You are on page 1of 10

9/28/2014

Lecture Overview
Introduction to Value Management (VM)
Value Management
The VM History
Topic Key Terms
Introduction to Value Management Definition of VM
Principles of VM
Lecturer VM Approach
Assoc. Prof. Wan Yusoff Wan Mahmood
Benefit of VM

Lecture Overview The VM History

Principles of VM Application Develop by Larry Miles during second world war


(1940s) at GEC, US.
When to Apply VM
Miles apply a functional approach to purchasing
Barriers in VM Implementation
by the comparison of alternate material on the
Approaches to VM functions required to perform by them.
Critical Success Factors The systems approach would involve value
Integrating VM in Construction and analysis that lead the name to Value
Analysis which initially developed around the
existing products.
INSPIRING CREATIVE AND INNOVATIVE MINDS

The VM History The VM History


US Navy start using the procedure in 1954. The VE first entered the construction industry in
Navy Engineering team then called the early 1960s when VE incentive provision were
technique Value Engineering as the included in construction contract.
technique was applied in the engineering field
During late 1960s and early 1970s VE begin to
at the design and specification stage.
be used during the design stage of
Over the time, VE used by other division of construction project.
the department of defence.
Over the past decade, there has been a trend
The growth in VE practice through different toward applying value techniques at earlier
government agencies and private industry led stage in a project life cycle.
to the establishment of SAVE in 1958.

1
9/28/2014

The VM History Key Terms


To distinguish this activity, the term value The approach taken when using VM
planning used for early conceptual design techniques differs according to the stages of
stage. the project life cycle at which it is applied.
Some authors and practitioners in later year Thus, it would be useful to be able to
then term this technique as Value differentiate between the type of approach
Management and wide separate usage in appropriate to each stage by defining them
Australia, New Zealand and U.K. However, the with different terms.
term Value Engineering is still used in North
America, many European countries and Japan.

Key Terms Typical Terms for VM Studies at Different Stages


TERMS TERMINOLOGY
VALUE MANAGEMENT
Value Management The title given to the full range of value techniques available. VALUE PLANNING VALUE VALUE
It is a higher order title and is not linked to a particular project ENGINEERING ANALYSIS
stage at which value techniques may be applied. (Strategic)

BRIEFING SKETCH PLAN WORKING DRAWING CONSTRUCTION POST-


CONSTRUCTION
Value Planning Refers to the value techniques applied during the planning
phases of a project. This is conducted during the briefing and
Inception Feasibility Outline Scheme Detail Production Bills of Tender Construction Post-Occupancy
sketch plan stage of a RIBA plan of work. Proposals Design Design Information Quantities Action Evaluation

Value Engineering The title given to value techniques applied during the design or
engineering phases of a project. It is conducted during the Royal Institute of British Architects (RIBA) Plan of Work
detail design and construction stage of the RIBA plan of
CONCEPT SCHEMATIC PRODUCTION CONSTRUCTION POST-
work. CONSTRUCTION

Value Analysis The title given to value techniques applied retrospectively to


Programming Program Schematic Design Design Construction Bidding Construction Post-Occupancy
completed projects to analyze or audit the project Evaluation Development Documents Action Evaluation
performance. The studies are conducted during the post-
construction related procedures and processes.
American Institute of Architects (AIA) Plan of Work

Definition of VM Definition of VM

Miles in the original context of value Mudge (1971) defines as a


management define as a philosophy systematic application of recognized
implemented by the use of a specific techniques which identify the
set of techniques, a body of function of a product or service,
knowledge, and a group of learned establish a monetary value for that
skills function, and provide the necessary
function reliably at lowest overall
cost

2
9/28/2014

Definition of VM Definition of VM

Value management is a systematic,


Dell Isola (1982) later simplified multi-disciplinary effort directed
the definition as, the creative toward analyzing the function of
organized approach whose projects for the purpose of achieving
objectives is to optimize the cost the best value at the lowest overall
and/or performance of a facility
or system life cycle project cost
(Norton & McElligott, 1995)

Definition of VM Definition of VM
Value management a proactive, Value management A structured and
creative, problem-solving service, analytical process which seeks to
using a multi disciplinary team achieve value for money by
oriented approach to make explicit providing all the necessary functions
the clients value system, at targeted at the lowest total cost consistent
stages through the development of a with required levels of quality and
project performance
(Kelly & Male, 1993) (Australia/New Zealand Standard AS/NZS 4183:1994)

Definition of VM Principles of VM
Value management is a style of Based on the above definition, its
management, particularly dedicated can be summarize that VM have the
to motivating people, developing following principles:
skills and promoting synergies and Structured process
innovation, with the aim of Cross disciplinary team
maximizing the overall performance Function based
of an organization Value
(European Standard EN 12973:2000)
Life cycle cost

3
9/28/2014

VM as Structured Process VM as Structured Process


The VM process uses tested and successful Thought Processes
procedures that are directed toward achieving
success in meeting the purposes for the project Creative
Analytical
by all involved.
The process instills common understanding, 1 - Analyse information 2 - Brainstorm Functions
generates high production and high performing
team activities, reduces the time necessary to 3 - Organise Functions 4 - Generate Ideas for
obtain a product, and focuses the effort on the Alternatives
purposes behind the project or activity being 5 - Evaluate Alternatives

studied. 6 - Develop Proposals


7 - Appraise Options
A standard job plan is used to guide the
entire process. 8 - Recommend Solutions

Cross Disciplinary Team Cross Disciplinary Team


A VM study is a multi-disciplinary Distinct Perspectives
effort. Comprehensive Approach
Shared Vision
It involves bringing together as a Consensus
team, a group of individuals who
collectively analyze all aspects of
the project under study.
They work together as a group
under the direction of VMTC who
lead them through VM job plan.

Cross Disciplinary Team What does the facilitator do?


Participant selection & stakeholder involvement is key to Lead the VM study process
success
Typical Team: Ensure there is an agreed desired outcome
Facilitator Advise on team selection
Client Commercial Manager Design appropriate VM study activities and
Client Representative structure
End user Ensure adequate preparation and information
Project Manager gathering
Cost Manager Lead the workshop process and generate shared
Planner understanding
Designer Ensure open, free and diverse contribution
Contractor Broker consensus decisions
Risk Manager
Other stakeholders
Apply the VM process to achieve team success

4
9/28/2014

Function Based Function Based


One of the most unique and useful The main functional purpose for
qualities of the VM is its use of the component being studied is the
functions to describe the activity or primary function.
product being studied. Things often happen as a result of
The value study breaks the project the choice of a component, or
into components so as to avoid something must be done to make
misunderstanding of the planned the selected component work as
intents for the project. needed. These functions are called
supporting or secondary functions.

What is a Function? Value


Expression of the need in terms of performances Common sense says that value relates what
you get to what you pay
rather than solutions
In value management common sense applies
Link between the need and the product and so value breaks down into a balance of
three things:
Basis of creative problem solving in VM
Performance : How well are those needs
Need met?
Expectation : What must the service do to
meet user/stakeholder expectation?
FUNCTION
Resource : What must be committed to
secure the service

Concept of Value Categories of Value


According to Carlos Fallon, Worth Esteem Value
Value = Cost The monetary sum an owner or
Value The most cost effective way to reliably
accomplish a function that will meet the users needs, user is willing to pay for prestige
desires and expectation. or appearance.
Worth The least cost of providing the needed The motivated desire to process
function and the required performance and is found
by means of comparison of costs of units which are
for the sake of possession.
functionally equivalent. The worth of sell function.
Cost The life cycle cost of a product/project.

5
9/28/2014

Categories of Value Categories of Value

Exchange Value Use Value


The monetary sum for which a The cost of basic function only.
product or service can be The monetary measure of a
traded or exchanged usefulness of a product or
Also the market value at a given service.
point of time.

How to Improve Value Life Cycle Cost


There are three major ways to improve
value by applying VM: The true cost of an item is not just
To provide for all the required project the amount of money that you
function but at reduced cost. pay when you buy it. Much more
is involved.
To provide additional desirable project
functions without adding cost. When you buy something, you
also buy its long-term effects.
To provide additional desirable project
functions while at same time reducing The initial costs plus these long-
cost. term costs are call life-cycle cost.

Life Cycle Cost Life Cycle Cost


LCC is a technique used during VM Where are the Hidden Costs?
study and its focuses on the total cost.
The Client
Total Cost = Initial Cost + Follow on Site
Cost
cost Fees Capital cost

Follow on costs (or Ownership cost) are Occupancy Furnishing

all the associated cost of running the Cost Energy

facility. It covers energy, maintenance, Maintenance


Cost
Cost
Operating
repair replacement, staffing, Etc. Cost

6
9/28/2014

Life Cycle Costing VM Approach


Life Cycle Costing VM is a team based management approach
For a 160 bed Hospital - Life span is 25 years which:
Case 1 : Initial Cost = RM 124 Millions
Identifies the required performance to
satisfy the business and stakeholder
needs; and
Determines the most appropriate
solution to suit the performance.

Conventional Approach Vs. Benefit of VM


VM Approach

INDIVIDUAL EFFORTS
Promote
System
Thinking
Project Staff
Optimize
Manager Designer Owner User Engineers Cost
Develop-
ment

Improve Why use Establish


Communi- Customer
cation VM? Needs
VM APPROACH
VM TEAM EFFORT
Identify &
Remove Vehicles for
Unneces- Change
sary Cost

VMCP

SOLUTION

Projects that Benefit from VM Principles of VM Application


Generally the types of projects benefiting most VM interventions should be undertaken when:
from Value Management include:
Costly Projects Key decisions need to be made
Conflicts or problems need to be resolved
Complex Projects Consensus needs to be achieved
Repetitive Projects Team building is required
Cost or Time overruns need to be
Projects with compressed Program addressed
Projects with Restricted Budgets Other identified benefits need to be
secured
Projects with High Visibility

7
9/28/2014

Principles of VM Application When to apply VM ?

VM should be applied flexibly to


reflect project needs
All facilitators should be trained Cost
Potential
Saving
or
Interventions will generally benefit Saving
Cost of
from independent facilitation Change

Interventions need to be
sufficiently broad to reflect all Planning Schematic
&
Analysis
Design
Design Working
Development Drawings
Construction
Documents Construction
Operation
&
Maintenance

project interests Project Life Cycle

Barriers in VM Implementation Approaches to VM


Too There are four basic approaches, by which
Expensive
VM can be implemented:
Waste of
No Time
Time
An in house programmed in which all of
the team as well as the VMTC are
employee of the organization.
Too The Not
Difficult Barriers Interested
In-house team members and an external
VMTC or facilitator.
Too I Do it
In-house team member supplemented by
Complex Anyway experts who cannot be provided by an in-
Dont
Want house organization as well as an external
Outsider
VMTC or facilitator.

Approaches to VM VM Critical Success Factors


Structured approach - follow an approved
VM job plan
A predominantly external group of The study should involved a multi-
individuals to conduct the VM study. disciplinary team with some VM
The group would consist of all of the knowledge
member of VM team as well as VM study should be facilitated or lead by
VMTC or facilitator together with a qualified VMTC/Facilitation skill
some in-house representation.
Does not pursue any changes which
detract from the projects requirement
or basic functions.

8
9/28/2014

How to assure the success


VM Critical Success Factors of the VM Program
Decision taker involved in workshop/
We need the right
study preparation.
Top management support. F
Facilitator
Use of functional analysis. or Leader

Implementation plan. T Timing Information I

Team

Integrating VM in Construction Integrating VM in Construction

Construction involved a huge capital However, merely keeping cost down


investment which incurred a significant is not enough: there is an increasing
fixed costs for not just efficiency but also for
High fixed costs have obvious effectiveness.
ramifications on the price of products or
No matter how efficiently a product
services provided.
or service is provided, it not be
Keeping cost low with traditional cost
successful unless it is wanted it is
management has been commonly
applied to improve competitiveness.
effective!

Integrating VM in Construction Integrating VM in Construction


Therefore, VM should be applied to address
While cost management seeks to do the business strategy issue of whether the
a thing right efficiency, VM seeks construction of a facility represents the best
manner in which to meet the organizations
to do the right thing effectiveness. needs.
VM is thus arguably of greater After decision to build, VM should then
important than, and should address the question of what should be
precede, cost management efforts. constructed to meet the organizational needs
and how to most effectively and efficiently
provide what it is that is to be built.

9
9/28/2014

Integrating VM in Construction Integrating VM in Construction


Value Management is effective in many areas Value Management in construction project
of the construction industry, and it can be should be a continuous process coupled with
utilized at different stages in the life of a formal studies focused on specific issues.
building. Formal studies should be undertaken at a
The greatest potential for the integration of project milestones to informed the review/
VM exists in three key value opportunities approval process, or at other times to suit the
Planning and design circumstances.
Construction The objectives of formal studies will change as
the project proceeds.
Maintenance and operation

Integrating VM in Construction
Value Management confirms achievement of
expectations at each stage of the project, supporting
progress to the next stage.
Typical milestones and the study objectives are
illustrated below:-
Project Stage Possible Objectives

Inception Establish need and required outcome

Concept Improve Strategy

Feasibility and Design Enhance Viability

Implementation and design Maximize cost effectiveness

Use Improve products or processes

10

You might also like