Project: Painting of Wall

Location: Mallorca Clubhouse


Subject: Estimate of Material and Labor Costs

Material Cost
Quantity Unit Description Amount
1 gal Premix paint 1,000.00

Labor Cost
1 skilled painter 500.00
1 helper 300.00
800.00

Total Cost: 1,800.00

Prepared by:

Engr. Herman B. Bibon


Mallorca Site Engineer

Noted By:

Engr. Henry D. Romero


Project Manager - Mallorca Villas
Project: Concreting of Sidewalk
Location: Mallorca Villas
Subject: Estimate of Material and Labor Cost

Material Cost
Item No. Description Qty Unit Amount
1 Cement 3 bags 720.00
2 White Sand 15 bags 270.00
3 Gravel 8 bags 256.00
Total: 1246.00
Labor Cost
1 mason 600.00
1 helper 400.00
Total: 1000.00

Total Cost: 2246.00 Php

Prepared By:

Herman B. Bibon
Mallorca Villas - Site Engineer

Noted By:

Engr. Henry D Romero


Mallorca Villas - Project Manager