Images to solve Oxidizer startup problems

Please send pictures or video to make sure all the following issues have been done well before leaving for the
commissioning. Thank for your support!

1. Make sure LNG to BN101 pressure should be at 300~400mbar, flow=40Nm3/h

2. Make sure LNG to BN102 pressure should be at 300~400mbar, flow=40Nm3/h. If cannot make sure the gas
pressure, the burner cannot work properly.

3. Make sure the gas pipelines connected to BN101 and BN102 has been cleaned well and the main gas pipelines
have been connected well, and make sure you can supply gas at any time.

4. Make sure the dust collecting cyclone before the gas entering the RTO can work well. If the dust in the waste gas
Ilustracin 300-420 mbar
hasnt been collected by the cyclone, the dust may cause the block of the
heat storage medium and affect the working of the whole system.

5. As mentioned before, there are Solenoid valves and limit switches for the 12 pneumatic valves, and 6 of them are
corrosion damaged. Have you solved it?

6. Make sure all the valves working well and the feedback signal working well.

7. Make sure all the temperature and the pressure sensors can detect well and the feedback signal can work well.
8. Make sure the wires and cables from the site to the electrical controller are in good condition with no breakout and
short sub

9. Make sure the electrical components inside the electrical controller and burner can work well. You should power on
to make sure there is no failure.

10. Make sure the UV is in good condition. And according to the actual installation of the UV interfaces, you should
prepare relative connectors, wire and cables.

11. Make sure all the motors can run well.