3 Level Programme

ID Task Name Duration Start Finish Predecessors Successors 16 Apr '17 7 May '17 28 May '17 18 Jun '17 9 Jul '17
M T W T F S S M T W T
1 3 LEVEL PROGRAMME 59 days Mon 8/5/17 Wed 5/7/17
2 Transfer Plate Completion 11 days Mon 8/5/17 Thu 18/5/17 63
3 Zone 1 0 days Mon 8/5/17 Mon 8/5/17 4FS+11 days,8 8/5
4 Zone 2 0 days Thu 18/5/17 Thu 18/5/17 3FS+11 days 36 18/5
5 Typical Floor (Units Floor) 59 days Mon 8/5/17 Wed 5/7/17
6 Level 7 32 days Mon 8/5/17 Thu 8/6/17
7 Zone 1 18 days Mon 8/5/17 Thu 25/5/17
8 Setting Out 1 day Mon 8/5/17 Mon 8/5/17 3 9,22
9 Rebar (90% at ground) (prefer 1 floor around 4m) 2 days Tue 9/5/17 Wed 10/5/17 8 10
10 Side Formwork 2 days Thu 11/5/17 Fri 12/5/17 9 11
11 Installation of M&E in wall 1 day Sat 13/5/17 Sat 13/5/17 10 12
12 2nd Side Formwork 1 day Sun 14/5/17 Sun 14/5/17 11 13
13 Slab Formwork 2 days Mon 15/5/17 Tue 16/5/17 12 14
14 1st BRC 2 days Wed 17/5/17 Thu 18/5/17 13 15
15 Installation of M&E in slab 1 day Fri 19/5/17 Fri 19/5/17 14 16
16 Top BRC 2 days Sat 20/5/17 Sun 21/5/17 15 17
17 Drop/Panel 1 day Mon 22/5/17 Mon 22/5/17 16 18
18 Inspection 1 day Tue 23/5/17 Tue 23/5/17 17 19
19 Casting 1 day Wed 24/5/17 Wed 24/5/17 18 20,66
20 Strip & Re-erect Props 1 day Thu 25/5/17 Thu 25/5/17 19
21 Zone 2 18 days Tue 9/5/17 Fri 26/5/17
22 Setting Out 1 day Tue 9/5/17 Tue 9/5/17 8 23,36
23 Rebar (90% at ground) (prefer 1 floor around 4m) 2 days Wed 10/5/17 Thu 11/5/17 22 24
24 Side Formwork 2 days Fri 12/5/17 Sat 13/5/17 23 25
25 Installation of M&E in wall 1 day Sun 14/5/17 Sun 14/5/17 24 26
26 2nd Side Formwork 1 day Mon 15/5/17 Mon 15/5/17 25 27
27 Slab Formwork 2 days Tue 16/5/17 Wed 17/5/17 26 28
28 1st BRC 2 days Thu 18/5/17 Fri 19/5/17 27 29
29 Installation of M&E in slab 1 day Sat 20/5/17 Sat 20/5/17 28 30
30 Top BRC 2 days Sun 21/5/17 Mon 22/5/17 29 31
31 Drop/Panel 1 day Tue 23/5/17 Tue 23/5/17 30 32
32 Inspection 1 day Wed 24/5/17 Wed 24/5/17 31 33
33 Casting 1 day Thu 25/5/17 Thu 25/5/17 32 34,80
34 Strip & Re-erect Props 1 day Fri 26/5/17 Fri 26/5/17 33
35 Zone 3 18 days Fri 19/5/17 Mon 5/6/17
36 Setting Out 1 day Fri 19/5/17 Fri 19/5/17 22,4 37,50
37 Rebar (90% at ground) (prefer 1 floor around 4m) 2 days Sat 20/5/17 Sun 21/5/17 36 38
38 Side Formwork 2 days Mon 22/5/17 Tue 23/5/17 37 39
39 Installation of M&E in wall 1 day Wed 24/5/17 Wed 24/5/17 38 40
40 2nd Side Formwork 1 day Thu 25/5/17 Thu 25/5/17 39 41
41 Slab Formwork 2 days Fri 26/5/17 Sat 27/5/17 40 42
42 1st BRC 2 days Sun 28/5/17 Mon 29/5/17 41 43
43 Installation of M&E in slab 1 day Tue 30/5/17 Tue 30/5/17 42 44
44 Top BRC 2 days Wed 31/5/17 Thu 1/6/17 43 45
45 Drop/Panel 1 day Fri 2/6/17 Fri 2/6/17 44 46
46 Inspection 1 day Sat 3/6/17 Sat 3/6/17 45 47
47 Casting 1 day Sun 4/6/17 Sun 4/6/17 46 48,94
48 Strip & Re-erect Props 1 day Mon 5/6/17 Mon 5/6/17 47
49 Zone 4 18 days Sat 20/5/17 Tue 6/6/17
50 Setting Out 1 day Sat 20/5/17 Sat 20/5/17 36 51
51 Rebar (90% at ground) (prefer 1 floor around 4m) 2 days Sun 21/5/17 Mon 22/5/17 50 52
52 Side Formwork 2 days Tue 23/5/17 Wed 24/5/17 51 53
53 Installation of M&E in wall 1 day Thu 25/5/17 Thu 25/5/17 52 54
54 2nd Side Formwork 1 day Fri 26/5/17 Fri 26/5/17 53 55
55 Slab Formwork 2 days Sat 27/5/17 Sun 28/5/17 54 56
56 1st BRC 2 days Mon 29/5/17 Tue 30/5/17 55 57
57 Installation of M&E in slab 1 day Wed 31/5/17 Wed 31/5/17 56 58
58 Top BRC 2 days Thu 1/6/17 Fri 2/6/17 57 59
59 Drop/Panel 1 day Sat 3/6/17 Sat 3/6/17 58 60
60 Inspection 1 day Sun 4/6/17 Sun 4/6/17 59 61
61 Casting 1 day Mon 5/6/17 Mon 5/6/17 60 62,108
62 Strip & Re-erect Props 1 day Tue 6/6/17 Tue 6/6/17 61
63 Sky Garden at Level 7 21 days Fri 19/5/17 Thu 8/6/17 2 108
64 Level 8 29 days Thu 25/5/17 Thu 22/6/17
65 Zone 1 14 days Thu 25/5/17 Wed 7/6/17

Prepared By: HSB ENG SDN BHD Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress

Page 1
3 Level Programme
ID Task Name Duration Start Finish Predecessors Successors 16 Apr '17 7 May '17 28 May '17 18 Jun '17 9 Jul '17
M T W T F S S M T W T
66 Setting Out 1 day Thu 25/5/17 Thu 25/5/17 19 67SS,80
67 Rebar (90% at ground) (prefer 1 floor around 4m) 2 days Thu 25/5/17 Fri 26/5/17 66SS 68
68 Side Formwork 1 day Sat 27/5/17 Sat 27/5/17 67 69
69 Installation of M&E in wall 1 day Sun 28/5/17 Sun 28/5/17 68 70
70 2nd Side Formwork 1 day Mon 29/5/17 Mon 29/5/17 69 71
71 Slab Formwork 2 days Tue 30/5/17 Wed 31/5/17 70 72
72 1st BRC 1 day Thu 1/6/17 Thu 1/6/17 71 73
73 Installation of M&E in slab 1 day Fri 2/6/17 Fri 2/6/17 72 74
74 Top BRC 1 day Sat 3/6/17 Sat 3/6/17 73 75
75 Drop/Panel 1 day Sun 4/6/17 Sun 4/6/17 74 76
76 Inspection 1 day Mon 5/6/17 Mon 5/6/17 75 77
77 Casting 1 day Tue 6/6/17 Tue 6/6/17 76 78,123
78 Strip & Re-erect Props 1 day Wed 7/6/17 Wed 7/6/17 77
79 Zone 2 14 days Fri 26/5/17 Thu 8/6/17
80 Setting Out 1 day Fri 26/5/17 Fri 26/5/17 66,33 81SS,94
81 Rebar (90% at ground) (prefer 1 floor around 4m) 2 days Fri 26/5/17 Sat 27/5/17 80SS 82
82 Side Formwork 1 day Sun 28/5/17 Sun 28/5/17 81 83
83 Installation of M&E in wall 1 day Mon 29/5/17 Mon 29/5/17 82 84
84 2nd Side Formwork 1 day Tue 30/5/17 Tue 30/5/17 83 85
85 Slab Formwork 2 days Wed 31/5/17 Thu 1/6/17 84 86
86 1st BRC 1 day Fri 2/6/17 Fri 2/6/17 85 87
87 Installation of M&E in slab 1 day Sat 3/6/17 Sat 3/6/17 86 88
88 Top BRC 1 day Sun 4/6/17 Sun 4/6/17 87 89
89 Drop/Panel 1 day Mon 5/6/17 Mon 5/6/17 88 90
90 Inspection 1 day Tue 6/6/17 Tue 6/6/17 89 91
91 Casting 1 day Wed 7/6/17 Wed 7/6/17 90 92,137
92 Strip & Re-erect Props 1 day Thu 8/6/17 Thu 8/6/17 91
93 Zone 3 14 days Mon 5/6/17 Sun 18/6/17
94 Setting Out 1 day Mon 5/6/17 Mon 5/6/17 80,47 95SS,108
95 Rebar (90% at ground) (prefer 1 floor around 4m) 2 days Mon 5/6/17 Tue 6/6/17 94SS 96
96 Side Formwork 1 day Wed 7/6/17 Wed 7/6/17 95 97
97 Installation of M&E in wall 1 day Thu 8/6/17 Thu 8/6/17 96 98
98 2nd Side Formwork 1 day Fri 9/6/17 Fri 9/6/17 97 99
99 Slab Formwork 2 days Sat 10/6/17 Sun 11/6/17 98 100
100 1st BRC 1 day Mon 12/6/17 Mon 12/6/17 99 101
101 Installation of M&E in slab 1 day Tue 13/6/17 Tue 13/6/17 100 102
102 Top BRC 1 day Wed 14/6/17 Wed 14/6/17 101 103
103 Drop/Panel 1 day Thu 15/6/17 Thu 15/6/17 102 104
104 Inspection 1 day Fri 16/6/17 Fri 16/6/17 103 105
105 Casting 1 day Sat 17/6/17 Sat 17/6/17 104 106,151
106 Strip & Re-erect Props 1 day Sun 18/6/17 Sun 18/6/17 105
107 Zone 4 14 days Fri 9/6/17 Thu 22/6/17
108 Setting Out 1 day Fri 9/6/17 Fri 9/6/17 94,61,63 109SS
109 Rebar (90% at ground) (prefer 1 floor around 4m) 2 days Fri 9/6/17 Sat 10/6/17 108SS 110
110 Side Formwork 1 day Sun 11/6/17 Sun 11/6/17 109 111
111 Installation of M&E in wall 1 day Mon 12/6/17 Mon 12/6/17 110 112
112 2nd Side Formwork 1 day Tue 13/6/17 Tue 13/6/17 111 113
113 Slab Formwork 2 days Wed 14/6/17 Thu 15/6/17 112 114
114 1st BRC 1 day Fri 16/6/17 Fri 16/6/17 113 115
115 Installation of M&E in slab 1 day Sat 17/6/17 Sat 17/6/17 114 116
116 Top BRC 1 day Sun 18/6/17 Sun 18/6/17 115 117
117 Drop/Panel 1 day Mon 19/6/17 Mon 19/6/17 116 118
118 Inspection 1 day Tue 20/6/17 Tue 20/6/17 117 119
119 Casting 1 day Wed 21/6/17 Wed 21/6/17 118 120,165
120 Strip & Re-erect Props 1 day Thu 22/6/17 Thu 22/6/17 119
121 Level 9 29 days Wed 7/6/17 Wed 5/7/17
122 Zone 1 14 days Wed 7/6/17 Tue 20/6/17
123 Setting Out 1 day Wed 7/6/17 Wed 7/6/17 77 124SS,137
124 Rebar (90% at ground) (prefer 1 floor around 4m) 2 days Wed 7/6/17 Thu 8/6/17 123SS 125
125 Side Formwork 1 day Fri 9/6/17 Fri 9/6/17 124 126
126 Installation of M&E in wall 1 day Sat 10/6/17 Sat 10/6/17 125 127
127 2nd Side Formwork 1 day Sun 11/6/17 Sun 11/6/17 126 128
128 Slab Formwork 2 days Mon 12/6/17 Tue 13/6/17 127 129
129 1st BRC 1 day Wed 14/6/17 Wed 14/6/17 128 130
130 Installation of M&E in slab 1 day Thu 15/6/17 Thu 15/6/17 129 131

Prepared By: HSB ENG SDN BHD Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress

Page 2
3 Level Programme
ID Task Name Duration Start Finish Predecessors Successors 16 Apr '17 7 May '17 28 May '17 18 Jun '17 9 Jul '17
M T W T F S S M T W T
131 Top BRC 1 day Fri 16/6/17 Fri 16/6/17 130 132
132 Drop/Panel 1 day Sat 17/6/17 Sat 17/6/17 131 133
133 Inspection 1 day Sun 18/6/17 Sun 18/6/17 132 134
134 Casting 1 day Mon 19/6/17 Mon 19/6/17 133 135
135 Strip & Re-erect Props 1 day Tue 20/6/17 Tue 20/6/17 134
136 Zone 2 14 days Thu 8/6/17 Wed 21/6/17
137 Setting Out 1 day Thu 8/6/17 Thu 8/6/17 123,91 138SS,151
138 Rebar (90% at ground) (prefer 1 floor around 4m) 2 days Thu 8/6/17 Fri 9/6/17 137SS 139
139 Side Formwork 1 day Sat 10/6/17 Sat 10/6/17 138 140
140 Installation of M&E in wall 1 day Sun 11/6/17 Sun 11/6/17 139 141
141 2nd Side Formwork 1 day Mon 12/6/17 Mon 12/6/17 140 142
142 Slab Formwork 2 days Tue 13/6/17 Wed 14/6/17 141 143
143 1st BRC 1 day Thu 15/6/17 Thu 15/6/17 142 144
144 Installation of M&E in slab 1 day Fri 16/6/17 Fri 16/6/17 143 145
145 Top BRC 1 day Sat 17/6/17 Sat 17/6/17 144 146
146 Drop/Panel 1 day Sun 18/6/17 Sun 18/6/17 145 147
147 Inspection 1 day Mon 19/6/17 Mon 19/6/17 146 148
148 Casting 1 day Tue 20/6/17 Tue 20/6/17 147 149
149 Strip & Re-erect Props 1 day Wed 21/6/17 Wed 21/6/17 148
150 Zone 3 14 days Sun 18/6/17 Sat 1/7/17
151 Setting Out 1 day Sun 18/6/17 Sun 18/6/17 137,105 152SS,165
152 Rebar (90% at ground) (prefer 1 floor around 4m) 2 days Sun 18/6/17 Mon 19/6/17 151SS 153
153 Side Formwork 1 day Tue 20/6/17 Tue 20/6/17 152 154
154 Installation of M&E in wall 1 day Wed 21/6/17 Wed 21/6/17 153 155
155 2nd Side Formwork 1 day Thu 22/6/17 Thu 22/6/17 154 156
156 Slab Formwork 2 days Fri 23/6/17 Sat 24/6/17 155 157
157 1st BRC 1 day Sun 25/6/17 Sun 25/6/17 156 158
158 Installation of M&E in slab 1 day Mon 26/6/17 Mon 26/6/17 157 159
159 Top BRC 1 day Tue 27/6/17 Tue 27/6/17 158 160
160 Drop/Panel 1 day Wed 28/6/17 Wed 28/6/17 159 161
161 Inspection 1 day Thu 29/6/17 Thu 29/6/17 160 162
162 Casting 1 day Fri 30/6/17 Fri 30/6/17 161 163
163 Strip & Re-erect Props 1 day Sat 1/7/17 Sat 1/7/17 162
164 Zone 4 14 days Thu 22/6/17 Wed 5/7/17
165 Setting Out 1 day Thu 22/6/17 Thu 22/6/17 151,119 166SS
166 Rebar (90% at ground) (prefer 1 floor around 4m) 2 days Thu 22/6/17 Fri 23/6/17 165SS 167
167 Side Formwork 1 day Sat 24/6/17 Sat 24/6/17 166 168
168 Installation of M&E in wall 1 day Sun 25/6/17 Sun 25/6/17 167 169
169 2nd Side Formwork 1 day Mon 26/6/17 Mon 26/6/17 168 170
170 Slab Formwork 2 days Tue 27/6/17 Wed 28/6/17 169 171
171 1st BRC 1 day Thu 29/6/17 Thu 29/6/17 170 172
172 Installation of M&E in slab 1 day Fri 30/6/17 Fri 30/6/17 171 173
173 Top BRC 1 day Sat 1/7/17 Sat 1/7/17 172 174
174 Drop/Panel 1 day Sun 2/7/17 Sun 2/7/17 173 175
175 Inspection 1 day Mon 3/7/17 Mon 3/7/17 174 176
176 Casting 1 day Tue 4/7/17 Tue 4/7/17 175 177
177 Strip & Re-erect Props 1 day Wed 5/7/17 Wed 5/7/17 176

Prepared By: HSB ENG SDN BHD Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress

Page 3