Installation Guide

Shandong LD Machinery Co., Ltd

Shandong Innovative & Craft Brewing Equipment Co., Ltd


Part 1: Overall View

1
Part 2: Installation
Step 1:
Put tanks on position based on layout. Pay attention to distance between tanks, distance between
tanks and wall.
Below pictures are only for reference.

Make a line on ground helps you put tanks


Put tanks in line for reference
in line easier

2
Check Distance Check Verticality

Step 2:
Sort out parts and tools.
Below pictures are only for reference.

Step 3:
Assemble brewhouse pipeline.
Below pictures are only for reference.

1. Pipelines, valves and parts are pasted with number. Put together pipes or valves that
with same numbers on them.

3
Step 4:
Assemble glycol water pipeline.
Below pictures are only for reference.

1. Glycol water comes to glycol water pump from glycol water tank. Then usually go in 2
ways with T connector at pump outlet. One way goes to fermentation system, another
way goes to PHE (Plate heat exchanger).

4
2. Plate heat exchange pipeline of glycol water

Fermentation system glycol water pipeline

3. Put tapes on external thread of


parts and tank pipe. 4. Put connectors or valve on
Make tapes thick, avoid leakage.

5. Set hot melt machine at 330-350℃, it costs


several minutes to reach this temperature

5
6. Design inlet
pipe based on
the space. We 7. Assemble these parts together with hot melt machine
make it with
90° elbow.

8. Glycol water pipeline of fermentation tank outlet

6
9. Glycol water pipeline of fermentation tank inlet

10. Glycol water pipeline of chiller.


You may have 2 chillers. Second chiller is also connected in this same way.

7
11. Assemble insulation pipe for fermentation tank and chiller

Step 5:
Assemble electric wires and signal wires.
Below pictures are only for reference.

1. Control cabinet overall view.


Only need to connect these wires.

2. Wires goes into control 3. This is main switch. 4. Remember white wire
through hole Connect your power position when put

8
temperature sensor in
source here
tank

5. For pump and motor, connect left or right 3 connectors in junction box

6. For fermentation system, firstly put this wire tube on tank

9
7. Connect wires for solenoid valve

8. Connect wires for temperature sensor.


Make sure the white wire position. It has to be at first position of sensor connector.

9. Connect wires for chiller

10
10. Connect wires for CIP heating element and pump

11. Connect wires for CIP plug, which connects with socket on control cabinet

Step 6:
Assemble steam boiler.
Below pictures are only for reference.

11
1. Electric steam boiler, water softener connection and setting

12
2. Electric steam boiler, connect wires, turn on boiler by switch A and B.
If only turn on one of switch B, boiler runs on half working capacity and power
consumption

1. Gas steam boiler, water softener connection.


Water softener setting , hose of salty box and drain port is same to electric steam
boiler

2. Gas steam boiler, gas inlet


a. Gas pressure requirement: 2-3Kpa for
50kg/h boiler; 3-4Kpa for 100kg/h boiler; 4-
5Kpa for 200kg/h boiler.

b. Require a pressure gauge to show gas


pressure

13
3. Gas steam boiler, connect wires, turn on boiler by switch on panel
Note: If you will not use the boiler for one week or more days, please drain all water in
boiler

Step 6:
Put parts on fermentation tank and BBT
Below pictures are only for reference.

These are 2 main designs


for fermentation tank. BBT
is similar with them.

Some time we customize


fermentation tank based
on client’s requirement.
So, you can put on parts
according to fermentation
tank drawing.

Isotonic hops adding device. This is Carbonation stone. This is optional, not in

14
optional, not in standard design. standard design.

Part 3: Pilot Run


Before run brewery, please you test run for a while to confirm each part is assembled well. Here is
instruction.

1. In glycol water tank, please fill 30% food grade glycol and 70% water.

2. We usually set chiller temperature at around -4 to -5℃, please confirm.

3. Run each pump and motor, if rotate reversely, please exchange wire position of any 2 wires
in junction box OR control cabinet.

4. For PID control cabinet, we have video of setting temperature on temperature controller.
Please contact us if you need them.

5. There is a time relay in control cabinet. Set


it as 15M05M by pressing the button.

6. Yeast tank

Part 4: Current Maintenance

1. Check glycol content in glycol water tank, it should be 28%-30%.

2. Open side protecting plate of chiller to check if condenser is dirty. Clean it with some soft
things. Don't use hard or sharp tools.

3. As to boiler, drain all the water through drain port each week. And keep drain port open, turn
on boiler switch to fill water in boiler, wash boiler for one minute.

4. Boiler softener. Set it to wash softener each week.

5. Salt box, keep water is full and keep you can see salt in box, so that guarantee salt content is
enough.