COST OF PROJECT (ETC) = N 1,784,475,000.00 ELECTRICAL SERVICES COST PROJECT FEES PAYABLE COST AMOUNT PAYABLE % N: K N: K Up to 5M 1.95 5,000,000.00 97,500.00
Up to 10M or part of part thereof 1.75 10,000,000.00 175,000.00
Up to 15M or part thereof 1.55 15,000,000.00 232,500.00
Up to 45M or part thereof 1.35 45,000,000.00 607,500.00
Up to 75M or part thereof 1.15 75,000,000.00 862,500.00 Up to 150m or 1.0 150,000,000.00 1,500,000.00 Part thereof Up to 200m or 0.85 200,000,000 1,700,000.00 Part thereof