You are on page 1of 5

SPE 93984

Well Testing Best Practice

Shi-Yi Zheng and Patrick Corbett

Institute of Petroleum Engineering, Heriot-Watt University, Scotland


2004 Society of Petroleum Engineers Inc.
measures, are critically reviewed. We term this approach: Well
This paper was prepared for presentation at the 14th Europec Biennial Conference held in Testing Best Practice (WTBP).
Madrid, Spain, 13-16 June 2005.

This paper was prepared for presentation at the 14th Europec Biennial Conference held in
Madrid, Spain, 13-16 June 2005.
Introduction
This paper was selected for presentation by an SPE Program Committee following review of
Transient pressure measurement while attempting to keep the
information contained in an abstract submitted by the author(s). Contents of the paper, as well flow rate constant has been accepted as an industry
presented, have not been reviewed by the Society of Petroleum Engineers and are subject to
correction by the author(s). The material, as presented, does not necessarily reflect any standard practice. This has been called, in general, well test.
position of the SPE, their officers, or members. Electronic reproduction, distribution, or storage
of any part of this paper for commercial purposes without the written consent of the Society of
So, as soon as well test is mentioned, it invariably means
Petroleum Engineers is prohibited. Permission to reproduce in print is restricted to an abstract transient pressure test. Otherwise, a test will be named
of not more than 300 words; illustrations may not be copied. The abstract must contain
conspicuous acknowledgment of where and by whom the paper was presented. Write specifically (e.g., production test).
Librarian, SPE, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A.,
fax 01-972-952-9435.
When the well bottom hole flowing pressure is kept
approximately constant, but measuring the flow rate change as
Abstract a function of time, i.e., the transient rate, this type of test is
This paper will present study results from a ten-year long oil referred to as decline curve analysis. It is increasingly used for
industry sponsored research project in this subject area. The the purpose of reservoir management.
survey of well testing practice covered situations from a range
of major oil companies in China, Europe and Russia, which According to operation procedures, well test (i.e. a transient
reflected problems that have long existed. These issues were pressure test includes pressure draw-down test) which is
further confirmed at the 2002 SPE well testing Forum. It was conducted by flowing the well with constant rate, while
realised there is a need to promote best practice in the oil measures the pressure change (decline) as a function of time,
industry, and in well testing in particular, and that was the pressure build-up test, which is done by closing a flowing well
motivation for this paper. to measure the pressure recovery (build-up) in the reservoir
against the time, fall-off test, which is completed by shutting
Well testing, regarded as transient pressure testing, is usually off an injection well, then measures the pressure fall-off as a
very expensive. Bad testing data resulting from lack of design, function of time.
preparation and unsupervised operation are really expensive.
The contribution from the test to your asset is negative if a In general, well test means both pressure drawdown and build-
decision is made based on the information derived from non- up tests. The test is combined and conducted continuously in a
representative data. Therefore, why not carefully prepare or series. The test flow rate and drawdown, or build-up durations
design your test beforehand? There should be no excuse after are designed according to the test objectives.
spending two million dollars for a test and failing to deliver
the information you expected. In our eleven years of research Well test objectives are classified in the following three major
and teaching experience worldwide in the subject area, we areas; this is also shown in Fig.1:
found that well test interpretation engineers need skills other
than in the subject itself in order to get more value from well 1. Well test for reservoir evaluation
testing. There is also a need to clarify the ambiguity in some 2. Well test for reservoir description
well testing concepts such as data, information, analysis and 3. Well test for reservoir management (monitoring)
interpretation, in order to develop a test procedure that is
generally easy to follow and understand. In this paper, the
Well test for reservoir evaluation
study results will address all issues from justifying a test to the
right procedures to conduct and interpret a test. The definition The objectives of the test include: test for flow
of a transient pressure test and a PI test, well test objectives capacity/productivity, initial reservoir pressure, fluid sampling
and alternative measurements available to consider in the oil for PVT analysis. These will provide some basic reservoir and
industry, as well as the advantages and disadvantages of these fluid parameters for reservoir evaluation.
2 Shiyi Zheng and Patrick Corbett 93984

Well test for reservoir description In the last ten years, fluvial reservoir characterization and
The objectives of the test are to derive information about research has been focused on the aspects of testing for
reservoir anisotropy, heterogeneity, drainage geometry and reservoir description and evaluation. The advance in well
boundary conditions such as constant pressure, no-flow and testing is the integration of geology and reservoir engineering
closed reservoir boundaries. These determinations ore often through numerical modelling and simulation of well test, i.e.
non-unique and several models with a range of parameters numerical well testing. This not only provides a platform for
might be investigated. integration, but also adds a further step in well testing
interpretation procedure well test forward modeling2, 5, 6, 8,10.
Well test for reservoir management
As illustrated in Fig.4, the solid line outlined an example when
The objectives of the test for reservoir management can be considering to test. The test objective is for reservoir
subdivided into the following three areas: evaluation, where fluid and rock properties are expected to be
derived from the test. According to the cost, these parameters
1. A test designed for the future monitoring of the reservoir. can be obtained through three alternative measurements such
Systematic test design, operation, analysis and interpretation at as wireline logs, wireline tester and sampler. So the final
appraisal phase. This will ensure value for information in
decision might be that there is no need to do well testing. In
reservoir description, evaluation and management. many areas the pressure to test comes from the need to
confirm reserves.
2. Extended well testing, which will consider long-term
pressure drawdown and build-up data from permanent down In Fig.5, as solid line outlined, it shows an example when
hole gauge. The objective of the test is to confirm hydrocarbon considering to test. The test objective is for reservoir
reserve, reservoir drive mechanism, reservoir description, where reservoir boundary and dynamic
boundary/compartmentalization, and geological performance are expected to be derived from the test. In this
structure/element/heterogeneity. These together will provide
case, none of the listed alternative measurements can satisfy
improved reservoir characterization, modelling and the test objectives. So the final decision is to do well testing.
simulation. However, in some countries, a test still cant be operated due
to the strict no CO2 emission policy (Fig.6).
3. Time-lapsed well testing during field development phase.
This will include selected well test study on reservoir model It should be pointed out that well testing for reservoir
and field well test data for the purpose of model calibration
management is not an entirely different test from those
and reservoir monitoring/management.
performed for reservoir description and reservoir evaluation. It
is a well-designed test that can fulfill all these three tasks (test
This application of well testing is different from fibre optic for reservoir description, evaluation and management) in a
reservoir temperature and pressure monitoring. Also this is systematic, yet continuous way. Further more, a test can be
different from reservoir decline curve analysis for production performed in a time-lapsed fashion (4D well testing) to
forecast and reservoir management. monitor reservoir property change such as kh, boundaries such
as sealing or leaky fault, change of OGC or OWC, injected
Well test best practice water front etc. etc. In this way, well testing is used for
Due to the cost, in order to justify if it is necessary or worth reservoir monitoring in order to provide information that will
testing (value for information), an engineer should always ask help to make decision in time for reservoir management.
herself (himself) the question: to test or not to test? If the
answer is YES, then the test objectives need to be clearly As reservoir management, well test is required to start at the
specified according to the description above. If the answer is right beginning of a field life as well as during the
NO, in order to achieve the test objectives (e.g. to get the development. Information about the reservoir, especially
required reservoir and fluid parameters), what are the wireline geological information on the architecture can be best
alternative measurements can be used? Fig.2 shows some extracted from a well test conducted at exploration or
options as some well test alternatives. Each of these can only appraisal phase3, 7. On this basis, well test conducted later has
achieve part of those from a well test operation. Several of a good reference to justify the results against fluid effects.
these measurements together may need to be combined in
order to obtain the total test results4. The key for the decision- Common well testing problems
making is the cost. Our experience over a broad geographic spread (China,
Europe and Russia) has identified recurrent problems that have
CO2 emission during a test in some countries or for some long existed in well testing practice and these can be classified
companies might be another restriction, which should be taken in the following eight aspects:
into account as well. To meet the particular test objective, a
test needs to be designed carefully before the operation. Fig.3 1. Lack of well test design: this problem exists in the oil
shows a workflow for justifying a well test program1. industry from east to the west. It is more difficult to
design a test than to do it. This is because either due to
limit of data required for the design, particularly at the
93984 Well Testing Best Practice 3

field appraisal phase, or due to the difficult in modeling strong well bore storage effect caused by using surface
inflow and outflow (for example, vertical lift performance shut-in will fail a build-up test. In reality, it may be
in a vertical well), which knowledge is from production difficult to do down-hole shut-in due to operation limit in
engineering side. So there is no prediction of the future a high temperature and high-pressure gas-condensate
test performance, which can be derived through well. (5) Well flowing below the bubble point pressure.
sensitivity studies during the design. A test outcome is left This this can be avoided with a proper well test design for
to some degree of risk, so surprises are often seen in the exploration or appraisal wells. The pressure drop during
test. the DD and well bottom hole flowing pressure can be
2. Design, operation and analysis of a well test by optimized through the NODAL analysis, which is part of
different team or persons: This happened more due to the well test design program.
organization structure than the technology itself. Some 5. Misunderstanding the test concept, limit of analysis
companies are still very much functional based, where method and basic requirement for the data: (1)
communication within the company is made through Analyzing PI test data using pressure derivative
functional office (most time by a person who has limited diagnostic: this is due to misunderstanding transient
discipline knowledge of the technology). Operation is pressure and production tests. Also due to not aware that
always successful, whilst the problem can be easily using pressure derivative curve for the purpose of
spotted by an experienced reservoir engineers from the diagnostic requires high-resolution data, which is only
data. In western oil industry, the situation is less of a available from the modern pressure gauges. (2) Only
problem because the company structure is asset based and analyzing BU, but ignoring the DD: the reason cause this
the feedback loop to other field data and the application is still due to lack of the understanding of well testing
are necessary. theory. Practically, it is difficult to get decent DD data
3. Using the same test program for all reservoirs: Almost due to difficult in controlling the flow rate. Pressure
all the oil companies have a pragmatic in-house testing build-up, on the other hand, is always good quality. So
program. This will give a generalized rate schedule and engineers get used to analyze BU data in order to get
test durations for flow and well shut-in. This is not what reservoir parameters. However, this doesnt mean that the
we define as well test design, which should be produced DD can be ignored. In our experience, DD data can
from modeling and numerical simulation. Since reservoirs provide invaluable information about the reservoir in
are all different in terms of size, rock and fluid properties, channel and closed reservoir systems12. (3) A short DD
heterogeneities, etc., a test program should be designed followed by a long BU: a pressure build-up is designed in
specifically in order to meet the test objectives. It can be a such that its duration will be long enough to recover the
pity to realize a boundary was detected from the reservoir volume experienced by the preceding DD, this
diagnostic plot, but can not define what kind of boundary usually 1.5 2 times of that from the preceding DD.
it really is due to lack of enough data (test not long Depending on the reservoir permeability and outer
enough). boundary conditions, this rule of thumb can be different.
4. Mis-operate a test: (1) Sampling or do running So why have a very long BU then? Only reason is that the
production logs during the drawdown (DD). Many tests operator or well test designer havent considered the right
conducted in this way because the operator thinks that as well testing procedure.
long as the final pressure build-up is ensured, the test is 6. Misuse or wrong interpret the test data: (1) No time to
successful. They forget that fact that the buildup (BU) analyze the data or analyze all the test data in the same
results critically rely on the preceding DD with respect to fashion: permeability and skin: some companies have
skin factor calculation and flow history. A done so many well tests, but the test data either not
disturbance during a well-stabilized DD period, will analyzed or simply looked at by a relatively junior
impact the BU data leading to the deviation of the engineer for reservoir permeability and skin using the
analysis. (2) Shut-in the well before flow rate same procedure. If some one calculates the cost to
stabilization: this is part of the problem identified in (1). conduct these tests, clearly, the test data treated this way
A disturbance such as sudden drop the rate during the cannot justify the value for information. (2) Pursue
DD, which will cause the pressure to build-up, then flow perfect match for well test analysis: a perfect match
continued, but not for long before the well shut-in. This between the analytical solution and tested data can easier
will impact the BU data. According to the pulse theory, it to mislead an interpreter. The key in well test analysis is
will take five times the duration of that of a disturbance, to get the model right. This requires a fully studies to the
in order to remove the impact of such a disturbance. (3) disciplines involved including sensitivity analysis. An
Using decreasing-rate schedule for multiple rate test interpretation based on a wrong model derived from a
rather than using increasing-rate: this was found from perfect match is meaningless, or rather misleading.
field examples from North Africa. The only advantage to However, a right model may not match the test data
do this in a gas well is to help cleaning-up the well exactly. (3) Comparing the derived model and property
damage caused by drilling and completion. As far as well such as permeability with those from different
test itself concerned, using an increasing rate schedule measurements: this is a matter of measurement scale,
will be much better than using a decreasing rate schedule. volume, and tolerance 11. Well testing yields multiple
(4) Using surface shut-in instead of down-hole shut-in: models and parameters with ranges of values. The
This is very crucial in gas-condensate reservoirs. The
4 Shiyi Zheng and Patrick Corbett 93984

uncertainty can be reduced when integrated with other decreasing during flow due to cleaning up. It is difficult to
data. analyze such a test.
7. Complicated model, simple well test behavior or vice
versa: a good example to discuss this problem is well Correct well testing procedure
testing naturally fractured reservoir, in which case, The key to ensure that a quality well test can be conducted is
fractures/fissures are easily found from core, logs, while to map out a right procedure, then strictly stick to it. A correct
the well test response shows a uniform reservoir behavior. well testing procedure should include the following stages in a
In this case, the test can be analyzed using the systematic way: test design through numerical modeling and
homogeneous model to derive the effective property of well test simulation with clear objectives test operation
the reservoir. Because if the heterogeneity of the reservoir supervised by testing engineer data evaluation to ensure the
distributed in 3-D space uniformly, then the resulting reliability, representativity of the test data analysis including:
reservoir becomes homogeneous reservoir. In another diagnostic using log-log plot and reservoir system type curves
case of well testing naturally fractured reservoirs, the (generated during the design), specialized analysis, matching
testing time is not long enough to see the total system (flow regimes and history matching) interpretation through
behavior (in most cases), so it is difficult to select well test forward modeling (data integration), well test
interpretation model according to the pressure derivative numerical simulation, and finally documentation. These
curve alone. Some time, the derivative curve shows a together are called Numerical Well Testing (NWT) for WTBP.
response similar to that from a complicated reservoir
model, but the reason causing this particular response is A well test report should address all these aspects in details
entirely different. The key is the timing of a specific flow together with the analysis of resulting uncertainty (model and
regime appearing. properties). The final well test model (forward model) is a
8. Other factors affecting well testing response and database for the future well test design, also can be used in
results: with a high-resolution pressure gauge down-hole, calibrating the existing full field reservoir simulation model.
any disturbance in the well and formation will be
recorded. In order to get decent data from a well test, a Conclusions
well-designed test with good test supervision can avoid
some of the problems. However, engineers also should be This paper presented a general procedure for considering well
prepared to learn how to identify the problems from the testing. According to the type of reservoirs, type of wells and
data. These problems as often seen from a well test are: government regulation in different countries, a specific best
(1) Liquid level rising during a test: when testing an oil practice guideline should be made available to the engineers in
reservoir with water cut or testing gas-condensate order to reduce cost and increase the value of information
reservoir, the liquid phase of the fluid will be segregated from well testing.
in the well-bore due to gravity causing the liquid level
rising during a test. This will impact the pressure recorded In the life of a field, wells need to be tested (monitored). Well
on the gauge. (2) Phase segregation in the well bore: this testing is very expensive. A well-planned test cannot only
can be identified from the Cartesian plot and pressure deliver the expected result; it also can save money through
derivative diagnostic plot in some tests. It is important to providing accurate information, which will eventually lead to
recognize this as a well bore behavior, while the timing of the right decision-making.
reservoir behavior will follow this later, where the radial
flow can be defined. (3) Derivative calculation artifact at In conclusion, this paper has covered the following:
Late Time Region (LTR): this is often seen when
analyzing pressure build-up data. During BU, when the Well Testing Best Practice (WTBP) as correct well
reservoir pressure is approaching the reservoir initial or testing procedure- a systematic approach in doing well
average pressure, the pressure differences measured testing is provided (also in a flow chart as attached
between a time interval is very small at LTR, so the figures). The oil companies might have their own best
derivative calculation by differentiation will yield practice guide made according to their specific reservoir
negative values. While most of the well testing software conditions, well and field situations.
does not allow these values to be plotted, where the After a decision has been made to test, a test plan should
noise appeared on the derivative curve at LTR include, in details, test design, operation procedures, data
vertically. This has nothing to do with reservoir (4) Time evaluation, test analysis procedures and integrated test
functioning (over correction at LTR): the disadvantage of interpretation through numerical well testing.
time functioning in analyzing pressure build-up data is it In terms of well testing objectives, it includes: (1) Well
will compress the time scale. This will lead to missing testing for Reservoir Evaluation in field exploration and
LTR behavior or misinterpret the LTR response12 (5) appraisal phase, (2) Well testing for Reservoir Description
Inaccurate rate history input: again, this will cause the in field appraisal and development phase, (3) Well
derivative from a BU at LTR to change slope resulting in testing for Reservoir Management in production and
selecting the wrong model for test analysis (6) Bottom development phase (well test and reservoir monitoring).
hole flowing pressure increase with time: this can be A well test best practice guide needs to define clear
recognized from Cartesian plot of the draw-down. The objectives for testing including to test or not to test?
reason causing this is the formation damage, so the skin is The value of information is essential to justify a test.
93984 Well Testing Best Practice 5

Common well testing problems are identified, and the 10. Zheng, S., Corbett, P., and Stewart, G., 1996, Variable formation
reasons causing these problems briefly described. thickness - Impact on pressure-transient-test permeability,
synopsis of SPE 36552, JPT, Nov., 1018-1021.
11. Zheng, S., Corbett, P., Ryseth, A., and Stewart, G., 2000,
Acknowledgement Uncertainty in well test and core permeability analysis: A case
We wish to acknowledge Shell, Wintershall, ConocoPhillips, study in fluvial channel reservoir, Northern North Sea, Norway,
and Yukos for sponsoring the research work within GEOTIPE AAPG Bulletin, 84(12), 1929-1954.
Project. ConocoPhillips, Wintershall and BG Group are 12. Zheng, S., Stewart, G., and Corbett, P., 2000, Analyzing pressure
acknowledged for their continued support within PRIME transient test in semi-infinite and finite reservoirs using de-
Project. Schlumberger and Edinburgh Petroleum Services superposition method, SPE 64753, SPE Int. Oil and Gas
Conference, Beijing, China, 7-10 Nov.
(EPS) are acknowledged for allowing the use of their software
packages during the course of the research. The authors thank
the mentoring of George Stewart as we came to grips with the
various data sets. The opinions expressed in this paper are
solely the authors and the conclusions are broadly for the
industry as a whole rather than any specific company.

Nomeclature
BU BuildUp
DD DrawDown
ETR Early Time Region
LTR Late Time Region

Reference
1. Bennett, C., 2002, BPs view of reduced emissions testing, SPE
Well Testing Forum, Bali, May.
2. Corbett, P., Zheng, S., Pinisetti, M., Mesmari, A. and Stewart, G.,
1998; The integration of geology and well testing for improved
fluvial reservoir characterisation, SPE 48880, presented at SPE
International Conference and Exhibition, Bejing, China, 2-6
Nov.
3. Gunter, G.W., Finneran, J.M., Hartmann, D.J., and Miller, D.J.,
1997 Early determination of reservoir flow units using an
integrated petrophysical approach, SPE 38679, Proceedings of
the Society of Petroleum Engineers Annual Technical
Conference and Exhibition, Formation Evaluation and Reservoir
Geology, Part 1, 373-380.
4. Hollaender, F., 2001, Well Testing To Test or Not To Test,
ATW Workshop notes, 14-16 November, London
5. Morton, K., Thomas, S., Corbett, P., and Davies, D., 2002,
Detailed analysis of probe permeameter and vertical interference
test permeability measurements in a heterogeneous reservoir,
Petroleum Geoscience, 8, 209-216.
6. Robertson, E., Corbett , P., Hurst, A., Satur, N., and Cronin, B.,
2002, Synthetic well test modelling in a high net-gross outcrop
system for turbidite reservoir description, Petroleum
Geoscience, 8, 19-30
7. Tyler, N. and R. J. Finley, 1991, "Architectural Controls on the
Recovery of Hydrocarbons from Sandstone Reservoirs," in The
Three-Dimensional Facies Architecture of Terrigenous Clastic
Sediments and Its Implications for Hydrocarbon Discovery and
Recovery, A. D. Miall and N. Tyler (eds.), SEPM Concepts
in Sedimentology and Paleontology, Tulsa, Oklahoma: 3 1-5.
8. Zheng, S., Corbett, P., and Emery, A., 2003, Geological
interpretation of well test analysis, An example from a fluvial
reservoir in the Gulf of Thailand, Journal of Petroleum Geology,
26(1), 49-64
9. Dubost, F.X., Zheng, S.Y., Corbett, PW.M., 2004, Analysis and
numerical modeling of wire line pressure tests in thin-bedded
turbidities, Journal of Petroleum Science and Engineering 45
247 261.

You might also like