ID Task Name Duration Start Finish Task Calendar 18 Jun '17 30 Jul '17

18 06 24
1 Aktivitas Pemasangan Pipa 8" di APRON 45 days Mon 03/07/17 Fri 11/08/17 Fabrication/Construction Onshore
2 Persiapan dan Mobilisasi 15 days Wed 05/07/17 Tue 18/07/17 Fabrication/Construction Onshore
3 Pengurusan PASS CREW di OTBAN 8 days Wed 05/07/17 Fri 14/07/17 Office
4 Inspeksi Alat Sebelum MOB 5 days Thu 13/07/17 Sat 15/07/17 24 Hours
5 Equipment seperti Genset, Mesin Las 4 days Thu 13/07/17 Fri 14/07/17 24 Hours
6 Alat-alat berat seperti Excavator 78, Trailer dan Pick Up 1 day Fri 14/07/17 Fri 14/07/17 24 Hours
7 Mobilisasi Material Pipa, Genset, Mesin las dan Alat safety 3 days Wed 12/07/17 Thu 13/07/17 24 Hours
8 Loading & Unloading Pipa 8" dan Casing 12" 1 day Wed 12/07/17 Wed 12/07/17 24 Hours
9 Mob Genset, Mesin las dan Alat supporting lainnya 1 day Wed 12/07/17 Wed 12/07/17 24 Hours
10 Mobilisasi Safety Sign, Fence, Lighting 1 day Wed 12/07/17 Wed 12/07/17 24 Hours
11 Site Construction Work 36 days Mon 10/07/17 Thu 10/08/17 Fabrication/Construction Onshore
12 Pekerjaan Pengelasan Pipa 200 Meter (2 Line)-Paralel 20 days Wed 12/07/17 Sat 29/07/17 Fabrication/Construction
13 Stringing Pipa untuk 200 Meter (2 Line)-Paralel Untuk di 1 day Mon 10/07/17 Mon 10/07/17 Fabrication/Construction
14 Setup Alat Pengelasan 1 day Wed 12/07/17 Wed 12/07/17 Fabrication/Construction Onshore
15 Fitup dan Pengelasan 2 days Wed 12/07/17 Thu 13/07/17 Fabrication/Construction Onshore
16 NDT 2 days Fri 14/07/17 Sat 15/07/17 Fabrication/Construction Onshore
17 FJC 2 days Fri 14/07/17 Sat 15/07/17 Fabrication/Construction Onshore
18 Tie-In antara 2 line - Paralel, NDT & FJC 3 hrs Sat 29/07/17 Sat 29/07/17 Fabrication/Construction Onshore
19 Site HDD Work 24 days Wed 12/07/17 Wed 02/08/17 Fabrication/Construction Onshore
20 Mobilisasi Alat HDD dan Alat Berat Masuk Ke Apron 1 day Wed 12/07/17 Wed 12/07/17 Fabrication/Construction Onshore
21 Setup Alat, Mixing Bentonite & Trial HDD Equipment 2 days Wed 12/07/17 Thu 13/07/17 Fabrication/Construction Onshore
22 Clearing & Excavation Area HDD Entry & Exit 1 day Fri 14/07/17 Fri 14/07/17 Fabrication/Construction Onshore
23 Initiation Pilot HDD Boring 7 days Fri 14/07/17 Thu 20/07/17 Fabrication/Construction Onshore
24 Reamer HDD Boring 3 days Tue 18/07/17 Thu 20/07/17 Fabrication/Construction Onshore
25 Cleaning & Simulasi tarik pipa 2 days Sat 22/07/17 Sun 23/07/17 Fabrication/Construction Onshore
26 Tarik Pipa 1 day Tue 25/07/17 Tue 25/07/17 Fabrication/Construction Onshore
27 Disconnect HDD Equpment 1 day Sat 29/07/17 Sat 29/07/17 Fabrication/Construction Onshore
28 Backfilling Area Entry & Exit 2 days Sun 30/07/17 Mon 31/07/17 Fabrication/Construction Onshore
29 Auger Boring Pintu Keluar/Masuk DPPU Hasanuddin 16 days Wed 12/07/17 Wed 26/07/17 Fabrication/Construction Onshore
30 Setup Auger Boring Equipment 2 days Wed 12/07/17 Thu 13/07/17 Fabrication/Construction Onshore
31 Clearing & Excavation Area Auger Boring Entry & Exit 2 days Wed 12/07/17 Thu 13/07/17 Fabrication/Construction Onshore
32 Initiation Auger Boring Pintu Keluar & Masuk DPPU 6 days Fri 14/07/17 Wed 19/07/17 Fabrication/Construction Onshore
33 Perbesar Lubang Auger Boring Pintu Keluar & Masuk 4 days Thu 20/07/17 Sun 23/07/17 Fabrication/Construction
34 Pasang Pipa 8" dan Casing 12" dalam lubang Auger Boring 2 days Mon 24/07/17 Tue 25/07/17 Fabrication/Construction Onshore
35 Open Cut 14 days Wed 26/07/17 Mon 07/08/17 Fabrication/Construction Onshore
36 Fabrikasi 10 days Wed 26/07/17 Thu 03/08/17 Fabrication/Construction Onshore
37 Setup Equipment Pengelasan 1 day Wed 26/07/17 Wed 26/07/17 Fabrication/Construction Onshore
38 Stringing Pipa untuk 300 Meter 1 day Thu 27/07/17 Thu 27/07/17 Fabrication/Construction Onshore
39 Fitup dan Pengelasan 3 days Thu 27/07/17 Sat 29/07/17 Fabrication/Construction Onshore
40 NDT 2 days Sat 29/07/17 Sun 30/07/17 Fabrication/Construction Onshore
41 FJC 2 days Mon 31/07/17 Tue 01/08/17 Fabrication/Construction Onshore
42 Galian 12 days Wed 26/07/17 Sat 05/08/17 Fabrication/Construction Onshore
43 Open Cut Menggunakan Excavator 7 days Wed 26/07/17 Tue 01/08/17 Fabrication/Construction Onshore
44 Lowering Pipa 1 day Tue 01/08/17 Tue 01/08/17 Fabrication/Construction Onshore
45 Backfilling Area Galian 3 days Tue 01/08/17 Thu 03/08/17 Fabrication/Construction Onshore
46 Tie In 10 days Wed 02/08/17 Thu 10/08/17 Fabrication/Construction Onshore
47 Tie In 8"di Area Open Cut (4 Titik Tie In) 7 days Wed 02/08/17 Tue 08/08/17 Fabrication/Construction Onshore

Task External Tasks Manual Task Finish-only Baseline Milestone


Split External Milestone Duration-only Deadline Baseline Summary
Project: Schedule Pekerjaan Pengelasan & HDD di Apron Milestone Inactive Task Manual Summary Rollup Critical Progress
Summary Inactive Milestone Manual Summary Critical Split Manual Progress
Project Summary Inactive Summary Start-only Baseline

Page 1 of 2
ID Task Name Duration Start Finish Task Calendar 18 Jun '17 30 Jul '17
18 06 24
48 Tie In 8" Pipa Open Cut dan Pipa HDD 4 days Wed 02/08/17 Sat 05/08/17 Fabrication/Construction Onshore
49 Backfilling Area Entry & Exit Auger Boring 4 days Wed 02/08/17 Sat 05/08/17 Fabrication/Construction Onshore

Task External Tasks Manual Task Finish-only Baseline Milestone


Split External Milestone Duration-only Deadline Baseline Summary
Project: Schedule Pekerjaan Pengelasan & HDD di Apron Milestone Inactive Task Manual Summary Rollup Critical Progress
Summary Inactive Milestone Manual Summary Critical Split Manual Progress
Project Summary Inactive Summary Start-only Baseline

Page 2 of 2