You are on page 1of 8

Fast cycling and rapid start-up:

new generation of plants


achieves impressive results
Reprint from:
Modern Power Systems, January 2011

Author:
Lothar Balling, Siemens AG,
Erlangen, Germany

Answers for energy.


COMBINED CYCLE

Fast cycling and rapid start-up:


new generation of plants
achieves impressive results
In last months issue an analysis of the operational characteristics of various power generation technologies
(pp 61-65) concluded that modern combined cycle power plants, with cycling and fast start capabilities, have
a number of advantages in a grid where a large percentage of renewables is envisaged, as in Germany, for
example. In this second article the theme of combined cycle plant operational flexibility is explored further.
Recent innovations in combined cycle technology are described, as well as newly commissioned power plants
that demonstrate what can be achieved.

Figure 1. Recent combined cycle projects with enhanced flexibility and fast start capabilities
Lothar Balling, Siemens,
Erlangen, Germany

he increased use of combined cycle

T plants for power generation over the


past decade can be attributed to their
high efficiencies, short execution times
and relatively low investment costs. But now
their potential for cycling and fast start-up is
becoming an increasingly important selling
point.
This need for increased flexibility first Pont sur Sambre, France Sloe Centrale, Netherlands
emerged at the end of the 1990s in the United
States and the United Kingdom. The price of
fuel continued to rise due to the large number
of plants being built during the boom. Plants
initially planned to have a base-load role were
shifted to the load regime of an intermediate-
load plant.
The challenge presented to projects by this
changed requirement gave birth to the idea of
trying to improve plant flexibility without
compromising plant service life or plant
efficiency.
As the market continued to develop, a Marchwood, England Pego, Portugal
demand for quicker start-ups soon followed
the demand for more frequent start-ups. This
market demand finally resulted in the launch
by Siemens of a development project called
FACY (FAst CYcling), which combined all
the initial engineering ideas into a single
integrated plant concept. The aim of the
resulting R&D programme was to design a
plant for an increased number of starts and to
reduce start-up times. If possible, no limits
were to be placed on the gas turbine by other
power plant components, such as the heat
recovery steam generator or steam turbine, Enecogen, Netherlands Hemweg and Diemen, Netherlands
during hot and warm starts.
In the course of the project, potential areas
came to light where further optimisation could until certain steam parameters have been While the first generation FACY reduced
be achieved, although these had to wait for a reached were eliminated as part of the start-up times for a hot start from 100 to 55
second development generation to be shortened Start on the Fly start-up minutes, the second generation succeeded in
implemented. procedure. In this procedure, the steam pushing start-up times down below the 40
The major improvement offered by this turbine is started up in parallel to the gas minute mark.
second generation involved the start-up turbine using the first steam which becomes The first plants incorporating the features of
procedure. Hold points at which a plant waits available after a hot start. both the first and second generations of the

2 www.modernpowersystems.com January 2010 Modern Power Systems


$0.#*/&%$:$-&

'JHVSF5IFSJTFPGSFOFXBCMFT &6
'JHVSF.BJOGFBUVSFTPGUIF'BTU$ZDMJOH '"$:
DPODFQU

&MFDUSJDJUZQSPEVDUJPO
58I
3FOFXBCMFT Stack damper
)ZESP
 'PTTJM
/VDMFBS ST stress
 controller BENSON technology
HRSG stand-by
 7% 18% heating

 10%
10%


54% 48% Condensate
 polishing plant
Optimised
 GT load ramp
 29% 24% High-capacity
de-superheater



FACY concept have now entered commercial High availability and reliability power '"TU$:DMJOHDPODFQU '"$:

operation (Figure 1). plants, such as combined cycle units, are The idea of focusing plant design on an
A good example is Sloe Centrale, a 2 x 430 required in order to compensate for increased number of fast starts originated
MW F-class single shaft plant in the fluctuating renewables. The requirements from market conditions and from specific
Netherlands, where 30-minute start-up with respect to grid support, which are usually projects. A multidisciplinary team of
times were recorded during acceptance tests, defined in a country-specific grid code, have component and plant experts (for the steam
while achieving over 59% net efficiency. recently become more rigorous for this reason. turbine, gas turbine, balance of plant and
Equally good results have been exhibited by Some of the most stringent requirements are auxiliary systems, I&C and steam generator)
other newly commissioned plants. This to be found in the UK grid code. Requirements was formed by Siemens around 2002 to
means that the second generation of FACY in the areas of load stabilisation at low identify improvement potential in the existing
has far surpassed expectations in a number frequencies, primary and secondary frequency plant concepts.
of cases. response, and island operation capability have The team identified the following priorities:
Shortening start-up times and improving presented a particular challenge to UK Maintaining pressure and temperature in
starting reliability while increasing the operators for quite some time. However, the the main components during shutdowns, by
number of starts was only one of many new recently handed over 840 MW multi-shaft F- using stack dampers, auxiliary steam, etc.
requirements with respect to plant flexibility. class Marchwood plant has finally Ready-for-operation water/steam cycle
An increasingly important driver (as demonstrated that the problem can be solved using a fully automated start-up concept
discussed in last months article) is the growing without compromising efficiency (over 58%) without manual operation or intervention
percentage of renewables envisaged on the by introducing additional technical features during hot start.
grid (see Figure 2). Wind and solar energy are and optimising the plant concept. Optimised component design (eg, high
not continuously available and difficult to A decisive factor in the success of Marchwood capacity and fast acting de-superheaters)
predict precisely. Reserve power generating was the integrated approach, which combined and plant operation to reduce material
capabilities must therefore be provided which the potentials of several systems and fatigue caused by load cycling.
can be activated quickly. Gas turbine based components in a single solution, including use Flexible operation concept to allow the
plants are an obvious choice here as they can of gas turbine compressor optimisation, firing operator to predetermine component
be started up at relatively short notice. The reserves, fast wet compression and other fatigue and to choose start-up time and
inherent inertia of other types of power measures, combined with an optimised ramp rate.
generating facilities is usually much greater, I&C/closed-loop control concept. Optimisation of the automation and control
making them largely unsuitable for use as a The new demand for extremely fast power concept.
rapidly available reserve source of power. generating availability is also becoming New start-up sequence, Start on the Fly,
There are, of course, other fast-responding apparent in CCGT developers economic to allow a nearly unrestrained ramp-up.
sources of power such as pumped storage. But assessments. Only a few years ago there were Figure 3 summarises the main features of the
they do not provide enough capacity to cover projects in which start-up times did not FACY concept. These measures help reduce
the renewable generating capacity in the figure at all in the assessment, whereas now start-up time significantly. They are modular
European grid system, with the prospect of we are seeing over 100 000 /min for some and are offered, configured and implemented
30% renewables by 2030. projects. on a project-specific basis.

'JHVSF%SVNUZQF)34(WT#FOTPOUZQF)34( Preserving warm start conditions


Major heat loss from the HRSG occurs
Drum-type HRSG Once-through BENSON through the stack and therefore a stack
damper is deployed to limit heat loss during
%SVN shut-down. Cooling down of the HRSG is
4FQBSBUPS considerably reduced and delayed.
4FQBSBUJPOPG Furthermore, auxiliary steam can be used to
XBUFSBOE
TUFBN %JSFDU heat the HRSG. These measures increase the
FWBQPSBUJPO
shut-down periods for which the criteria for
hot and warm starts remain applicable.
Exhaust gas flow Exhaust gas flow Ready-for-operation mode of water/steam cycle
Auxiliary steam is also used to maintain the
water/steam cycle in a ready-for-operation
mode. This means auxiliary steam is fed into
the gland steam system of the steam turbine.
Keeping the gland steam system in operation
Superheater Evaporator Superheater Evaporator prevents air from being drawn into the steam
turbine and the condenser. Since the steam

3
$0.#*/&%$:$-&

'JHVSFi4UBSUPOUIF'MZum BOJNQSPWFETUBSUVQTFRVFODF 'JHVSF5IF.8


1POUTVS4BNCSF
DPNCJOFEDZDMFQMBOU
Parallel loading
of steam turbine Improved Conventional 4$$'4

and gas turbine start-up sequence start-up sequence


Plant load

Improvement GT and ST
loading

27 min
Steam take
over
Load hold to wait for
ST start-up 4QFFE

GT loading Time &YIBVTUUFNQ


1MBOU
PVUQVU

turbine and the condenser are sealed off from be significantly


the ambient air, the condenser vacuum pumps increased, by
can maintain the vacuum. reducing stress
To enhance the start-up procedure, the induced fatigue in the
condensate polishing plant can be used to high pressure section
bring the water/steam cycle within specified of the HRSG.
chemistry limits faster. Also, a
temperature-
Optimised component design and plant controlled start-up
operation to reduce material fatigue process, using an
In a conventional HRSG the high pressure optimised high-
drum is one of the most critical components capacity de-
in the start-up and ramping procedure. As a superheater to limit steam temperatures Two additional start-up modes FAST
thick-walled component it is exposed to large during the start-up, has been developed for and COST-EFFECTIVE in addition to
temperature gradients and high operating warm and cold starts. This reduces thermal the NORMAL mode have been
pressures. Thermal stress in the high-pressure stress in critical components of the steam introduced. The operator has the option of
drum walls limits the load-, start up- and shut turbine. choosing the appropriate start-up mode
down- gradients of the HRSG. depending on such factors as current
However there is no high pressure drum in Optimising the automation electricity market prices. Maintenance
a Benson-type boiler, so these limits do not There are essentially two ways in which intervals can be extended using the COST
apply. The Benson boiler technology automation system is optimised to support EFFECTIVE setting, while the FAST
employs once-through steam generation, improved start-up: mode permits controlled fast start-up, but
which means that conventional separation of Design limits are fully exploited through the entails increased maintenance
steam and boiling water inside a drum is not use of closed-loop control instead of earlier requirements.
necessary. Instead, steam is generated empirically based approaches. A turbine The start-up procedure is automated to a level
directly within the evaporator tubes, as stress controller is used to determine that enables hot starts with only a few operator
shown in Figure 4. thermal stress based on temperature actions, the aim being to minimise inefficient
Use of Benson technology allows the differences measured within the steam and unproductive periods during start-up
number of permissible starts and cycling turbine and ensures that stress limits are not preparations. Draining and venting are largely
events during the plant lifetime to exceeded. The turbine stress controller automated, for example.
makes it possible to
'JHVSF shorten the start-up Second-generation FACY Start on the Fly
5IF.8 time without reducing In addition to the features included in the
*STDIJOH the lifetime of heat- original FACY concept, a procedure for
DPNCJOFE critical turbine parallel start-up of gas and steam turbines has
DZDMFQMBOU components. been developed. It is based on monitoring and
4$$' 

'JHVSF-PBETUBCJMJTBUJPOBUMPXGSFRVFODZJOBDDPSEBODFXJUIUIF6,
HSJEDPEF

 'SFRVFODZ '-'%%  


PGBDUJWF
~ 827 MW
QPXFSPVUQVU
~ 762 MW
Plant start-up time ~ 30 Total plant load

GT 1/2

ST
'PS$$(5
ST load
Module:
QSPGJMFUPCFNFU
GT1 load GPSBNJOJNVNPG
GT2 load NJOVUFT
PGBDUJWF
QPXFSPVUQVU
Note: 'SFRVFODZ'-'%% JTUIFSFMBZUSJQTFUUJOHPGUIFGJSTUTUBHFPG
UIF"VUPNBUJD-PX'SFRVFODZ%FNBOE%JTDPOOFDUJPO4DIFNF

4
$0.#*/&%$:$-&

'JHVSF-PBETUBCJMJTBUJPOBUMPXGSFRVFODZ .BSDIXPPEUFTUSFTVMUT

Compressor Fast wet


turn up compression
.8 
 
 .#"%(@92])7-@

 .#:$&@92]1&-.8
  .#6%'@:2]:8$1&@LHT
  .#:%6@92]98'T

 
 
18 MW with
 fast wet
 compression
 6 MW by
  IGV control
 

 
 

Simulated
grid frequency
'JHVSF5IF.8.BSDIXPPEDPNCJOFEDZDMFQMBOU 4$$'.4

controlling the temperature gradients within most stringent requirements imposed on plant output can be compensated for by rapidly
limits acceptable for all critical plant dynamics are to be found in the grid code of opening the guide vanes on the compressor.
components and on long term turbine the UK, reflecting its island geography. Three The fuel flow is increased at the same time.
operating experience over a range of steam of the most critical considerations are: load This can compensate for a drop in power of
conditions. The new concept enables the plant stabilisation at low frequencies; primary and around 6 MW.
to be started-up without any gas turbine load secondary frequency response; and island In unfavourable operating conditions,
hold points, enabling a new start-up sequence operation capability. however, this increase in output will not be
to be implemented see Figure 5. The main sufficient on its own. In this case Fast Wet
innovation is the early steam turbine starting Load stabilisation at low frequencies Compression (a patented Siemens concept)
point with earlier acceleration and loading of Normal fluctuations in the balance between can be used to mobilise a further power
the turbine. generation and consumption are reflected in reserve of around 12 MW.
fluctuations in grid frequency which can be Fast Wet Compression consists of spraying
3FDFOUPQFSBUJOHSFTVMUT compensated for by means of routine demineralised water into the compressor
The features described above have been frequency control measures. The frequency inlet. The mass of the injected water increases
implemented in plants across Europe and can, however, also decrease or even increase the mass flow through the compressor. The
excellent results have been achieved in single significantly in the event of unusually large evaporating water also cools the air flow at
shaft as well as in multi shaft configurations. disturbances. the compressor inlet. The air density and
Two notable examples are the Pont sur Sambre Unfortunately a decrease in grid frequency consequently the mass flow through the
F-class single shaft plant in France and the F- also means a reduction in turbine speed and compressor increase due to this cooling
class multi shaft configuration at Irsching 5 in subsequently a decrease of power output. This process. Rapid activation of the system
Germany, Figures 6 and 7, respectively. decrease in speed causes the compressor in a constitutes a challenge to control systems, as
Both units have demonstrated the capability gas turbine to produce a reduced volumetric the fast increase in power output requires
to start-up and reach full load in about 30 flow, thus decreasing gas turbine output if perfect co-ordination between the gas
minutes folowing an overnight shut down, appropriate compensatory measures are not turbine control system and the water
without compromising efficiency, achieving implemented. injection.
levels of over 58% and over 59%, respectively. The United Kingdom grid code stipulates These grid support features have been
It is noteworthy, that the single shaft that power output must be maintained for a validated and demonstrated in the
operating concept allows parallel start up of minimum of 5 minutes in the event of a Marchwood F-class multi shaft plant in the
several units at a site, resulting in multiples of, frequency drop, down to 49.5 Hz so as to UK, at a power output of about 840 MW and
eg, 430 MW, being available in around 30 avoid further taxing of the grid due to under- over 58% efficiency (Figure 9).
minutes, as has been demonstrated at Sloe frequency. If a greater decrease in frequency Plots from the Marchwood tests are shown
Centrale, with its two units. occurs, the grid code permits a maximum in Figure 10. It can be seen that an 18 MW
decrease in output of 5%, down to 47 Hz, as increase was achieved (for each gas turbine)
(SJETVQQPSU illustrated in Figure 8. by opening the compressor IGVs and then
In liberalised electricity markets, the To counteract this decrease in power output, initiating fast wet compression, thus meeting
minimum requirements for power plant several measures for increased output can be the requirement of the United Kingdom grid
dynamics are set out in grid codes. Some of the implemented at short notice. The decrease in code.

'JHVSF'SFRVFODZSFTQPOTFBUMPXBOEIJHIGSFRVFODJFTJO 'JHVSF'SFRVFODZSFTQPOTFUFTUBUMPXGSFRVFODZ .BSDIXPPE 


BDDPSEBODFXJUI6,HSJEDPEF +VMZ EBUBGPSPOF(5


3$  3FHJTUFSFE$BQBDJUZ
Primary Secondary
 response response
1SJNBSZTFDPOEBSZIJHIGSFRVFODZSFTQPOTFMFWFM PO3$

.(  .JOJNVN(FOFSBUJPO
%.0-  %FTJHOFE.JOJNVN .8 )[
 0QFSBUJOH-FWFM  

%ZOBNJD QMBOUMPBE QSJNBSZ   .#:$&@92]1&-.8
PQFSBUJOH .#:%6@92]98'T
[POF GSFRVFODZSFTQPOTF  
 JODSFBTFCZT  
  
 

   53.7 MW in 30 sec
-PBEJOH PO3$


 45 MW in 10 sec
  
%.0-  

 

 
 .( 
Simulated net
  frequency
1SJNBSZTFDPOEBSZ)JHI 1MBOUEFQFOEFOUSFRVJSFNFOU

5
$0.#*/&%$:$-&

'JHVSF*TMBOEPQFSBUJPOUFTUBU.BSDIXPPE EBUBGPSPOF(5

'JHVSF5ZQJDBMFMFDUSJDJUZQSJDFDVSWF .8I
DPNQBSFEXJUI
 
 HBTBOE$0DPTUT +BOVBSZ  &VSPQFBO&OFSHZ&YDIBOHF


 

  


Simulated grid
frequency 
 
 Power output

 
 

 
 269.5 -140.0 -11.1
 &MFDUSJDJUZQSJDF&&9
0.000 0.000 0.000
  (BT$0 DPTUTBUGVMMMPBE
10:11:11 00:00:04 00:00:04
 M:1 M:2 M:3
 
 


1SJNBSZBOETFDPOEBSZGSFRVFODZ Figure 12 illustrates the results of tests done smaller than 55% of rated power in this case.
SFTQPOTF on the Marchwood plant and clearly shows This load reduction must be effected
The purpose of load stabilisation at low that the required additional power is achieved sufficiently quickly that the island frequency
frequencies is to prevent further both after 10 seconds and after 30 seconds. In remains below 52 Hz. Grid studies based on
destabilisation of the grid when the frequency fact, performance is significantly better than the UK National Grid requirements show that
decreases due to major disturbances. Primary that required by the grid code in both the load reduction must take place within
and secondary frequency responses are now instances. around 8 seconds.
required for grid support during normal Another aspect of the grid code, also shown The power plant must detect island
operation. For this purpose the UK grid code in Figure 11, is high frequency response, formation automatically and take immediate
stipulates that a power plant operating at part namely that load must be reduced by 10% of action. As soon as island operating mode is
load must be capable of making additional rated power within 10 seconds in the event of activated, permitted load change ramps are
power available. Figure 11 illustrates the over-frequencies of up to 500 mHz. However, set to the maximum value. The inlet guide
relevant part of the UK grid code. We can see when it comes to load reduction the island vanes in the gas turbine compressor are
that a power plant operating at under 80% operation requirement (see next section) is closed without delay. At the same time the
load must be able to make available at least even more stringent. various closed-loop controls ensure that the
10% of its rated power within 10 seconds in power is decreased at the maximum rate of
the event of a decrease in frequency. For Island operation capability change for load. Maintaining flame stability
secondary frequency response 10% of its rated The primary objective of island operation and avoiding potential flash backs in the
power must be made available within 30 capability is to stabilise the grid, in the event combustion system are the main objectives
seconds. Figure 11 shows that the of excess power and an abrupt drop in of closed-loop control optimisation, so
requirements are reduced when the plant is consumption within an islanded portion of the as to avoid emergency shutdown of the
operating at loads over 80%. grid, resulting in a very rapid frequency gas turbine.
Unlike load stabilisation at low frequency, increase. The power plant must react to this Figure 13 illustrates an island operation test
there is no need to look for a further power frequency increase by throttling back to at Marchwood. The gas turbine output was
reserve in this case. The challenge lies more in stabilise the frequency, thus avoiding a forced decreased by 52% within 4 seconds as the result
the speed at which the power must be made shut-down due to over-frequency. of a simulated fast frequency increase of 0.9
available. Uncontrolled shut-down of power plants Hz, without initiating a plant trip. A further
To meet the requirements of the grid code, can result in a grid collapse, which is why the decrease of 4% was achieved in the following
we rely on fast repositioning of the compressor UK grid code stipulates that power plants 4 seconds. Thus performance again exceeded
IGVs coupled with fuel control optimised to must be capable of rapidly decreasing from grid code requirements.
such an extent that load ramps are possible rated power to the design minimum operating
without destabilising combustion. level (DMOL). The DMOL must not be Transfer to the H
Meanwhile, these basic plant features
'JHVSF(SJEDPEFUFTUBU*STDIJOH demonstrated in F-class plants are being
44$)
JOPQFODZDMFNPEF transferred also to H-class technology and
have already been validated in open cycle
operation at Irsching 4 (Figure 14),
demonstrating that even this latest and
highest efficiency technology is capable of
supporting the same stringent grid code
requirements.

5IFCPUUPNMJOFCFOFGJUTUPUIF
PQFSBUPS
ca. 380 MW  The previous sections clearly demonstrate that
FACY and Start on the Fly permit a reduction
in start-up times as well as an increased
 number of start-ups, enabling nightly power
60 % / 225 MW load 60 % / 225 MW load plant shut-downs. The latter offers two
reduction in < 1 min. increase in < 1 min. additional benefits:

Carbon dioxide emissions are minimised by
shortening inefficient plant start-ups.
Active Maximum electrical efficiency is reached
power faster and total emissions are reduced.

Since nightly shutdowns and reliable start-
ups become economically feasible, overall
carbon dioxide emissions are further
reduced as inefficient overnight parking at

6
$0.#*/&%$:$-&

load is avoided. Other power plants within 'JHVSF4BWJOHTJOHBTDPOTVNQUJPOBOEBWPJEFE$0 FNJTTJPOTSFTVMUJOHGSPNOJHIUUJNF


the grid can then be operated at full load and TIVUEPXO5IJTJTCBTFEPOBHBTQSJDFPG.8I $0 DPTUTPG.8IBOEBOJHIUUJNF
maximum efficiency. FMFDUSJDJUZQSJDFPG.8I5IFQFSGPSNBODFEBUBBSFCBTFEPOBO4$$'TJOHMFTIBGU
Operators benefit from this, primarily QMBOUXJUIBDPPMJOHUPXFS
through fuel savings and a reduction in carbon
dioxide emissions during the start-up phase. Reduction of gas consumption and CO2 emissions (per night) Economic impact (per year)
Shortening the start-up time by using Start on Cost for operation/shut down
the Fly for a hot start offers an estimated Gas consumption (t) CO2 emission (t) and start up ()
added value of more than 3 million euros 
alone, assuming that the savings described U U NJMMJPO
above are realised over the service life of a 430
MW power plant.   
The option of disconnecting the plant from
the grid overnight offers enormous potential
in the form of savings in operating costs.
Night-time electricity prices have been at
such a low level in the European system that
a combined cycle power plant could no longer   
be operated at a profit during the night due to
high gas and carbon dioxide costs (see Figure
15). To minimise these losses, power plants are 1BSU 4IVUEPXO 1BSU 4IVUEPXO 1BSU 4IVUEPXO
MPBE 4UBSUPOUIF'MZ MPBE 4UBSUPOUIF'MZ MPBE 4UBSUPOUIF'MZ
operated at part load or are shut down
#BTFEPOTUBSUTQB
altogether at night.
Reducing the load already brings about a
significant reduction in losses. However
when the load decreases, so does overall power plant operator with an additional individual countries. No monetary valuation
efficiency, meaning that gas and carbon economic benefit for every start. of the additional plant flexibility is included in
dioxide costs can only be reduced Figure 16 shows the carbon dioxide and fuel tender specifications as yet. For this reason
disproportionately. savings which can be achieved by night-time todays plants are designed purely based on
In addition to the positive effect of load shutdown using FACY compared with night- grid code specifications. Depending on the
reduction, shutting a power plant down at time part-load operation at about 25%. We level of electricity market liberalisation,
night can achieve other significant benefits. can see that the power plant in this example however, the various flexibility features enable
Only shut-down and start-up costs are can avoid up to 130 tons of gas consumption additional earnings to be generated, in
incurred, for example. Restrictions relating to and 362 tons of carbon dioxide emissions per particular by participating in the frequency
the permitted number of start-ups for the plant night through night-time shutdown. This reserve market.
have been significantly reduced, thanks to the increases the annual power plant profit by 4.8 Another potential benefit is that plants with
FACY programme. FACY and Start on the million euros as compared with night-time high reliability and operational flexibility,
Fly have also significantly reduced start-up part-load operation. able to cope well under disturbed grid
times. The result is lower gas consumption and Today grid support features arise primarily conditions, can expect to be prioritised for
lower carbon dioxide emissions, providing the from the grid access requirements of the dispatch. MPS

4FWFSO1PXFSIBOEFEPWFS
0OFPGUIFMBUFTUBEEJUJPOTUPUIFGMFFUPGGMFYJCMF4JFNFOTDPNCJOFEDZDMFQMBOUTJODPNNFSDJBM
PQFSBUJPOJT4FWFSO1PXFS 6TLNPVUI OFBS/FXQPSUJO8BMFT 6,5IJTXBTIBOEFEPWFSUP%POH
&OFSHZPO/PWFNCFS POFXFFLBIFBEPGTDIFEVMF5IF.8F'DMBTTTJOHMFTIBGUQMBOU
JTFRVJQQFEXJUINBOZPGUIFDZDMJOHBOEGBTUTUBSUVQGFBUVSFTEFTDSJCFEJOUIFNBJOBSUJDMF BOE
MJLFPUIFSQMBOUTNFOUJPOFEUIFSF JTBCMFUPBDIJFWFGVMMPVUQVUJOPOMZNJOVUFTGPMMPXJOHBO
PWFSOJHIUTIVUEPXO
8JUI'BTU8FU$PNQSFTTJPOBOEPUIFSGFBUVSFT UFTUTBU4FWFSOIBWFJOEJDBUFEUIBUJUTQFSGPSNBODF
JOUFSNTPG6,HSJEDPEFTVQQPSUJTBUMFBTUBTHPPEBTUIBUPG.BSDIXPPE TFFQQ

5IFQMBOUTIJHIEFHSFFPGPQFSBUJOHGMFYJCJMJUZBMTPNFBOTUIBUJUJTDBQBCMFPGWFSZRVJDLMZ
DPNQFOTBUJOHGPSUIFGMVDUVBUJOHGFFEJOGSPNXJOEUVSCJOFT
6TFPGBOBJSDPPMFEDPOEFOTFSJOTUFBEPGBDPPMJOHUPXFSBOEBQQMJDBUJPOPGBOJOOPWBUJWFXBTUF
XBUFSDPODFQUBMTPNJOJNJTFTXBUFSDPOTVNQUJPO
&GGJDJFODZJTBCPVUBOE UIBOLTUPBEWBODFECVSOFSUFDIOPMPHZ UIFQMBOUTOJUSPHFOPYJEFFNJTTJPOMFWFMTBSFWFSZMPX BSPVOEQQN
*OUFSNTPGIFBMUITBGFUZEVSJOHDPOTUSVDUJPO UIFQSPKFDUIBTBMTPCFFOFYFNQMBSZ DMPDLJOHVQNPSFUIBOUISFFNJMMJPOXPSLJOHIPVSTXJUIPVUBMPTU
UJNFBDDJEFOU XJUIPWFSXPSLFSTPOUIFTJUFBUQFBLUJNFT

- 50%
Power / frequency in 4s
Primary frequency response: Power / frequency
Primary Secondary )[
resp. response r'SFRVFODZN)[ 
.8
.8 )[ r3FRVJSFEMPBENJOT 

Island operation:
-PBEJOHCZ r"DIJFWFE .8 BQQS

.8   r3FRVJSFE7FSZGBTUMPBESFEVDUJPO


-PBEJOHCZ  PGBUMFBTUPGSBUFE$$QPXFS
 .8  XJUIPVUUSJQ USJHHFSFECZ 
 
 N)[
Secondary frequency response: 
  4UBCMF r"DIJFWFE+PJOUSFEVDUJPOPG(5BOE
 r'SFRVFODZN)[ 'SFRVFODZ EFMPBEJOH 45PGBQQSPYPGSBUFE$$
 
 r3FRVJSFEMPBENJOT  JODSFBTF CZ.8 QPXFSXJUIJOT
'SFRVFODZ N)[
 EFDSFBTF r"DIJFWFE .8 BQQS

r#PUIUVSCJOFTSFNBJOJOTUBCMF
N)[  
PQFSBUJPOGPSIJHIFTUGMFYJCJMJUZ
 



1MVT r'PSTJOHMFTIBGUPOMZQPTTJCMFXJUI

  .JOVT JOUFHSBUFE(UBOE45DPOUSPM
 TPMVUJPO

 Time
Time  


3FTVMUTPGHSJEDPEFTVQQPSUUFTUTBUUIFOFX4FWFSO1PXFSDPNCJOFEDZDMFQMBOU

7
This article appeared in:
Modern Power Systems
January 2011, Page 3541
Copyright 2011 by
Modern Power Systems

This reprint is published by:


Siemens AG
Energy Sector
Freyeslebenstrasse 1
91058 Erlangen, Germany

Siemens Energy, Inc.


4400 Alafaya Trail
Orlando, FL 32826-2399, USA

For more information, please contact


our Customer Support Center.
Phone: +49 180/524 70 00
Fax: +49 180/524 24 71
(Charges depending on provider)
E-mail: support.energy@siemens.com

Fossil Power Generation Division


Order No. E50001-G220-A133-X-4A00
Printed in Germany
Dispo 05400, c4bs No. 7813
TH 224-110395 | BR | 430097 SD 07113.0

Printed on elementary chlorine-free bleached paper.

All rights reserved.


Trademarks mentioned in this document
are the property of Siemens AG, its affiliates,
or their respective owners.

Subject to change without prior notice.


The information in this document contains general
descriptions of the technical options available, which
may not apply in all cases. The required technical
options should therefore be specified in the contract.

www.siemens.com/energy

You might also like