You are on page 1of 7

Proceedings of Pile 2013, June 2-4th 2013

QUANTIFYING THE EFFECT OF LIMITED SITE INVESTIGATION ON THE COST OF


BUILDING CONSTRUCTION WITH PILE FOUNDATION

A. Arsyad, A. Djamaluddin, A. Thaha. T. Harianto, L. Samang

ABSTRACT: It is widely accepted that soil investigation conducted in construction projects is limited. The scope of
soil investigation is dictated by budget allocation rather than the proper need of characterizing soil properties. The
budget allocated for soil investigation ranges from 0.1% to3% of the construction budget. Poor soil investigation can
result in foundation failure leading to construction delay or even structural damage with live loss. Otherwise, it can
cause over-design of foundation with consequence of high project cost. This paper investigated the effect of limited
soil investigation on the cost of foundation work in a building construction project. Case study was undertaken on the
project of Engineering Faculty New Campus in Gowa South Sulawesi Indonesia, located in the sedimentary deposit of
River Jeneberang. To characterize the soil properties of the Geology Building with the area of 200116 m 2, soil
investigations were conducted with limited amount, consisting of 4 CPTs and 2 SPTs. The limited site investigation
was found to increase additional cost of pile foundation, accounted for 21% of the total pile foundation cost.
Therefore, Geostatistical methods including Kriging and Inverse Distance were employed to estimate bearing stratum
of pile foundation with limited site investigation. The use of Geostatistical methods was found to reduce the additional
cost to be 7.14% and 6.21% for Kriging and Inverse Distance respectively. The addition of 3 CPTs into the existing
site investigation conducted was also found to reduce additional cost of pile foundation to be 4.93%. The results
suggested that sufficient amount of site investigation with the use of Geostatistical method could enhance the design
of pile foundation and reduce unpredicted cost of pile foundation during construction.

Keywords: Soil Variability, Pile Foundation, Limited Soil Investigation, Construction Cost.

INTRODUCTION limited SI performed in the New Campus Project of


Faculty of Engineering, Hasanuddin University in Gowa
Over the last 30 years, site investigations (SI) have South Sulawesi. The study evaluates its effect on the
been undertaken in construction projects within limited project cost. Later, in the final section of this paper, the
amount (Institute of Civil Engineers 1991). This is due to study proposes a number of geostatistical methods and
budget allocated for SI is often minimized in order to additional SI to enhance the reliability of SI and design
reduce preliminary cost of project, rather than being of pile foundation.
allocated to characterize properly soil properties. It is
well understood that ground risk is one of the highest
risk in design and construction of civil engineering and CASE STUDY
building project (Littlejohn et al, 1994). Thus, limited SI
will increase the risk, either the risk foundation/structural The project of Engineering Faculty New Campus,
design failure or the risk of additional cost for repair and Hasanuddin Universitys is located about 19 km
additional construction with the consequence of over southeast of Makassar, the capital of South of Sulawesi.
budget (ASFE 1996). There is no clear guidance of The project has been constructing several buildings over
determining the scope of SI for building and civil the area of 630330 m2, including Faculty and Center of
engineering projects. Several countries have established Technology, Civil Engineering, Architecture, Electrical
such code of determining the scope of SI, including Engineering, Mechanical Engineering, Geology
Malaysia, Singapore, Hong Kong, Taiwan, and China Engineering, and Naval Engineering Buildings. The
(Moh, 2004). In contrast, Indonesia has no such object of the study is Geology Building, whose pile
guidance of proper amount of SI. This has resulted in foundations have been constructed since 2011 and
determining the amount of SI on the basis of common recently its structure is under construction. The Geology
practice and personal experience of engineer. Building stands on the area of 200116 m2.
This study investigates the effect of limited SI on For designing pile foundation of the Geology
cost of building construction project, particularly on the Building, the project characterized the soil properties
cost of pile foundation. Case study was undertaken on with 4 cone penetration tests (CPTs) and 2 standard
penetration tests (SPT-borehole). The amount of those
Sis was suggested to be adequate to cover all
variabilities of the soil. CPTs consist of S42, S43, S44,
S45 while SPT-boreholes are B17 and B18. Figure 1
presents the distribution of CPT and SPT data across the
field. It can be seen that SI sampling is combination of 2
CPTs and one SPT-borehole for one building area.
Figure 2 presents the data of CPTs and SPT across
the Geology Building. Due to pile foundation is end-
bearing pile supported by bearing stratum, the CPTs and
SPTs must identify the level where bearing stratum
lying. It was found that the bearing stratum varies from
the shallowest (-5.80 m) to the deepest one (-12.20 m).
The SPTs shows -9.25 m and -10.25 m. The bearing
stratum consists of dark grey sand and fine gravel with
some breccias. As we can see in Figure 2, the bearing
stratum is located under 6 meters yellowish brown silty
clay layer with low plasticity. On the top of silty clay,
there are 2 meter reddish brown clay. The stratigraphy
indicates such transported sediments compacted and High variability of bearing stratum levels, as seen
deposited overlying volcanic rock of Batu Rappe- Figure 2, make determining planned pile length quite
Cindako formation. The sediment is agented by River difficult. That is why the contractor ordered concrete
Jeneberang, a main river located 1.5 km south from The pile (PC Spun type) within various lengths, such as 10
Geology Building. m, 11 m and 12 m as bottom pile and 6 m as top pile.
The 10 m pile can be planted in the northern side of the
building due to the S-42 and B-17 indicated 5.8 meter
and 9.25 m depth of the bearing stratum. 10 m pile was
considered more than enough to cover the northern side.
Otherwise, 12 m pile into the southern side is due to the
S-43 and S-44 showing the bearing stratum at around
10.25 meters. In the south-eastern site, the bearing
stratum is very deep (12.2 m). Therefore, the contractor
planned 12 + 6 m piles to be planted there.

Difference between Designed Pile Length and


Driven Pile Length
As the driving of piles into the ground was
undertaken, the length of pile needed to reach bearing
stratum different than the designed pile length. As a
consequence, the contractor had to order more additional
piles. For instance, nearby Building Geology B, the
contractor estimated that bearing stratum at -10.4 meter
from the CPT S 44b and planted 12 meters pile. Yet, this
estimation was not valid as the driven pile over 14 m.
The pile driving needed several additional 6 m piles,
and the pile constructed became 12 + 6 meter. Such
inaccurate estimation of the bearing stratum was also
found in the eastern part of planned Geology Building B.
The CPT S45 indicates the bearing stratum at 12.20
meters, but the driven pile is around 8-9 meters.
Figure2.CPTsandSPTBoreholesonPlannedGeologyBuilding.

S42
S45

B17
B18
GeologyB
GeologyA
S43
S44

Figure1.PlannedGeologyBuildingandDistributionsofCPTsandSPTBoreholes
estimated as the difference between planned and It is contours. Second is the addition of more 3 CPTs into the
It is shown by Figure 3, the difference between existing CPTs and SPTs to achieve more accurate
designed pile and driven pile is so significant. The estimated bearing stratum.
project must extend the length of pile driven. The piles
need extension is about 35% of the total piles. The Geostatistical Method
bearing stratum seems to be underestimated. It is around Kriging and Inverse Distance methods were
17% of the total piles, the pile had to be cut since the employed to estimate the contour of bearing stratum.
bearing stratum was overestimated. Only 48% of the Kriging (1951), is a geostatistical estimator used to
total piles were well estimated length. If the cost of pile estimate a value of a random field at empty soil data,
extension was quantified, in which the construction cost whereas inverse distance is multivariate interpolation for
of pile with 500 mm diameter is assumed to be 1.5 a known scattered set of soil data points. In this study, by
million rupiahs per meter, it was found that the extension using Kriging and later compared with Inverse Distance
of pile has led to additional cost, about 21% of the total Methods, we estimated bearing stratum depths at
budget allocated (Table 1). locations where CPTs and SPTs do not exist. It can be
seen in Figure 4 that the bearing stratum contours
Table 1. Estimated and Real Cost of Pile Foundations generated using Kriging Method is different than that
generated using Inverse Distance Method. Kriging
Configurations Estimated Real Cost Additional Method indicates one spot in the site with the depth over
of pile Cost (in million cost (in -12.5 m while Inverse Distance shows two spots with the
foundations (in million rupiahs) million depth over -12.5 m.
rupiahs) rupiahs)
45 10 m 675 828 153 1 2 .5
12
3612 m 648 756 108 S42 S45 1 1 .5

78 m 84 84 0 11
1 0 .5
86 m 72 126 54 10

Total 1.479 1.794 315 B17 B18 9 .5


9
Percentage 100% 121% 21% 8 .5
S43 8

S44 7 .5
7
6 .5
6
5 .5

1 2 .5
12
1 1 .5
11
1 0 .5
10
9 .5
9
8 .5
8
7 .5
7
6 .5
Figure3.DifferencebetweenPlannedPileLengthsand 6
PlantedPileLengths 5 .5

(a)
PROPOSED METHOD OF ENHANCING S45
S42 (b)
ESTIMATEDBEARINGSTRATUM
Figure 4. Bearing Stratum Contours drawn using (a)
In order to achieve a reliable estimation of bearing Kriging and (b) Inverse Distance Methods.
B17
stratum of pile foundation designed for Geology B18
Building, two techniques can be implemented. First is These contours were evaluated by comparing them
the use of Geostatistical method including Kriging and S43stratum contours generated using the
with the bearing
S44construction. The real
data of driven piles during the
Inverse Distance methods to draw bearing stratum
bearing stratum contour indicates two spots with depth
about -15 m lying at the center, northern side and
western side of the field (Figure 5). It was also
observed that the contour generated using Inverse
Distance shows more similarity to the real bearing
stratum. However, both Kriging and Inverse Distance
methods infer such lack of accurate estimation
particularly the maximum depth of bearing stratum. In
this case, either Kriging or Inverse Distance suggested
-12.5 m as maximum depth while the existing bearing
stratum suggested -15 m.

15
1 4 .5
14
1 3 .5
13
1 2 .5
12
1 1 .5
11
1 0 .5
10
9 .5
9
8 .5
8
7 .5
7
6 .5
6

(a)
(b)
Figure 5. Bearing Stratum Contour Generated based Figure 6. Comparison between Designed Pile
on Data of Driven Piles during the Construction. Lengths and Constructed Pile Lengths Generated by (a)
Kriging and (b) Inverse Distance
Figure 6 presents the comparison between planned Addition of more 3 CPTs
pile and planted pile using Kriging and Inverse Distance. Even though Geostatistical methods was performed,
Both Kriging and Inverse Distance are able to reduce the the gap between designed pile and constructed pile
gap between the planned (designed) and planted lengths was still found. Therefore, we added more 3
(constructed) pile. The Inverse Distance shows more CPTs and evaluated its effect on the estimation of
significant effect of reducing the gap compared to the bearing stratum under the Geology Building. In this
Kriging method. way, 3 CPTs were added to the existing 4 CPTs and 2
SPTs. The additional CPTs were located at the west and
south corners (SA-1, SA-2) and the centers (SA-3) of the
Building Geology A (Figure 7). SA-1 identifies the
bearing stratum at -9 m, while SA-2 indicates the bearing
stratum at -8.8 and SA-3 at -13 m. The additional CPTs
appears to enhance the contour of bearing stratum
(Figure 8). The contour becomes more similar to the real
bearing stratum contour. The additional CPTs also can
improve the designed pile lengths and its gap to the
constructed pile lengths lessen. As we can see in Figure
9, the gap between the designed and constructed pile
lengths becoming smaller.
Table 2 shows the effect of using geostatistical
method and additional SI on the discrepancy between
estimated cost and real cost. The additional CPTs was
found to improve the reliability of designed pile lengths
and estimated cost of the pile foundation. The project
just bears the additional cost, accounted for 4.93% of the
total project budget. On the other hand, the use of
Geostatistical method can reduce additional cost to be

SA3

SA1
SA2
7.14% and 6.21% for Kriging and Inverse Distance Additional 1,705.0 1,794 88.5 (4.93%)
respectively. CPTs

CONCLUSSIONS

1. Limited SI can cause additional cost of pile


foundation. For the case of pile foundation at
Geology Building, the project must afford 21%
additional cost due to the SI with 4 CPTs and 2
SPTs is too limited to characterize properly
bearing stratum of the field.
2. The additional cost can be reduced by
Figure 7. Additional 3 CPTs in the Geology Building. performing Geostatistical methods such as
Kriging and Inverse Distance to estimate bearing
13
1 2 .5 stratum contours.
12
1 1 .5
3. The Inverse Distance seems to be more effective
11 to estimate bearing stratum contours of pile
1 0 .5
10 foundation with limited SI.
9 .5
4. By adding 3 CPTs into existing 4 CPTs and 2
9
8 .5 SPTs, the estimated bearing stratum can be
8
7 .5
enhanced. Therefore, the additional cost, which
7 is caused by inaccurate estimated bearing
6 .5
6 stratum, can be minimized, accounted for 4.93%
5 .5
of the total cost of pile foundation.
Figure 8. Bearing Stratum Contours Generated using
Existing 4 CPTs and 2 SPTs and additional 3 CPTs.

ACKNOWLEDGMENTS
The authors would like to thank to the Project
Implemented Unit (PIU) of New Campus of Engineering
Faculty Hasanuddin University for sharing the data of
the project.

REFERENCES
Figure 8. Gap between Designed and Constructed
Pile Lengths due to the additional 3 CPTs. ASFE. (1996). Case Histories of Professional Liability
Losses: ASFE Case Histories, ASFE: Professional
Firms Practicing in the Geosciences, Maryland, USA.
Table 2. Estimated and Real Cost due the use of Institution of Civil Engineers. 1991. Inadequate site
Geostatistical Method and additional CPTs investigation, Thomas Telford, London.
Krige D G. (1951). "A Statistical Approach to Some
Estimated Real Cost Additional
Mine Valuations and Allied Problems at the
Cost (in million cost (in million
Witwatersrand," unpublished Master's Thesis,
(in million rupiahs) rupiahs)
University of Witwatersrand.
rupiahs)
Littlejohn, G. S., Cole, K. W., and Mellors, T. W. (1994).
"Without Site Investigation Ground is a Hazard."
Kriging 1,665.9 1,794 128.1 (7.14%)
Proceeding of Institution of Civil Engineers, 102.,
Inverse 1,682.55 1,794 111.45
pp.72-78.
Distance (6.21%)
Moh, Z.C. (2004). Site investigation and geotechnical
failures. International Conference on Structural and
Foundation Failures, Singapore.

You might also like