Professional Documents
Culture Documents
FIGURES
To provide further service to our readers, computer screen figures from the 7th Edition have been provided in this
PDF file. This may be especially useful where the original is in color but only a black, white and grey-tone image is
printed in the text. In addition, readers may zoom in on these various graphics.
Figure 4.1.1 Original plan is start cooking (10 min.,) begin eating while finishing cooking
Actual was started cooking breakfast, dropped eggs, cleaned up, continue cooking
CPM scheduled at start and rescheduled at 5 minutes point
In Primavera P3 and P3e/c software, use one custom data code for quantity and a second for productivity rate. A
standard activity code may also be reserved to note the units of quantity recorded. Enter the quantity (numeric) and
create a Global Change to calculate the productivity rate for all non-zero duration activities (equal to quantity
divided by original duration.)
Figure 6.3.1 Use of Custom Data Items and Global Change to Calculate Productivity Rates
1
2
Figure 9.4.1 Primavera P3 Logs note detail of utility installation activity under direction of one foreman
Figure 9.4.2 Primavera P3 Logs note individual bents of a drainage pipe Each line is checked off as performed
Figure 9.4.3 Primavera P3 Logs note individual bents of a drainage pipe Each bent is checked off as performed
Figure 9.4.4 Primavera P3e/c Steps allows user to specify tasks within the Place 2 SURFACE COURSE activity
User may check-off as work performed 19mm 1st Course is 67%, 9.5mm 2nd Course is 33% of this 4 day activity
3
2000 2001
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN
3 10 17 24 31 7 14 21 28 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29
0 10 0,47 20 30 20,0 50 60 15,0 70 80 15,0 90 100 20,0 110 120 10,0 140 150 0,0
NOTICE TO FOUNDATIONS - START NOT SLAB ON SLAB ON CURTAIN WALL 1ST FLOOR 1ST FLOOR TURNOVER FOR
PROCEED EARLIER THAN 15MAR00 DECK FLOOR 2 DECK FLOOR 4 INSTALLATION STUD & DRYWALL COMMERCIAL RENTAL INCOME
10 20 5,47 30 40 15,0 60 70 15,0 80 90 15,0 100 108 10,0 130 140 10,0
MOBILIZE STRUCTURAL STEEL SLAB ON ROOF DECK 1ST FLOOR 1ST FLOOR
FLOORS 1 TO 5 DECK FLOOR 3 & ROOFING MECHANICAL PUNCHLIST
40 50 15,0 120 130 15,0 440 450 0,0
SLAB ON 1ST FLOOR FLOORS 2 - 4 TURNOVER
GRADE FINISHES FOR RESIDENTIAL RENTAL
105 109 7,3 225 430 0,25 430 440 10,0
1ST FLOOR PUNCHLIST FOR
ELECTRICAL ROUGH-IN FLOORS 2 THROUGH 4
109 110 0,3 420 430 15,0
4TH FLOOR
FINISHES
109 205 0,12 410 420 10,0
4TH FLOOR
STUD & DRYWALL
200 208 10,0
2ND FLOOR
MECHANICAL
300 308 10,0 425 430 0,5
3RD FLOOR
MECHANICAL
400 408 10,0
4TH FLOOR
MECHANICAL
205 209 7,9 420 425 10,5
2ND FLOOR 4TH FLOOR
ELECTRICAL ROUGH-IN ELECTRICAL FINISHES
209 305 0,9
4
2000 2001
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN
3 10 17 24 31 7 14 21 28 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29
0 10 0,47 40 50 15,0 120 130 15,0140 150 0,0
NOTICE TO SLAB ON 1ST FLOOR 1ST FLOOR TURNOVER FOR
PROCEED GRADE FINISHES COMMERCIAL RENTAL INCOME
10 20 5,47 30 40 15,0 60 70 15,0 80 90 15,0 100 108 10,0 130 140 10,0
MOBILIZE STRUCTURAL STEEL SLAB ON ROOF DECK 1ST FLOOR 1ST FLOOR
FLOORS 1 TO 5 DECK FLOOR 3 & ROOFING MECHANICAL PUNCHLIST
0 20 52,0 20 30 20,0 50 60 15,0 70 80 15,0 90 100 20,0 110 120 10,0 150 450 30,0
INTERNAL ACTIVITY TO FOUNDATIONS - START NOT SLAB ON SLAB ON CURTAIN WALL 1ST FLOOR INTERNAL ACTIVITY TO
SUPPORT SNET 15MAR00 EARLIER THAN 15MAR00 DECK FLOOR 2 DECK FLOOR 4 INSTALLATION STUD & DRYWALL SUPPORT FNLT 14OCT00
105 109 7,3 225 430 0,25 430 440 10,0
1ST FLOOR PUNCHLIST FOR
ELECTRICAL ROUGH-IN FLOORS 2 THROUGH 4
INTERNAL ACTIVITY 0 - 20 CREATED 109 110 0,3 420 430 15,0
4TH FLOOR
TO SUPPORT SNET 15MAR00 CONTRAINT 109 205 0,12
FINISHES
410 420 10,0
4TH FLOOR
STUD & DRYWALL
200 208 10,0 440 450 0,0
2ND FLOOR FLOORS 2 - 4 TURNOVER
MECHANICAL FOR RESIDENTIAL RENTAL
INTERNAL ACTIVITY 150 - 450 CREATED 300 308 10,0 425 430 0,5
3RD FLOOR
MECHANICAL
TO SUPPORT FNLT 14NOV00 CONSTRAINT 400 408 10,0
4TH FLOOR
MECHANICAL
205 209 7,9 420 425 10,5
2ND FLOOR 4TH FLOOR
ELECTRICAL ROUGH-IN ELECTRICAL FINISHES
209 305 0,9
Figure 9.8.1 Internal logic for supporting SNET and FNLT constraints.
5
Figure 9.11.1 FNLT box, if used, will set this date as LF of project.
Figure 9.11.2 FNLT box, if used, will set earlier of this date or calculated LF as the LF of this activity
6
Figure 9.11.3 Filter defining critical as all activities with less than 11 days total float.
Figure 9.11.4 Sort instruction to list by early start, then by most critical for each date.
7
Figure 9.11.5 Graphic created by use of filter and sort instruction to list only near-critical activities.
Figure 9.11.6 Critical Activities to be designated as all those with under 11 days of total float.
8
Figure 9.11.7 Critical Activities now designated as those with under 11 days of total float.
Figure 9.11.8 Critical Activities now designated as those with under 11 days of total float
9
Figure 9.14.1 Choice of Retained Logic vs. Progress Override
10
Figure 9.17.1 Activity Code Dictionary and Organize dialog boxes.
11
Figure 9.17.3 Detail of project organized by subcontractor
12
Figure 9.17.5 Summary Bar Dialog Box
Figure 9.20.1 Configuration screen to choose linkage of percent complete schedule vs. cost
13
ACTIVITY FORM DINI
I node: 3 J node: 13 TF: 0
Title: Hammock #1 PCT: 0.0
ES: 14JUN00 EF: 21JUL00 Orig. duration: 27* Actual Start:
Activity Codes:
--------------------------------------------------------------------------------
DATE CONSTRAINTS:
14
TD-01 DINI
ORIG
I NODE J NODE DUR DESCRIPTION
------ ------ ----- ------------------------------------------------
2 3 2 ROUGH GRADE
3 13 27* Hammock #1
3 4 15 DRILL WELL
3 6 4 WATER TANK FOUNDATIONS
3 9 10 EXCAVATE FOR SEWER
3 10 1 EXCAVATE ELECTRIC MANHOLES
3 12 6 OVERHEAD POLE LINE
4 5 2 INSTALL WELL PUMP
5 8 8 UNDERGROUND WATER PIPING
6 7 10 ERECT WATER TANK
7 8 10 TANK PIPING & VALVES
8 13 2 CONNECT WATER PIPING
9 11 5 INSTALL SEWER AND BACKFILL
10 11 5 INSTALL ELECTRICAL MANHOLES
11 12 3 INSTALL ELECTRICAL DUCT BANK
12 13 5 PULL IN FEEDER
13 14 1 BUILDING LAYOUT
--------------------------------------------------------------------------------
ACT ID: DES: RES: ACC:
--------------------------------------------------------------------------------
Commands: Add Copy Delete Edit Help Insert-res Next Return autoSort Table
Figure 11.6.1a Hammock in ADM
1 2 3 4 5 6 7 8 9 10 11 12 13
22 22
EXCAVATE FOR SEWER/ INSTALL SEWER AND INSTALL ELECTRICAL
10/ 9 BACKFILL/5/ 11 DUCT BANK/3/
21 21
EXCAVATE ELECTRIC INSTALL ELECTRICAL
MANHOLES/1/ 10 MANHOLES/5/
20 20
19 19
WATER TANK TANK PIPING &
FOUNDATIONS/4/ 6 ERECT WATER TANK/10/ 7 VALVES/10/
18 18
UNDERGROUND WATER CONNECT WATER
DRILL WELL/15/ 4 INSTALL WELL PUMP/2/ 5 PIPING/8/ 8 PIPING/2/
17 17
15
Figure 11.6.2 Hammock in PDM
Figure 11.6.3 Cannot create a hammock from Activity #12 to #300 as start of #13 is driven by #8
16
Figure 11.6.4 Cannot create a hammock from Act #12 to #300 in PDM except with dummy activity
17
NOTE ERRONEOUS REPORTING OF 5 DAY LAG USED TO
TF=2 FOR PREDECESSOR TO #220 INCLUDE 7 DAY CURE
18
Figure 11.12.2 Hammock as included activity accepted by P3 and SureTrak, but not by P3e/c
Figure 12.2.1 CPM calculates completion on 02APR01, MCA SPERT calculates 85% chance of completion by 11MAY01
19
Figure 12.2.2 Pertmasters MCA software calculates the Activity #30 has only a 52% chance of being critical
20
Figure 12.2.3 Comparison of CPM calculation (second bar) to that of SPERT (first bar) default distribution
21
Figure 12.2.4 Pertmaster calculates 91 of 154 activities of John Doe project will never become critical, 19 activities have a 51%
to 60% chance of becoming critical, only 3 have a 81% to 90% of becoming critical, none are guaranteed to be critical.
22
Figure 13.5.2 Options to start new, open existing, open recent , or import a project
23
Figure 13.5.4 Choosing to display the restraints between activities
24
Figure 13.5.6 Dialog boxes for setting data details on restraints
25
Figure 13.5.8 Example where restraints for movement of ironworker crew are globally Ignored
Figure 13.5.9 Wallpaper to be applied after one of several walls is plastered prepare to split activity
26
Figure 13.5.10 Activity 140 is split, a virtual PS4 restraint created to Activity 180
Figure 13.5.11 PS4 logic from activity 150 portion of 140 to 180 is not shown
27
Figure 13.6.3 Pertmaster supports stretched duration activities
28
Figure 14.2.1 Comparison of P3 and Suretrak Schedule Option Screens
29
Figure 14.3.2 Opening Screen to P6 via a web browser
30
Figure 14.4.2 Adding and placing a new Enterprise
31
Figure 14.4.3 Process of adding a new project to the database.
32
Figure 14.4.4 Opening the Program Manager and choosing a project.
33
Figure 14.4.5 Selecting global or project level codes.
34
Figure 14.4.7 Three levels of codes.
35
Figure 14.5.1 Project Activity Data inTabular and Bar-chart View
36
Figure 14.5.3 P6 Calendar View Expanded to JULY
Figure 14.6.1 Process to create a reflection project from an existing update or baseline
37
Figure 14.6.2 Initiation of the merge reflection project process
38
Figure 14.10.1 Pertmaster Open-End Diagnostic
Figure 14.10.2 Risk Register maps correlation of common risks to multiple activities
39
Figure 14.10.3 Pertmaster risk analysis typically set for 1000 iterations
Compare deterministic
schedule vs. a
probabilistic schedule
(P50 & P80)
40
Figure 14.11.1 Opening a New Project with MSProject 2007
41
Figure 14.11.5 Adding New Activities and Setting Restraints Between Activities
Figure 14.11.6 Dialog Box for Entry of Predecessor Restraint Detail Information
42
Figure 14.11.7 Inserting New Activities and Replacing Predecessor Column with Unique Predecessor
Figure 14.11.8 Inserting New Columns for Remaining Duration, Percent Complete and Actual Start
43
Figure 14.11.9 Reporting % Complete Initiates Some Recalculations of Remaining Duration and Dates
Figure 14.11.10 Entering Actual Start/Finish Data, and Setting/Displaying the Data Date for this Update
44
Figure 14.11.11 Displaying the Tracking Toolbar and Rescheduling Work Based Upon Inputs
45
Figure 14.11.13 Selected View of John Doe Project in MSProject2007
46
WhileinOpenPlanselecttoolsonthemenubar
ThenclickDataSources
SelectDataSourceyouwanttoreadfrom
47
Figure 14.12.2 Open Plan Project Properties User may set default calendar for lags, but not to predecessor
Figure 12.12..3 Open Plan Activity Details dialog box at Relationships tab
48
Figure 12.6.4 Open Plan Network View
49
Figure 14.12.5 Open Plan Pure Logic Views (Zoomed Out and In) of John Doe Project
50
Figure 14.12.6 Open Plan bar chart showing Monte Carlo risk analysis data
Bar chart highlights criticality index and mean dates
Green = Never Critical Yellow = 0-50% chance of being critical
Red = 51-100% chance of being critical Gray bar represents Mean Early Start Mean Early Finish bar
51
In P3e/c there is the option to choose which calendar will be assigned as a default. The drop-down box choice of
calendar and long-name description of calendar reduces the potential confusion of designation of Calendar #1 or #2
or #3, but also increases the width of column required to display this information and may increase the effort
required to enter the information.
This too can be ameliorated by renaming your standard calendars as 5D, 6D and 7D, renaming the column
from Calendar to Cal and adjusting the column width appropriately.
52
Figure 16.7.2 Multiple cost codes for one activity means activity is listed several times in cost reports
In Primavera P3 Project Planner, a means exists to get around the Building A, 5th Floor, NW Quadrant coding
noted in the preceding section by the use of Aliases.
53
54
Figure 16.9.2 Primavera Alias illustrated
Figure 18.5.1 Pertmaster analysis measures likelihood that a change in duration of one activity may shift the critical path
55
Figure 18.8.1 Global Calendar and global holiday list
56
Figure 18.8.3 7-Day Calendar and Holiday List Exceptions
57
Figure 19.18.1 Schedule calculation algorithm switches
58
Figure 20.7.2 John Doe in PDM Plant-Warehouse
Figure 20.7.2 John Doe in PDM Warehouse alternate view (not in text)
59
Figure 20.7.3 Detail of John Doe 20.7.2 Confluence at Building Watertight milestone event
60
Figure 20.7.4 John Doe in PDM Office
61
Figure 20.7.5 Detail of John Doe 20.7.2 Confluence shown with Milestone (ADM node 37)
62
Figure 20.7.6 Detail of John Doe 18.7.2 Combining activities 35 and 409 in PDM
63
Figure 20.8.1 John Doe project in RDM format. Compare to Figures 20.5.4 (in ADM) and 20.7.2 (in PDM). Note
special restraint (link) categories from Activity 300 to 301 (R=resource, use same crew) and from 701 to 307
(J=Just-in-Time). Also note use of dedicated Milestones at Event 37e and 58e.
Figure 21.10.1 John Doe project resource histogram and cumulative curve for early dates
64
Figure 21.10.2 Resource histogram with stacked resources
65
Figure 21.10.4 John Doe projectleveled for a maximum of 10 electricians
Figure 24.10.1 Critical Path for a One Path Linear Project (Based on John Doe Project)
66
%
100
9
90
8
80
7
70
60
%
50
40
3
30
2
20
1
10
0 0
6 13 20 27 3 10 17
DEC DEC DEC DEC JAN JAN JAN
04 04 04 04 05 05 05
LATEST DATE 18 JAN 5 6001MPRJ.MC Sheet 1 of 1
EXPECTED DATE 27 DEC 4
Probability Analysis Date Revision Checked Approved
EARLIEST DATE 8 DEC 4
TARGET DATE 21 DEC 04 John Doe Critical Path Activities
Standard -15%/+20% Distribution
Plot Date 27OCT04
(c) Primavera Systems, Inc. Finish Date of Project
Figure 24.10.3 Alternate Critical Paths for a project without long duration procurement activities
67
%
100 10
90 9
80 8
70 7
60 6
%
50 5
40 4
30 3
20 2
10 1
0 0
6 13 20 27 3 10 17
DEC DEC DEC DEC JAN JAN JAN
04 04 04 04 05 05 05
LATEST DATE 17 JAN 5 6 0 02 M PR J .M C S h ee t 1 of 1
EXPECTED DATE 27 DEC 4
Probability Analysis Date Revision Checked Approved
EARLIEST DATE 7 DEC 4
TARGET DATE 21 DEC 04 John Doe without Procurement
Standard -15%/+20% Distribution
Plot Date 27OCT04
(c) Primavera Systems, Inc. Finish Date of Project
Figure 24.10.4 Probability for a project without long duration procurement activities
Figure 24.10.5 Alternate Critical Path for a project with long duration procurement activities
%
100
7
90
6
80
70
5
60
%
50
3
40
30
2
20
1
10
0 0
13 20 27 3 10 17 24 31 7
DEC DEC DEC JAN JAN JAN JAN JAN FEB
04 04 04 05 05 05 05 05 05
LATEST DATE 7 FEB 5 5O E0 M PR J. MC Sh e et 1 of 1
CPM IN CONSTRUCTION MANAGEMENT - 5TH EDITI
EXPECTED DATE 8 JAN 5
O'BRIEN KREITZBERG & ASSOC., INC. Date Revision Checked Approved
EARLIEST DATE 14 DEC 4
TARGET DATE 22 DEC 04 JOHN DOE PROJECT PDM VERSION
Standard -15%/+20% Distribution
Plot Date 27OCT04
(c) Primavera Systems, Inc. Finish Date of Project
Figure 24.10.6 Probability for a project with long duration procurement activities
68
Figure 25.3.4 Computer generated cost forecast for the John Doe projectEarly & LateCumulative.
Figure 25.3.5 Computer generated cost forecast for the John Doe projectEarly datesCumulative and Histogram.
69
Figure 26.6.1 Microsoft screen to open an existing project from any subdirectory in the world
70
Figure 26.6.4 Microsoft Project Professional 2007 Dashboard
71
Figure 27.1.1 Opening a new project in P3
72
Figure 27.1.3 Autolink
Figure 27.2.1
73
Figure 27.2.2
Figure 27.2.3
74
Figure 27.8.1 Two concurrent critical paths cannot be distinguished in a simple Early Start printout
75
Figure 27.8.4 Backward pass of alternate critical paths
76
Figure 27.8.5 Grouping by PLOT code
77
Figure 27.8.7 Filter for Winter Concrete
78
Figure 27.8.10 Organization
79
Figure 27.9.1 Timescale overview content
80
Figure 27.9.4 Time Scaled Logic Diagram of John Doe Project by Netpoint GPM software
81
Figure 27.9.6 CASCAD-e software Logic OFF, Logic ON
Figure 27.9.7 Time Scaled Logic Diagram of John Doe Project by CASCAD-e software
82
Figure 27.14-1 Superintendents Turn-Around Document
83
Figure 28.4.1 Choice of algorithm
Figure 29.13.2 P3e/c does not allow user to status a reduced remaining duration until an actual start date is entered
84
Activity A is followed by Activity B via a Start-to-Start relationship with 15 day lag (all days are calendar days)
Activity A is statused to RD=10 on 06MAY06 (ahead of schedule) but actual start date is not entered
But if actual start of 01MAY06 is entered for Activity A, early start of 16MAY06 is calculated for Activity B
85
If Activity A is statused 100% complete without an actual start of finish date, early start of 21MAY06 is calculated for Activity B
If Activity A is statused 100% complete with an actual start but not an actual finish, P3 illustrates a bar finishing the original
estimated finish date but does not record that date on tabular format, and continues to calculate Activity B lag from 01MAY06
Even if Activity A is completed three weeks early, and all actual dates reported, the early start of Activity B is still calculated as
01MAY06 plus 15 days. Is this what the superintendent meant when saying Activity A is expected to take 20 days, Activity B
can start when Activity A is done?
Updating without an actual start date does not reduce the remaining lag
Now that an actual start, but not finish, has been reported, updating reduces the remaining lag
Continued updating with an actual start but without actual finish eventually allows next activity to start
Figure 29.13.3 Problems with reporting status for durations of activities and durations between activities
86
8/10 8/10
8/11 80% 8/13
chipped inlet hold 20%
87
Figure 31.1.2 Project Overview rename version
88
1997
APR MAY JUN JUL
21 28 5 12 19 26 2 9 16 23 30
SPAN #2 24500 2,11 24600 3,10 24700 1,7 24830 3,8 24870 3,7
RB SPAN#2 ERECT RB SPAN#2 STAY IN RB SPAN#2 RB POUR#2A RB POUR#4
STRUC STEEL PLACE METAL FORMS SHEAR CONNECTOR FORM & POUR DECK FORM & POUR DECK
24780 4,7
RB SPAN#3
REBAR
24770 4,7
RB SPAN#4
REBAR
SPAN #5 24530 2,11 24620 3,11 24710 1,7 24820 3,21 24880 1,9
RB SPAN#5 ERECT RB SPAN#5 STAY IN RB SPAN#5 RB SET STRIP RB POUR STRIP
STRUC STEEL PLACE METAL FORMS SHEAR CONNECTOR SEAL DAMS SEAL BLOCKOUTS
SPAN #2 24500 2,20 24600 3,18 24700 1,18 24760 4,15 24830 3,15 24870 3,15
RB SPAN#2 ERECT RB SPAN#2 STAY IN RB SPAN#2 RB SPAN#2 RB POUR#2A RB POUR#4
STRUC STEEL PLACE METAL FORMS SHEAR CONNECTOR REBAR FORM & POUR DECK FORM & POUR DECK
SPAN #3 24510 2,21 24610 3,18 24670 4,16 24730 1,19 24900 3,15
RB SPAN#3 ERECT RB SPAN#3 STAY IN RB SPAN#3 RB SPAN#3 RB POUR#5
STRUC STEEL PLACE METAL FORMS OVERHANG FORMWORK SHEAR CONNECTOR FORM & POUR DECK
SPAN #4 24520 2,22 24630 3,23 24680 4,16 24770 15 24840 3,15
RB SPAN#4 ERECT RB SPAN#4 STAY IN RB SPAN#4 RB SPAN#4 RB POUR#2B
STRUC STEEL PLACE METAL FORMS OVERHANG FORMWORK REBAR FORM & POUR DECK
Activity Classification: TYPE OF WORK The Phoenixville - Mont Clare Bridge Replacement over the Schuykill River is part of a PennDOT project
ERECT STRUCTURAL STEEL R/I UTILITIES & DRAINAGE STAY IN PLACE METAL FORMS OVERHANG FORMWORK with a $12,000 per day incentive/disincentive contract clause.
Project Finish 25NOV97 * PENNDOT RT 29 SEC. 6B & 6M headed by Fredric L. Plotnick, Esq., P.E., was the scheduling consultant.
Figure 33.12.3 Impact of the modified sequence upon the traditional approach
89
Figure 33.13.2 Summary of work on 2nd floor with partial detail shown
90
1990
CODE TOTL JAN FEB MAR APR
VALUE TASK FLR /TASK FLT 2 3 4 5 6 7 8 9 10 11 12 13 14 15
020 20 LOWER LEVEL INSTALL STUDS 23
022 22 LOWER LEVEL INSTALL DRYWALL 43
024 24 LOWER LEVEL TAPE DRYWALL 43
026 26 LOWER LEVEL APPLY FLOORING 18
030 30 LOWER LEVEL INSTALL CEILING GRID 16
034 34 LOWER LEVEL INSTALL CEILING LIGHTING 17
060 60 LOWER LEVEL INSTALL CASEWORK 44
062 62 LOWER LEVEL INSTALL CASEWORK ELECTRIC 46
070 70 LOWER LEVEL INSTALL PLUMBING FIXTURES 48
0EQ EQ LOWER LEVEL INSTALL EQUIPMENT 16
120 20 FIRST FLOOR INSTALL STUDS 25
122 22 FIRST FLOOR INSTALL DRYWALL 28
124 24 FIRST FLOOR TAPE DRYWALL 33
126 26 FIRST FLOOR APPLY FLOORING 35
130 30 FIRST FLOOR INSTALL CEILING GRID 34
134 34 FIRST FLOOR INSTALL CEILING LIGHTING 35
160 60 FIRST FLOOR INSTALL CASEWORK 34
162 62 FIRST FLOOR INSTALL CASEWORK ELECTRIC 36
170 70 FIRST FLOOR INSTALL PLUMBING FIXTURES 49
1EQ EQ FIRST FLOOR INSTALL EQUIPMENT 40
220 20 SECOND FLOOR INSTALL STUDS 26
222 22 SECOND FLOOR INSTALL DRYWALL 27
224 24 SECOND FLOOR TAPE DRYWALL 18
226 26 SECOND FLOOR APPLY FLOORING 43
230 30 SECOND FLOOR INSTALL CEILING GRID 40
234 34 SECOND FLOOR INSTALL CEILING LIGHTING 42
260 60 SECOND FLOOR INSTALL CASEWORK 40
262 62 SECOND FLOOR INSTALL CASEWORK ELECTRIC 43
270 70 SECOND FLOOR INSTALL PLUMBING FIXTURES 47
320 20 THIRD FLOOR INSTALL STUDS 29
322 22 THIRD FLOOR INSTALL DRYWALL 18
324 24 THIRD FLOOR TAPE DRYWALL 20
326 26 THIRD FLOOR APPLY FLOORING 26
330 30 THIRD FLOOR INSTALL CEILING GRID 24
334 34 THIRD FLOOR INSTALL CEILING LIGHTING 26
360 60 THIRD FLOOR INSTALL CASEWORK 42
362 62 THIRD FLOOR INSTALL CASEWORK ELECTRIC 45
370 70 THIRD FLOOR INSTALL PLUMBING FIXTURES 48
3EQ EQ THIRD FLOOR INSTALL EQUIPMENT -5
420 20 FOURTH FLOOR INSTALL STUDS 29
422 22 FOURTH FLOOR INSTALL DRYWALL 26
424 24 FOURTH FLOOR TAPE DRYWALL 30
426 26 FOURTH FLOOR APPLY FLOORING 40
430 30 FOURTH FLOOR INSTALL CEILING GRID 39
434 34 FOURTH FLOOR INSTALL CEILING LIGHTING 40
460 60 FOURTH FLOOR INSTALL CASEWORK 39
462 62 FOURTH FLOOR INSTALL CASEWORK ELECTRIC 44
470 70 FOURTH FLOOR INSTALL PLUMBING FIXTURES 48
520 20 FIFTH FLOOR INSTALL STUDS 25
522 22 FIFTH FLOOR INSTALL DRYWALL 7
524 24 FIFTH FLOOR TAPE DRYWALL 35
526 26 FIFTH FLOOR APPLY FLOORING 21
530 30 FIFTH FLOOR INSTALL CEILING GRID 41
534 34 FIFTH FLOOR INSTALL CEILING LIGHTING 21
560 60 FIFTH FLOOR INSTALL CASEWORK 42
562 62 FIFTH FLOOR INSTALL CASEWORK ELECTRIC 44
570 70 FIFTH FLOOR INSTALL PLUMBING FIXTURES 48
5EQ EQ FIFTH FLOOR INSTALL EQUIPMENT 21
CODE TOTL
VALUE TASK FLR /TASK FLT
020 20 LOWER LEVEL INSTALL STUDS 23
022 22 LOWER LEVEL INSTALL DRYWALL 43
024 24 LOWER LEVEL TAPE DRYWALL 43
026 26 LOWER LEVEL APPLY FLOORING 18
030 30 LOWER LEVEL INSTALL CEILING GRID 16
034 34 LOWER LEVEL INSTALL CEILING LIGHTING 17
060 60 LOWER LEVEL INSTALL CASEWORK 44
062 62 LOWER LEVEL INSTALL CASEWORK ELECTRIC 46
070 70 LOWER LEVEL INSTALL PLUMBING FIXTURES 48
0EQ EQ LOWER LEVEL INSTALL EQUIPMENT 16
120 20 FIRST FLOOR INSTALL STUDS 25
122 22 FIRST FLOOR INSTALL DRYWALL 28
124 24 FIRST FLOOR TAPE DRYWALL 33
126 26 FIRST FLOOR APPLY FLOORING 35
Figure 33.13.3 The network has 3503 detail activities, but the owner see only 58 summary activities
Figure 36.15.4 and 38.4.1 Time scale network drawing showing steel delay - TIE Analysis
91
Figure 38.4.2 Collapsed As-Built (But-For) Analysis
92
Figure 38.4.4 Windows Analysis Window #2
93
Figure 38.4.6 Windows Analysis Window #1 Alternate A
94
CHAPTER 14.1 of the CD-ROM (Primavera Project Planner P3 Demo folder; Primavera P3 HowTo.pdf file)
Note references to Chapter 24 are from previous placement in 6th edition
95
Figure 24.1.3 Primavera Quick Open An Existing Project Screen
Figure 24.1.4 Setting a Project Finish Date will cause a project completing earlier to show a positive, non-zero total
float for the critical path.
96
Figure 24.1.5 Setting a FNLT constraint upon the last activity will cause a project completing earlier to show a zero
total float critical path.
Figure 24.1.6 Checking the exclusive box permits changing Activity IDs.
97
Figure 24.1.7 Opening Screen for a New Project
Figure 24.1.8 Point & Click vs. <ALT> keys vs. <CTRL> hot keys.
98
Figure 24.1.9 Barchart portion of screen split vertically.
99
Figure 24.1.10 Barchart portion of screen split horizontally.
Figure 24.1.11 Pure Logic or PERT view of network with Primaveras Trace Logic highlighted
with two generations shown.
100
Figure 24.6.1 Sample Mixed Summary & Detail Screen from point & click exercise, setup.
Figure 24.6.2 Sample Mixed Summary & Detail Screen from point & click exercise, results.
101
Figure 24.7.1 Standard Report SR-06 setup screens
102
Figure 24.8.1 Summary Barchart with Detail Provided, setup and dialog boxes.
103
Figure 24.8.3 Blowup of Section of Summary Barchart with Detail Provided.
104
Figure 24.8.5 Timescale Logic Graphic Report, results.
105
ADDITIONAL GRAPHICS FROM PAST EDITIONS
4800
4400 EARLY
4000
LATE
3600
3200
2800
2400
2000
1600
1200
800
400
0
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
2000 2001
Figure 20.3
x Thousand
1000 990
900 889
800 801
700
628
600
541 538
509
500 482
481
447
435
400
355
300
275 263 268
254 247
100 88
36
8
0
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
2000 2001
Figure 20.4
106
1200
1175 1168
1100
1000
900
800
700
612
600
545
500
400
300 294
200 193
148 158 160
112
100
45
0
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
2000 2001
Figure 20.17
4400
4000
EARLY
3600
3200
2800
LATE
2400
2000
1600
1200
800
400
0
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
2000 2001
Figure 20.8
107