SAP_HR 604 87
EA-HR 606 49
TARGET
SAP_HR 604 98
EA-HR 606 60
PRE REQUISITE
SL Toolset
PATCHES
Status
Generate stack file only for HR Patches using
Maintenance Planner
Download Patches
Copy stack XML file and Patches in EPS/in Directory
PRE-CHECKS
PROCESS
Start Upgrading using SUM in Development
POST PROCESSING
Release all the background jobs (BTCTRNS2)
Run SGEN ( SGEN compiles all programs.SGEN reduces ABAP load on the system)
Take full Backup
PLANNING A SYSTEM UPDATE OR UPGRADE USING MAINTENANCE PLANNER
Prerequisites
To perform any kind of update or upgrade, the system should be in a Verified state,
indicating that the
System description complies with SAP product modelling
Maintenance Planner
https://support.sap.com/solution-manager/processes/maintenance-
management/maintenance-planner.html
In the above Link lick on Maintenance Planner we reach the below screen
https://apps.support.sap.com/sap(bD1lbiZjPTAwMQ==)/support/mp/index.html
Choose the System (ERD) Currently the system is not in Verified state
Click on the system ERD we get the screen below
Click Verify
I have selected SCC-DIMP 606 from Planning and clicked confirm on top right corner
I have selected Ignore IW BEP 200 from planning and clicked confirm.
Click Next
There was a popup in the above screen which disappeared in few seconds
I clicked Next
I clicked on Download Correction File which was getting downloaded at bottom left corner
I clicked on the Circle on top left corner
I have made the changes with the help of Gordon and verified all ERP systems
NEW
Click Plan
Select EHP6 for SAP ERP 6.0 (Selected this because we are only updating HR Patches) and
select the current the current SP Level.
Click Confirm Selection
Expanded ABAP then unchecked all and just selected SAP_HR & EA-HR
Then Clicked on on top right corner got the popup below in which I have
clicked on Select ALL and then clicked OK