KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 2 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 3 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 4 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 5 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 6 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 7 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 8 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 9 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 10 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 11 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 12 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 13 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 14 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 15 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 16 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 17 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 18 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 19 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 20 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 21 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 22 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 23 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 24 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 25 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 26 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 27 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 28 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 29 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 30 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 31 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 32 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 33 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 34 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 35 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 36 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWI
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 37 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
B01 ONCOLOGY BUILDING GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL-01 FLOOR
SD EGS ELECTRICAL 10-Nov-13 Yes C 9-Nov-13 S
PLAN (MASTER PLAN)
B01 ONCOLOGY BUILDING GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL-01 FLOOR
SD EGS ELECTRICAL 10-Nov-13 Yes C 10-Nov-13 S
PLAN (SEGMENT-H1)
B01 ONCOLOGY BUILDING LIGHTNING PROTECTION SYSTEM LAYOUT FOR LEVEL -2 (MASTER PLAN) SD EGS ELECTRICAL 10-Nov-13 Yes C 10-Nov-13 S
B01 ONCOLOGY BUILDING LIGHTNING PROTECTION SYSTEM LAYOUT FOR LEVEL -2 (SEGMENT-H)
SD LPS ELECTRICAL 10-Nov-13 Yes C 10-Nov-13 S
(PART-1)
B01 ONCOLOGY BUILDING LIGHTNING PROTECTION SYSTEM LAYOUT FOR LEVEL-2 (SEGMENT h1)
SD LPS ELECTRICAL 10-Nov-13 Yes C 10-Nov-13 S
(PART-2)
B01 ONCOLOGY BUILDING LIGHTNING PROTECTION SYSTEM LAYOUT FOR LEVEL-3 (SEGMENT-H1)
SD LPS ELECTRICAL 10-Nov-13 Yes C 10-Nov-13 S
(PART-2)
B01 ONCOLOGY BUILDING LIGHTNING PROTECTION SYSTEM LAYOUT FOR LEVEL-7 (SEGMENT-H)
SD LPS ELECTRICAL 10-Nov-13 Yes C 10-Nov-13 S
(LOWER ROOF)
B01 ONCOLOGY BUILDING LIGHTNING PROTECTION SYSTEM LAYOUT FOR LEVEL-8 (SEGMENT-H)
SD LPS ELECTRICAL 10-Nov-13 Yes C 10-Nov-13 S
(UPPER ROOF)
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1- MASTER PLAN (SEGMENT H1&H2) SD H0 ELECTRICAL 1-Dec-13 Yes C 1-Dec-13 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1- MASTER PLAN (SEGMENT H1&H2) SD H0 ELECTRICAL 19-Dec-13 Yes C 18-Dec-13 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1- MASTER PLAN (SEGMENT H1&H2) SD H0 ELECTRICAL 26-Apr-14 Yes C 21-Apr-14 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1- MASTER PLAN (SEGMENT H1&H2) SD H0 ELECTRICAL 14-May-14 Yes B 7-May-14 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1- MASTER PLAN (SEGMENT H1&H2) SD H0 ELECTRICAL 9-Jun-14 Yes B 3-Jun-14 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1- MASTER PLAN (SEGMENT H1&H2) SD H0 ELECTRICAL 7-Jan-15 Yes A 1-Jan-15 V
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1- (SEGMENT H1) SD H1 ELECTRICAL 1-Dec-13 Yes C 27-Nov-13 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1- (SEGMENT H1) SD H1 ELECTRICAL 7-Dec-13 Yes C 19-Dec-13 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1- (SEGMENT H1) SD H1 ELECTRICAL 26-Apr-14 Yes C 21-Apr-14 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1- (SEGMENT H1) SD H1 ELECTRICAL 14-May-14 Yes B 7-May-14 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1- (SEGMENT H1) SD H1 ELECTRICAL 9-Jun-14 Yes B 3-Jun-14 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1- (SEGMENT H1) SD H1 ELECTRICAL 7-Jan-15 Yes A 1-Jan-15 V
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1 - (SEGMENT H2) SD H2 ELECTRICAL 1-Dec-13 Yes C 27-Nov-13 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1 - (SEGMENT H2) SD H2 ELECTRICAL 7-Dec-13 Yes C 19-Dec-13 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1 - (SEGMENT H2) SD H2 ELECTRICAL 26-Apr-14 Yes C 21-Apr-14 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1 - (SEGMENT H2) SD H2 ELECTRICAL 14-May-14 Yes B 7-May-14 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVELS1 - (SEGMENT H2) SD H2 ELECTRICAL 9-Jun-14 Yes B 3-Jun-14 V
Page 38 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 MASTER PLAN (SEGMENT- H&H1) SD H0 ELECTRICAL 1-Dec-13 Yes C 26-Nov-13 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 MASTER PLAN (SEGMENT- H&H1) SD H0 ELECTRICAL 8-Dec-13 Yes C 26-Nov-13 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 MASTER PLAN (SEGMENT- H&H1) SD H0 ELECTRICAL 24-Dec-13 Yes C 12-Dec-13 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 MASTER PLAN (SEGMENT- H&H1) SD H0 ELECTRICAL 24-Jan-14 Yes B 23-Jan-14 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 MASTER PLAN (SEGMENT- H&H1) SD H0 ELECTRICAL 22-Feb-14 Yes B 18-Feb-14 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 MASTER PLAN (SEGMENT- H&H1) SD H0 ELECTRICAL 14-Jul-14 Yes C 12-Jul-14 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 MASTER PLAN (SEGMENT-
SD H0 ELECTRICAL 2-Aug-14 Yes A 2-Aug-14 V
H&H2 ,H3)
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 FLOOR PLAN (SEGMENT- H) SD H0 ELECTRICAL 1-Dec-13 Yes C 26-Nov-13 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 FLOOR PLAN (SEGMENT- H) SD H0 ELECTRICAL 24-Dec-13 Yes C 12-Jul-14 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 FLOOR PLAN (SEGMENT- H) SD H0 ELECTRICAL 23-Jan-14 Yes B 23-Jan-14 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 FLOOR PLAN (SEGMENT- H) SD H1 ELECTRICAL 22-Feb-14 Yes B 18-Feb-14 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 FLOOR PLAN (SEGMENT- H) SD H1 ELECTRICAL 14-Jul-14 Yes C 12-Jul-14 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 FLOOR PLAN (SEGMENT- H1 & H3 ) SD H1 ELECTRICAL 2-Aug-14 Yes A 2-Aug-14 V
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01FLOOR PLAN (SEGMENT- H1) SD H1 ELECTRICAL 1-Dec-13 Yes C 26-Nov-13 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01FLOOR PLAN (SEGMENT- H1) SD H1 ELECTRICAL 24-Dec-13 Yes C 12-Dec-13 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01FLOOR PLAN (SEGMENT- H1) SD H1 ELECTRICAL 23-Jan-14 Yes B 23-Jan-14 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01FLOOR PLAN (SEGMENT- H1) SD H2 ELECTRICAL 22-Feb-14 Yes B 18-Feb-14 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01FLOOR PLAN (SEGMENT- H1) SD H2 ELECTRICAL 14-Jul-14 Yes C 12-Jul-14 S
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01FLOOR PLAN (SEGMENT- H2&H3) SD H2 ELECTRICAL 2-Aug-14 Yes A 2-Aug-14 V
LIGHTING PROTECTION SYSTEM LAYOUT FOR LEVEL-2 MASTER PLAN SD H0 ELECTRICAL 1-Dec-13 Yes B 26-Nov-13 S
LIGHTING PROTECTION SYSTEM LAYOUT FOR LEVEL-2 MASTER PLAN SD H0 ELECTRICAL 23-Aug-14 Yes B 21-Aug-14 V
LIGHTING PROTECTION SYSTEM LAYOUT FOR LEVEL-2 (SEGMENT-H1) SD H1 ELECTRICAL 1-Dec-13 Yes B 26-Nov-13 S
LIGHTING PROTECTION SYSTEM LAYOUT FOR LEVEL-2 (SEGMENT-H1) SD H1 ELECTRICAL 23-Aug-14 Yes B 21-Aug-14 V
LIGHTING PROTECTION SYSTEM LAYOUT FOR LEVEL-2 (SEGMENT-H) SD H0 ELECTRICAL 1-Dec-13 Yes B 26-Nov-13 S
LIGHTING PROTECTION SYSTEM LAYOUT FOR LEVEL-2 (SEGMENT-H) SD H0 ELECTRICAL 23-Aug-14 Yes B 21-Aug-14 V
Page 39 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
LIGHTING PROTECTION SYSTEM LAYOUT FOR LEVEL-3 (SEGMENT-H1) SD H1 ELECTRICAL 1-Dec-13 Yes A 26-Nov-13 V
LIGHTING PROTECTION SYSTEM LAYOUT FOR LEVEL-7 (SEGMENT-H)- LOWER ROOF SD H0 ELECTRICAL 1-Dec-13 Yes A 26-Nov-13 V
LIGHTING PROTECTION SYSTEM LAYOUT FOR LEVEL-8 (SEGMENT-H)- UPPER ROOF SD H0 ELECTRICAL 1-Dec-13 Yes A 26-Nov-13 V
POWER SYSTEM LAYOUT FOR LEVEL-1 (LOW LEVEL) VERSA HD-10,18MV LINAC ROOM SD H0 ELECTRICAL 3-Dec-13 Yes D 3-Dec-13 V
POWER SYSTEM LAYOUT FOR LEVEL-1 (HIGH LEVEL ABOVE CEILING) VERSA HD-10,18MV LINAC ROOM SD H0 ELECTRICAL 3-Dec-13 Yes D 3-Dec-13 V
POWER SYSTEM LAYOUT FOR LEVEL-1 (HIGH LEVEL ABOVE CEILING) VERSA HD-10,18MV LINAC ROOM SD H0 ELECTRICAL 3-Dec-13 Yes D 3-Dec-13 V
GENERAL EQUIPMENT LAYOUT PLAN- VERSA HD-10,18 MV SD H0 ELECTRICAL 3-Dec-13 Yes D 3-Dec-13 V
LIGHTING SYSTEM LAYOUT FOR LEVEL 01 VERSA HD-10,18MV- LINAC ROOM SD H0 ELECTRICAL 3-Dec-13 Yes D 3-Dec-13 V
POWER SYSTEM LAYOUT FOR LEVEL-S1- MASTER PLAN (SEGMENT- H&H1) SD H0 ELECTRICAL 3-Dec-13 Yes C 4-Dec-13 S
POWER SYSTEM LAYOUT FOR LEVEL-S1- MASTER PLAN (SEGMENT- H&H1) SD H0 ELECTRICAL 14-Jun-14 Yes C 17-Jun-14 S
POWER SYSTEM LAYOUT FOR LEVEL-S1- MASTER PLAN (SEGMENT- H1&H2) SD H0 ELECTRICAL 16-Aug-14 Yes A 11-Aug-14 S
POWER SYSTEM LAYOUT FOR LEVEL-S1- MASTER PLAN (SEGMENT- H1&H2) SD H0 ELECTRICAL 7-Jan-15 Yes D 1-Jan-15 V
POWER SYSTEM LAYOUT FOR LEVEL-S1- (SEGMENT- H1) SD H0 ELECTRICAL 3-Dec-13 Yes B 4-Dec-13 S
POWER SYSTEM LAYOUT FOR LEVEL-S1- (SEGMENT- H1) SD H0 ELECTRICAL 14-Jun-14 Yes C 17-Jun-14 S
POWER SYSTEM LAYOUT FOR LEVEL-S1- (SEGMENT- H1) SD H0 ELECTRICAL 16-Aug-14 Yes A 11-Aug-14 S
POWER SYSTEM LAYOUT FOR LEVEL-S1- (SEGMENT- H1) SD H1 ELECTRICAL 7-Jan-15 Yes D 1-Jan-15 V
POWER SYSTEM LAYOUT FOR LEVEL-S1- (SEGMENT-H2) SD H1 ELECTRICAL 3-Dec-13 Yes B 4-Dec-13 S
POWER SYSTEM LAYOUT FOR LEVEL-S1- (SEGMENT-H2) SD H1 ELECTRICAL 14-Jun-14 Yes C 17-Jun-14 S
POWER SYSTEM LAYOUT FOR LEVEL-S1- (SEGMENT-H2) SD H0 ELECTRICAL 16-Aug-14 Yes A 11-Aug-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL S1- MASTER PLAN (SEGMENT-H&H1) SD H0 ELECTRICAL 3-Dec-13 Yes B 4-Dec-13 S
LIGHTING SYSTEM LAYOUT FOR LEVEL S1- MASTER PLAN (SEGMENT-H1&H2) SD H0 ELECTRICAL 23-Mar-14 Yes C 24-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL S1- MASTER PLAN (SEGMENT-H1&H2) SD H0 ELECTRICAL 30-Apr-14 Yes C 24-Apr-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL S1- MASTER PLAN (SEGMENT-H1&H2) SD H0 ELECTRICAL 14-May-14 Yes B 17-May-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL S1- MASTER PLAN (SEGMENT-H1&H2) SD H0 ELECTRICAL 7-Jan-15 Yes B 1-Jan-15 V
LIGHTING SYSTEM LAYOUT FOR LEVEL S1- (SEGMENT-H) SD H0 ELECTRICAL 3-Dec-13 Yes B 4-Dec-13 S
Page 40 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
LIGHTING SYSTEM LAYOUT FOR LEVEL S1- (SEGMENT-H1) SD H1 ELECTRICAL 23-Mar-14 Yes C 24-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL S1- (SEGMENT-H1) SD H1 ELECTRICAL 30-Apr-14 Yes C 24-Apr-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL S1- (SEGMENT-H1) SD H1 ELECTRICAL 14-May-14 Yes B 17-May-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL S1- (SEGMENT-H1) SD H1 ELECTRICAL 7-Jan-15 Yes B 1-Jan-15 V
LIGHTING SYSTEM LAYOUT FOR LEVEL S1- (SEGMENT-H1) SD H1 ELECTRICAL 3-Dec-13 Yes C 4-Dec-13 S
LIGHTING SYSTEM LAYOUT FOR LEVEL S1- (SEGMENT-H2) SD H2 ELECTRICAL 23-Mar-14 Yes C 24-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL S1- (SEGMENT-H2) SD H2 ELECTRICAL 30-Apr-14 Yes C 24-Apr-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL S1- (SEGMENT-H2) SD H2 ELECTRICAL 14-May-14 Yes B 17-May-14 V
FIRE ALARM& VOICE EVACUATION SYSTEM LEVELS1- MASTER PLAN (SEGMENT-H&H1) SD H0 ELECTRICAL 18-Dec-13 Yes C 12-Dec-13 S
FIRE ALARM& VOICE EVACUATION SYSTEM LEVELS1- MASTER PLAN (SEGMENT-H1&H2) SD H0 ELECTRICAL 10-Mar-14 Yes B 11-Mar-14 v
FIRE ALARM& VOICE EVACUATION SYSTEM LEVELS1- (SEGMENT-H) SD H0 ELECTRICAL 18-Dec-13 Yes C 12-Dec-13 S
FIRE ALARM& VOICE EVACUATION SYSTEM LEVELS1- (SEGMENT-H1) SD H1 ELECTRICAL 10-Mar-14 Yes B 11-Mar-14 v
FIRE ALARM& VOICE EVACUATION SYSTEM LEVELS1- (SEGMENT- H1) SD H0 ELECTRICAL 18-Dec-13 Yes C 12-Dec-13 S
FIRE ALARM& VOICE EVACUATION SYSTEM LEVELS1- (SEGMENT- H2) SD H2 ELECTRICAL 10-Mar-14 Yes B 11-Mar-14 v
BUILDING MANAGEMENT SYSTEM FOR LEVEL-S1- MASTER PLAN (SEGMENT- H1&H2) SD H0 ELECTRICAL 22-Dec-13 Yes C 19-Dec-13 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-S1- MASTER PLAN (SEGMENT- H1&H2) SD H1 ELECTRICAL 2-Mar-14 Yes C 2-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-S1- MASTER PLAN (SEGMENT- H1&H2) SD H1 ELECTRICAL 25-Apr-14 Yes A 18-May-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-S1- MASTER PLAN (SEGMENT- H1&H2) SD H1 ELECTRICAL 7-Jan-15 OverDue P V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-S1- (SEGMENT- H1) SD H0 ELECTRICAL 22-Dec-13 Yes C 19-Dec-13 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-S1- (SEGMENT- H1) SD H1 ELECTRICAL 2-Mar-14 Yes C 2-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-S1- (SEGMENT- H1) SD H1 ELECTRICAL 25-Apr-14 Yes A 18-May-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-S1- (SEGMENT- H1) SD H1 ELECTRICAL 7-Jan-15 OverDue P V
Page 41 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
BUILDING MANAGEMENT SYSTEM FOR LEVEL-S1 (SEGMENT- H2) SD H0 ELECTRICAL 22-Dec-13 Yes C 19-Dec-13 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-S1 (SEGMENT- H2) SD H2 ELECTRICAL 2-Mar-14 Yes C 2-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-S1 (SEGMENT- H2) SD H2 ELECTRICAL 25-Apr-14 Yes A 18-May-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-S1 (SEGMENT- H2) SD H2 ELECTRICAL 7-Jan-15 OverDue P V
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H1 SD H1 ELECTRICAL 22-Feb-14 Yes C 24-Feb-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H1 SD H1 ELECTRICAL 30-Mar-14 Yes B 6-May-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H1 SD H1 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H1 SD H1 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H1 SD H1 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-1) SD H1 ELECTRICAL 22-Feb-14 Yes C 24-Feb-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-1) SD H1 ELECTRICAL 30-Mar-14 Yes B 6-May-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-1) SD H1 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-1) SD H1 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-1) SD H1 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-2) SD H1 ELECTRICAL 22-Feb-14 Yes C 24-Feb-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-2) SD H1 ELECTRICAL 30-Mar-14 Yes B 6-May-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-2) SD H1 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-2) SD H1 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-2) SD H1 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-3) SD H1 ELECTRICAL 22-Feb-14 Yes C 24-Feb-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-3) SD H1 ELECTRICAL 30-Mar-14 Yes B 6-May-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-3) SD H1 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-3) SD H1 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-3) SD H1 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-4) SD H1 ELECTRICAL 22-Feb-14 Yes C 24-Feb-14 S
Page 42 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-4) SD H1 ELECTRICAL 30-Mar-14 Yes B 6-May-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-4) SD H1 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-4) SD H1 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H1 (PART-4) SD H1 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H2 SD H2 ELECTRICAL 22-Feb-14 Yes C 24-Feb-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H2 SD H2 ELECTRICAL 30-Mar-14 Yes B 6-May-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H2 SD H2 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H2 SD H2 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H2 SD H2 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-1) SD H2 ELECTRICAL 22-Feb-14 Yes C 24-Feb-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-1) SD H2 ELECTRICAL 30-Mar-14 Yes B 6-May-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-1) SD H2 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-1) SD H2 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-1) SD H2 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-2) SD H2 ELECTRICAL 22-Feb-14 Yes C 24-Feb-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-2) SD H2 ELECTRICAL 30-Mar-14 Yes B 6-May-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-2) SD H2 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-2) SD H2 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-2) SD H2 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-3) SD H2 ELECTRICAL 22-Feb-14 Yes C 24-Feb-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-3) SD H2 ELECTRICAL 30-Mar-14 Yes B 6-May-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-3) SD H2 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-3) SD H2 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-3) SD H2 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-4) SD H2 ELECTRICAL 22-Feb-14 Yes C 24-Feb-14 S
Page 43 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-4) SD H2 ELECTRICAL 30-Mar-14 Yes B 6-May-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-4) SD H2 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-4) SD H2 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 SEGMENT-H2 (PART-4) SD H2 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 SD H3 ELECTRICAL 22-Feb-14 Yes C 24-Feb-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 SD H3 ELECTRICAL 30-Mar-14 Yes B 6-May-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 SD H3 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 SD H3 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 SD H3 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 (PART-1) SD H3 ELECTRICAL 22-Feb-14 Yes C 24-Feb-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 (PART-1) SD H3 ELECTRICAL 30-Mar-14 Yes B 6-May-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 (PART-1) SD H3 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 (PART-1) SD H3 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 (PART-1) SD H3 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 (PART-2) SD H3 ELECTRICAL 22-Feb-14 Yes C 24-Feb-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 (PART-2) SD H3 ELECTRICAL 30-Mar-14 Yes B 6-May-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 (PART-2) SD H3 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 (PART-2) SD H3 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -01 MASTER PLAN SEGMENT-H3 (PART-2) SD H3 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
STRUCTURED CABLING LAYOUT LEVEL-1 PLAN (SEGMENT-H1) (MASTER PLAN) SD H1 ELECTRICAL 4-Mar-14 Yes C 9-Mar-14 v
STRUCTURED CABLING LAYOUT LEVEL-1 PLAN (SEGMENT-H1) (PART-1) SD H1 ELECTRICAL 4-Mar-14 Yes C 9-Mar-14 v
STRUCTURED CABLING LAYOUT LEVEL-1 PLAN (SEGMENT-H1) (PART-2) SD H1 ELECTRICAL 4-Mar-14 Yes C 9-Mar-14 v
STRUCTURED CABLING LAYOUT LEVEL-1 PLAN (SEGMENT-H1) (PART-3) SD H1 ELECTRICAL 4-Mar-14 Yes C 9-Mar-14 v
STRUCTURED CABLING LAYOUT LEVEL-1 PLAN (SEGMENT-H1) (PART-4) SD H1 ELECTRICAL 4-Mar-14 Yes C 9-Mar-14 v
STRUCTURED CABLING LAYOUT LEVEL-1 PLAN (SEGMENT-H2) (MASTER PLAN) SD H2 ELECTRICAL 4-Mar-14 Yes C 9-Mar-14 v
Page 44 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
STRUCTURED CABLING LAYOUT LEVEL-1 PLAN (SEGMENT-H2) (PART-1) SD H2 ELECTRICAL 4-Mar-14 Yes C 9-Mar-14 v
STRUCTURED CABLING LAYOUT LEVEL-1 PLAN (SEGMENT-H2) (PART-2) SD H2 ELECTRICAL 4-Mar-14 Yes C 9-Mar-14 v
STRUCTURED CABLING LAYOUT LEVEL-1 PLAN (SEGMENT-H2) (PART-3) SD H2 ELECTRICAL 4-Mar-14 Yes C 9-Mar-14 v
STRUCTURED CABLING LAYOUT LEVEL-1 PLAN (SEGMENT-H2) (PART-4) SD H2 ELECTRICAL 4-Mar-14 Yes C 9-Mar-14 v
STRUCTURED CABLING LAYOUT LEVEL-1 PLAN (SEGMENT-H3) (MASTER PLAN) SD H3 ELECTRICAL 4-Mar-14 Yes C 9-Mar-14 v
STRUCTURED CABLING LAYOUT LEVEL-1 PLAN (SEGMENT-H3) (PART-1) SD H3 ELECTRICAL 4-Mar-14 Yes C 9-Mar-14 v
STRUCTURED CABLING LAYOUT LEVEL-1 PLAN (SEGMENT-H3) (PART-2) SD H3 ELECTRICAL 4-Mar-14 Yes C 9-Mar-14 v
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 12-Mar-14 Yes B 12-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 16-Nov-14 Yes C 19-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H1) PART-1 OF 4 SD H1 ELECTRICAL 12-Mar-14 Yes B 12-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H1) PART-1 OF 4 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H1) PART-1 OF 4 SD H1 ELECTRICAL 16-Nov-14 Yes C 19-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H1) PART-2 OF 4 SD H1 ELECTRICAL 12-Mar-14 Yes B 12-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H1) PART-2 OF 4 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H1) PART-2 OF 4 SD H1 ELECTRICAL 16-Nov-14 Yes C 19-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H1) PART-3 OF 4 SD H1 ELECTRICAL 12-Mar-14 Yes B 12-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H1) PART-3 OF 4 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H1) PART-3 OF 4 SD H1 ELECTRICAL 16-Nov-14 Yes C 19-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H1) PART-4 OF 4 SD H1 ELECTRICAL 12-Mar-14 Yes B 12-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H1) PART-4 OF 4 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H1) PART-4 OF 4 SD H1 ELECTRICAL 16-Nov-14 Yes C 19-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 MASTER PLAN (SEGMENT-H2) SD H2 ELECTRICAL 12-Mar-14 Yes B 12-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 MASTER PLAN (SEGMENT-H2) SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 MASTER PLAN (SEGMENT-H2) SD H2 ELECTRICAL 16-Nov-14 Yes C 19-Nov-14 V
Page 45 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H2) PART-1 OF 4 SD H2 ELECTRICAL 12-Mar-14 Yes B 12-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H2) PART-1 OF 4 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H2) PART-1 OF 4 SD H2 ELECTRICAL 16-Nov-14 Yes C 19-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H2) PART-2 OF 4 SD H2 ELECTRICAL 12-Mar-14 Yes B 12-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H2) PART-2 OF 4 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H2) PART-2 OF 4 SD H2 ELECTRICAL 16-Nov-14 Yes C 19-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H2) PART-3 OF 4 SD H2 ELECTRICAL 12-Mar-14 Yes B 12-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H2) PART-3 OF 4 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H2) PART-3 OF 4 SD H2 ELECTRICAL 16-Nov-14 Yes C 19-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H2) PART-4 OF 4 SD H2 ELECTRICAL 12-Mar-14 Yes B 12-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H2) PART-4 OF 4 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H2) PART-4 OF 4 SD H2 ELECTRICAL 16-Nov-14 Yes C 19-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 MASTER PLAN (SEGMENT-H3) SD H3 ELECTRICAL 12-Mar-14 Yes B 12-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 MASTER PLAN (SEGMENT-H3) SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 MASTER PLAN (SEGMENT-H3) SD H3 ELECTRICAL 16-Nov-14 Yes C 19-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H3) PART- 1 OF 2 SD H3 ELECTRICAL 12-Mar-14 Yes B 12-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H3) PART- 1 OF 2 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H3) PART- 1 OF 2 SD H3 ELECTRICAL 16-Nov-14 Yes C 19-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H3) PART- 2 OF 2 SD H3 ELECTRICAL 12-Mar-14 Yes B 12-Mar-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H3) PART- 2 OF 2 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-1 (SEGEMENT-H3) PART- 2 OF 2 SD H3 ELECTRICAL 16-Nov-14 Yes C 19-Nov-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 12-Mar-14 Yes C 12-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 27-Apr-14 Yes B 27-May-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 23-Aug-14 Yes B 4-Sep-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H1 (PART-1 OF 4) SD H1 ELECTRICAL 12-Mar-14 Yes C 12-Mar-14 S
Page 46 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H1 (PART-1 OF 4) SD H1 ELECTRICAL 27-Apr-14 Yes B 27-May-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H1 (PART-1 OF 4) SD H1 ELECTRICAL 23-Aug-14 Yes B 4-Sep-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H1 (PART-2 OF 4) SD H1 ELECTRICAL 12-Mar-14 Yes C 12-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H1 (PART-2 OF 4) SD H1 ELECTRICAL 27-Apr-14 Yes B 27-May-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H1 (PART-2 OF 4) SD H1 ELECTRICAL 23-Aug-14 Yes B 4-Sep-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H1 (PART-3 OF 4) SD H1 ELECTRICAL 12-Mar-14 Yes C 12-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H1 (PART-3 OF 4) SD H1 ELECTRICAL 27-Apr-14 Yes B 27-May-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H1 (PART-3 OF 4) SD H1 ELECTRICAL 23-Aug-14 Yes B 4-Sep-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H1 (PART-4 OF 4) SD H1 ELECTRICAL 12-Mar-14 Yes C 12-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H1 (PART-4 OF 4) SD H1 ELECTRICAL 27-Apr-14 Yes B 27-May-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H1 (PART-4 OF 4) SD H1 ELECTRICAL 23-Aug-14 Yes A 4-Sep-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 MASTER PLAN (SEGMENT-H2) SD H2 ELECTRICAL 12-Mar-14 Yes C 12-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 MASTER PLAN (SEGMENT-H2) SD H2 ELECTRICAL 27-Apr-14 Yes B 27-May-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 MASTER PLAN (SEGMENT-H2) SD H2 ELECTRICAL 23-Aug-14 Yes B 25-Aug-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H2 (PART-1 OF 4) SD H2 ELECTRICAL 12-Mar-14 Yes C 12-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H2 (PART-1 OF 4) SD H2 ELECTRICAL 27-Apr-14 Yes B 27-May-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H2 (PART-1 OF 4) SD H2 ELECTRICAL 23-Aug-14 Yes B 25-Aug-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H2 (PART-2 OF 4) SD H2 ELECTRICAL 12-Mar-14 Yes C 12-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H2 (PART-2 OF 4) SD H2 ELECTRICAL 27-Apr-14 Yes B 27-May-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H2 (PART-2 OF 4) SD H2 ELECTRICAL 23-Aug-14 Yes B 25-Aug-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H2 (PART-3 OF 4) SD H2 ELECTRICAL 12-Mar-14 Yes C 12-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H2 (PART-3 OF 4) SD H2 ELECTRICAL 27-Apr-14 Yes B 27-May-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H2 (PART-3 OF 4) SD H2 ELECTRICAL 23-Aug-14 Yes B 25-Aug-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H2 (PART-4 OF 4) SD H2 ELECTRICAL 12-Mar-14 Yes C 12-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H2 (PART-4 OF 4) SD H2 ELECTRICAL 27-Apr-14 Yes B 27-May-14 S
Page 47 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H2 (PART-4 OF 4) SD H2 ELECTRICAL 23-Aug-14 Yes B 25-Aug-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 MASTER PLAN (SEGMENT-H3) SD H3 ELECTRICAL 12-Mar-14 Yes C 12-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 MASTER PLAN (SEGMENT-H3) SD H3 ELECTRICAL 27-Apr-14 Yes B 27-May-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 MASTER PLAN (SEGMENT-H3) SD H3 ELECTRICAL 23-Aug-14 Yes B 25-Aug-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H3 (PART-1 OF 2) SD H3 ELECTRICAL 12-Mar-14 Yes C 12-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H3 (PART-1 OF 2) SD H3 ELECTRICAL 27-Apr-14 Yes B 27-May-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H3 (PART-1 OF 2) SD H3 ELECTRICAL 23-Aug-14 Yes B 25-Aug-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H3 (PART-2 OF2) SD H3 ELECTRICAL 12-Mar-14 Yes C 12-Mar-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H3 (PART-2 OF2) SD H3 ELECTRICAL 27-Apr-14 Yes B 27-May-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -1 PLAN SEGEMENT-H3 (PART-2 OF2) SD H3 ELECTRICAL 23-Aug-14 Yes B 25-Aug-14 V
PUBLIC ADDRESS AND VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 15-Mar-14 Yes C 17-Mar-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 30-Aug-14 Yes C 30-Aug-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 5-Oct-14 Yes C 12-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 22-Nov-14 Yes C 23-Nov-14 V
PUBLIC ADDRESS AND VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-1/4) SD H1 ELECTRICAL 15-Mar-14 Yes C 17-Mar-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-1/4) SD H1 ELECTRICAL 30-Aug-14 Yes C 30-Aug-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-1/4) SD H1 ELECTRICAL 5-Oct-14 Yes C 12-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-1/4) SD H1 ELECTRICAL 22-Nov-14 Yes C 23-Nov-14 V
PUBLIC ADDRESS AND VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-2/4) SD H1 ELECTRICAL 15-Mar-14 Yes C 17-Mar-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-2/4) SD H1 ELECTRICAL 30-Aug-14 Yes C 30-Aug-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-2/4) SD H1 ELECTRICAL 5-Oct-14 Yes C 12-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-2/4) SD H1 ELECTRICAL 22-Nov-14 Yes C 23-Nov-14 V
PUBLIC ADDRESS AND VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-3/4) SD H1 ELECTRICAL 15-Mar-14 Yes C 17-Mar-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-3/4) SD H1 ELECTRICAL 30-Aug-14 Yes C 30-Aug-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-3/4) SD H1 ELECTRICAL 5-Oct-14 Yes C 12-Oct-14 S
Page 48 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-3/4) SD H1 ELECTRICAL 22-Nov-14 Yes C 23-Nov-14 V
PUBLIC ADDRESS AND VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-4/4) SD H1 ELECTRICAL 15-Mar-14 Yes C 17-Mar-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-4/4) SD H1 ELECTRICAL 30-Aug-14 Yes C 30-Aug-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-4/4) SD H1 ELECTRICAL 5-Oct-14 Yes C 12-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H1 (PART-4/4) SD H1 ELECTRICAL 22-Nov-14 Yes C 23-Nov-14 V
PUBLIC ADDRESS AND VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 MASTER PLAN (SEGMENT-H2) SD H2 ELECTRICAL 15-Mar-14 Yes C 17-Mar-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 MASTER PLAN (SEGMENT-H2) SD H2 ELECTRICAL 30-Aug-14 Yes C 30-Aug-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 MASTER PLAN (SEGMENT-H2) SD H2 ELECTRICAL 5-Oct-14 Yes C 12-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 MASTER PLAN (SEGMENT-H2) SD H2 ELECTRICAL 22-Nov-14 Yes C 23-Nov-14 V
PUBLIC ADDRESS AND VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-1/4) SD H2 ELECTRICAL 15-Mar-14 Yes C 17-Mar-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-1/4) SD H2 ELECTRICAL 30-Aug-14 Yes C 30-Aug-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-1/4) SD H2 ELECTRICAL 5-Oct-14 Yes C 12-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-1/4) SD H2 ELECTRICAL 22-Nov-14 Yes C 23-Nov-14 V
PUBLIC ADDRESS AND VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-2/4) SD H2 ELECTRICAL 15-Mar-14 Yes C 17-Mar-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-2/4) SD H2 ELECTRICAL 30-Aug-14 Yes C 30-Aug-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-2/4) SD H2 ELECTRICAL 5-Oct-14 Yes C 12-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-2/4) SD H2 ELECTRICAL 22-Nov-14 Yes C 23-Nov-14 V
PUBLIC ADDRESS AND VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-3/4) SD H2 ELECTRICAL 15-Mar-14 Yes C 17-Mar-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-3/4) SD H2 ELECTRICAL 30-Aug-14 Yes C 30-Aug-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-3/4) SD H2 ELECTRICAL 5-Oct-14 Yes C 12-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-3/4) SD H2 ELECTRICAL 22-Nov-14 Yes C 23-Nov-14 V
PUBLIC ADDRESS AND VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-4/4) SD H2 ELECTRICAL 15-Mar-14 Yes C 17-Mar-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-4/4) SD H2 ELECTRICAL 30-Aug-14 Yes C 30-Aug-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-4/4) SD H2 ELECTRICAL 5-Oct-14 Yes C 12-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H2 (PART-4/4) SD H2 ELECTRICAL 22-Nov-14 Yes C 23-Nov-14 V
Page 49 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
PUBLIC ADDRESS AND VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 MASTER PLAN (SEGMENT-H3) SD H3 ELECTRICAL 15-Mar-14 Yes C 17-Mar-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 MASTER PLAN (SEGMENT-H3) SD H3 ELECTRICAL 30-Aug-14 Yes C 30-Aug-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 MASTER PLAN (SEGMENT-H3) SD H3 ELECTRICAL 5-Oct-14 Yes C 12-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 MASTER PLAN (SEGMENT-H3) SD H3 ELECTRICAL 22-Nov-14 Yes C 23-Nov-14 V
PUBLIC ADDRESS AND VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H3 (PART-1/2) SD H3 ELECTRICAL 15-Mar-14 Yes C 17-Mar-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H3 (PART-1/2) SD H3 ELECTRICAL 30-Aug-14 Yes C 30-Aug-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H3 (PART-1/2) SD H3 ELECTRICAL 5-Oct-14 Yes C 12-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H3 (PART-1/2) SD H3 ELECTRICAL 22-Nov-14 Yes C 23-Nov-14 V
PUBLIC ADDRESS AND VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H3 (PART-2/2) SD H3 ELECTRICAL 15-Mar-14 Yes C 17-Mar-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H3 (PART-2/2) SD H3 ELECTRICAL 30-Aug-14 Yes C 30-Aug-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H3 (PART-2/2) SD H3 ELECTRICAL 5-Oct-14 Yes C 12-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-01 PLAN SEGMENT-H3 (PART-2/2) SD H3 ELECTRICAL 22-Nov-14 Yes C 23-Nov-14 V
TYPICAL INSTALLATION DETAILS FOR FIRE ALARM SYSTEM SD 00 ELECTRICAL 30-Mar-14 Yes B 6-May-14 S
TYPICAL INSTALLATION DETAILS FOR FIRE ALARM SYSTEM SD 00 ELECTRICAL 25-Oct-14 Yes C 23-Oct-14 V
CABLE ROUTING SYSREM LAYOUT FOR LEVEL-S1 (SEGMENT-H1) SD H1 ELECTRICAL 25-Apr-14 Yes C 21-Apr-14 S
CABLE ROUTING SYSREM LAYOUT FOR LEVEL-S1 (SEGMENT-H1) SD H1 ELECTRICAL 28-Jul-14 Yes C 3-Aug-14 S
CABLE ROUTING SYSREM LAYOUT FOR LEVEL-S1 (SEGMENT-H1) SD H1 ELECTRICAL 5-Sep-14 Yes C 6-Sep-14 S
CABLE ROUTING SYSREM LAYOUT FOR LEVEL-S1 (SEGMENT-H1) SD H1 ELECTRICAL 29-Oct-14 Yes B 23-Oct-14 S
CABLE ROUTING SYSREM LAYOUT FOR LEVEL-S1 (SEGMENT-H1) SD H1 ELECTRICAL 7-Jan-15 Yes A 1-Jan-15 V
INFORMATION COMMUNICATION TECHNOGY LEVEL S1- MASTER PLAN (SEGMENT-H1 & H2) SD H0 ELECTRICAL 25-Apr-14 Yes D 20-May-14 S
INFORMATION COMMUNICATION TECHNOGY LEVEL S1- MASTER PLAN (SEGMENT-H1 & H2) SD H0 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION COMMUNICATION TECHNOGY LEVEL S1- MASTER PLAN (SEGMENT-H1 & H2) SD H0 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 S
INFORMATION COMMUNICATION TECHNOGY LEVEL S1- MASTER PLAN (SEGMENT-H1 & H2) SD H0 ELECTRICAL 24-Nov-14 Yes C 24-Nov-14 s
INFORMATION COMMUNICATION TECHNOGY LEVEL S1- MASTER PLAN (SEGMENT-H1 & H2) SD H0 ELECTRICAL 7-Jan-15 OverDue p V
Page 50 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
CABLE ROUTING SYSTEM LAYOUT FOR LEVEL-01 MASTER PLAN (SEGMENT-H1, H2 & H3) SD H0 ELECTRICAL 17-Jun-14 Yes C 21-Jun-14 S
CABLE ROUTING SYSTEM LAYOUT FOR LEVEL-01 MASTER PLAN (SEGMENT-H1, H2 & H3) SD H0 ELECTRICAL 31-Aug-14 Yes A 2-Sep-14 V
CABLE ROUTING SYSTEM LAYOUT FOR LEVEL-01 (SEGMENT-H1) SD H1 ELECTRICAL 17-Jun-14 Yes C 21-Jun-14 S
CABLE ROUTING SYSTEM LAYOUT FOR LEVEL-01 (SEGMENT-H1) SD H1 ELECTRICAL 31-Aug-14 Yes A 2-Sep-14 V
CABLE ROUTING SYSTEM LAYOUT FOR LEVEL-01 (SEGMENT-H2) SD H2 ELECTRICAL 17-Jun-14 Yes C 21-Jun-14 S
CABLE ROUTING SYSTEM LAYOUT FOR LEVEL-01 (SEGMENT-H2) SD H2 ELECTRICAL 31-Aug-14 Yes A 2-Sep-14 V
CABLE ROUTING SYSTEM LAYOUT FOR LEVEL-01 (SEGMENT-H3) SD H3 ELECTRICAL 17-Jun-14 Yes C 21-Jun-14 S
CABLE ROUTING SYSTEM LAYOUT FOR LEVEL-01 (SEGMENT-H3) SD H3 ELECTRICAL 31-Aug-14 Yes A 2-Sep-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 19-Jul-14 Yes C 9-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, SEGMENT H1 (PART-3 OF 4) SD H1 ELECTRICAL 19-Jul-14 Yes C 9-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, SEGMENT H1 (PART-3 OF 4) SD H1 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, SEGMENT H1 (PART-4 OF 4) SD H1 ELECTRICAL 19-Jul-14 Yes C 9-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, SEGMENT H1 (PART-4 OF 4) SD H1 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, MASTER PLAN (SEGMENT-H2) SD H2 ELECTRICAL 19-Jul-14 Yes C 9-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, MASTER PLAN (SEGMENT-H2) SD H2 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, SEGMENT H2 (PART-1 OF 4) SD H2 ELECTRICAL 19-Jul-14 Yes C 9-Aug-14 S
Page 51 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, SEGMENT H2 (PART-1 OF 4) SD H2 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, SEGMENT H2 (PART-2 OF 4) SD H2 ELECTRICAL 19-Jul-14 Yes C 9-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, SEGMENT H2 (PART-2 OF 4) SD H2 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, MASTER PLAN (SEGMENT-H3) SD H3 ELECTRICAL 19-Jul-14 Yes C 9-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, MASTER PLAN (SEGMENT-H3) SD H3 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, SEGMENT-H3 (PART-2 OF 2) SD H3 ELECTRICAL 19-Jul-14 Yes C 9-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL 02, SEGMENT-H3 (PART-2 OF 2) SD H3 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL 04 MASTER PLAN (SEGMENT - H1) SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL 04 MASTER PLAN (SEGMENT - H1) SD H1 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL 04 MASTER PLAN (SEGMENT - H1) SD H1 ELECTRICAL 20-Dec-14 Yes C 20-Dec-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03 MASTER PLAN (SEGMENT - H1) SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03 MASTER PLAN (SEGMENT - H1) SD H1 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03 MASTER PLAN (SEGMENT - H1) SD H1 ELECTRICAL 13-Dec-14 Yes C 13-Dec-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03-(SEGMENT -H1) PART-3 OF 4 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03-(SEGMENT -H1) PART-3 OF 4 SD H1 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03-(SEGMENT -H1) PART-3 OF 4 SD H1 ELECTRICAL 13-Dec-14 Yes C 13-Dec-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03-(SEGMENT -H1) PART-4 OF 4 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03-(SEGMENT -H1) PART-4 OF 4 SD H1 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03-(SEGMENT -H1) PART-4 OF 4 SD H1 ELECTRICAL 13-Dec-14 Yes C 13-Dec-14 V
BUILDING MANAGEMENT SYSTE M FOR LEVEL -03 MASTER PLAN (SEGMENT - H2) SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTE M FOR LEVEL -03 MASTER PLAN (SEGMENT - H2) SD H1 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 S
BUILDING MANAGEMENT SYSTE M FOR LEVEL -03 MASTER PLAN (SEGMENT - H2) SD H1 ELECTRICAL 13-Dec-14 Yes C 13-Dec-14 V
BUILDING MANAGEMENT SYSTE M FOR LEVEL -03 MASTER PLAN (SEGMENT - H2) PART 1 OF 4 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTE M FOR LEVEL -03 MASTER PLAN (SEGMENT - H2) PART 1 OF 4 SD H1 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 S
BUILDING MANAGEMENT SYSTE M FOR LEVEL -03 MASTER PLAN (SEGMENT - H2) PART 1 OF 4 SD H1 ELECTRICAL 13-Dec-14 Yes C 13-Dec-14 V
Page 52 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
BUILDING MANAGEMENT SYSTE M FOR LEVEL -03 MASTER PLAN (SEGMENT - H2) PART 2 OF 4 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTE M FOR LEVEL -03 MASTER PLAN (SEGMENT - H2) PART 2 OF 4 SD H2 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 S
BUILDING MANAGEMENT SYSTE M FOR LEVEL -03 MASTER PLAN (SEGMENT - H2) PART 2 OF 4 SD H2 ELECTRICAL 13-Dec-14 Yes C 13-Dec-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03 MASTER PLAN (SEGMENT -H3) SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03 MASTER PLAN (SEGMENT -H3) SD H3 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03 MASTER PLAN (SEGMENT -H3) SD H3 ELECTRICAL 13-Dec-14 Yes C 13-Dec-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03 (SEGMENT -H3) PART 2 OF 2 SD H1 ELECTRICAL 16-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03 (SEGMENT -H3) PART 2 OF 2 SD H3 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL-03 (SEGMENT -H3) PART 2 OF 2 SD H3 ELECTRICAL 13-Dec-14 Yes C 13-Dec-14 V
LIGHTING SYSTEM LAYOUT LEVEL -04 MASTER PLAN (SEGMENT -H1) SD H1 ELECTRICAL 23-Aug-14 Yes C 27-Aug-14 S
LIGHTING SYSTEM LAYOUT LEVEL -04 MASTER PLAN (SEGMENT -H1) SD H1 ELECTRICAL 24-Nov-14 Yes C 25-Nov-14 S
LIGHTING SYSTEM LAYOUT LEVEL -04 MASTER PLAN (SEGMENT -H1) SD H1 ELECTRICAL 23-Dec-14 Yes A 15-Dec-14 V
LIGHTING SYSTEM LAYOUT LEVEL -04 PLAN (SEGMENT -H1) PART 03 OF 04 SD H1 ELECTRICAL 23-Aug-14 Yes B 27-Aug-14 S
LIGHTING SYSTEM LAYOUT LEVEL -04 PLAN (SEGMENT -H1) PART 03 OF 04 SD H1 ELECTRICAL 23-Dec-14 Yes A 15-Dec-14 V
LIGHTING SYSTEM LAYOUT LEVEL -04 PLAN (SEGMENT -H1) PART 04 OF 04 SD H1 ELECTRICAL 23-Aug-14 Yes C 27-Aug-14 S
LIGHTING SYSTEM LAYOUT LEVEL -04 PLAN (SEGMENT -H1) PART 04 OF 04 SD H1 ELECTRICAL 24-Nov-14 Yes C 25-Nov-14 S
LIGHTING SYSTEM LAYOUT LEVEL -04 PLAN (SEGMENT -H1) PART 04 OF 04 SD H1 ELECTRICAL 23-Dec-14 Yes A 15-Dec-14 V
LIGHTING SYSTEM LAYOUT LEVEL -04 PLAN (SEGMENT -H3) PART 02 OF 02 SD H3 ELECTRICAL 23-Aug-14 Yes B 27-Aug-14 S
LIGHTING SYSTEM LAYOUT LEVEL -04 PLAN (SEGMENT -H3) PART 02 OF 02 SD H3 ELECTRICAL 23-Dec-14 Yes A 15-Dec-14 V
POWER SYSTEM LAYOUT LEVEL -02 (SEGMENT -H1, H2 & H3 ) MASTER PLAN SD H0 ELECTRICAL 23-Aug-14 Yes B 25-Aug-14 S
POWER SYSTEM LAYOUT LEVEL -02 (SEGMENT -H1, H2 & H3 ) MASTER PLAN SD H0 ELECTRICAL 10-Nov-14 Yes C 3-Nov-14 S
POWER SYSTEM LAYOUT LEVEL -02 (SEGMENT -H1, H2 & H3 ) MASTER PLAN SD H0 ELECTRICAL 9-Dec-14 Yes A 2-Dec-14 V
POWER SYSTEM LAYOUT LEVEL -002 (SEGMENT -H1 ) MASTER PLAN SD H1 ELECTRICAL 23-Aug-14 Yes B 25-Aug-14 S
POWER SYSTEM LAYOUT LEVEL -002 (SEGMENT -H1 ) MASTER PLAN SD H1 ELECTRICAL 10-Nov-14 Yes C 3-Nov-14 S
POWER SYSTEM LAYOUT LEVEL -002 (SEGMENT -H1 ) MASTER PLAN SD H1 ELECTRICAL 9-Dec-14 Yes A 2-Dec-14 V
Page 53 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
POWER SYSTEM LAYOUT LEVEL-02 (SEGMENT -H2) MASTER PLAN SD H2 ELECTRICAL 23-Aug-14 Yes B 25-Aug-14 S
POWER SYSTEM LAYOUT LEVEL-02 (SEGMENT -H2) MASTER PLAN SD H2 ELECTRICAL 10-Nov-14 Yes C 3-Nov-14 S
POWER SYSTEM LAYOUT LEVEL-02 (SEGMENT -H2) MASTER PLAN SD H2 ELECTRICAL 9-Dec-14 Yes A 2-Dec-14 V
POWER SYSTEM LAYOUT LEVEL-02 (SEGMENT -H3) MASTER PLAN SD H3 ELECTRICAL 23-Aug-14 Yes B 25-Aug-14 S
POWER SYSTEM LAYOUT LEVEL-02 (SEGMENT -H3) MASTER PLAN SD H3 ELECTRICAL 10-Nov-14 Yes C 3-Nov-14 S
POWER SYSTEM LAYOUT LEVEL-02 (SEGMENT -H3) MASTER PLAN SD H3 ELECTRICAL 9-Dec-14 Yes A 2-Dec-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL -05- MASTER PLAN (SEGMENT-H1 ) SD H1 ELECTRICAL 24-Aug-14 Yes C 21-Aug-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL -05- MASTER PLAN (SEGMENT-H1 ) SD H1 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL -05- MASTER PLAN (SEGMENT-H1 ) SD H1 ELECTRICAL 14-Dec-14 Yes C 29-Dec-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -5 ( MASTER PLAN ) (SEGMENT -H1) SD H1 ELECTRICAL 25-Aug-14 Yes C 28-Aug-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -5 ( MASTER PLAN ) (SEGMENT -H1) SD H1 ELECTRICAL 24-Nov-14 Yes C 25-Nov-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -5 ( MASTER PLAN ) (SEGMENT -H1) SD H1 ELECTRICAL 23-Dec-14 Yes A 15-Dec-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -5 PLAN (SEGMENT -H1) PART 03 OF 04 SD H1 ELECTRICAL 25-Aug-14 Yes B 28-Aug-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -5 PLAN (SEGMENT -H1) PART 03 OF 04 SD H1 ELECTRICAL 24-Nov-14 Yes C 25-Nov-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -5 PLAN (SEGMENT -H1) PART 03 OF 04 SD H1 ELECTRICAL 23-Dec-14 Yes A 15-Dec-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -5 PLAN (SEGMENT -H1) PART 04 OF 04 SD H1 ELECTRICAL 25-Aug-14 Yes C 28-Aug-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -5 PLAN (SEGMENT -H1) PART 04 OF 04 SD H1 ELECTRICAL 24-Nov-14 Yes A 18-Dec-14 V
LIGHTING SYSTEM LAYOUT FOR LEVEL -5 PLAN (SEGMENT -H3) PART 02 OF 02 SD H3 ELECTRICAL 25-Aug-14 Yes B 28-Aug-14 S
LIGHTING SYSTEM LAYOUT FOR LEVEL -5 PLAN (SEGMENT -H3) PART 02 OF 02 SD H3 ELECTRICAL 23-Dec-14 Yes A 15-Dec-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL -06 - MASTER PLAN (SEGMENT- H1) SD H1 ELECTRICAL 25-Aug-14 Yes C 6-Sep-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL -06 - MASTER PLAN (SEGMENT- H1) SD H1 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 S
Page 54 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
BUILDING MANAGEMENT SYSTEM FOR LEVEL -06 - MASTER PLAN (SEGMENT- H1) SD H1 ELECTRICAL 28-Dec-14 Yes C 29-Dec-14 V
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H1) MASTER PLAN SD H1 ELECTRICAL 25-Aug-14 Yes B 30-Aug-14 V
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H1) PART 01 OF 04 SD H1 ELECTRICAL 25-Aug-14 Yes A 30-Aug-14 V
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H1) PART 02 OF 04 SD H1 ELECTRICAL 25-Aug-14 Yes A 30-Aug-14 V
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H1) PART 03 OF 04 SD H1 ELECTRICAL 25-Aug-14 Yes A 30-Aug-14 V
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H1) PART 04 OF 04 SD H1 ELECTRICAL 25-Aug-14 Yes A 30-Aug-14 V
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H2) MASTER PLAN SD H2 ELECTRICAL 25-Aug-14 Yes C 30-Aug-14 S
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H2) MASTER PLAN SD H2 ELECTRICAL 4-Nov-14 Yes C 2-Nov-14 V
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H2) PART 01 OF 04 SD H2 ELECTRICAL 25-Aug-14 Yes C 30-Aug-14 S
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H2) PART 01 OF 04 SD H2 ELECTRICAL 4-Nov-14 Yes C 2-Nov-14 V
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H2) PART 02 OF 04 SD H2 ELECTRICAL 25-Aug-14 Yes A 30-Aug-14 V
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H2) PART 03 OF 04 SD H2 ELECTRICAL 25-Aug-14 Yes B 30-Aug-14 V
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H2) PART 04 OF 04 SD H2 ELECTRICAL 25-Aug-14 Yes A 30-Aug-14 V
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H3) MASTER PLAN SD H3 ELECTRICAL 25-Aug-14 Yes C 30-Aug-14 S
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H3) MASTER PLAN SD H3 ELECTRICAL 4-Nov-14 Yes C 2-Nov-14 V
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H3) PART 01 OF 02 SD H3 ELECTRICAL 25-Aug-14 Yes A 30-Aug-14 V
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H3) PART 02 OF 02 SD H3 ELECTRICAL 25-Aug-14 Yes C 30-Aug-14 S
POWER SYSTEM LAYOUT FOR LEVEL -1 (SEGMENT -H3) PART 02 OF 02 SD H3 ELECTRICAL 4-Nov-14 Yes C 2-Nov-14 V
POWER PLANT HVAC SYASTEM LAYOUT FOR LEVEL -03 (MASTER PLAN ) ( SEGMENT - H1, H2, & H3) SD H0 ELECTRICAL 27-Aug-14 Yes C 1-Sep-14 S
POWER PLANT HVAC SYASTEM LAYOUT FOR LEVEL -03 (MASTER PLAN ) ( SEGMENT - H1, H2, & H3) SD H0 ELECTRICAL 22-Nov-14 Yes A 19-Nov-14 V
POWER PLANT HVAC SYASTEM LAYOUT FOR LEVEL -03 ( SEGMENT -H1) PART -3 SD H1 ELECTRICAL 27-Aug-14 Yes C 1-Sep-14 S
POWER PLANT HVAC SYASTEM LAYOUT FOR LEVEL -03 ( SEGMENT -H1) PART -3 SD H1 ELECTRICAL 22-Nov-14 Yes A 19-Nov-14 V
POWER PLANT HVAC SYASTEM LAYOUT FOR LEVEL -03 ( SEGMENT -H1) PART -4 SD H1 ELECTRICAL 27-Aug-14 Yes C 1-Sep-14 S
POWER PLANT HVAC SYASTEM LAYOUT FOR LEVEL -03 ( SEGMENT -H1) PART -4 SD H1 ELECTRICAL 22-Nov-14 Yes A 19-Nov-14 V
POWER PLANT HVAC SYASTEM LAYOUT FOR LEVEL -03 ( SEGMENT -H 2) PART -1 SD H2 ELECTRICAL 27-Aug-14 Yes C 1-Sep-14 S
Page 55 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
POWER PLANT HVAC SYASTEM LAYOUT FOR LEVEL -03 ( SEGMENT -H 2) PART -1 SD H2 ELECTRICAL 22-Nov-14 Yes A 19-Nov-14 V
POWER PLANT HVAC SYASTEM LAYOUT FOR LEVEL -03 ( SEGMENT -H 2) PART -2 SD H2 ELECTRICAL 27-Aug-14 Yes C 1-Sep-14 S
POWER PLANT HVAC SYASTEM LAYOUT FOR LEVEL -03 ( SEGMENT -H 2) PART -2 SD H2 ELECTRICAL 22-Nov-14 Yes A 19-Nov-14 V
POWER PLANT HVAC SYASTEM LAYOUT FOR LEVEL -03 ( SEGMENT -H 3) PART -2 SD H3 ELECTRICAL 27-Aug-14 Yes C 1-Sep-14 S
POWER PLANT HVAC SYASTEM LAYOUT FOR LEVEL -03 ( SEGMENT -H 3) PART -2 SD H3 ELECTRICAL 22-Nov-14 Yes A 19-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -02 MASTER PLAN SEGMENT -H1 SD H1 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -02 MASTER PLAN SEGMENT -H1 SD H1 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H1 (PART 01 OF 04) SD H1 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H1 (PART 01 OF 04) SD H1 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H1 (PART 02 OF 04) SD H1 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H1 (PART 02 OF 04) SD H1 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H1 (PART 03 OF 04) SD H1 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H1 (PART 03 OF 04) SD H1 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H1 (PART 04 OF 04) SD H1 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H1 (PART 04 OF 04) SD H1 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -02 MASTER PLAN SEGMENT -H2 SD H2 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -02 MASTER PLAN SEGMENT -H2 SD H2 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H2 (PART-01 OF 02) SD H2 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H2 (PART-01 OF 02) SD H2 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H2 (PART-02 OF 02) SD H2 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H2 (PART-02 OF 02) SD H2 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -02 MASTER PLAN SEGMENT -H3 SD H3 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -02 MASTER PLAN SEGMENT -H3 SD H3 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H3 (PART-01 OF 02) SD H3 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H3 (PART-01 OF 02) SD H3 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
Page 56 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H3 (PART-02 OF 02) SD H3 ELECTRICAL 27-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -02 SEGMENT -H3 (PART-02 OF 02) SD H3 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 (SEGMENT -H1) MASTER PLAN SD H1 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 (SEGMENT -H1) MASTER PLAN SD H1 ELECTRICAL 23-Nov-14 Yes B 24-Nov-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H1) PART-1 SD H1 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H1) PART-1 SD H1 ELECTRICAL 23-Nov-14 Yes B 24-Nov-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H1) PART-2 SD H1 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H1) PART-2 SD H1 ELECTRICAL 23-Nov-14 Yes B 24-Nov-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H1) PART-3 SD H1 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H1) PART-3 SD H1 ELECTRICAL 23-Nov-14 Yes B 24-Nov-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H1) PART-4 SD H1 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H1) PART-4 SD H1 ELECTRICAL 23-Nov-14 Yes B 24-Nov-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H2) MASTER PLAN SD H2 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H2) MASTER PLAN SD H2 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H2) PART-1 SD H2 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H2) PART-1 SD H2 ELECTRICAL 23-Nov-14 Yes B 24-Nov-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H2) PART-2 SD H2 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H2) PART-2 SD H2 ELECTRICAL 23-Nov-14 Yes C 24-Nov-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H2) PART-3 SD H2 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H2) PART-3 SD H2 ELECTRICAL 23-Nov-14 Yes B 24-Nov-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H2) PART-4 SD H2 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H2) PART-4 SD H2 ELECTRICAL 23-Nov-14 Yes B 24-Nov-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H3) MASTER PLAN SD H3 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H3) MASTER PLAN SD H3 ELECTRICAL 23-Nov-14 Yes B 24-Nov-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H3) PART-1 SD H3 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
Page 57 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H3) PART-1 SD H3 ELECTRICAL 23-Nov-14 Yes B 24-Nov-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H3) PART-2 SD H3 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-1 PLAN (SEGMENT -H3) PART-2 SD H3 ELECTRICAL 23-Nov-14 Yes B 24-Nov-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-02 (SEGMENT -H1) MASTER PLAN SD H1 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-02 (SEGMENT -H1) MASTER PLAN SD H1 ELECTRICAL 26-Oct-14 Yes C 27-Oct-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-02 PLAN (SEGMENT -H1) PART- 3 OF 4 SD H1 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-02 PLAN (SEGMENT -H1) PART- 3 OF 4 SD H1 ELECTRICAL 26-Oct-14 Yes C 27-Oct-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-02 PLAN (SEGMENT -H1) PART- 4 OF 4 SD H1 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-02 PLAN (SEGMENT -H1) PART- 4 OF 4 SD H1 ELECTRICAL 26-Oct-14 Yes C 27-Oct-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-02 (SEGMENT -H2) MASTER PLAN SD H2 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-02 (SEGMENT -H2) MASTER PLAN SD H2 ELECTRICAL 26-Oct-14 Yes C 27-Oct-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-02 PLAN (SEGMENT -H2) PART 01 OF 04 SD H2 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-02 PLAN (SEGMENT -H2) PART 01 OF 04 SD H2 ELECTRICAL 26-Oct-14 Yes C 27-Oct-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-02 PLAN (SEGMENT -H2) PART 04 OF 04 SD H2 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-02 PLAN (SEGMENT -H2) PART 04 OF 04 SD H2 ELECTRICAL 26-Oct-14 Yes C 27-Oct-14 V
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-02 PLAN (SEGMENT -H3) PART 02 OF 04 SD H3 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
INFORMATION AND COMMUNICATION TECHNOLOGY LEVEL-02 PLAN (SEGMENT -H3) PART 02 OF 04 SD H3 ELECTRICAL 26-Oct-14 Yes C 27-Oct-14 V
LIGHTING SYSTEM LAYOUT MASTER PLAN LEVEL-2 ( SEGMENT - H1, H2 & H3) SD H0 ELECTRICAL 31-Aug-14 Yes C 3-Sep-14 S
LIGHTING SYSTEM LAYOUT MASTER PLAN LEVEL-2 ( SEGMENT - H1, H2 & H3) SD H0 ELECTRICAL 22-Nov-14 Yes A 19-Nov-14 V
LIGHTING SYSTEM LAYOUT LEVEL-2 ( SEGMENT - H1) PART-3 OF 4 SD H1 ELECTRICAL 31-Aug-14 Yes B 3-Sep-14 V
LIGHTING SYSTEM LAYOUT LEVEL-2 ( SEGMENT - H1) PART-4 OF 4 SD H1 ELECTRICAL 31-Aug-14 Yes C 3-Sep-14 S
LIGHTING SYSTEM LAYOUT LEVEL-2 ( SEGMENT - H1) PART-4 OF 4 SD H1 ELECTRICAL 22-Nov-14 Yes A 19-Nov-14 V
LIGHTING SYSTEM LAYOUT LEVEL-2 ( SEGMENT - H2) PART-1 OF 4 SD H2 ELECTRICAL 31-Aug-14 Yes B 3-Sep-14 V
LIGHTING SYSTEM LAYOUT LEVEL-2 ( SEGMENT - H2) PART-2 OF 4 SD H2 ELECTRICAL 31-Aug-14 Yes A 3-Sep-14 V
LIGHTING SYSTEM LAYOUT LEVEL-2 ( SEGMENT - H3) PART-2 OF 2 SD H3 ELECTRICAL 31-Aug-14 Yes C 3-Sep-14 S
Page 58 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
LIGHTING SYSTEM LAYOUT LEVEL-2 ( SEGMENT - H3) PART-2 OF 2 SD H3 ELECTRICAL 22-Nov-14 Yes A 19-Nov-14 V
LIGHTING SYSTEM LAYOUT MASTER LEVEL -2 MEZZANINE (SEGMENT-H1,H3 & H3) SD H0 ELECTRICAL 31-Aug-14 Yes C 3-Sep-14 S
LIGHTING SYSTEM LAYOUT MASTER LEVEL -2 MEZZANINE (SEGMENT-H1,H3 & H3) SD H0 ELECTRICAL 22-Nov-14 Yes A 19-Nov-14 V
POWER SYSTEM LAYOUT FOR LEVEL -03 MASTER PLAN ( SEGMENT - H1 & H3) SD H1 ELECTRICAL 31-Aug-14 Yes C 2-Sep-14 V
POWER SYSTEM LAYOUT FOR LEVEL -03 PLAN ( SEGMENT -H1) PART-3 OF 4 SD H1 ELECTRICAL 31-Aug-14 Yes C 2-Sep-14 V
POWER SYSTEM LAYOUT FOR LEVEL -03 PLAN ( SEGMENT -H1) PART-4 OF 4 SD H1 ELECTRICAL 31-Aug-14 Yes C 2-Sep-14 V
POWER SYSTEM LAYOUT FOR LEVEL -03 PLAN ( SEGMENT -H3) PART-2 OF 2 SD H3 ELECTRICAL 31-Aug-14 Yes C 2-Sep-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -03 MASTER PLAN (SEGMENT - H1 , H2 & H3) SD H0 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -03 MASTER PLAN (SEGMENT - H1 , H2 & H3) SD H0 ELECTRICAL 10-Nov-14 Yes C 12-Nov-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -03 MASTER PLAN (SEGMENT - H1 , H2 & H3) SD H0 ELECTRICAL 3-Dec-14 Yes C 2-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H1 ) PART 3 OF 4 SD H1 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H1 ) PART 3 OF 4 SD H1 ELECTRICAL 10-Nov-14 Yes C 12-Nov-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H1 ) PART 3 OF 4 SD H1 ELECTRICAL 3-Dec-14 Yes C 2-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H1 ) PART 4 OF 4 SD H1 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H1 ) PART 4 OF 4 SD H1 ELECTRICAL 10-Nov-14 Yes C 12-Nov-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H1 ) PART 4 OF 4 SD H1 ELECTRICAL 3-Dec-14 Yes C 2-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H2 ) PART 1 OF 4 SD H2 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H2 ) PART 1 OF 4 SD H2 ELECTRICAL 10-Nov-14 Yes C 12-Nov-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H2 ) PART 1 OF 4 SD H2 ELECTRICAL 3-Dec-14 Yes C 2-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H2 ) PART 2 OF 4 SD H2 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H2 ) PART 2 OF 4 SD H2 ELECTRICAL 10-Nov-14 Yes C 12-Nov-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H2 ) PART 2 OF 4 SD H2 ELECTRICAL 3-Dec-14 Yes C 2-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H3 ) PART 2 OF 2 SD H3 ELECTRICAL 31-Aug-14 Yes C 30-Aug-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H3 ) PART 2 OF 2 SD H3 ELECTRICAL 10-Nov-14 Yes C 12-Nov-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL -03 (SEGMENT - H3 ) PART 2 OF 2 SD H3 ELECTRICAL 3-Dec-14 Yes C 2-Dec-14 V
Page 59 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
LIGHTING SYSTEM LAYOUT LEVEL-03 MASTER PLAN (SEGMENT -H1 & H3) SD H0 ELECTRICAL 31-Aug-14 Yes C 6-Sep-14 S
LIGHTING SYSTEM LAYOUT LEVEL-03 MASTER PLAN (SEGMENT -H1 & H3) SD H0 ELECTRICAL 22-Nov-14 Yes A 19-Nov-14 V
LIGHTING SYSTEM LAYOUT LEVEL-03 PLAN (SEGMENT -H1) PART- 3 OF 4 SD H1 ELECTRICAL 31-Aug-14 Yes C 6-Sep-14 S
LIGHTING SYSTEM LAYOUT LEVEL-03 PLAN (SEGMENT -H1) PART- 3 OF 4 SD H1 ELECTRICAL 22-Nov-14 Yes A 19-Nov-14 V
LIGHTING SYSTEM LAYOUT LEVEL-03 PLAN (SEGMENT -H1) PART- 4 OF 4 SD H1 ELECTRICAL 31-Aug-14 Yes C 6-Sep-14 S
LIGHTING SYSTEM LAYOUT LEVEL-03 PLAN (SEGMENT -H1) PART- 4 OF 4 SD H1 ELECTRICAL 22-Nov-14 Yes A 19-Nov-14 V
LIGHTING SYSTEM LAYOUT LEVEL-03 PLAN (SEGMENT -H3 ) PART- 2 OF 2 SD H3 ELECTRICAL 31-Aug-14 Yes C 6-Sep-14 S
LIGHTING SYSTEM LAYOUT LEVEL-03 PLAN (SEGMENT -H3 ) PART- 2 OF 2 SD H3 ELECTRICAL 22-Nov-14 Yes A 19-Nov-14 V
BUILDING MANAGEMENT SYSTEM FOR LEVEL 07- MASTER PLAN (SEGMENT -H1|) SD H1 ELECTRICAL 2-Sep-14 Yes C 3-Sep-14 S
BUILDING MANAGEMENT SYSTEM FOR LEVEL 07- MASTER PLAN (SEGMENT -H1|) SD H1 ELECTRICAL 24-Nov-14 Yes C 24-Nov-14 V
BUILDING MANGEMENT SYSTEM FOR LEVEL -08- MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 2-Sep-14 Yes C 3-Sep-14 S
BUILDING MANGEMENT SYSTEM FOR LEVEL -08- MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 24-Nov-14 Yes C 24-Nov-14 V
POWER SYSTEM LAYOUT LEVEL -07 (SEGMENT -H1) SD H0 ELECTRICAL 6-Sep-14 Yes C 6-Sep-14 S
POWER SYSTEM LAYOUT LEVEL -07 (SEGMENT -H1) SD H0 ELECTRICAL 24-Nov-14 Yes A 22-Nov-14 V
LIGHTING SYSTEM LAYOUT LEVEL-07 PLAN (SEGMENT-H1) SD H1 ELECTRICAL 6-Sep-14 Yes C 6-Sep-14 S
LIGHTING SYSTEM LAYOUT LEVEL-07 PLAN (SEGMENT-H1) SD H1 ELECTRICAL 24-Nov-14 Yes C 24-Nov-14 V
LIGHTING SYSTEM LAYOUT LEVEL-08 PLAN (SEGMENT-H1) SD H1 ELECTRICAL 6-Sep-14 Yes C 6-Sep-14 S
LIGHTING SYSTEM LAYOUT LEVEL-08 PLAN (SEGMENT-H1) SD H1 ELECTRICAL 24-Nov-14 Yes C 24-Nov-14 V
POWER FOR HVAC SYSTEM LAYOUT LEVEL-04 (MASTER PLAN ) SEGMENT - H1, H2, & H3) SD H0 ELECTRICAL 6-Sep-14 Yes C 6-Sep-14 S
POWER FOR HVAC SYSTEM LAYOUT LEVEL-04 (MASTER PLAN ) SEGMENT - H1, H2, & H3) SD H0 ELECTRICAL 24-Nov-14 Yes A 22-Nov-14 V
Page 60 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
POWER FOR HVAC SYSTEM LAYOUT LEVEL-04 PLAN SEGMENT - H1 -PART 3 OF 4 SD H1 ELECTRICAL 6-Sep-14 Yes C 6-Sep-14 S
POWER FOR HVAC SYSTEM LAYOUT LEVEL-04 PLAN SEGMENT - H1 -PART 3 OF 4 SD H1 ELECTRICAL 24-Nov-14 Yes A 22-Nov-14 V
POWER FOR HVAC SYSTEM LAYOUT LEVEL-04 PLAN SEGMENT - H1 -PART 4 OF 4 SD H1 ELECTRICAL 6-Sep-14 Yes C 6-Sep-14 S
POWER FOR HVAC SYSTEM LAYOUT LEVEL-04 PLAN SEGMENT - H1 -PART 4 OF 4 SD H1 ELECTRICAL 24-Nov-14 Yes A 22-Nov-14 V
POWER FOR HVAC SYSTEM LAYOUT LEVEL-04 PLAN SEGMENT - H3 -PART 2 OF 2 SD H3 ELECTRICAL 6-Sep-14 Yes C 6-Sep-14 S
POWER FOR HVAC SYSTEM LAYOUT LEVEL-04 PLAN SEGMENT - H3 -PART 2 OF 2 SD H3 ELECTRICAL 24-Nov-14 Yes A 22-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-04 MASTER PLAN ( SEGMENT- H1,H2 & H3) SD H0 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-04 MASTER PLAN ( SEGMENT- H1,H2 & H3) SD H0 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-04 PLAN ( SEGMENT- H1) PART-3 OF 4 SD H1 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-04 PLAN ( SEGMENT- H1) PART-3 OF 4 SD H1 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-04 PLAN ( SEGMENT- H1) PART-4 OF 4 SD H1 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-04 PLAN ( SEGMENT- H1) PART-4 OF 4 SD H1 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-04 PLAN ( SEGMENT- H2) PART-1 OF 4 SD H2 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-04 PLAN ( SEGMENT- H2) PART-1 OF 4 SD H2 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-04 PLAN ( SEGMENT- H2) PART-2 OF 4 SD H2 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-04 PLAN ( SEGMENT- H2) PART-2 OF 4 SD H2 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-04 PLAN ( SEGMENT- H3) PART-2 OF 2 SD H3 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-04 PLAN ( SEGMENT- H3) PART-2 OF 2 SD H3 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 MASTER PLAN (SEGMENT - H1, H2 & H3) SD H0 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 MASTER PLAN (SEGMENT - H1, H2 & H3) SD H0 ELECTRICAL 26-Oct-14 Yes C 23-Oct-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 MASTER PLAN (SEGMENT - H1, H2 & H3) SD H0 ELECTRICAL 25-Nov-14 Yes C 23-Nov-14 V
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H1) (PART 4 OF 4) SD H1 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H1) (PART 4 OF 4) SD H1 ELECTRICAL 26-Oct-14 Yes C 23-Oct-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H1) (PART 4 OF 4) SD H1 ELECTRICAL 25-Nov-14 Yes C 23-Nov-14 V
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H2) (PART 1 OF 4) SD H2 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
Page 61 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H2) (PART 1 OF 4) SD H2 ELECTRICAL 26-Oct-14 Yes C 23-Oct-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H2) (PART 1 OF 4) SD H2 ELECTRICAL 25-Nov-14 Yes C 23-Nov-14 V
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H2) (PART 2 OF 4) SD H2 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H2) (PART 2 OF 4) SD H2 ELECTRICAL 26-Oct-14 Yes C 23-Oct-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H2) (PART 2 OF 4) SD H2 ELECTRICAL 25-Nov-14 Yes C 23-Nov-14 V
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H2) (PART 4 OF 4) SD H2 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H2) (PART 4 OF 4) SD H2 ELECTRICAL 26-Oct-14 Yes C 23-Oct-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H2) (PART 4 OF 4) SD H2 ELECTRICAL 25-Nov-14 Yes C 23-Nov-14 V
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H3 ) (PART 2 OF 2) SD H3 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H3 ) (PART 2 OF 2) SD H3 ELECTRICAL 26-Oct-14 Yes C 23-Oct-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -02 PLAN (SEGMENT - H3 ) (PART 2 OF 2) SD H3 ELECTRICAL 25-Nov-14 Yes C 23-Nov-14 V
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -03 MASTER PLAN (SEGMENT - H1, H2 & H3) SD H0 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -03 MASTER PLAN (SEGMENT - H1, H2 & H3) SD H0 ELECTRICAL 24-Nov-14 Yes C 23-Nov-14 V
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -03 (SEGMENT - H1) PART 3 OF 4 SD H1 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -03 (SEGMENT - H1) PART 3 OF 4 SD H1 ELECTRICAL 24-Nov-14 Yes C 23-Nov-14 V
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -03 (SEGMENT - H1) PART 4 OF 4 SD H1 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -03 (SEGMENT - H1) PART 4 OF 4 SD H1 ELECTRICAL 24-Nov-14 Yes C 23-Nov-14 V
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -03 (SEGMENT - H2) PART 1 OF 4 SD H2 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -03 (SEGMENT - H2) PART 1 OF 4 SD H2 ELECTRICAL 24-Nov-14 Yes C 23-Nov-14 V
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -03 (SEGMENT - H2) PART 2 OF 4 SD H2 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -03 (SEGMENT - H2) PART 2 OF 4 SD H2 ELECTRICAL 24-Nov-14 Yes C 23-Nov-14 V
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -03 (SEGMENT - H3) PART 2 OF 2 SD H3 ELECTRICAL 8-Sep-14 Yes C 10-Sep-14 S
VOICE EVACAUTION SYSTEM LAYOUT LEVEL -03 (SEGMENT - H3) PART 2 OF 2 SD H3 ELECTRICAL 24-Nov-14 Yes C 23-Nov-14 V
LIGHTING SYSTEM LAYOUT LEVEL - 06 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 8-Sep-14 Yes C 9-Sep-14 S
LIGHTING SYSTEM LAYOUT LEVEL - 06 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 24-Nov-14 Yes A 22-Nov-14 V
Page 62 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
LIGHTING SYSTEM LAYOUT LEVEL - 06 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 8-Sep-14 Yes C 9-Sep-14 S
LIGHTING SYSTEM LAYOUT LEVEL - 06 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 24-Nov-14 Yes A 22-Nov-14 V
LIGHTING SYSTEM LAYOUT LEVEL - 06 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 8-Sep-14 Yes C 9-Sep-14 S
LIGHTING SYSTEM LAYOUT LEVEL - 06 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 24-Nov-14 Yes A 22-Nov-14 V
CABLE ROUTING SYSTEM FOR LEVEL-03 (MASTER PLAN) SD H0 ELECTRICAL 13-Sep-14 Yes D 2-Sep-14 S
CABLE ROUTING SYSTEM FOR LEVEL-03 (MASTER PLAN) SD H0 ELECTRICAL 24-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-2M SEGMENT-H3 & H2 MASTER PLAN SD H0 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-2M SEGMENT-H3 & H2 MASTER PLAN SD H0 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-2M SEGMENT-H3 PART-2 H3 SD H3 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-2M SEGMENT-H3 PART-2 H3 SD H3 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-2M SEGMENT-H2 PART-1 H2 SD H2 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-2M SEGMENT-H2 PART-1 H2 SD H2 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-04 PLAN (SEGMENT-H1, H2 & H3) (MASTER PLAN) SD H0 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-04 PLAN (SEGMENT-H1, H2 & H3) (MASTER PLAN) SD H0 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-04 PLAN (SEGMENT-H1) (PART-3 OF 4) SD H1 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-04 PLAN (SEGMENT-H1) (PART-3 OF 4) SD H1 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-04 PLAN (SEGMENT-H1) (PART-4 OF 4) SD H1 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-04 PLAN (SEGMENT-H1) (PART-4 OF 4) SD H1 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-04 PLAN (SEGMENT-H2) (PART-1 OF 4) SD H2 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-04 PLAN (SEGMENT-H2) (PART-1 OF 4) SD H2 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-04 PLAN (SEGMENT-H2) (PART-2 OF 4) SD H2 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-04 PLAN (SEGMENT-H2) (PART-2 OF 4) SD H2 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-04 PLAN (SEGMENT-H3) (PART-2 OF 2) SD H3 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
Page 63 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
VOICE EVACUATION SYSTEM LAYOUT LEVEL-04 PLAN (SEGMENT-H3) (PART-2 OF 2) SD H3 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-06 PLAN (SEGMENT-H1,H2 & H3) (MASTER PLAN) SD H0 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-06 PLAN (SEGMENT-H1,H2 & H3) (MASTER PLAN) SD H0 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-06 PLAN (SEGMENT-H1) (PART-3 OF 4) SD H1 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-06 PLAN (SEGMENT-H1) (PART-3 OF 4) SD H1 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-06 PLAN (SEGMENT-H1) (PART-4 OF 4) SD H1 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-06 PLAN (SEGMENT-H1) (PART-4 OF 4) SD H1 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-06 PLAN (SEGMENT-H2) (PART-1 OF 4) SD H2 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-06 PLAN (SEGMENT-H2) (PART-1 OF 4) SD H2 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-06 PLAN (SEGMENT-H2) (PART-2 OF 4) SD H2 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-06 PLAN (SEGMENT-H2) (PART-2 OF 4) SD H2 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-06 PLAN (SEGMENT-H3) (PART-2 OF 2) SD H3 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-06 PLAN (SEGMENT-H3) (PART-2 OF 2) SD H3 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-05 PLAN (SEGMENT-H1,H2 & H3) (MASTER PLAN) SD H0 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-05 PLAN (SEGMENT-H1,H2 & H3) (MASTER PLAN) SD H0 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-05 PLAN (SEGMENT-H1) (PART-3 OF 4) SD H1 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-05 PLAN (SEGMENT-H1) (PART-3 OF 4) SD H1 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-05 PLAN (SEGMENT-H1) (PART-4 OF 4) SD H1 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-05 PLAN (SEGMENT-H1) (PART-4 OF 4) SD H1 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-05 PLAN (SEGMENT-H2) (PART-1 OF 4) SD H2 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-05 PLAN (SEGMENT-H2) (PART-1 OF 4) SD H2 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-05 PLAN (SEGMENT-H2) (PART-2 OF 4) SD H2 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-05 PLAN (SEGMENT-H2) (PART-2 OF 4) SD H2 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
VOICE EVACUATION SYSTEM LAYOUT LEVEL-05 PLAN (SEGMENT-H3) (PART-2 OF 2) SD H3 ELECTRICAL 14-Sep-14 Yes C 13-Sep-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL-05 PLAN (SEGMENT-H3) (PART-2 OF 2) SD H3 ELECTRICAL 23-Nov-14 Yes C 2-Dec-14 V
Page 64 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
POWER SYSTEM LAYOUT LEVEL-4 (MASTER PLAN) (SEGMENT-H1 & H3) SD H0 ELECTRICAL 15-Sep-14 Yes C 11-Sep-14 S
POWER SYSTEM LAYOUT LEVEL-4 (MASTER PLAN) (SEGMENT-H1 & H3) SD H0 ELECTRICAL 24-Nov-14 Yes A 24-Nov-14 V
POWER SYSTEM LAYOUT LEVEL-4 PLAN (SEGMENT-H1) (PART-3 OF 4) SD H1 ELECTRICAL 15-Sep-14 Yes C 11-Sep-14 S
POWER SYSTEM LAYOUT LEVEL-4 PLAN (SEGMENT-H1) (PART-3 OF 4) SD H1 ELECTRICAL 24-Nov-14 Yes A 24-Nov-14 V
POWER SYSTEM LAYOUT LEVEL-4 PLAN (SEGMENT-H1) (PART-4 OF 4) SD H1 ELECTRICAL 15-Sep-14 Yes C 11-Sep-14 S
POWER SYSTEM LAYOUT LEVEL-4 PLAN (SEGMENT-H1) (PART-4 OF 4) SD H1 ELECTRICAL 24-Nov-14 Yes A 24-Nov-14 V
POWER SYSTEM LAYOUT LEVEL-4 PLAN (SEGMENT-H3) (PART-2 OF 2) SD H3 ELECTRICAL 15-Sep-14 Yes C 11-Sep-14 S
POWER SYSTEM LAYOUT LEVEL-4 PLAN (SEGMENT-H3) (PART-2 OF 2) SD H3 ELECTRICAL 24-Nov-14 Yes A 24-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-05 MASTER PLAN (SEGMNET- H1, H2 & H3) SD H0 ELECTRICAL 19-Sep-14 Yes C 20-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-05 MASTER PLAN (SEGMNET- H1, H2 & H3) SD H0 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-05 PLAN (SEGMNET- H1) PART- 3 OF 4 SD H1 ELECTRICAL 19-Sep-14 Yes C 20-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-05 PLAN (SEGMNET- H1) PART- 3 OF 4 SD H1 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-05 PLAN (SEGMNET- H1) PART- 4 OF 4 SD H1 ELECTRICAL 19-Sep-14 Yes C 20-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-05 PLAN (SEGMNET- H1) PART- 4 OF 4 SD H1 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-05 PLAN (SEGMNET- H2) PART- 1 OF 4 SD H2 ELECTRICAL 19-Sep-14 Yes C 20-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-05 PLAN (SEGMNET- H2) PART- 1 OF 4 SD H2 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-05 PLAN (SEGMNET- H2) PART- 2 OF 4 SD H2 ELECTRICAL 19-Sep-14 Yes C 20-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-05 PLAN (SEGMNET- H2) PART- 2 OF 4 SD H2 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-05 PLAN (SEGMNET- H3) PART- 2 OF 2 SD H3 ELECTRICAL 19-Sep-14 Yes C 20-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-05 PLAN (SEGMNET- H3) PART- 2 OF 2 SD H3 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
POWER SYSTEM LAYOUT FOR LEVEL-05 MASGTER PLAN ( SEGMENT -H1 & H3) SD H0 ELECTRICAL 22-Sep-14 Yes C 18-Sep-14 S
POWER SYSTEM LAYOUT FOR LEVEL-05 MASGTER PLAN ( SEGMENT -H1 & H3) SD H0 ELECTRICAL 24-Nov-14 Yes A 24-Nov-14 V
POWER SYSTEM LAYOUT FOR LEVEL -05 PLAN ( SEGMENT -G1) PART 3 OF 4 SD H1 ELECTRICAL 22-Sep-14 Yes B 18-Sep-14 V
POWER SYSTEM LAYOUT FOR LEVEL -05 PLAN ( SEGMENT -G1) PART 4 OF 4 SD H1 ELECTRICAL 22-Sep-14 Yes B 18-Sep-14 V
POWER SYSTEM LAYOUT FOR LEVEL-05 PLAN (SEGMENT - H3) PART 2 OF 2 SD H3 ELECTRICAL 22-Sep-14 Yes C 18-Sep-14 S
Page 65 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
POWER SYSTEM LAYOUT FOR LEVEL-05 PLAN (SEGMENT - H3) PART 2 OF 2 SD H3 ELECTRICAL 24-Nov-14 Yes A 24-Nov-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-06 MASTER PLAN ( SEGMENT- H1 H2 & H3) SD H0 ELECTRICAL 22-Sep-14 Yes C 24-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-06 MASTER PLAN ( SEGMENT- H1 H2 & H3) SD H0 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-06 PLAN ( SEGMENT- H1) PLAN-3 OF 4 SD H1 ELECTRICAL 22-Sep-14 Yes C 24-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-06 PLAN ( SEGMENT- H1) PLAN-3 OF 4 SD H1 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-06 PLAN ( SEGMENT- H1) PLAN- 4 OF 4 SD H1 ELECTRICAL 22-Sep-14 Yes C 24-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-06 PLAN ( SEGMENT- H1) PLAN- 4 OF 4 SD H1 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-06 PLAN ( SEGMENT- H2) PLAN- 1 OF 4 SD H2 ELECTRICAL 22-Sep-14 Yes C 24-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-06 PLAN ( SEGMENT- H2) PLAN- 1 OF 4 SD H2 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-06 PLAN ( SEGMENT- H2) PLAN- 2 OF 4 SD H2 ELECTRICAL 22-Sep-14 Yes C 24-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-06 PLAN ( SEGMENT- H2) PLAN- 2 OF 4 SD H2 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
FIRE ALARM SYSTEM LAYOUT LEVEL-06 PLAN ( SEGMENT- H3) PLAN- 2 OF 2 SD H3 ELECTRICAL 22-Sep-14 Yes C 24-Sep-14 S
FIRE ALARM SYSTEM LAYOUT LEVEL-06 PLAN ( SEGMENT- H3) PLAN- 2 OF 2 SD H3 ELECTRICAL 22-Nov-14 Yes C 1-Dec-14 V
POWER FOR HVAC SYSTEM LAYOUT FOR LEVEL-07 PLAN (SEGMENT- H1) SD H1 ELECTRICAL 22-Sep-14 Yes C 24-Sep-14 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVEL-07 PLAN (SEGMENT- H1) SD H1 ELECTRICAL 24-Nov-14 Yes C 24-Nov-14 V
POWER FOR HVAC SYSTEM LAYOUT FOR LEVEL-08 PLAN ( SEGMENT-H1) SD H1 ELECTRICAL 22-Sep-14 Yes C 24-Sep-14 S
POWER FOR HVAC SYSTEM LAYOUT FOR LEVEL-08 PLAN ( SEGMENT-H1) SD H1 ELECTRICAL 24-Nov-14 Yes A 24-Nov-14 V
POWER FOR HVAC SYSTEM LAYOUT LEVEL-5 (MASTER PLAN) (SEGMENT-H1, H2, H3) SD H0 ELECTRICAL 3-Oct-14 Yes A 27-Sep-14 V
POWER FOR HVAC SYSTEM LAYOUT LEVEL-5 PLAN (SEGMENT-H1) (PART-3 OF 4) SD H1 ELECTRICAL 3-Oct-14 Yes A 27-Sep-14 V
POWER FOR HVAC SYSTEM LAYOUT LEVEL-5 PLAN (SEGMENT-H1) (PART-4 OF 4) SD H1 ELECTRICAL 3-Oct-14 Yes A 27-Sep-14 V
POWER FOR HVAC SYSTEM LAYOUT LEVEL-5 (SEGMENT-H3) (PART-2 OF 2) SD H3 ELECTRICAL 3-Oct-14 Yes A 27-Sep-14 V
POWER FOR HVAC SYSTEM LAYOUT LEVEL-6 (MASTER PLAN) (SEGMENT-H1, H2, H3) SD H0 ELECTRICAL 3-Oct-14 Yes B 29-Sep-14 V
POWER FOR HVAC SYSTEM LAYOUT LEVEL-6 (SEGMENT-H1) PART-3 OF 4 SD H1 ELECTRICAL 3-Oct-14 Yes B 29-Sep-14 V
POWER FOR HVAC SYSTEM LAYOUT LEVEL-6 (SEGMENT-H1) PART-4 OF 4 SD H1 ELECTRICAL 3-Oct-14 Yes B 29-Sep-14 V
POWER FOR HVAC SYSTEM LAYOUT LEVEL-6 PLAN (SEGMENT-H3) PART-2 OF 2 SD H3 ELECTRICAL 3-Oct-14 Yes B 29-Sep-14 V
Page 66 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
VOICE EVACUATION SYSTEM SINGLE LINE DIAGRAM FOR LEVEL -01 SD H0 ELECTRICAL 12-Oct-14 Yes C 16-Oct-14 V
VOICE EVACUATION SYSTEM LAYOUT MASTER PLAN LEVEL - S1 SEGMENT-H1 & H2 SD H0 ELECTRICAL 25-Oct-14 Yes C 23-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT MASTER PLAN LEVEL - S1 SEGMENT-H1 & H2 SD H0 ELECTRICAL 26-Nov-14 Yes B 24-Nov-14 S
VOICE EVACUATION SYSTEM LAYOUT MASTER PLAN LEVEL - S1 SEGMENT-H1 & H2 SD H0 ELECTRICAL 7-Jan-15 OverDue P V
VOICE EVACUATION SYSTEM LAYOUT LEVEL - S1 SEGMENT-H1 SD H1 ELECTRICAL 25-Oct-14 Yes C 23-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL - S1 SEGMENT-H1 SD H1 ELECTRICAL 26-Nov-14 Yes B 24-Nov-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL - S1 SEGMENT-H2 SD H2 ELECTRICAL 25-Oct-14 Yes C 23-Oct-14 S
VOICE EVACUATION SYSTEM LAYOUT LEVEL - S1 SEGMENT-H2 SD H2 ELECTRICAL 26-Nov-14 Yes B 24-Nov-14 V
INFORMATION & COMMUNICATION TECHNOLOGY LEVEL-02 PLAN (SEGMENT-H3) PART-1 OF 2 SD H3 ELECTRICAL 26-Oct-14 Yes C 27-Oct-14 V
INFORMATION & COMMUNICATION TECHNOLOGY LEVEL-02 PLAN (SEGMENT-H3) MASTER PLAN SD H3 ELECTRICAL 26-Oct-14 Yes C 27-Oct-14 V
INFORMATION & COMMUNICATION TECHNOLOGY LEVEL-02 PLAN (SEGMENT-H2) PART-2 OF 4 SD H2 ELECTRICAL 26-Oct-14 Yes C 27-Oct-14 V
INFORMATION & COMMUNICATION TECHNOLOGY LEVEL-02 MEZZ. (SEGMENT-H2 & H3) MASTER PLAN SD H0 ELECTRICAL 26-Oct-14 Yes C 27-Oct-14 V
INFORMATION & COMMUNICATION TECHNOLOGY LEVEL-02 MEZZ. (SEGMENT-H2) PART-1 OF 4 SD H2 ELECTRICAL 26-Oct-14 Yes C 27-Oct-14 V
INFORMATION & COMMUNICATION TECHNOLOGY LEVEL-02 MEZZ. (SEGMENT-H3) PART-2 OF 2 SD H3 ELECTRICAL 26-Oct-14 Yes C 27-Oct-14 V
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H1) MASTER PLAN SD H1 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 S
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H1) MASTER PLAN SD H1 ELECTRICAL 29-Nov-14 Yes A 27-Nov-14 V
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H1) PART 1 OF 4 SD H1 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 S
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H1) PART 1 OF 4 SD H1 ELECTRICAL 29-Nov-14 Yes A 27-Nov-14 V
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H1) PART 2 OF 4 SD H1 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 S
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H1) PART 2 OF 4 SD H1 ELECTRICAL 29-Nov-14 Yes A 27-Nov-14 V
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H1) PART 3 OF 4 SD H1 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 S
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H1) PART 3 OF 4 SD H1 ELECTRICAL 29-Nov-14 Yes A 27-Nov-14 V
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H1) PART 4 OF 4 SD H1 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 S
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H1) PART 4 OF 4 SD H1 ELECTRICAL 29-Nov-14 Yes A 27-Nov-14 V
Page 67 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H2) MASTER PLAN SD H2 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 S
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H2) MASTER PLAN SD H2 ELECTRICAL 29-Nov-14 Yes A 27-Nov-14 V
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H2) PART 1 OF 4 SD H2 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 S
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H2) PART 1 OF 4 SD H2 ELECTRICAL 29-Nov-14 Yes A 27-Nov-14 V
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H2) PART 2 OF 4 SD H2 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 S
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H2) PART 2 OF 4 SD H2 ELECTRICAL 29-Nov-14 Yes A 27-Nov-14 V
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H2) PART 3 OF 4 SD H2 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 S
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H2) PART 3 OF 4 SD H2 ELECTRICAL 29-Nov-14 Yes A 27-Nov-14 V
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H2) PART 4 OF 4 SD H2 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 S
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H2) PART 4 OF 4 SD H2 ELECTRICAL 29-Nov-14 Yes A 27-Nov-14 V
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H3) MASTER PLAN SD H3 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 S
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H3) MASTER PLAN SD H3 ELECTRICAL 29-Nov-14 Yes A 27-Nov-14 V
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H3) PART 1 OF 2 SD H3 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 S
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H3) PART 1 OF 2 SD H3 ELECTRICAL 29-Nov-14 Yes A 27-Nov-14 V
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H3) PART 2 OF 2 SD H3 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 S
POWER FOR HVAC SYTEM LAYOUT LEVEL - 1 (SEGMENT - H3) PART 2 OF 2 SD H3 ELECTRICAL 29-Nov-14 Yes A 27-Nov-14 V
LEVEL - 01 DATA ROOM # TR - 836 L.C. EQUIPMENT LAYOUT & DETAILS SD 00 ELECTRICAL 29-Oct-14 Yes C 28-Oct-14 V
LEVEL - 01 DATA ROOM # TR - 2638 L.C. EQUIPMENT LAYOUT & DETAILS SD 00 ELECTRICAL 29-Oct-14 Yes C 28-Oct-14 V
LEVEL - 01 DATA ROOM # TR - 2617 L.C. EQUIPMENT LAYOUT & DETAILS SD 00 ELECTRICAL 29-Oct-14 Yes C 28-Oct-14 V
LEVEL - 02 DATA ROOM # TR - 2487 L.C. EQUIPMENT LAYOUT & DETAILS SD 00 ELECTRICAL 29-Oct-14 Yes C 28-Oct-14 V
LEVEL - 03 DATA ROOM # TR - 1071 L.C. EQUIPMENT LAYOUT & DETAILS SD 00 ELECTRICAL 29-Oct-14 Yes C 28-Oct-14 V
POWER SYSTEM LAYOUT LEVEL - 6 MASTER PLAN (SEGMENT - H1 & H3) SD H0 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 V
POWER SYSTEM LAYOUT LEVEL - 6 MASTER PLAN (SEGMENT - H1 & H3) SD H0 ELECTRICAL 6-Dec-14 Yes A 2-Dec-14 V
POWER SYSTEM LAYOUT LEVEL - 6 PLAN (SEGMENT - H1) PART 3 OF 4 SD H1 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 V
POWER SYSTEM LAYOUT LEVEL - 6 PLAN (SEGMENT - H1) PART 3 OF 4 SD H1 ELECTRICAL 6-Dec-14 Yes A 2-Dec-14 V
Page 68 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
POWER SYSTEM LAYOUT LEVEL - 6 PLAN (SEGMENT - H1) PART 4 OF 4 SD H1 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 V
POWER SYSTEM LAYOUT LEVEL - 6 PLAN (SEGMENT - H1) PART 4 OF 4 SD H1 ELECTRICAL 6-Dec-14 Yes A 2-Dec-14 V
POWER SYSTEM LAYOUT LEVEL - 6 PLAN (SEGMENT - H3) PART 2 OF 2 SD H3 ELECTRICAL 29-Oct-14 Yes C 25-Oct-14 V
POWER SYSTEM LAYOUT LEVEL - 6 PLAN (SEGMENT - H3) PART 2 OF 2 SD H3 ELECTRICAL 6-Dec-14 Yes A 2-Dec-14 V
Page 69 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
FRE ALARM SYSTEM SINGLE LINE DIAGRAM (PART-3) SD H0 ELECTRICAL 10-Nov-14 Yes C 12-Nov-14 V
CABLE ROUTING SYSTEM LAYOUT FOR LEVEL - 02 (MASTER PALN - SEGMENT 0 H1, H2 & H3) SD H0 ELECTRICAL 22-Nov-14 Yes C 17-Nov-14 V
CABLE ROUTING SYSTEM LAYOUT FOR LEVEL - 02 SEGMENT - H1 SD H1 ELECTRICAL 22-Nov-14 Yes C 17-Nov-14 V
CABLE ROUTING SYSTEM LAYOUT FOR LEVEL - 02 SEGMENT - H2 SD H2 ELECTRICAL 22-Nov-14 Yes C 17-Nov-14 V
CABLE ROUTING SYSTEM LAYOUT FOR LEVEL - 02 SEGMENT - H3 SD H3 ELECTRICAL 22-Nov-14 Yes C 17-Nov-14 V
SUBSTATION CABLE ROUTING LAYOUT (SS-TR-12A & SS-TR-12B) (UNDER RAISED FLOOR) LEVEL-02,
SD H2 ELECTRICAL 22-Nov-14 Yes C 17-Nov-14 V
SEGMENT - H2
SUBSTATION EQUIPMENT & CABLE ROUTING LAYOUT (SS-TR-12A & SS-TR-12B) (HIGH LEVEL) LEVEL-02
SD H2 ELECTRICAL 22-Nov-14 Yes C 17-Nov-14 V
SEGMENT-H2.
SUBSTATION CABLE ROUTING LAYOUT (SS-TR-12a & SS-TR-12B) LEVEL-02 MEZZ. FLOOR SEGMENT-H2 SD H2 ELECTRICAL 22-Nov-14 Yes C 17-Nov-14 V
FIRE ALARM SYSTEM SINGLE LINE DIAGRAM (LEVEL- L02 & L2M) SD H0 ELECTRICAL 22-Nov-14 Yes C 25-Nov-14 V
INFORMATION COMMUNICATION TECHNOLOGY SYSTEM FOR LEVEL-06 - MASTER PLAN (SEGMENT-H1,
SD H0 ELECTRICAL 23-Nov-14 Yes C 1-Dec-14 V
H2 & H3)
INFORMATION COMMUNICATION TECHNOLOGY SYSTEM FOR LEVEL-06 -PLAN (SEGMENT-H1) PART - 3
SD H1 ELECTRICAL 23-Nov-14 Yes C 1-Dec-14 V
OF 4
INFORMATION COMMUNICATION TECHNOLOGY SYSTEM FOR LEVEL-06 -PLAN (SEGMENT-H1) PART - 4
SD H1 ELECTRICAL 23-Nov-14 Yes C 1-Dec-14 V
OF 4
INFORMATION COMMUNICATION TECHNOLOGY SYSTEM FOR LEVEL-06 -PLAN (SEGMENT-H2) PART - 1
SD H2 ELECTRICAL 23-Nov-14 Yes C 1-Dec-14 V
OF 2
INFORMATION COMMUNICATION TECHNOLOGY SYSTEM FOR LEVEL-06 -PLAN (SEGMENT-H2) PART - 2
SD H2 ELECTRICAL 23-Nov-14 Yes C 1-Dec-14 V
OF 2
INFORMATION COMMUNICATION TECHNOLOGY SYSTEM FOR LEVEL-06 -PLAN (SEGMENT-H3) PART - 2
SD H3 ELECTRICAL 23-Nov-14 Yes C 1-Dec-14 V
OF 2
INFORMATION COMMUNICATION TECHNOLOGY SYSTEM FOR LEVEL-05 - MASTER PLAN (SEGMENT-H1,
SD H0 ELECTRICAL 23-Nov-14 Yes C 1-Dec-14 V
H2 & H3)
INFORMATION COMMUNICATION TECHNOLOGY SYSTEM FOR LEVEL-05 -PLAN (SEGMENT-H1) PART - 3
SD H1 ELECTRICAL 23-Nov-14 Yes C 1-Dec-14 V
OF 4
INFORMATION COMMUNICATION TECHNOLOGY SYSTEM FOR LEVEL-05 -PLAN (SEGMENT-H1) PART - 4
SD H1 ELECTRICAL 23-Nov-14 Yes C 1-Dec-14 V
OF 4
Page 70 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
FIRE ALARM SYSTEM LAYOUT MASTER LEVEL 07 (SEGMENT-H1) SD H1 ELECTRICAL 23-Nov-14 Yes C 1-Dec-14 V
VOICE EVACAUATION SYSTEM LAYOUT MASTER PLAN LEVEL 07 FOR (SEGMENT- H1 & H2) SD H1 ELECTRICAL 24-Nov-14 Yes B 24-Nov-14 V
CABLE ROUTING SYSTEM LAYOUT LEVEL-04 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 24-Nov-14 Yes C 25-Nov-14 V
CABLE ROUTING SYSTEM LAYOUT LEVEL-05 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 24-Nov-14 Yes C 25-Nov-14 V
CABLE ROUTING SYSTEM LAYOUT LEVEL-06 MASTER PLAN (SEGMENT-H1) SD H1 ELECTRICAL 24-Nov-14 Yes C 25-Nov-14 V
GROUNDING SYSTEM LAYOUT D&T MASTER PLAN LEVEL 01 SD BC ELECTRICAL 16-Dec-14 Yes C 14-Dec-14 S
GROUNDING SYSTEM LAYOUT D&T MASTER PLAN LEVEL 01 SD BC ELECTRICAL 4-Jan-15 Yes A 30-Dec-14 V
GROUNDING SYSTEM LAYOUT D&T SEGMENT (B1)LEVEL 01 SD B1 ELECTRICAL 16-Dec-14 Yes A 14-Dec-14 S
GROUNDING SYSTEM LAYOUT D&T SEGMENT (B1)LEVEL 01 SD B1 ELECTRICAL 4-Jan-15 Yes A 30-Dec-14 V
Page 71 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
GROUNDING SYSTEM LAYOUT D&T SEGMENT (B2)LEVEL 01 SD B2 ELECTRICAL 16-Dec-14 Yes A 14-Dec-14 V
GROUNDING SYSTEM LAYOUT D&T SEGMENT (B3)LEVEL 01 SD B3 ELECTRICAL 16-Dec-14 Yes A 14-Dec-14 V
GROUNDING SYSTEM LAYOUT D&T SEGMENT (C1)LEVEL 01 SD C1 ELECTRICAL 16-Dec-14 Yes A 14-Dec-14 V
GROUNDING SYSTEM LAYOUT D&T SEGMENT (C2)LEVEL 01 SD C2 ELECTRICAL 16-Dec-14 Yes A 14-Dec-14 V
GROUNDING SYSTEM LAYOUT D&T SEGMENT (C3)LEVEL 01 SD C3 ELECTRICAL 16-Dec-14 Yes A 14-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT D&T MASTER PLAN LEVEL-02 SD BC ELECTRICAL 24-Dec-14 Yes C 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL -02 FLOOR PLAN D&T (SEGMENT -B1) SD B1 ELECTRICAL 24-Dec-14 Yes C 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL -02 FLOOR PLAN D&T (SEGMENT -B2) SD B2 ELECTRICAL 24-Dec-14 Yes C 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL -02 FLOOR PLAN D&T (SEGMENT -B3) SD B3 ELECTRICAL 24-Dec-14 Yes C 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL -02 FLOOR PLAN D&T (SEGMENT -C1) SD C1 ELECTRICAL 24-Dec-14 Yes C 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL -02 FLOOR PLAN D&T (SEGMENT -C2) SD C2 ELECTRICAL 24-Dec-14 Yes C 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL -02 FLOOR PLAN D&T (SEGMENT -C3) SD C3 ELECTRICAL 24-Dec-14 Yes C 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL -03 FLOOR PLAN D&T (MASTER PLAN) SD BC ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL -03 FLOOR PLAN D&T (SEGMENT-B1) SD B1 ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL -03 FLOOR PLAN D&T (SEGMENT-B2) SD B2 ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL -03 FLOOR PLAN D&T (SEGMENT-C1) SD C1 ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL -03 FLOOR PLAN D&T (SEGMENT-C2) SD C2 ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT D&T MASTER PLAN LEVEL-04 SD BC ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL 04 FLOOR PLAN D&T ( SEGMENT-B1) SD B1 ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL 04 FLOOR PLAN D&T ( SEGMENT-B2) SD B2 ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL 04 FLOOR PLAN D&T ( SEGMENT-C1) SD C1 ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL 04 FLOOR PLAN D&T ( SEGMENT-C2) SD C2 ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT D&T MASTER PLAN LEVEL-06 SD BC ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL 06 FLOOR PLAN D&T (SEGMENT-B1) SD B1 ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL 06 FLOOR PLAN D&T (SEGMENT-B2) SD B2 ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL 06 FLOOR PLAN D&T (SEGMENT-C1) SD C1 ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
Page 72 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL 06 FLOOR PLAN D&T (SEGMENT-C2) SD C2 ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT D&T MASTER PLAN LEVEL07 SD BC ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION YSTEM LAYOUT LEVEL 07 FLOOR PLAN D&T (SEGMENT -B1) SD B1 ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
LIGHTING PROTECTION SYSTEM LAYOUT LEVEL-07 FLOOR PLAN D&T (SEGMENT-B2) SD B2 ELECTRICAL 24-Dec-14 Yes A 18-Dec-14 V
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 FLOOR MASTER PLAN ( SEGMENT
SD A ELECTRICAL 30-Dec-14 Yes A 24-Dec-14 V
- A1, A2&A3)
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 FLOOR PLAN ( SEGMENT - A1) SD A1 ELECTRICAL 30-Dec-14 Yes A 24-Dec-14 V
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 FLOOR PLAN ( SEGMENT - A2) SD A2 ELECTRICAL 30-Dec-14 Yes A 24-Dec-14 V
GROUNDING SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL 01 FLOOR PLAN ( SEGMENT - A3) SD A3 ELECTRICAL 30-Dec-14 Yes A 24-Dec-14 V
GROUNDING SYSTEM LAYOUT MASTER ROOF FLOOR PLAN SD A0 ELECTRICAL 30-Dec-14 Yes A 24-Dec-14 V
B08 - WATER TANK EARTHING SYSTEM SCHEMATIC SD A0 ELECTRICAL 5-Jan-15 Yes D 24-Dec-14 V
GROUNDING SYSTEM LAYOUT MASTER LEVEL 03 - FLOOR PLAN SD A0 ELECTRICAL 17-Jan-15 OverDue P V
GROUNDING SYSTEM LAYOUT LEVEL 03 - FLOOR PLAN (SEGMENT A1) SD A1 ELECTRICAL 17-Jan-15 OverDue P V
GROUNDING SYSTEM LAYOUT LEVEL 03 - FLOOR PLAN (SEGMENT A2) SD A2 ELECTRICAL 17-Jan-15 OverDue P V
LIGHTNING PROTECTION SYSTEM FOR LEVEL - 02 (MASTER PLAN) SD A0 ELECTRICAL 17-Jan-15 OverDue P V
LIGHTNING PROTECTION SYSTEM FOR LEVEL - 02 (SEGMENT A2) SD A2 ELECTRICAL 17-Jan-15 OverDue P V
LIGHTNING PROTECTION SYSTEM FOR LEVEL - 02 (SEGMENT A3) SD A3 ELECTRICAL 17-Jan-15 OverDue P V
LIGHTNING PROTECTION SYSTEM LAYOUT - FOR LEVEL - 08 (MASTER PLAN) SD A0 ELECTRICAL 17-Jan-15 OverDue P V
LIGHTNING PROTECTION SYSTEM LAYOUT FOR LEVEL - 08 (SEGMENT A1) SD A1 ELECTRICAL 17-Jan-15 OverDue P V
LIGHTNING PROTECTION SYSTEM LAYOUT FOR LEVEL - 08 (SEGMENT A2) SD A2 ELECTRICAL 17-Jan-15 OverDue P V
AMBULATORY CARE CENTER EARTHING SYSTEM SCHEMATICS PART -1 SD A1 ELECTRICAL 17-Jan-15 OverDue P V
AMBULATORY CARE CENTER EARTHING SYSTEM SCHEMATICS PART -2 SD A2 ELECTRICAL 17-Jan-15 OverDue P V
LIGHTING PROTECTION SYSTEM LAYOUT MASTER PLAN LEVEL 01 SD B7 ELECTRICAL 17-Jan-15 OverDue P V
LIGHTING PROTECTION SYSTEM LAYOUT MASTER PLAN ROOF PLAN SD B7 ELECTRICAL 17-Jan-15 OverDue P V
Page 73 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
TED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
Page 74 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAW
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 75 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAW
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 76 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAW
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 77 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAW
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 78 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAW
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 79 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
CTED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN (MASTER PLAN) SEGMENT-H1 SD H1 MECHANICAL 18-Mar-14 Yes C 17-Mar-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN (MASTER PLAN) SEGMENT-H1 SD H1 MECHANICAL 30-Apr-14 Yes A 28-Apr-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN (MASTER PLAN) SEGMENT-H1 SD H1 MECHANICAL 22-Jul-14 Yes A 2-Aug-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN (MASTER PLAN) SEGMENT-H1 SD H1 MECHANICAL 7-Jan-15 Yes A 30-Dec-14 V
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H1 (PART-1/4) SD H1 MECHANICAL 18-Mar-14 Yes C 17-Mar-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H1 (PART-1/4) SD H1 MECHANICAL 30-Apr-14 Yes A 28-Apr-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H1 (PART-1/4) SD H1 MECHANICAL 22-Jul-14 Yes A 2-Aug-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H1 (PART-1/4) SD H1 MECHANICAL 7-Jan-15 Yes A 30-Dec-14 V
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H1 (PART-2/4) SD H1 MECHANICAL 18-Mar-14 Yes C 17-Mar-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H1 (PART-2/4) SD H1 MECHANICAL 30-Apr-14 Yes A 28-Apr-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H1 (PART-2/4) SD H1 MECHANICAL 22-Jul-14 Yes A 2-Aug-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H1 (PART-2/4) SD H1 MECHANICAL 7-Jan-15 Yes A 30-Dec-14 V
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H1 (PART-3/4) SD H1 MECHANICAL 18-Mar-14 Yes C 17-Mar-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H1 (PART-3/4) SD H1 MECHANICAL 30-Apr-14 Yes B 28-Apr-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H1 (PART-3/4) SD H1 MECHANICAL 22-Jul-14 Yes A 2-Aug-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H1 (PART-3/4) SD H1 MECHANICAL 7-Jan-15 Yes A 30-Dec-14 V
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN (MASTER PLAN) SEGMENT-H2 SD H2 MECHANICAL 18-Mar-14 Yes C 17-Mar-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN (MASTER PLAN) SEGMENT-H2 SD H2 MECHANICAL 30-Apr-14 Yes A 28-Apr-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN (MASTER PLAN) SEGMENT-H2 SD H2 MECHANICAL 22-Jul-14 Yes C 2-Aug-14 V
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H2 (PART-1/4) SD H2 MECHANICAL 18-Mar-14 Yes C 17-Mar-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H2 (PART-1/4) SD H2 MECHANICAL 30-Apr-14 Yes A 28-Apr-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H2 (PART-1/4) SD H2 MECHANICAL 22-Jul-14 Yes C 2-Aug-14 V
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H2 (PART-3/4) SD H2 MECHANICAL 18-Mar-14 Yes C 17-Mar-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H2 (PART-3/4) SD H2 MECHANICAL 30-Apr-14 Yes A 28-Apr-14 S
HVAC SYSTEM LAY OUT FOR LEVEL-S1 PLAN SEGMENT-H2 (PART-3/4) SD H2 MECHANICAL 22-Jul-14 Yes C 2-Aug-14 V
Page 80 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
CTED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
CHILLED WATER PIPING LAYOUT FOR LEVEL-S1 MASTER PLAN (SEGMENT-H1) SD H1 MECHANICAL 30-Apr-14 Yes A 28-Apr-14 S
CHILLED WATER PIPING LAYOUT FOR LEVEL-S1 MASTER PLAN (SEGMENT-H1) SD H1 MECHANICAL 22-Jul-14 Yes B 2-Aug-14 S
CHILLED WATER PIPING LAYOUT FOR LEVEL-S1 MASTER PLAN (SEGMENT-H1) SD H1 MECHANICAL 7-Jan-15 Yes A 30-Dec-14 V
CHILLED WATER PIPING LAYOUT FOR LEVEL-S1 MASTER PLAN (SEGMENT-H1) PART-1 / 4 SD H1 MECHANICAL 30-Apr-14 Yes A 28-Apr-14 S
CHILLED WATER PIPING LAYOUT FOR LEVEL-S1 MASTER PLAN (SEGMENT-H1) PART-1 / 4 SD H1 MECHANICAL 22-Jul-14 Yes B 2-Aug-14 S
CHILLED WATER PIPING LAYOUT FOR LEVEL-S1 MASTER PLAN (SEGMENT-H1) PART-1 / 4 SD H1 MECHANICAL 7-Jan-15 Yes A 30-Dec-14 V
CHILLED WATER PIPING LAYOUT FOR LEVEL-S1 MASTER PLAN (SEGMENT-H1) PART- 3 / 4 SD H1 MECHANICAL 30-Apr-14 Yes A 28-Apr-14 S
CHILLED WATER PIPING LAYOUT FOR LEVEL-S1 MASTER PLAN (SEGMENT-H1) PART- 3 / 4 SD H1 MECHANICAL 22-Jul-14 Yes B 2-Aug-14 S
CHILLED WATER PIPING LAYOUT FOR LEVEL-S1 MASTER PLAN (SEGMENT-H1) PART- 3 / 4 SD H1 MECHANICAL 7-Jan-15 Yes A 30-Dec-14 V
CHILLED WATER PIPING LAYOUT FOR LEVEL-S1 MASTER PLAN (SEGMENT-H2) SD H2 MECHANICAL 30-Apr-14 Yes A 28-Apr-14 S
CHILLED WATER PIPING LAYOUT FOR LEVEL-S1 MASTER PLAN (SEGMENT-H2) SD H2 MECHANICAL 22-Jul-14 Yes C 2-Aug-14 V
CHILLED WATER PIPING LAYOUT FOR LEVEL-S1 MASTER PLAN (SEGMENT-H2) PART-1 / 4 SD H2 MECHANICAL 30-Apr-14 Yes A 28-Apr-14 S
CHILLED WATER PIPING LAYOUT FOR LEVEL-S1 MASTER PLAN (SEGMENT-H2) PART-1 / 4 SD H2 MECHANICAL 22-Jul-14 Yes C 2-Aug-14 V
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H1 ) PART-01 OF 04 SD H1 MECHANICAL 24-Aug-14 Yes C 25-Aug-14 S
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H1 ) PART-01 OF 04 SD H1 MECHANICAL 28-Oct-14 Yes B 30-Oct-14 V
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H1 ) PART-02 OF 04 SD H1 MECHANICAL 24-Aug-14 Yes C 25-Aug-14 S
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H1 ) PART-02 OF 04 SD H1 MECHANICAL 28-Oct-14 Yes B 30-Oct-14 V
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H1 ) PART-03 OF 04 SD H1 MECHANICAL 24-Aug-14 Yes C 25-Aug-14 S
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H1 ) PART-03 OF 04 SD H1 MECHANICAL 28-Oct-14 Yes B 30-Oct-14 V
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H1 ) PART-04 OF 04 SD H1 MECHANICAL 24-Aug-14 Yes C 25-Aug-14 S
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H1 ) PART-04 OF 04 SD H1 MECHANICAL 28-Oct-14 Yes B 30-Oct-14 V
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H2 ) PART-01 OF 04 SD H2 MECHANICAL 24-Aug-14 Yes C 25-Aug-14 S
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H2 ) PART-01 OF 04 SD H2 MECHANICAL 28-Oct-14 Yes B 30-Oct-14 V
Page 81 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
CTED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H2 ) PART-02 OF 04 SD H2 MECHANICAL 24-Aug-14 Yes C 25-Aug-14 S
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H2 ) PART-02 OF 04 SD H2 MECHANICAL 28-Oct-14 Yes B 30-Oct-14 V
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H2 ) PART-03 OF 04 SD H2 MECHANICAL 24-Aug-14 Yes C 25-Aug-14 S
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H2 ) PART-03 OF 04 SD H2 MECHANICAL 28-Oct-14 Yes B 30-Oct-14 V
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H2 ) PART-04 OF 04 SD H2 MECHANICAL 24-Aug-14 Yes C 25-Aug-14 S
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H2 ) PART-04 OF 04 SD H2 MECHANICAL 28-Oct-14 Yes B 30-Oct-14 V
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H3 ) PART-01 OF 02 SD H3 MECHANICAL 24-Aug-14 Yes C 25-Aug-14 S
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H3 ) PART-01 OF 02 SD H3 MECHANICAL 28-Oct-14 Yes B 30-Oct-14 V
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H3 ) PART -02 OF 02 SD H3 MECHANICAL 24-Aug-14 Yes C 25-Aug-14 S
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN ( SEGMENT -H3 ) PART -02 OF 02 SD H3 MECHANICAL 28-Oct-14 Yes B 30-Oct-14 V
CHILLED WATER LAYOUT FOR LEVEL-01 PLAN (SEGMENT-H1 ) PART-2 SD H1 MECHANICAL 30-Aug-14 Yes C 30-Aug-14 S
CHILLED WATER LAYOUT FOR LEVEL-01 PLAN (SEGMENT-H1 ) PART-2 SD H1 MECHANICAL 22-Nov-14 Yes C 24-Nov-14 V
CHILLED WATER LAYOUT FOR LEVEL-01 PLAN (SEGMENT-H3 ) PART-2 SD H3 MECHANICAL 30-Aug-14 Yes C 30-Aug-14 S
CHILLED WATER LAYOUT FOR LEVEL-01 PLAN (SEGMENT-H3 ) PART-2 SD H3 MECHANICAL 22-Nov-14 Yes C 24-Nov-14 V
CHILLED WATER PIPING FOR LEVEL-02 PLAN (SEGMENT-H1) PART-3 OF 4) SD H1 MECHANICAL 2-Sep-14 Yes C 2-Sep-14 S
CHILLED WATER PIPING FOR LEVEL-02 PLAN (SEGMENT-H1) PART-3 OF 4) SD H1 MECHANICAL 22-Nov-14 Yes C 24-Nov-14 V
CHILLED WATER PIPING FOR LEVEL-02 PLAN (SEGMENT-H2) PART-1 OF 4) SD H2 MECHANICAL 2-Sep-14 Yes C 2-Sep-14 S
CHILLED WATER PIPING FOR LEVEL-02 PLAN (SEGMENT-H2) PART-1 OF 4) SD H2 MECHANICAL 22-Nov-14 Yes C 24-Nov-14 V
CHILLED WATER PIPING FOR LEVEL-02 PLAN (SEGMENT-H2) PART-2 OF 4) SD H2 MECHANICAL 2-Sep-14 Yes C 2-Sep-14 S
CHILLED WATER PIPING FOR LEVEL-02 PLAN (SEGMENT-H2) PART-2 OF 4) SD H2 MECHANICAL 22-Nov-14 Yes C 24-Nov-14 V
CHILLED WATER PIPING FOR LEVEL-02 PLAN (SEGMENT-H3) PART-2 OF 2) SD H3 MECHANICAL 2-Sep-14 Yes C 2-Sep-14 S
CHILLED WATER PIPING FOR LEVEL-02 PLAN (SEGMENT-H3) PART-2 OF 2) SD H3 MECHANICAL 22-Nov-14 Yes C 24-Nov-14 V
CHILLED WATER PIPING FOR LEVEL-02 MEZZ. PLAN (SEGMENT-H1) PART 3 OF 4 SD H1 MECHANICAL 2-Sep-14 Yes C 2-Sep-14 S
CHILLED WATER PIPING FOR LEVEL-02 MEZZ. PLAN (SEGMENT-H1) PART 3 OF 4 SD H1 MECHANICAL 22-Nov-14 Yes C 24-Nov-14 V
CHILLED WATER PIPING FOR LEVEL-02 MEZZ. PLAN (SEGMENT-H1) PART 4 OF 4 SD H1 MECHANICAL 2-Sep-14 Yes C 2-Sep-14 S
Page 82 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
CTED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
CHILLED WATER PIPING FOR LEVEL-02 MEZZ. PLAN (SEGMENT-H1) PART 4 OF 4 SD H1 MECHANICAL 22-Nov-14 Yes C 24-Nov-14 V
CHILLED WATER PIPING FOR LEVEL-02 MEZZ. PLAN (SEGMENT-H2) PART 1 OF 4 SD H2 MECHANICAL 2-Sep-14 Yes C 2-Sep-14 S
CHILLED WATER PIPING FOR LEVEL-02 MEZZ. PLAN (SEGMENT-H2) PART 1 OF 4 SD H2 MECHANICAL 22-Nov-14 Yes C 24-Nov-14 V
CHILLED WATER PIPING FOR LEVEL-02 MEZZ. PLAN (SEGMENT-H2) PART 2 OF 4 SD H2 MECHANICAL 2-Sep-14 Yes C 2-Sep-14 S
CHILLED WATER PIPING FOR LEVEL-02 MEZZ. PLAN (SEGMENT-H2) PART 2 OF 4 SD H2 MECHANICAL 22-Nov-14 Yes C 24-Nov-14 V
CHILLED WATER PIPING FOR LEVEL -02 MEZZ. PLAN (SEGMENT-H3) PART-2 OF 2 SD H3 MECHANICAL 2-Sep-14 Yes C 2-Sep-14 S
CHILLED WATER PIPING FOR LEVEL -02 MEZZ. PLAN (SEGMENT-H3) PART-2 OF 2 SD H3 MECHANICAL 22-Nov-14 Yes C 24-Nov-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -03 PLAN (SEGNMENT-H1) PART-3 OF 4 SD H1 MECHANICAL 19-Sep-14 Yes C 20-Sep-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -03 PLAN (SEGMENT-H1) PART- 4 OF 4 SD H1 MECHANICAL 19-Sep-14 Yes C 20-Sep-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -03 PLAN (SEGMENT-H2) PART- 1 OF 4 SD H2 MECHANICAL 19-Sep-14 Yes C 20-Sep-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -03 PLAN (SEGMENT-H2) PART- 2 OF 4 SD H2 MECHANICAL 19-Sep-14 Yes C 20-Sep-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -03 PLAN (SEGMENT-H3) PART- 2 OF 2 SD H3 MECHANICAL 19-Sep-14 Yes C 20-Sep-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -02 PLAN (SEGMENT-H1) PART-3 OF 4 SD H1 MECHANICAL 11-Oct-14 Yes C 23-Oct-14 S
HVAC SYSTEM LAYOUT FOR LEVEL -02 PLAN (SEGMENT-H1) PART-3 OF 4 SD H1 MECHANICAL 22-Nov-14 Yes C 25-Nov-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -02 PLAN (SEGMENT-H1) PART-4 OF 4 SD H1 MECHANICAL 11-Oct-14 Yes C 23-Oct-14 S
HVAC SYSTEM LAYOUT FOR LEVEL -02 PLAN (SEGMENT-H1) PART-4 OF 4 SD H1 MECHANICAL 22-Nov-14 Yes C 25-Nov-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -02 PLAN (SEGMENT-H2) PART-1 OF 4 SD H2 MECHANICAL 11-Oct-14 Yes C 23-Oct-14 S
HVAC SYSTEM LAYOUT FOR LEVEL -02 PLAN (SEGMENT-H2) PART-1 OF 4 SD H2 MECHANICAL 22-Nov-14 Yes C 25-Nov-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -02 PLAN (SEGMENT-H2) PART-2 OF 4 SD H2 MECHANICAL 11-Oct-14 Yes C 23-Oct-14 S
HVAC SYSTEM LAYOUT FOR LEVEL -02 PLAN (SEGMENT-H2) PART-2 OF 4 SD H2 MECHANICAL 22-Nov-14 Yes C 25-Nov-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -02 PLAN (SEGMENT-H2) PART-4 OF 4 SD H2 MECHANICAL 11-Oct-14 Yes C 23-Oct-14 S
HVAC SYSTEM LAYOUT FOR LEVEL -02 PLAN (SEGMENT-H2) PART-4 OF 4 SD H2 MECHANICAL 22-Nov-14 Yes C 25-Nov-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -02 PLAN (SEGMENT-H3) PART-2 OF 2 SD H3 MECHANICAL 11-Oct-14 Yes C 23-Oct-14 S
HVAC SYSTEM LAYOUT FOR LEVEL -02 PLAN (SEGMENT-H3) PART-2 OF 2 SD H3 MECHANICAL 22-Nov-14 Yes C 25-Nov-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -02 MEZZ. PLAN (SEGMENT-H1) PART-3 OF 4 SD H1 MECHANICAL 11-Oct-14 Yes C 23-Oct-14 S
Page 83 of 114
H-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
CTED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE DRAWING
DRAWING TITLE TYPE DISCIPLINE REPLY APPROVA REPLY DATE
REQUIRED BY STATUS
L STATUS
HVAC SYSTEM LAYOUT FOR LEVEL -02 MEZZ. PLAN (SEGMENT-H1) PART-3 OF 4 SD H1 MECHANICAL 22-Nov-14 Yes C 25-Nov-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -02 MEZZ. PLAN (SEGMENT-H1) PART-4 OF 4 SD H1 MECHANICAL 11-Oct-14 Yes C 23-Oct-14 S
HVAC SYSTEM LAYOUT FOR LEVEL -02 MEZZ. PLAN (SEGMENT-H1) PART-4 OF 4 SD H1 MECHANICAL 22-Nov-14 Yes C 25-Nov-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -02 MEZZ. PLAN (SEGMENT-H2) PART-1 OF 4 SD H2 MECHANICAL 11-Oct-14 Yes C 23-Oct-14 S
HVAC SYSTEM LAYOUT FOR LEVEL -02 MEZZ. PLAN (SEGMENT-H2) PART-1 OF 4 SD H2 MECHANICAL 22-Nov-14 Yes C 25-Nov-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -02 MEZZ. PLAN (SEGMENT-H2) PART- 2 OF 4 SD H2 MECHANICAL 11-Oct-14 Yes C 23-Oct-14 S
HVAC SYSTEM LAYOUT FOR LEVEL -02 MEZZ. PLAN (SEGMENT-H2) PART- 2 OF 4 SD H2 MECHANICAL 22-Nov-14 Yes C 25-Nov-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -02 MEZZ. PLAN (SEGMENT-H2) PART- 4 OF 4 SD H2 MECHANICAL 11-Oct-14 Yes C 23-Oct-14 S
HVAC SYSTEM LAYOUT FOR LEVEL -02 MEZZ. PLAN (SEGMENT-H2) PART- 4 OF 4 SD H2 MECHANICAL 22-Nov-14 Yes C 25-Nov-14 V
HVAC SYSTEM LAYOUT FOR LEVEL -02 MEZZ. PLAN (SEGMENT-H3) PART- 2 OF 2 SD H3 MECHANICAL 11-Oct-14 Yes C 23-Oct-14 S
HVAC SYSTEM LAYOUT FOR LEVEL -02 MEZZ. PLAN (SEGMENT-H3) PART- 2 OF 2 SD H3 MECHANICAL 22-Nov-14 Yes C 25-Nov-14 V
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN (SEGMENT -H1) MASTER PLAN SD H1 MECHANICAL 28-Oct-14 Yes B 30-Oct-14 V
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN (SEGMENT -H2) MASTER PLAN SD H2 MECHANICAL 28-Oct-14 Yes B 30-Oct-14 V
HVAC SYSTEM LAYOUT FOR LEVEL-01 PLAN (SEGMENT -H3) MASTER PLAN SD H3 MECHANICAL 28-Oct-14 Yes B 30-Oct-14 V
HVAC SYSTEM LAYOUT FOR LEVEL-04 PLAN (SEGMENT- H1) PART -3 OF 4 SD H1 MECHANICAL 22-Nov-14 Yes C 24-Nov-14 V
HVAC SYSTEM LAYOUT FOR LEVEL-04 PLAN (SEGMENT- H1) PART 4 OF 4 SD H1 MECHANICAL 22-Nov-14 Yes C 24-Nov-14 V
CHILLED WATER LAYOUT FOR LEVEL -01 MASTER PLAN (SEGMENT - H1) SD H1 MECHANICAL 22-Nov-14 Yes C 24-Nov-14 V
Page 84 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 85 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 86 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 87 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 88 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 89 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 90 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 91 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 92 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 93 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 94 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 95 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 96 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 97 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 98 of 114
KING FAISAL SPECIALIST HOSPITAL & RESEARCH CENTER, JEDDAH
KFSH-STRUCTURAL SHOP DRAWIN
ABREVIATIONS USED : A = APPROVED , B = APPROVED AS NOTED , C = REVISE & RESUBMIT , D = REJECTED , S = SUPERCEDED , V = VALID
SUB.CON.CODE
PROJECT NO
DWG TYPE
SEGMENT
S.TRADE
SERIAL
TRADE
DWG
LEVEL
ZONE
SUB Date of
Sl.No SUBMITTAL NO CONTRACTOR REV
REV NO submission
NO
Page 99 of 114
-STRUCTURAL SHOP DRAWINGS SUBMITTAL LOG
CTED , S = SUPERCEDED , V = VALID 7-May-17
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 1/4) SD H0 PLUMBING 1-Dec-13 Yes C 24-Nov-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 1/4) SD H0 PLUMBING 19-Dec-13 Yes B 15-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 1/4) SD H1 plumbing 15-Mar-14 Yes B 11-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 1/4) SD H1 plumbing 1-Apr-14 Yes B 31-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 1/4) SD H1 PLUMBING 8-Jul-14 Yes A 12-Jul-14 V
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 2/4) SD H0 PLUMBING 1-Dec-13 Yes C 24-Nov-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 2/4) SD H0 PLUMBING 19-Dec-13 Yes B 15-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 2/4) SD H1 plumbing 15-Mar-14 Yes C 11-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 2/4) SD H1 plumbing 1-Apr-14 Yes B 31-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 2/4) SD H1 PLUMBING 8-Jul-14 Yes B 12-Jul-14 V
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 3/4) SD H0 PLUMBING 1-Dec-13 Yes C 1-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 3/4) SD H0 PLUMBING 19-Dec-13 Yes B 15-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 3/4) SD H1 PLUMBING 15-Mar-14 Yes B 11-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 3/4) SD H1 PLUMBING 1-Apr-14 Yes B 31-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 3/4) SD H1 PLUMBING 8-Jul-14 Yes A 12-Jul-14 V
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 4/4) SD H0 PLUMBING 1-Dec-13 Yes C 1-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 4/4) SD H0 PLUMBING 19-Dec-13 Yes B 15-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 4/4) SD H1 PLUMBING 15-Mar-14 Yes B 11-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 4/4) SD H1 PLUMBING 1-Apr-14 Yes B 31-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING (PART 4/4) SD H1 PLUMBING 8-Jul-14 Yes B 12-Jul-14 V
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING MASTER PLAN SD H0 PLUMBING 22-Dec-13 Yes B 15-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING MASTER PLAN SD H1 PLUMBING 15-Mar-14 Yes C 11-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING MASTER PLAN SD H1 PLUMBING 1-Apr-14 Yes B 31-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT-H1 MASTER PLAN SD H1 PLUMBING 8-Jul-14 Yes A 12-Jul-14 V
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING SEGMENT 2 PART1/2 SD H0 PLUMBING 22-Dec-13 Yes B 15-Dec-13 S
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING SEGMENT 2 PART1/2 SD H3 PLUMBING 15-Mar-14 Yes B 11-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING SEGMENT 3 MASTER PLAN SD H3 PLUMBING 8-Jul-14 Yes C 12-Jul-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING SEGMENT 3 MASTER PLAN SD H3 PLUMBING 8-Aug-14 Yes A 18-Aug-14 V
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING SEGMENT 2 PART2/2 SD H3 PLUMBING 22-Dec-13 Yes B 15-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING SEGMENT 2 PART2/2 SD H3 PLUMBING 15-Mar-14 Yes B 11-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING SEGMENT 2 PART2/2 SD H3 PLUMBING 8-Jul-14 Yes C 12-Jul-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING SEGMENT 2 PART2/2 SD H3 PLUMBING 8-Aug-14 Yes A 18-Aug-14 V
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H (PART 1/4) SD H0 PLUMBING 22-Dec-13 Yes B 18-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H (PART 1/4) SD H0 PLUMBING 16-Aug-14 Yes B 21-Aug-14 S
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H (PART 1/4) SD H0 PLUMBING 7-Jan-15 Yes A 31-Dec-14 V
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H (PART 2/4) SD H0 PLUMBING 22-Dec-13 Yes B 18-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H (PART 2/4) SD H0 PLUMBING 16-Aug-14 Yes B 21-Aug-14 S
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H1 (PART 2/4) SD H1 PLUMBING 7-Jan-15 Yes A 31-Dec-14 V
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H (PART 3/4) SD H0 PLUMBING 22-Dec-13 Yes B 18-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H (PART 3/4) SD H0 PLUMBING 16-Aug-14 Yes B 21-Aug-14 S
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H1 (PART 3/4) SD H1 PLUMBING 7-Jan-15 Yes A 31-Dec-14 V
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H2 (PART 1/4) SD H2 PLUMBING 22-Dec-13 Yes B 18-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H2 (PART 1/4) SD H2 PLUMBING 16-Aug-14 Yes B 21-Aug-14 S
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H2 (PART 1/4) SD H2 PLUMBING 7-Jan-15 Yes A 31-Dec-14 V
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H1 (PART 3/4) SD H1 PLUMBING 22-Dec-13 Yes B 18-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H2 (PART 3/4) SD H1 PLUMBING 16-Aug-14 Yes B 21-Aug-14 S
DRAINAGE SYSTEM LAYOUT LEVEL S1 FLOOR PLAN SEGMENT-H2 (PART 3/4) SD H2 PLUMBING 7-Jan-15 Yes A 31-Dec-14 V
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING MASTER PLAN-SEGMENT H1 SD H1 PLUMBING 29-Dec-13 Yes B 24-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING MASTER PLAN-SEGMENT H2 SD H2 PLUMBING 5-Mar-14 Yes C 2-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING MASTER PLAN-SEGMENT H2 SD H2 PLUMBING 30-Mar-14 Yes B 24-Mar-14 S
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING MASTER PLAN-SEGMENT H2 SD H2 PLUMBING 5-Jul-14 Yes A 1-Jul-14 V
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H1 (PART 1/4) SD H1 PLUMBING 29-Dec-13 Yes B 24-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H2 (PART 1/4) SD H2 PLUMBING 5-Mar-14 Yes C 2-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H2 (PART 1/4) SD H2 PLUMBING 30-Mar-14 Yes B 24-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H2 (PART 1/4) SD H2 PLUMBING 5-Jul-14 Yes A 1-Jul-14 V
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H1 (PART 2/4) SD H1 PLUMBING 29-Dec-13 Yes B 24-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H2 (PART 2/4) SD H2 PLUMBING 5-Mar-14 Yes C 2-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H2 (PART 2/4) SD H2 PLUMBING 30-Mar-14 Yes B 24-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H2 (PART 2/4) SD H2 PLUMBING 5-Jul-14 Yes A 1-Jul-14 V
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H1 (PART 3/4) SD H1 PLUMBING 29-Dec-13 Yes B 24-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H2 (PART 3/4) SD H2 PLUMBING 5-Mar-14 Yes C 2-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H2 (PART 3/4) SD H2 PLUMBING 30-Mar-14 Yes B 24-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H2 (PART 3/4) SD H2 PLUMBING 5-Jul-14 Yes A 1-Jul-14 V
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H1 (PART 4/4) SD H1 PLUMBING 29-Dec-13 Yes B 24-Dec-13 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H2 (PART 4/4) SD H2 PLUMBING 5-Jan-14 Yes C 2-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H2 (PART 4/4) SD H2 PLUMBING 30-Mar-14 Yes B 24-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL 01 FLOOR PLAN UNDER GROUND PIPING-SEGMENT H2 (PART 4/4) SD H2 PLUMBING 5-Jul-14 Yes A 1-Jul-14 V
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H (PART-1/4) SD H0 PLUMBING 23-Jan-14 Yes B 26-Jan-14 V
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H (PART-1/4) SD H0 PLUMBING 7-Jan-15 Yes B 3-Jan-15 V
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H (PART-2/4) SD H0 PLUMBING 23-Jan-14 Yes A 26-Jan-14 S
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H (PART-2/4) SD H1 PLUMBING 5-Jul-14 Yes B 1-Jul-14 S
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H (PART-2/4) SD H1 PLUMBING 6-Sep-14 Yes B 6-Sep-14 V
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H (PART-2/4) SD H1 PLUMBING 7-Jan-15 Yes B 3-Jan-15 V
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H (PART-3/4) SD H0 PLUMBING 23-Jan-14 Yes C 26-Jan-14 S
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H1 (PART-3/4) SD H1 PLUMBING 28-Mar-14 Yes B 29-Mar-14 S
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H1 (PART-3/4) SD H1 PLUMBING 5-Jul-14 Yes B 1-Jul-14 V
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H1 (PART-3/4) SD H1 PLUMBING 7-Jan-15 Yes B 3-Jan-15 V
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H1 (PART-1/4) SD H1 PLUMBING 23-Jan-14 Yes C 26-Jan-14 S
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H2 (PART-1/4) SD H2 pLUMBING 28-Mar-14 Yes B 29-Mar-14 S
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H2 (PART-1/4) SD H2 PLUMBING 10-Jun-14 Yes B 7-Jun-14 V
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H2 (PART-1/4) SD H2 PLUMBING 7-Jan-15 Yes B 3-Jan-15 V
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H1 (PART-3/4) SD H1 PLUMBING 23-Jan-14 Yes C 26-Jan-14 S
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H2 (PART-3/4) SD H2 pLUMBING 28-Mar-14 Yes B 29-Mar-14 S
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H2 (PART-3/4) SD H2 PLUMBING 10-Jun-14 Yes B 7-Jun-14 S
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H2 (PART-3/4) SD H2 PLUMBING 1-Jul-14 Yes B 26-Jun-14 V
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN SEGMENT - H2 (PART-3/4) SD H2 PLUMBING 7-Jan-15 Yes B 3-Jan-15 V
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN - MASTER PLAN (SEGMENT - H) SD H0 PLUMBING 28-Jan-14 Yes C 26-Jan-14 S
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN - MASTER PLAN (SEGMENT - H1) SD H1 PLUMBING 28-Mar-14 Yes B 29-Mar-14 S
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN - MASTER PLAN (SEGMENT - H1) SD H1 PLUMBING 5-Jul-14 Yes B 1-Jul-14 V
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN - MASTER PLAN (SEGMENT - H1) SD H1 PLUMBING 7-Jan-15 Yes B 3-Jan-15 V
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN - MASTER PLAN (SEGMENT - H1) SD H1 PLUMBING 28-Jan-14 Yes C 26-Jan-14 S
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN - MASTER PLAN (SEGMENT - H2) SD H2 pLUMBING 28-Mar-14 Yes B 29-Mar-14 S
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN - MASTER PLAN (SEGMENT - H2) SD H2 PLUMBING 10-Jun-14 Yes B 7-Jun-14 S
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN - MASTER PLAN (SEGMENT - H2) SD H2 PLUMBING 1-Jul-14 Yes B 2-Jun-14 V
BUILDERS WORK LAYOUT LEVEL - S1 FLOOR PLAN - MASTER PLAN (SEGMENT - H2) SD H2 PLUMBING 7-Jan-15 Yes B 3-Jan-15 V
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H1 (MASTER PLAN) SD H1 PLUMBING 9-Mar-14 Yes B 8-Mar-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H1 (MASTER PLAN) SD H1 PLUMBING 8-Aug-14 Yes B 12-Aug-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H1 (MASTER PLAN) SD H1 PLUMBING 7-Jan-15 Yes B 31-Dec-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H1 (PART-1/4) SD H1 PLUMBING 9-Mar-14 Yes B 8-Mar-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H1 (PART-1/4) SD H1 PLUMBING 8-Aug-14 Yes B 12-Aug-14 S
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H1 (PART-1/4) SD H1 PLUMBING 7-Jan-15 Yes B 31-Dec-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H1 (PART-3/4) SD H1 PLUMBING 9-Mar-14 Yes B 8-Mar-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H1 (PART-3/4) SD H1 PLUMBING 8-Aug-14 Yes B 12-Aug-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H1 (PART-3/4) SD H1 PLUMBING 7-Jan-15 Yes B 31-Dec-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 9-Mar-14 Yes B 8-Mar-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 8-Aug-14 Yes C 12-Aug-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 30-Sep-14 Yes A 30-Sep-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 9-Mar-14 Yes B 8-Mar-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 8-Aug-14 Yes C 12-Aug-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 30-Sep-14 Yes A 30-Sep-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 9-Mar-14 Yes B 8-Mar-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 8-Aug-14 Yes C 12-Aug-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL S1 FLOOR PLAN - SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 30-Sep-14 Yes A 30-Sep-14 V
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (MASTER PLAN) SD H1 PLUMBING 15-Mar-14 Yes C 12-Mar-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (MASTER PLAN) SD H1 PLUMBING 26-Apr-14 Yes A 30-Apr-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (MASTER PLAN) SD H1 PLUMBING 8-Aug-14 Yes A 12-Aug-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (MASTER PLAN) SD H1 PLUMBING 7-Jan-15 Yes A 31-Dec-14 V
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (PART-1/4) SD H1 PLUMBING 15-Mar-14 Yes C 12-Mar-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (PART-1/4) SD H1 PLUMBING 26-Apr-14 Yes A 30-Apr-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (PART-1/4) SD H1 PLUMBING 8-Aug-14 Yes A 12-Aug-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (PART-1/4) SD H1 PLUMBING 7-Jan-15 Yes A 31-Dec-14 V
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (PART-2/4) SD H1 PLUMBING 15-Mar-14 Yes C 12-Mar-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (PART-2/4) SD H1 PLUMBING 26-Apr-14 Yes A 30-Apr-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (PART-2/4) SD H1 PLUMBING 8-Aug-14 Yes A 12-Aug-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (PART-2/4) SD H1 PLUMBING 7-Jan-15 Yes A 31-Dec-14 V
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (PART-3/4) SD H1 PLUMBING 15-Mar-14 Yes C 12-Mar-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (PART-3/4) SD H1 PLUMBING 26-Apr-14 Yes A 30-Apr-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (PART-3/4) SD H1 PLUMBING 8-Aug-14 Yes A 12-Aug-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H1 (PART-3/4) SD H1 PLUMBING 7-Jan-15 Yes A 31-Dec-14 V
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 15-Mar-14 Yes C 12-Mar-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 26-Apr-14 Yes A 30-Apr-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 8-Aug-14 Yes C 12-Aug-14 V
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 30-Sep-14 Yes A 30-Sep-14 V
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 15-Mar-14 Yes C 12-Mar-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 26-Apr-14 Yes A 1-May-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 8-Aug-14 Yes C 12-Aug-14 V
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 30-Sep-14 Yes A 30-Sep-14 V
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 15-Mar-14 Yes C 12-Mar-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 26-Apr-14 Yes A 30-Apr-14 S
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 8-Aug-14 Yes C 12-Aug-14 V
FIRE FIGHTING SYSTEM LAYOUT LEVEL -S1 FLOOR PLAN SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 30-Sep-14 Yes A 30-Sep-14 V
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN UNDER GROUND PIPING SEGMENT-H3 (PART-1/2) SD H3 PLUMBING 15-Mar-14 Yes B 11-Mar-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN UNDER GROUND PIPING SEGMENT-H3 (PART-1/2) SD H3 PLUMBING 8-Jul-14 Yes C 12-Jul-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN UNDER GROUND PIPING SEGMENT-H3 (PART-1/2) SD H3 PLUMBING 8-Aug-14 Yes A 18-Aug-14 V
BUILDERS WORK LAYOUT LEVEL-01 FLOOR PLAN SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 30-Mar-14 Yes B 31-Mar-14 V
BUILDERS WORK LAYOUT LEVEL-01 FLOOR PLAN SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 30-Mar-14 Yes B 31-Mar-14 V
BUILDERS WORK LAYOUT LEVEL-01 FLOOR PLAN SEGMENT-H2 (PART-2/4) SD H2 PLUMBING 30-Mar-14 Yes B 31-Mar-14 V
BUILDERS WORK LAYOUT LEVEL-01 FLOOR PLAN SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 30-Mar-14 Yes B 31-Mar-14 V
BUILDERS WORK LAYOUT LEVEL-01 FLOOR PLAN SEGMENT-H2 (PART-4/4) SD H2 PLUMBING 30-Mar-14 Yes B 31-Mar-14 V
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (MASTER PLAN) SD H1 PLUMBING 16-Apr-14 Yes B 12-Apr-14 s
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (MASTER PLAN) SD H1 PLUMBING 4-Sep-14 Yes C 4-Sep-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (MASTER PLAN) SD H1 PLUMBING 4-Nov-14 Yes C 5-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (PART-1/4) SD H1 PLUMBING 16-Apr-14 Yes B 9-Apr-14 s
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (PART-1/4) SD H1 PLUMBING 4-Sep-14 Yes C 4-Sep-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (PART-1/4) SD H1 PLUMBING 4-Nov-14 Yes C 5-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (PART-2/4) SD H1 PLUMBING 16-Apr-14 Yes B 12-Apr-14 s
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (PART-2/4) SD H1 PLUMBING 4-Sep-14 Yes C 4-Sep-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (PART-2/4) SD H1 PLUMBING 4-Nov-14 Yes C 5-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (PART-3/4) SD H1 PLUMBING 16-Apr-14 Yes B 12-Apr-14 s
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (PART-3/4) SD H1 PLUMBING 4-Sep-14 Yes C 4-Sep-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (PART-3/4) SD H1 PLUMBING 4-Nov-14 Yes C 5-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (PART-4/4) SD H1 PLUMBING 16-Apr-14 Yes B 12-Apr-14 s
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (PART-4/4) SD H1 PLUMBING 4-Sep-14 Yes C 4-Sep-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H1 (PART-4/4) SD H1 PLUMBING 4-Nov-14 Yes C 5-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 16-Apr-14 Yes B 12-Apr-14 s
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 4-Sep-14 Yes C 4-Sep-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 4-Nov-14 Yes C 5-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 16-Apr-14 Yes B 12-Apr-14 s
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 4-Sep-14 Yes C 4-Sep-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 4-Nov-14 Yes C 5-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (PART-2/4) SD H2 PLUMBING 16-Apr-14 Yes B 12-Apr-14 s
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (PART-2/4) SD H2 PLUMBING 4-Sep-14 Yes C 4-Sep-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (PART-2/4) SD H2 PLUMBING 4-Nov-14 Yes C 5-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 16-Apr-14 Yes B 12-Apr-14 s
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 4-Sep-14 Yes C 4-Sep-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 4-Nov-14 Yes C 5-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (PART-4/4) SD H2 PLUMBING 16-Apr-14 Yes B 12-Apr-14 s
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (PART-4/4) SD H2 PLUMBING 4-Sep-14 Yes C 4-Sep-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H2 (PART-4/4) SD H2 PLUMBING 4-Nov-14 Yes C 5-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H3 (MASTER PLAN) SD H3 PLUMBING 16-Apr-14 Yes B 12-Apr-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H3 (MASTER PLAN) SD H3 PLUMBING 4-Sep-14 Yes C 4-Sep-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H3 (MASTER PLAN) SD H3 PLUMBING 4-Nov-14 Yes C 5-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H3 (PART-1/2) SD H3 PLUMBING 16-Apr-14 Yes B 12-Apr-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H3 (PART-1/2) SD H3 PLUMBING 4-Sep-14 Yes C 4-Sep-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H3 (PART-1/2) SD H3 PLUMBING 4-Nov-14 Yes C 5-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H3 (PART-2/2) SD H3 PLUMBING 16-Apr-14 Yes B 12-Apr-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H3 (PART-2/2) SD H3 PLUMBING 4-Sep-14 Yes C 4-Sep-14 S
DRAINAGE SYSTEM LAYOUT LEVEL-01 FLOOR PLAN HIGH LEVEL PIPING SEGMENT-H3 (PART-2/2) SD H3 PLUMBING 4-Nov-14 Yes C 5-Nov-14 V
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 26-May-14 Yes C 22-May-14 S
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 25-Aug-14 Yes C 30-Aug-14 S
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 2-Nov-14 Yes C 3-Nov-14 V
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (MASTER PLAN) SD H2 PLUMBING 16-Nov-14 Yes A 13-Nov-14 V
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 26-May-14 Yes C 22-May-14 S
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 25-Aug-14 Yes C 30-Aug-14 S
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 2-Nov-14 Yes C 3-Nov-14 V
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-1/4) SD H2 PLUMBING 16-Nov-14 Yes A 13-Nov-14 V
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-2/4) SD H2 PLUMBING 26-May-14 Yes C 22-May-14 S
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-2/4) SD H2 PLUMBING 25-Aug-14 Yes C 30-Aug-14 S
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-2/4) SD H2 PLUMBING 2-Nov-14 Yes C 3-Nov-14 V
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-2/4) SD H2 PLUMBING 16-Nov-14 Yes A 13-Nov-14 V
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 26-May-14 Yes C 22-May-14 S
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 25-Aug-14 Yes C 30-Aug-14 S
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 2-Nov-14 Yes C 3-Nov-14 V
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-3/4) SD H2 PLUMBING 16-Nov-14 Yes A 13-Nov-14 V
DRAINAGE SYSTEM LAHYOUT LEVEL-02 FLOOR PLAN SEGMENT- H2 (MASTER PLAN) SD H2 PLUMBING 26-May-14 Yes C 22-May-14 S
DRAINAGE SYSTEM LAHYOUT LEVEL-02 FLOOR PLAN SEGMENT- H2 (MASTER PLAN) SD H2 PLUMBING 20-Nov-14 Yes A 22-Nov-14 V
DRAINAGE SYTEM LAYOUT LEVEL-01 FLOOR PLAN SEGMENT-H2 PART 1 OF 4 SD H2 PLUMBING 26-May-14 Yes C 22-May-14 S
DRAINAGE SYTEM LAYOUT LEVEL-01 FLOOR PLAN SEGMENT-H2 PART 1 OF 4 SD H2 PLUMBING 20-Nov-14 Yes A 22-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL -01 FLOOR PLAN SEGMENT -H2 PART 2 OF 4 SD H2 PLUMBING 26-May-14 Yes C 22-May-14 S
DRAINAGE SYSTEM LAYOUT LEVEL -01 FLOOR PLAN SEGMENT -H2 PART 2 OF 4 SD H2 PLUMBING 20-Nov-14 Yes A 22-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL -01 FLOOR PLAN SEGMENT -H2 PART 3 OF 4 SD H2 PLUMBING 26-May-14 Yes C 22-May-14 S
DRAINAGE SYSTEM LAYOUT LEVEL -01 FLOOR PLAN SEGMENT -H2 PART 3 OF 4 SD H2 PLUMBING 20-Nov-14 Yes A 22-Nov-14 V
DRAINAGE SYSTEM LAYOUT LEVEL -01 FLOOR PLAN SEGMENT -H2 PART 4 OF 4 SD H2 PLUMBING 26-May-14 Yes C 22-May-14 S
DRAINAGE SYSTEM LAYOUT LEVEL -01 FLOOR PLAN SEGMENT -H2 PART 4 OF 4 SD H2 PLUMBING 20-Nov-14 Yes A 22-Nov-14 V
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-4/4) SD H2 PLUMBING 26-May-14 Yes C 22-May-14 S
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-4/4) SD H2 PLUMBING 25-Aug-14 Yes C 30-Aug-14 S
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-4/4) SD H2 PLUMBING 2-Nov-14 Yes C 3-Nov-14 V
BUILDERS WORK LAYOUT LEVEL 02 FLOOR PLAN SEGMENT-H2 (PART-4/4) SD H2 PLUMBING 16-Nov-14 Yes A 13-Nov-14 V
PLUMBIN G ENLARGED DETAIL SAND INTERCEPTOR DETAIL SD 00 PLUMBING 8-Jul-14 Yes B 12-Jul-14 V
B UILDER WORK LAYOUT LEVEL 01 FLOOR PLAN SEGMENT - H1 (MASTER PLAN ) SD H1 PLUMBING 2-Aug-14 Yes C 2-Aug-14 S
B UILDER WORK LAYOUT LEVEL 01 FLOOR PLAN SEGMENT - H1 (MASTER PLAN ) SD H1 PLUMBING 27-Aug-14 Yes B 28-Aug-14 V
BUILDER WORK LAYOUT LEVEL- 01 FLOOR PLAN SEGMENT - H1 (PART-1 / 4) SD H1 PLUMBING 2-Aug-14 Yes C 2-Aug-14 S
BUILDER WORK LAYOUT LEVEL- 01 FLOOR PLAN SEGMENT - H1 (PART-1 / 4) SD H1 PLUMBING 27-Aug-14 Yes B 28-Aug-14 V
BUILDER WORK LAYOUT LEVEL 01 FLOOR PLAN SEGMENT -H1 (PART-2/4) SD H1 PLUMBING 2-Aug-14 Yes C 2-Aug-14 S
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
BUILDER WORK LAYOUT LEVEL 01 FLOOR PLAN SEGMENT -H1 (PART-2/4) SD H1 PLUMBING 27-Aug-14 Yes B 28-Aug-14 V
BUILDER WORK LAYOUT LEVEL 01 FLOOR PLAN SEGMENT -H1 (PART-2/4) SD H1 PLUMBING 6-Sep-14 Yes B 6-Sep-14 V
BUILDER WORK LAYOUT LEVEL 01 FLOOR PLAN SEGMENT -H1 ( PLAN - 3 / 4) SD H1 PLUMBING 2-Aug-14 Yes C 2-Aug-14 S
BUILDER WORK LAYOUT LEVEL 01 FLOOR PLAN SEGMENT -H1 ( PLAN - 3 / 4) SD H1 PLUMBING 27-Aug-14 Yes B 28-Aug-14 V
BUILDER WORK LAYOUT LEVEL 01 FLOOR PLAN SEGMENT -H1 ( PART-4 / 4 ) SD H1 PLUMBING 2-Aug-14 Yes C 2-Aug-14 S
BUILDER WORK LAYOUT LEVEL 01 FLOOR PLAN SEGMENT -H1 ( PART-4 / 4 ) SD H1 PLUMBING 27-Aug-14 Yes B 28-Aug-14 V
BUILDER WORK LAYOUT LEVEL -01 FLOOR PLAN - MASTER PLAN (SEGMENT-H3) SD H3 PLUMBING 8-Aug-14 Yes B 18-Aug-14 V
BUILDER WORK LAYOUT LEVEL -01 FLOOR PLAN - MASTER PLAN (SEGMENT-H3) PART -01 OF 02 SD H3 PLUMBING 8-Aug-14 Yes B 18-Aug-14 V
BUILDER WORK LAYOUT LEVEL -01 FLOOR PLAN - MASTER PLAN (SEGMENT-H3) PART -02 OF 02 SD H3 PLUMBING 8-Aug-14 Yes B 18-Aug-14 V
DRAINAGE SYSTEM LAYOUT FOR LEVEL-S1, MASTER PLAN (SEGMENT - H1) SD H1 PLUMBING 16-Aug-14 Yes B 21-Aug-14 S
DRAINAGE SYSTEM LAYOUT FOR LEVEL-S1, MASTER PLAN (SEGMENT - H1) SD H1 PLUMBING 7-Jan-15 Yes A 31-Dec-14 V
DRAINAGE SYSTEM LAYOUT FOR LEVEL-S1, MASTER PLAN (SEGMENT - H2) SD H2 PLUMBING 16-Aug-14 Yes B 21-Aug-14 S
DRAINAGE SYSTEM LAYOUT FOR LEVEL-S1, MASTER PLAN (SEGMENT - H2) SD H2 PLUMBING 7-Jan-15 Yes A 31-Dec-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H1 (MASTER PLAN) SD H1 PLUMBING 14-Sep-14 Yes C 13-Sep-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H1 (MASTER PLAN) SD H1 PLUMBING 5-Nov-14 Yes C 5-Nov-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H1 (PART-1/4) SD H1 PLUMBING 14-Sep-14 Yes C 13-Sep-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H1 (PART-1/4) SD H1 PLUMBING 5-Nov-14 Yes C 5-Nov-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H1 (PART-2/4) SD H1 PLUMBING 14-Sep-14 Yes C 13-Sep-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H1 (PART-2/4) SD H1 PLUMBING 5-Nov-14 Yes C 5-Nov-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H1 (PART-3/4) SD H1 PLUMBING 14-Sep-14 Yes C 13-Sep-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H1 (PART-3/4) SD H1 PLUMBING 5-Nov-14 Yes C 5-Nov-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H1 (PART-4/4) SD H1 PLUMBING 14-Sep-14 Yes C 13-Sep-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H1 (PART-4/4) SD H1 PLUMBING 5-Nov-14 Yes C 5-Nov-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H2 (MASTER PLAN) SD H2 PLUMBING 14-Sep-14 Yes C 13-Sep-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H2 (MASTER PLAN) SD H2 PLUMBING 5-Nov-14 Yes C 5-Nov-14 V
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H2 (PART-1/4) SD H2 PLUMBING 14-Sep-14 Yes C 13-Sep-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H2 (PART-1/4) SD H2 PLUMBING 5-Nov-14 Yes C 5-Nov-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H2 (PART-2/4) SD H2 PLUMBING 14-Sep-14 Yes C 13-Sep-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H2 (PART-2/4) SD H2 PLUMBING 5-Nov-14 Yes C 5-Nov-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H2 (PART-3/4) SD H2 PLUMBING 14-Sep-14 Yes C 13-Sep-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H2 (PART-3/4) SD H2 PLUMBING 5-Nov-14 Yes C 5-Nov-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H2 (PART-4/4) SD H2 PLUMBING 14-Sep-14 Yes C 13-Sep-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H2 (PART-4/4) SD H2 PLUMBING 5-Nov-14 Yes C 5-Nov-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H3 (MASTER PLAN) SD H3 PLUMBING 14-Sep-14 Yes C 13-Sep-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H3 (MASTER PLAN) SD H3 PLUMBING 5-Nov-14 Yes C 5-Nov-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H3 (PART-1/2) SD H3 PLUMBING 14-Sep-14 Yes C 13-Sep-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H3 (PART-1/2) SD H3 PLUMBING 5-Nov-14 Yes C 5-Nov-14 V
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H3 (PART-2/2) SD H3 PLUMBING 14-Sep-14 Yes C 13-Sep-14 S
WATER SUPPLY SYSTEM LAYOUT LEVEL 01 FLOOR PLAN SEGEMENT-H3 (PART-2/2) SD H3 PLUMBING 5-Nov-14 Yes C 5-Nov-14 V
B # 08 WATER TANK CENTRAL UTILITY PLANT BUILDERS WORK SD B8 PLUMBING 12-Oct-14 Yes C 3-Nov-14 V
BUILDERS WORK LAYOUT LEVEL -03 FLOOR PLAN SEGMENT -H2 ( MASTER PLAN ) SD H2 PLUMBING 11-Nov-14 Yes B 9-Nov-14 V
BUILDERS WORK LAYOUT LEVEL -03 FLOOR PLAN SEGMENT -H2 (PART- 1-4) SD H2 PLUMBING 11-Nov-14 Yes B 9-Nov-14 V
BUILDERS WORK LAYOUT LEVEL -03 FLOOR PLAN SEGMENT -H2 (PART- 2-4) SD H2 PLUMBING 11-Nov-14 Yes B 9-Nov-14 V
BUILDERS WORK LAYOUT LEVEL -03 FLOOR PLAN SEGMENT -H2 (PART- 4-4) SD H2 PLUMBING 11-Nov-14 Yes B 9-Nov-14 V
FIRE FIGHTING LAYOUT LEVEL- 01 MASTER PLAN (HIGH LEVEL PIPING) SEGMENT- H1 SD H1 PLUMBING 20-Nov-14 Yes C 19-Nov-14 V
FIRE FIGHTING LAYOUT FOR LEVEL- 01 PLAN (HIGH LEVEL PIPING) SEGMENT- H1 - PART- 1 OF 4 SD H1 PLUMBING 20-Nov-14 Yes C 19-Nov-14 V
FIRE FIGHTING LAYOUT FOR LEVEL- 01 PLAN (HIGH LEVEL PIPING) SEGMENT- H1 - PART- 2 OF 4 SD H1 PLUMBING 20-Nov-14 Yes C 19-Nov-14 V
FIRE FIGHTING LAYOUT FOR LEVEL- 01 PLAN (HIGH LEVEL PIPING) SEGMENT- H1 - PART- 3 OF 4 SD H1 PLUMBING 20-Nov-14 Yes C 19-Nov-14 V
FIRE FIGHTING FOR LAYOUT LEVEL- 01 PLAN (HIGH LEVEL PIPING) SEGMENT- H1 - PART- 4 OF 4 SD H1 PLUMBING 20-Nov-14 Yes C 19-Nov-14 V
FIRE FIGHTING FOR LAYOUT LEVEL- 01 MASTER PLAN (HIGH LEVEL PIPING) SEGMENT- H2 SD H2 PLUMBING 20-Nov-14 Yes C 19-Nov-14 V
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
FIRE FIGHTING FOR LAYOUT LEVEL- 01 PLAN (HIGH LEVEL PIPING) SEGMENT- H2 - PART- 1 OF 4 SD H2 PLUMBING 20-Nov-14 Yes C 19-Nov-14 V
FIRE FIGHTING FOR LAYOUT LEVEL- 01 PLAN (HIGH LEVEL PIPING) SEGMENT- H2 - PART- 2 OF 4 SD H2 PLUMBING 20-Nov-14 Yes C 19-Nov-14 V
FIRE FIGHTING FOR LAYOUT LEVEL- 01 PLAN (HIGH LEVEL PIPING) SEGMENT- H2 - PART- 3 OF 4 SD H2 PLUMBING 20-Nov-14 Yes C 19-Nov-14 V
FIRE FIGHTING FOR LAYOUT LEVEL- 01 PLAN (HIGH LEVEL PIPING) SEGMENT- H2 - PART- 4 OF 4 SD H2 PLUMBING 20-Nov-14 Yes C 19-Nov-14 V
FIRE FIGHTING LAYOUT LEVEL- 01 MASTER PLAN (HIGH LEVEL PIPING) SEGMENT- H3 SD H3 PLUMBING 20-Nov-14 Yes C 20-Nov-14 V
FIRE FIGHTING LAYOUT LEVEL- 01 PLAN (HIGH LEVEL PIPING) SEGMENT- H3 - PART- 1 OF 2 SD H3 PLUMBING 20-Nov-14 Yes C 20-Nov-14 V
FIRE FIGHTING LAYOUT LEVEL- 01 PLAN (HIGH LEVEL PIPING) SEGMENT- H3 - PART- 2 OF 2 SD H3 PLUMBING 20-Nov-14 Yes C 20-Nov-14 V
Water Supply layout for level -02 high level piping master plan segment H1 SD H1 PLUMBING 20-Nov-14 Yes C 15-Nov-14 V
Water Supply layout for level -02 high level piping segment H1 part 3\4 SD H1 PLUMBING 20-Nov-14 Yes C 15-Nov-14 V
Water Supply layout for level -02 high level piping segment H1 part 4\4 SD H1 PLUMBING 20-Nov-14 Yes C 15-Nov-14 V
Water Supply layout for level -02 high level piping master plan segment H2 SD H2 PLUMBING 20-Nov-14 Yes C 15-Nov-14 V
Water Supply layout for level -02 high level piping segment H2 Part 1\4 SD H2 PLUMBING 20-Nov-14 Yes C 15-Nov-14 V
Water Supply layout for level -02 high level piping master plan segment H3 SD H3 PLUMBING 20-Nov-14 Yes C 15-Nov-14 V
Water Supply layout for level -02 high level piping segment H2 Part 2\2 SD H3 PLUMBING 20-Nov-14 Yes C 15-Nov-14 V
Drainage layout for level -02 master plan segment H1 SD H1 PLUMBING 20-Nov-14 Yes C 22-Nov-14 V
Drainage layout for level -02 plan segment H1 Part -1\4 SD H1 PLUMBING 20-Nov-14 Yes C 22-Nov-14 V
Drainage layout for level -02 plan segment H1 Part -2\4 SD H1 PLUMBING 20-Nov-14 Yes C 22-Nov-14 V
Drainage layout for level -02 plan segment H1 Part -3\4 SD H1 PLUMBING 20-Nov-14 Yes C 22-Nov-14 V
Drainage layout for level -02 plan segment H1 Part -4\4 SD H1 PLUMBING 20-Nov-14 Yes C 22-Nov-14 V
Drainage layout for level -02 master plan segment H3 SD H3 PLUMBING 20-Nov-14 Yes C 22-Nov-14 V
Drainage layout for level -02 plan segment H3 Part 1\2 SD H3 PLUMBING 20-Nov-14 Yes C 22-Nov-14 V
Drainage layout for level -02 plan segment H3 Part 2\2 SD H3 PLUMBING 20-Nov-14 Yes C 22-Nov-14 V
WATER SUPPLY LAYOUT FOR LEVEL- 02 MASTER PLAN (SEGMENT-H1) SD H1 PLUMBING 20-Nov-14 Yes C 17-Nov-14 V
WATER SUPPLY LAYOUT FOR LEVEL- 02 PLAN (SEGMENT-H1) PART- 3 OF 4 SD H1 PLUMBING 20-Nov-14 Yes C 17-Nov-14 V
WATER SUPPLY LAYOUT FOR LEVEL- 02 PLAN (SEGMENT-H1) PART- 4 OF 4 SD H1 PLUMBING 20-Nov-14 Yes C 17-Nov-14 V
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
WATER SUPPLY LAYOUT FOR LEVEL- 02 MASTER PLAN (SEGMENT-H2) SD H2 PLUMBING 20-Nov-14 Yes C 17-Nov-14 V
WATER SUPPLY LAYOUT FOR LEVEL- 02 PLAN (SEGMENT-H2) PART- 1 OF 4 SD H2 PLUMBING 20-Nov-14 Yes C 17-Nov-14 V
WATER SUPPLY LAYOUT FOR LEVEL- 02 PLAN (SEGMENT-H2) PART- 2 OF 4 SD H2 PLUMBING 20-Nov-14 Yes C 17-Nov-14 V
WATER SUPPLY LAYOUT FOR LEVEL- 02 PLAN (SEGMENT-H2) PART- 4 OF 4 SD H2 PLUMBING 20-Nov-14 Yes C 17-Nov-14 V
WATER SUPPLY LAYOUT FOR LEVEL- 02 MASTER PLAN (SEGMENT-H3) SD H3 PLUMBING 20-Nov-14 Yes C 17-Nov-14 V
WATER SUPPLY LAYOUT FOR LEVEL- 02 PLAN (SEGMENT-H3) PART- 2 OF 2 SD H3 PLUMBING 20-Nov-14 Yes C 17-Nov-14 V
MEDICAL GASES PIPING LAYOUT FOR LEVEL - 1, MASTER PLAN (SEGMENT - H1) SD H1 PLUMBING 22-Nov-14 Yes C 27-Nov-14 V
MEDICAL GASES PIPING LAYOUT FOR LEVEL -1 PLAN (SEGMENT - H1) (PART - 1 OF 4) SD H1 PLUMBING 22-Nov-14 Yes C 27-Nov-14 V
MEDICAL GASES PIPING LAYOUT FOR LEVEL - 1, PLAN (SEGMENT - H1) (PART - 3 OF 4) SD H1 PLUMBING 22-Nov-14 Yes C 27-Nov-14 V
MEDICAL GASES PIPING LAYOUT FOR LEVEL-1 PLAN (SEGMENT - H1) (PART - 2 OF 4) SD H1 PLUMBING 22-Nov-14 Yes C 27-Nov-14 V
MEDICAL GASES PIPING LAYOUT FOR LEVEL - 1, PLAN (SEGMENT - H1) (PART - 4 OF 4) SD H1 PLUMBING 22-Nov-14 Yes C 27-Nov-14 V
MEDICAL GASES PIPING LAYOUT FOR LEVEL - 1, MASTER PLAN (SEGMENT - H2) SD H2 PLUMBING 22-Nov-14 Yes C 27-Nov-14 V
MEDICAL GASES PIPING LAYOUT FOR LEVEL - 1 PLAN (SEGMENT-H2) (PART-1 OF 4) SD H2 PLUMBING 22-Nov-14 Yes C 27-Nov-14 V
MEDICAL GASES PIPING LAYOUT FOR LEVEL - 1 PLAN (SEGMENT-H2) (PART-2 OF 4) SD H2 PLUMBING 22-Nov-14 Yes C 27-Nov-14 V
MEDICAL GASES PIPING LAYOUT FOR LEVEL - 1 PLAN (SEGMENT-H2) (PART-3 OF 4) SD H2 PLUMBING 22-Nov-14 Yes C 27-Nov-14 V
MEDICAL GASES PIPING LAYOUT FOR LEVEL - 1, MASTER PLAN (SEGMENT - H3) SD H3 PLUMBING 22-Nov-14 Yes C 27-Nov-14 V
MEDICAL GASES PIPING LAYOUT FOR LEVEL - 1 PLAN (SEGMENT - H3) (PART - 1 OF 2) SD H3 PLUMBING 22-Nov-14 Yes C 27-Nov-14 V
MEDICAL GASES PIPING LAYOUT FOR LEVEL - 1, PLAN (SEGMENT - H3) (PART - 2 OF 2) SD H3 PLUMBING 22-Nov-14 Yes C 27-Nov-14 V
BUILDERS WORK LAYOUT FOR LEVEL - 2, MASTER PLAN (SEGMENT-H1) SD H1 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
BUILDERS WORK LAYOUT FOR LEVEL - 2, PLAN (SEGMENT - H1) / (PART - 1/4) SD H1 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
BUILDERS WORK LAYOUT FOR LEVEL - 2, PLAN (SEGMENT - H1) / (PART - 2/4) SD H1 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
BUILDERS WORK LAYOUT FOR LEVEL - 2, PLAN (SEGMENT - H1) / (PART - 3/4) SD H1 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
BUILDERS WORK LAYOUT FOR LEVEL - 2, PLAN (SEGMENT - H1) / (PART - 4/4) SD H1 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
BUILDERS WORK LAYOUT FOR LEVEL - 2, MASTER PLAN (SEGMENT-H3) SD H3 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
BUILDERS WORK LAYOUT FOR LEVEL - 2 PLAN (SEGMENT - H3) / (PART - 1/2) SD H3 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
BUILDERS WORK LAYOUT FOR LEVEL - 2 PLAN (SEGMENT - H3) / (PART - 2/2) SD H3 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
BUILDERS WORK LAYOUT FOR LEVEL -2 MASTER PLAN (SEGMENT -H2) SD H2 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
BUILDERS WORK LAYOUT FOR LEVEL -2 (SEGMENT -H2) PART 1 OF 4 SD H2 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
BUILDERS WORK LAYOUT FOR LEVEL -2 (SEGMENT -H2) PART 2 OF 4 SD H2 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
BUILDERS WORK LAYOUT FOR LEVEL -2 (SEGMENT -H3) PART 2 OF 2 SD H3 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
FIRE FIGHTING SYSTEM LAYOUTFOR LEVEL- 02 FLOOR PLAN - MASTER PLAN
SD H1 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
SEGMENT - H1
FIRE FIGHTING SYSTEM LAYOUT LEVEL- 02 PLAN - SEGMENT- H1
SD H1 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
PART- 3 OF 4
FIRE FIGHTING SYSTEM LAYOUT LEVEL- 02 PLAN - SEGMENT- H1
SD H1 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
PART- 4 OF 4
FIRE FIGHTING SYSTEM LAYOUT LEVEL- 02 FLOOR PLAN - MASTER PLAN - SEGMENT- H2 SD H2 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
FIRE FIGHTING SYSTEM LAYOUT LEVEL- 02 FLOOR PLAN - SEGMENT- H2 PART- 1 OF 4 SD H2 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
FIRE FIGHTING SYSTEM LAYOUT LEVEL- 02 PLAN - SEGMENT- H2
SD H2 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
PART- 2 OF 4
FIRE FIGHTING SYSTEM LAYOUT LEVEL- 02 FLOOR PLAN - MASTER PLAN - SEGMENT- H3 SD H3 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
FIRE FIGHTING SYSTEM LAYOUT LEVEL- 02 FLOOR PLAN - SEGMENT- H3 PART- 2 OF 2 SD H3 PLUMBING 22-Nov-14 Yes C 20-Nov-14 V
BUILDERS WORK LAYOUT LEVEL S1 FLOOR PLAN (TUNNEL AREA) SEGMENT - E1 (ICU) SD E1 PLUMBING 4-Jan-15 Yes C 29-Dec-14 V
BUILDERS WORK LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT A-1,
SD A PLUMBING 12-Jan-15 OverDue P V
A2 & A3)
BUILDERS WORK LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT A-1)
SD A1 PLUMBING 12-Jan-15 OverDue P V
(PART 1/2)
BUILDERS WORK LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT A-1)
SD A1 PLUMBING 12-Jan-15 OverDue P V
(PART 2/2)
BUILDERS WORK LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT A-2)
SD A2 PLUMBING 12-Jan-15 OverDue P V
(PART 1/2)
BUILDERS WORK LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT A-3)
SD A3 PLUMBING 12-Jan-15 OverDue P V
(PART 1/4)
BUILDERS WORK LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT A-3)
SD A3 PLUMBING 12-Jan-15 OverDue P V
(PART 2/4)
BUILDERS WORK LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT A-3)
SD A3 PLUMBING 12-Jan-15 OverDue P V
(PART 3/4)
BUILDERS WORK LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT A-3)
SD A3 PLUMBING 12-Jan-15 OverDue P V
(PART 4/4)
BUILDERS WORK LAYOUT MASTER FOUNDATION DETAILS SD A0 PLUMBING 12-Jan-15 OverDue P V
DRAINAGE SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT -
SD A PLUMBING 12-Jan-15 OverDue P V
A, A2 & A3)
DRAINAGE SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT -
SD A1 PLUMBING 12-Jan-15 OverDue P V
A1) (PART 1/2)
SEGMENT
RESPONSE
DRAWING
DRAWING TITLE TYPE DISCIPLINE REQUIRED REPLY APPROVA REPLY DATE
STATUS
BY L STATUS
DRAINAGE SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT -
SD A1 PLUMBING 12-Jan-15 OverDue P V
A1) (PART 2/2)
DRAINAGE SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT -
SD A2 PLUMBING 12-Jan-15 OverDue P V
A2) (PART 1/2)
DRAINAGE SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT -
SD A2 PLUMBING 12-Jan-15 OverDue P V
A2) (PART 2/2)
DRAINAGE SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT -
SD A3 PLUMBING 12-Jan-15 OverDue P V
A3) (PART 1/4)
DRAINAGE SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT -
SD A3 PLUMBING 12-Jan-15 OverDue P V
A3) (PART 2/4)
DRAINAGE SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT -
SD A3 PLUMBING 12-Jan-15 OverDue P V
A3) (PART 3/4)
DRAINAGE SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT -
SD A3 PLUMBING 12-Jan-15 OverDue P V
A3) (PART 4/4)
DRAINAGE SYSTEM LAYOUT MASTER FOUNDATION TYPICAL DETAILS - (SEGMENT - A3) (PART 1/1) SD A PLUMBING 12-Jan-15 OverDue P V
WATER SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT - A1,
SD A PLUMBING 11-Jan-15 OverDue P V
A2 & A3)
WATER SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT - A1,
SD A1 PLUMBING 11-Jan-15 OverDue P V
A2 & A3) (PART 1/2)
WATER SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT - A1)
SD A1 PLUMBING 11-Jan-15 OverDue P V
(PART 2/2)
WATER SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT - A2)
SD A2 PLUMBING 11-Jan-15 OverDue P V
(PART 1/2)
WATER SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT - A2)
SD A2 PLUMBING 11-Jan-15 OverDue P V
(PART 2/2)
WATER SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT - A3)
SD A3 PLUMBING 11-Jan-15 OverDue P V
(PART 1/4)
WATER SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT - A3)
SD A3 PLUMBING 11-Jan-15 OverDue P V
(PART 2/4)
WATER SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT - A3)
SD A3 PLUMBING 11-Jan-15 OverDue P V
(PART 3/4)
WATER SYSTEM LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT - A3)
SD A3 PLUMBING 11-Jan-15 OverDue P V
(PART 4/4)
BUILDERS WORK LAYOUT MASTER FOUNDATION AND LEVEL - S01 FLOOR MASTER PLAN (SEGMENT A-2)
SD A2 PLUMBING 12-Jan-15 OverDue P V
(PART 2/2)