WHEREAS, the DENR Administrative Order No. 30, Series of 2003 and
its revised procedural manual, ensure that environmental considerations were
incorporated into the Environmental Impact Assessment (EIA) process at an
early stage to streamline the current procedure in the conduct of the EIA
process to improve the effectiveness as a planning, regulatory and management
tool, and enhance maximum public participation.
96-37 and integrating such definition in the LLDA Rules and Regulations,
thereby clarifying further the development activities to secure LLDA Clearance),
Board Resolution No. 223, Series of 2004, (Further clarifying the definition of
development activities required to secure LLDA Clearance) and Board
Resolution No. 286, Series of 2006 (Adopting the Reckoning Period for
Imposition of Administrative Fine for Operating without Valid LLDA Clearance
and Discharge Permit), shall be modified or amended accordingly through this
board resolution;
FINALLY, all existing rules and regulations which are inconsistent with
this Resolution are hereby revoked, modified and repealed accordingly.
This Board Resolution shall take effect thirty (30) days upon publication
in a newspaper of general circulation and to be registered in the U.P. Law
Centers National Administrative Register.
RODRIGO E. CABRERA
Vice-Chairman
ATTESTED BY:
SECTION 3. SCOPE and COVERAGE. These IRR shall cover all those
developmental and productive economic activities within the Laguna de Bay
Region, except those productive economic activities within the 12.5 meter
elevation otherwise known as the shoreland of Laguna de Bay as defined under
Section 41 of R.A. 4850 as amended.
4.3. Discharge - includes, but is not limited to, the act of spilling,
leaking, pumping, pouring, emitting, emptying, releasing or
dumping of any material into a water body or onto land from which
it might flow or drain into said water.
4.8. Laguna de Bay Shoreland Area also known as the buffer zone is
that part of the lakebed along the lakeshore lying at elevation 12.50
meters and below and alternately submerged or exposed by the
normal annual rising and lowering of the lake levels. Datum
elevation is a point 10.00 meters below Mean Lower Low Water
(M.L.L.W). This is a linear strip of open space designed to separate
incompatible elements or uses, or to control pollution/nuisance and
for identifying and defining development areas or zones.
4.10. Waste any material either solid, liquid, semisolid, contained gas
or other forms resulting from industrial, commercial, mining or
agricultural operations, or from community and household activities
that is devoid of usage and discarded.
5.4.3. Fuel stations, fuel depots, fuel storage and refilling facilities,
and other similar services;
6.1.1. Has not ceased operations for a period of Two (2) consecutive
years since 1976;
Upon filling of application, the proponent shall pay the processing fee and the
applicable clearance fee in accordance with the schedule of fees listed under
B.R. 224, Series of 2004 (Annex C), any proposed change in the fees and
charges shall be covered by another Board Resolution.
If the previous application has been declared suspended and revoked pursuant
to Section 10 of this IRR, the proponent shall submit a new application and
pay anew the processing fees for LC and such fines and penalties as may be
imposed thereon.
Any and all proposed, ongoing or completed expansion inconsistent with the
previously issued LC of an establishment shall be covered by a new LC.
Change of name/ownership shall require an establishment to apply for an
amendment of the previously issued LC
After due notice and hearing, the Authority may suspend or revoke any valid
clearance on the following grounds:
10.5. Other lawful and valid causes and grounds provided by law.
RULE IV SANCTIONS
However, for those previously exempted by Board Resolution No. 223 series of
2004, no administrative fine shall be imposed against establishments; provided
that an application for LLDA Clearance has been filed within Six (6) months
upon the effectivity of this issuance.
The imposition of administrative fine does not preclude the Authority from
issuing any order or from instituting appropriate civil or criminal action in
court as the circumstances may warrant.
SECTION 13. EFFECTIVITY. This IRR shall take effect thirty (30) days upon
publication in a newspaper of general circulation.
ANNEX A
Application Form
PCS 1
Name of Establishment :
Tax Identification Number (TIN): Year Established/Operated:
Business Address:
Number and Street: Barangay:
City/Town: Province and Zip Code:
Tel. No.: Fax No.:
Location of Project/Development:
Number and Street: Barangay:
City/Town: Province and Zip Code:
Sub-basin:
I certify that the information above and on the following parts are true, complete and
accurate to the best of my knowledge.
____________________________ __________________________
Signature of Agent Signature of Chief Executive Officer
_____________________________ _______________________________
Title Title
Date: _______________________ Date: _______________________
1. Business Activity - complete a separate form for each major business activity
occurring on the premises.
a. Industrial
Business Activity: ________________________________ PSIC: __________
Capital Investment/Total Project Cost: P _______________ Area: ___________
Raw Materials
_______________________ _____ _____ _____ _____ _____ _____
_______________________ _____ _____ _____ _____ _____ _____
_______________________ _____ _____ _____ _____ _____ _____
_______________________ _____ _____ _____ _____ _____ _____
b. Agricultural
Type: Piggery ( ) Poultry Farm ( ) Duck Farm ( )
Others, specify__________________________________
c. Subdivision/Condominium/Housing Devt.
Project Name : ________________________________________________
Location : ___________________________________________________
Area : ___________________________________ has. ______________
No. of units/rooms : ____________________________________________
d. Institution
Area : _______________________________________________________
Location : ____________________________________________________
No. of rooms/stalls/beds : ________________________________________
e. Other Projects
Type : _______________________________________________________
Area/Capacity: _________________________________________________
/APP_LC2.DOC/ 10 July 98
- 3 -
Production Time :
No. of hours/day : ___________________________ shifts/day__________
No. of days/month : _____________________________________________
No. of months/year : ____________________________________________
NOTARY PUBLIC
/APP_LC2.DOC/ 10 July 98
ANNEX B
TABLE OF CONTENTS
2. PROJECT DESCRIPTION
2.1.Project Location and Area (Show title, legend, scale, project location
and political boundaries (from sitio/barangay to region)
CLIENT AGENCY
Step Activity Activity Division/Person Duration of
Responsible Activity
1 Secures, fills-up, Provides forms, Clearance and 20 minutes
and submits checklist of Permits Division
application form requirements, and (CPD) / Licensing
and requirements schedule of fees Officer
(Includes explanation
of requirements and
process).
Evaluates submitted CPD / Engineer 20 minutes
documents. (Includes
evaluation and
checking of
correctness of the
documents submitted
according to form and
substance)
Assesses and approves Finance / 20 minutes
fees. Accountant
(Includes recording in
the ledger)
2 Pays fees Receives payment and Finance / 10 minutes
issues Official Receipt Cashier
(Includes checking of
bills to determine
genuineness, encoding
of official receipt
number, date, and
amount paid)
Receives application CPD / Licensing 5 minutes
and issues claim stub Officer
Evaluates technical CPD / Engineer 20 WD
documents and
prepares evaluation
report and LC/LX.
(Includes technical
review of project
proposal description
and conduct of on-site
inspection)
Reviews and approves CPD / Head 1 hour
evaluation report and
recommends approval
of LC/LX
Approves LC/LX and OGM / GM 4 hours
affixes LLDA dry seal.
(Includes the review of
the evaluation report
and determination of
extent of complete
staff work given to the
evaluation of the
submitted documents)
3 Receives LC/LX Releases LC/LX OGM / Clerk 10 minutes
LC Exemption and LC Amendment Application Process
CLIENT AGENCY
Step Activity Activity Division/Person Duration of
Responsible Activity
1 Secures, fills-up, Provides forms, CPD / Licensing 20 minutes
and submits checklist of Officer
application form requirements, and
and requirements schedule of fees
(Includes explanation
of requirements and
process)
Evaluates submitted CPD / Engineer 20 minutes
documents. (Includes
evaluation and
checking of
correctness of the
documents submitted
according to form and
substance)
Assesses and approves Finance / 20 minutes
fees. (Includes the Accountant
review and evaluation
of data that will be
used in the
computation of fees
and recording in the
ledger)
2 Pays fees Receives payment and Finance / 10 minutes
issues Official Receipt Cashier
(Includes checking of
bills to determine
genuineness, encoding
of official receipt
number, date, and
amount paid)
Receives application CPD / Licensing 5 minutes
and issues claim stub Officer
Evaluates project CPD / Engineer 8 WD
description, prepares
evaluation report and
LE/LA. (Includes
technical review of
project proposal
description and
conduct of on-site
inspection, if
necessary)
Reviews and approves CPD / Head 1 hour
evaluation report and
recommends approval
of LE/LA
Approves LE/LA and OGM / GM 4 hours
affixes LLDA dry seal
3 Receives LE/LA Releases LE/LA OGM / Clerk 10 minutes
ANNEX E
Type of Application - Sub Basin Year Applied - Sequential No. PSIC Code
Example 1:
First application of LLDA Clearance, for hog farming at Rodriguez, Rizal applied
on year 2010
Example 2: