Pallet has been introduced for B515 cond and UPH introduced.

TIMELINE REQUIRED.- micro split up is required.


B515 COND PROJECT
Furnace- monitoring (Time line/ Back up / before after/ hourly monitorin
g (8/6)/ complete report (15/6))
A-ENTRY evap proof leak test2 (
300T die loader implementation. (30 to 20sec)