Professional Documents
Culture Documents
Department A
Cost of Production Report
For the month of April 2013
Material X Material Y Conversion Cost
Quantity Schedule
Actual Qty WD EUP WD EUP WD EUP
In Process 4/1 15,000.00 100% 15,000.00 0% - 25% 3,750.00
Started 95,000.00
Total 110,000.00
Transferred to Department B
In Process 4/1 15,000.00 0% - 100% 15,000.00 75% 11,250.00 1
Started 85,000.00 100% 85,000.00 100% 85,000.00 100% 85,000.00 1
In Process 4/30 10,000.00 100% 10,000.00 0% - 25% 2,500.00 1
Total 110,000.00 95,000.00 100,000.00 98,750.00 2
Total 5,966,557.96
In Process 4/30
Cost from Dept A 18,000 X 46.303600 833,464.79 1
Material Z 18,000 X 4.488000 80,784.00 1
Skill M 18,000 X 2.514286 45,257.14 1
Skill N 10,800 X 2.292020 24,753.82 1
Overhead 14,400 X 0.211268 3,042.25 987,302.01 1
6,953,859.97 20
50% 100%
Skill M Skill N
100% 100%
0
Total 5,966,557.96
In Process 4/30
Cost from Dept A 18,000 X 46.303600 833,464.79 1
Material Z 18,000 X 4.488000 80,784.00 1
Skill M 18,000 X 2.514286 45,257.14 1
Skill N 10,800 X 2.292020 24,753.82 1
Overhead 14,400 X 0.211268 3,042.25 987,302.01 1
6,953,859.97 20
50% 100%
Skill M Skill N
100% 100%
0
F&A Company
Cost of Production Report
For the month of April 2013
In process end
Materials 900 X 5.50 4,950
Labor 750 X 8.25 6,188
Overhead 300 X 6.25 1,875
Total Cost as accounted for
Materials is added 30% at the start, plus 30% when 50% complete as to labor and the remainin
the products are 90% complete as to labor.
Required
Prepare the cost of production report of F&A Company for the month of April assuming t
current cost per units for Materials is P5.50, Labor is P8.25, and Overhead is P6.25.
Overhead
WD EUP
55% 1,100 2
45% 900 2
100% 12,500 2
20% 300 2
13,700
14,800 5.50 2
14,750 8.25 2
13,700 6.25 2
20.00
20.00
2
2
30,700 2
250,000 280,700.00 2
2
2
13,012.50 2
293,712.50 28
Transferred to Department B
In Process 4/1 15,000.00 0% - 75% 11,250.00 40% 6,000.00 1
Started 85,000.00 100% 85,000.00 100% 85,000.00 100% 85,000.00 1
In Process 4/30 10,000.00 100% 10,000.00 100% 10,000.00 90% 9,000.00 1
Total 110,000.00 95,000.00 106,250.00 100,000.00 2
CMCA Corporation
Department B
Cost of Production Report
For the month of April 2013
Total 5,614,926.36
In Process 4/30
Cost from Dept A 18,000 X 42.011413 756,205.43
Material Z 18,000 X 4.488000 80,784.00
Skill M 18,000 X 2.514286 45,257.14
Skill N 10,800 X 2.292020 24,753.82
Overhead 14,400 X 0.188510 2,714.54 909,714.94
6,524,641.30
0% 50% 100%
Skill M Skill N
100% 100%
0
Total 5,614,926.36
In Process 4/30
Cost from Dept A 18,000 X 42.011413 756,205.43
Material Z 18,000 X 4.488000 80,784.00
Skill M 18,000 X 2.514286 45,257.14
Skill N 10,800 X 2.292020 24,753.82
Overhead 14,400 X 0.188510 2,714.54 909,714.94
6,524,641.30
0% 50% 100%
Skill M Skill N
100% 100%
0
1
1
1
2
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
22
1
1
1
1
1
22
77
77
Para kareng mak
40% 60%
mulala
PPP Manufacturing Co. operates two consecutive departments (A and B). The following information pert
production of the two departments for August 2013.
Department A Depart
Units WD Units
Production Data
In process 8/1 6,000 30% 7,000
Started 35,000
Transferred out ? 31,000
Normal Loss 1,000 1,500
In Process 8/31 ? 20% 7,500
Cost Data
In Process 8/1
Transferred in 7,920.00
Cost in this department
Materials 1,785.00 3,885.00
Labor 891.00 1,890.00
Overhead 927.00 2,226.00
Transferred in
Cost added in August
Department B
Actual Materials
Qty. Schedule
Units WD EUP
In process Beginning 7,000 50% 3,500
Started this period 33,000
Total 40,000
Completed and Transferred
In process Beginning 7,000 50% 3,500
Started this period 24,000 100% 24,000
Normal Loss 1,500 0% -
In Process End 7,500 50% 3,750
40,000 31,250
In Process 8/31
Cost from Department A 7,500 1.399524 10,496.43
Materials 3,750 1.1200 4,200.00
Labor 3,000 0.4600 1,380.00
Overhead 3,000 0.5250 1,575.00
Adjustment for lost units 7,500 - -
70% 4,200
100% 27,000
100% 1,000
20% 1,400
33,600
7,988.45
36,096.55 44,085.00
1,000.00
3,521.00
48,606.00
Labor
WD EUP
60% -
40% 2,800
100% 24,000
0% -
40% 3,000
29,800
31,250 1.120000
29,800 0.460000
29,800 0.525000
2.105000
3.504524
22,599.00
84,108.57 106,707.57 107469.4762
17,651.43 17889.52381
124,359.00
RGU Adjusment
33,000.00 0.0402121
31,500.00 0.0666440
PPP Manufacturing Co. operates two consecutive departments (A and B). The following information pert
production of the two departments for August 2013.
Department A Depart
Units WD Units
Production Data
In process 8/1 6,000 30% 7,000
Started 35,000
Transferred out ? 31,000
Normal Loss 1,000 1,500
In Process 8/31 ? 20% 7,500
Cost Data
In Process 8/1
Transferred in 7,920.00
Cost in this department
Materials 1,785.00 3,885.00
Labor 891.00 1,890.00
Overhead 927.00 2,226.00
Transferred in
Cost added in August
In Process 8/31
Materials 7,000 0.2970 2,079.00
Labor 1,400 0.5100 714.00
Overhead 1,400 0.5200 728.00
Department B
Actual Materials
Qty. Schedule
Units WD EUP
In process Beginning 7,000 50% 3,500
Started this period 33,000
Total 40,000
Completed and Transferred
In process Beginning 7,000 50% 3,500
Started this period 24,000 100% 24,000
Normal Loss 1,500 0% -
In Process End 7,500 50% 3,750
40,000 31,250
In Process 8/31
Cost from Department A 7,500 1.431270 10,734.52
Materials 3,750 1.1200 4,200.00
Labor 3,000 0.4600 1,380.00
Overhead 3,000 0.5250 1,575.00
Adjustment for lost units 7,500 - -
70% 4,200
100% 27,000
100% 1,000
20% 1,400
33,600
8,170.27
36,914.73 45,085.00
3,521.00
48,606.00
Labor
WD EUP
60% -
40% 2,800
100% 24,000
0% -
40% 3,000
29,800
31,250 1.120000
29,800 0.460000
29,800 0.525000
2.105000
3.536270
22,599.00
84,870.48 107,469.48 107469.4762
17,889.52 17889.52381
125,359.00
RGU Adjusment
33,000.00 0.0402121
31,500.00 0.0681557
Normal Loss
> Costs of normal loss are accounted as product cost, meaning all unrecoverable cost of normal loss
are to be shouldered by the remaining good units
> Remaining good units are those units who already passed the quality control inspection (QCI).
> Work done assigned to normal lost units
For Materials, it will depend on when do they add the materials
For Conversion Cost if evenly applied
If discovered at the start work done is Zero
If discovered at the end work done is 100%
If discovered during work done is Zero
If discovered at specific point of production work done is equal to QCI
Abnormal Loss
> Unrecoverable cost of abnormal spoilage is accounted separately, which is recognized as either
part of the Factory Overhead Control or Period Cost.
> Work done assigned to normal
For Materials, it will depend on when do they add the materials
For Conversion Cost
If discovered at the start work done is Zero
If discovered at the end work done is 100%
If discovered during work done is Zero
If discovered at specific point of production work done is equal to QCI
PPP Manufacturing Co. operates two consecutive departments (A and B). The following information pert
production of the two departments for August 2013.
Department A Depart
Units WD Units
Production Data
In process 8/1 6,000 30% 7,000
Started 35,000
Transferred out ? 31,000
Loss Units 1,000 1,500
In Process 8/31 ? 20% 7,500
Cost Data
In Process 8/1
Transferred in 7,920.00
Cost in this department
Materials 1,785.00 3,885.00
Labor 891.00 1,890.00
Overhead 927.00 2,226.00
Transferred in
Cost added in August
In Process 8/31
Materials 7,000 0.2970 2,079.00
Labor 1,400 0.5100 714.00
Overhead 1,400 0.5200 728.00
Department B
Actual Materials
.
Units WD EUP
In process Beginning 7,000 50% 3,500
Started this period 33,000
Total 40,000
Completed and Transferred
In process Beginning 7,000 50% 3,500
Started this period 24,000 100% 24,000
Normal Loss 495 0% -
Abnormal Loss 1,005 0% -
In Process End 7,500 50% 3,750
40,000 31,250
In Process 8/31
Cost from Department A 7,500 1.352540 10,144.05
Materials 3,750 1.1200 4,200.00
Labor 3,000 0.4600 1,380.00
Overhead 3,000 0.5250 1,575.00
Adjustment for lost units 7,500 0.021254 159.41
70% 4,200
100% 27,000
100% 660
100% 340
20% 1,400
33,600
8,088.24
36,545.58 44,633.82
3,521.00
451.18
48,606.00
Labor
WD EUP
60% -
40% 2,800
100% 24,000
0% -
0% -
40% 3,000
29,800
31,250 1.120000
29,800 0.460000
29,800 0.525000
2.105000
0.021254
3.478794
22,599.00
83,491.06 106,090.06
17,458.46
1,359.30
124,907.82
RGU Adjusment
33,000.00 0.0265400
31,500.00 0.0212542
PPP Manufacturing Co. operates two consecutive departments (A and B). The following information pert
production of the two departments for August 2013.
Department A Depart
Units WD Units
Production Data
In process 8/1 6,000 30% 7,000
Started 35,000
Transferred out ? 31,000
Normal Loss 1,000 1,500
In Process 8/31 ? 20% 7,500
Cost Data
In Process 8/1
Transferred in 7,920.00
Cost in this department
Materials 1,785.00 3,885.00
Labor 891.00 1,890.00
Overhead 927.00 2,226.00
Transferred in
Cost added in August
In Process 8/31
Materials 7,000 0.2970 2,079.00
Labor 1,400 0.5100 714.00
Overhead 1,400 0.5200 728.00
Factory Overhead 1,000 1.327000
Department B
Actual Materials
Qty. Schedule
Units WD EUP
In process Beginning 7,000 50% 3,500
Started this period 33,000
Total 40,000
Completed and Transferred
In process Beginning 7,000 50% 3,500
Started this period 24,000 100% 24,000
Normal Loss 1,500 0% -
In Process End 7,500 50% 3,750
40,000 31,250
In Process 8/31
Cost from Department A 7,500 1.326000 9,945.00
Materials 3,750 1.1200 4,200.00
Labor 3,000 0.4600 1,380.00
Overhead 3,000 0.5250 1,575.00
Factory Overhead Control 1,500 1.3260
70% 4,200
100% 27,000
100% 1,000
20% 1,400
33,600
7,929.00
35,829.00 43,758.00
3,521.00
1,327.00
48,606.00
Labor
WD EUP
60% -