Professional Documents
Culture Documents
Timesheet
Project: ROADS & DRAINAGE FOR SITE 1, PHASE 2 - MAIN ENTRANCE, SITE 2 & DETENTION POND
SITE 6
DAYS WORKED FOR THE WEEK
Sun Mon Tues Wed Thur Fri Sat
No. Name Position Total Hours
19 20 21 22 23 24 25
1 Ganga Bisnauth Tractor Operator 0 10 10 10 10 0 0 40
2 Anthony Sankarsingh Excavator Operator 0 10 10 10 5 10 0 45
3 Ganeshram Samaroo Excavator Operator 0 10 10 5 10 10 0 45
4 Jaswan Samaroo Loader Operator 0 10 10 5 10 10 0 45
5 Premchan Birbal Roller Operator 0 10 10 5 10 10 0 45
6 Duran Balroop Surveyor 0 10 0 10 10 10 10 50
7 Roger Ragbir Surveyor Assistant 0 0 0 10 10 10 0 30
2 Baldeo Seepersad Labourer 0 10 10 10 10 10 10 60
8 Brandon Lee Chong Supervisor 0 10 10 10 10 10 10 60
Construction
9 Darrel Mohammed Manager 0 0 0 0 0 0 0 0