Parametric estimate of Project Cost

Quantity Price
Cost Item Quantity Unit Price (Php)
Identification Identification

Formworks 100 pieces Rough takeoff 4,000 Vendor quotes


Scaffoldings 500 pieces Rough takeoff 300 Vendor quotes
Portland Cement 3,000 tons Rough takeoff 11,000 Estimating guides
Coarse aggregates 5,000 tons Rough takeoff 6,000 Estimating guides
Fine aggregates 3,000 tons Rough takeoff 6,000 Estimating guides
Reinforcing steel
2,000 tons Rough takeoff 12,000 Estimating guides
bars

Cement Mixers 4 units Rough takeoff 25,000 Vendor quotes

Heavy
Equipments(e.g. 2 units Detailed takeoff 400,000 Local contractor
Crane)

Machineries 7 units Rough takeoff 8,000 Vendor quote

1 job
Mobilization Ratio takeoff 120,000 Local contractor

Electrical services 3 jobs Rough takeoff 20,000 Local contractor

Earthwork
activities (e.g 2 jobs Rough takeoff 250,000 Local contractor
excavation)

Surveying 2 jobs Rough takeoff 75,000 Local contractor


Pipe lay-outing 2 jobs Rough takeoff 42,000 Local contractor
Drainage 2 jobs Rough takeoff 40,000 Local contractor
Safety
100 units Rough takeoff 150,000 Vendor quotes
equipments
Signals and
20 units Rough takeoff 60,000 Local contractor
signages

Field investigation 2 jobs Ratio takeoff 150,000 Vendor quotes


Noise controls 1 job Rough takeoff 50,000 Vendor quotes

Traffic
1 job Ratio takeoff 45,000 Vendor quotes
management
Project process value assignment

Work Packages PV and EV measurement method

Mobilization Apportioned Effort

Land Preparation Level of effort

Field Investigation Level of effort

Surveying Level of effort

Dewatering Level of effort

Drainage pipe lay-outing and installation Level of effort

Procurement of equipments Fixed Formula

Portland Cement Fixed Formula

Earthwork Apportioned Effort

Equipments and Supplies Weighted Milestone

Electrical services Apportioned Effort

Aggregates Fixed Formula

Reinforcing steels Fixed Formula

Heavy Equipments Weighted Milestone