PRESSURE TEST FOR WATERLINES
Project : Sukhotai Model Block 7 Lot 6 and Block 7 Lot 21
Location : Racha Mansions, South Forbes City, Brgy Inchican, Silang , Cavite
Contractor : Elvil Construction
Date Conducted : July 10-11, 2017 Time Started : 8:30 AM
Initial Pressure : 105 psi Time Finished : 8:30 AM
Final Pressure : 100 psi Duration : 24 hrs
Observation : The test was conducted using testing pump with a maximum
gage of 100psi. The initial water pressure was approximately
105 psi at 8:30AM of July 10, 2017. It then dropped to 100 psi
after 24 hrs. It has been observed that the waterline pipes
withstand a 100 psi pressure for both house model.
Performed By: Witnessed By:
Engr. Mark Follero / Engr. Jobert Aliga
Contractor's Representative CLI - Site Engineers