
4. Limit the allowable weight to pass the bridge collapse. Contributing to the design error was the
failure of Sverdrup & Parcels quality control
One view of the line is as shown in Figure 2. procedures to ensure that the appropriate main truss
gusset plate calculations were performed for the I-
35W Highway Bridge and the inadequate design
review by Federal and State transportation officials.
Contributing to the accident was the generally [5] (2007). I-35 Bridge Collapse, Minneapolis,
accepted practice among Federal and State MN. U.S. Department of Transportation Federal
transportation officials of giving inadequate attention Highway Association. [Online article].
to gusset plates during inspections for conditions of
distortion, such as bowing, and of excluding gusset Available:http://www.fhwa.dot.gov/pressroom/fsi35.h
plates in load rating analyses. tm

VI. REFERENCE [6] Chang, Kenneth, Wald, Matthew L. (2007,


Aug. 3). Minneapolis Bridge Had Passed
[1] Extracted from Highway Accident Report Inspections. The New York Times. [Online article]
Collapse of I-35W Highway Bridge Minneapolis,
Minnesota. Available:http://www.nytimes.com/2007/08/03/us/03
safety.html
Available:http://www.ntsb.gov/doclib/reports/2008/H
AR0803.pdf [7] J. Walker. (2011, Oct. 4). Improving and
Restoring The Urban Infrastructures Of Pittsburgh:
[2] Brewer, John. "I-35W Bridge collapses over Ethics And Education. University of Pittsburgh,
Mississippi River; 7 dead." St. Paul Pioneer Press 01 Swanson School of Engineering. [Online article]
Aug 2007.
Available:www.pitt.edu/~jhw27/Writing
[3] http://abcnews.go.com/Blotter/bridge- %20Assignment%203.docx
collapse-anniversary-safe-drivers

[4] http://www.studymode.com/essays/i-35W-
Ethical-Problem-618113.html

You might also like