Professional Documents
Culture Documents
Fast Cycling and Rapid Start-Up US PDF
Fast Cycling and Rapid Start-Up US PDF
Author:
Lothar Balling, Siemens AG,
Erlangen, Germany
Figure 1. Recent combined cycle projects with enhanced flexibility and fast start capabilities
Lothar Balling, Siemens,
Erlangen, Germany
'JHVSF5IFSJTFPGSFOFXBCMFT &6
'JHVSF.BJOGFBUVSFTPGUIF'BTU$ZDMJOH '"$:
DPODFQU
&MFDUSJDJUZQSPEVDUJPO
58I
3FOFXBCMFT Stack damper
)ZESP
'PTTJM
/VDMFBS ST stress
controller BENSON technology
HRSG stand-by
7% 18% heating
10%
10%
54% 48% Condensate
polishing plant
Optimised
GT load ramp
29% 24% High-capacity
de-superheater
FACY concept have now entered commercial High availability and reliability power '"TU$:DMJOHDPODFQU '"$:
operation (Figure 1). plants, such as combined cycle units, are The idea of focusing plant design on an
A good example is Sloe Centrale, a 2 x 430 required in order to compensate for increased number of fast starts originated
MW F-class single shaft plant in the fluctuating renewables. The requirements from market conditions and from specific
Netherlands, where 30-minute start-up with respect to grid support, which are usually projects. A multidisciplinary team of
times were recorded during acceptance tests, defined in a country-specific grid code, have component and plant experts (for the steam
while achieving over 59% net efficiency. recently become more rigorous for this reason. turbine, gas turbine, balance of plant and
Equally good results have been exhibited by Some of the most stringent requirements are auxiliary systems, I&C and steam generator)
other newly commissioned plants. This to be found in the UK grid code. Requirements was formed by Siemens around 2002 to
means that the second generation of FACY in the areas of load stabilisation at low identify improvement potential in the existing
has far surpassed expectations in a number frequencies, primary and secondary frequency plant concepts.
of cases. response, and island operation capability have The team identified the following priorities:
Shortening start-up times and improving presented a particular challenge to UK Maintaining pressure and temperature in
starting reliability while increasing the operators for quite some time. However, the the main components during shutdowns, by
number of starts was only one of many new recently handed over 840 MW multi-shaft F- using stack dampers, auxiliary steam, etc.
requirements with respect to plant flexibility. class Marchwood plant has finally Ready-for-operation water/steam cycle
An increasingly important driver (as demonstrated that the problem can be solved using a fully automated start-up concept
discussed in last months article) is the growing without compromising efficiency (over 58%) without manual operation or intervention
percentage of renewables envisaged on the by introducing additional technical features during hot start.
grid (see Figure 2). Wind and solar energy are and optimising the plant concept. Optimised component design (eg, high
not continuously available and difficult to A decisive factor in the success of Marchwood capacity and fast acting de-superheaters)
predict precisely. Reserve power generating was the integrated approach, which combined and plant operation to reduce material
capabilities must therefore be provided which the potentials of several systems and fatigue caused by load cycling.
can be activated quickly. Gas turbine based components in a single solution, including use Flexible operation concept to allow the
plants are an obvious choice here as they can of gas turbine compressor optimisation, firing operator to predetermine component
be started up at relatively short notice. The reserves, fast wet compression and other fatigue and to choose start-up time and
inherent inertia of other types of power measures, combined with an optimised ramp rate.
generating facilities is usually much greater, I&C/closed-loop control concept. Optimisation of the automation and control
making them largely unsuitable for use as a The new demand for extremely fast power concept.
rapidly available reserve source of power. generating availability is also becoming New start-up sequence, Start on the Fly,
There are, of course, other fast-responding apparent in CCGT developers economic to allow a nearly unrestrained ramp-up.
sources of power such as pumped storage. But assessments. Only a few years ago there were Figure 3 summarises the main features of the
they do not provide enough capacity to cover projects in which start-up times did not FACY concept. These measures help reduce
the renewable generating capacity in the figure at all in the assessment, whereas now start-up time significantly. They are modular
European grid system, with the prospect of we are seeing over 100 000 /min for some and are offered, configured and implemented
30% renewables by 2030. projects. on a project-specific basis.
3
$0.#*/&%$:$-&
Improvement GT and ST
loading
27 min
Steam take
over
Load hold to wait for
ST start-up 4QFFE
'JHVSF-PBETUBCJMJTBUJPOBUMPXGSFRVFODZJOBDDPSEBODFXJUIUIF6,
HSJEDPEF
GT 1/2
ST
'PS$$(5
ST load
Module:
QSPGJMFUPCFNFU
GT1 load GPSBNJOJNVNPG
GT2 load NJOVUFT
PGBDUJWF
QPXFSPVUQVU
Note: 'SFRVFODZ'-'%% JTUIFSFMBZUSJQTFUUJOHPGUIFGJSTUTUBHFPG
UIF"VUPNBUJD-PX'SFRVFODZ%FNBOE%JTDPOOFDUJPO4DIFNF
4
$0.#*/&%$:$-&
'JHVSF-PBETUBCJMJTBUJPOBUMPXGSFRVFODZ .BSDIXPPEUFTUSFTVMUT
Simulated
grid frequency
'JHVSF5IF.8.BSDIXPPEDPNCJOFEDZDMFQMBOU 4$$'.4
controlling the temperature gradients within most stringent requirements imposed on plant output can be compensated for by rapidly
limits acceptable for all critical plant dynamics are to be found in the grid code of opening the guide vanes on the compressor.
components and on long term turbine the UK, reflecting its island geography. Three The fuel flow is increased at the same time.
operating experience over a range of steam of the most critical considerations are: load This can compensate for a drop in power of
conditions. The new concept enables the plant stabilisation at low frequencies; primary and around 6 MW.
to be started-up without any gas turbine load secondary frequency response; and island In unfavourable operating conditions,
hold points, enabling a new start-up sequence operation capability. however, this increase in output will not be
to be implemented see Figure 5. The main sufficient on its own. In this case Fast Wet
innovation is the early steam turbine starting Load stabilisation at low frequencies Compression (a patented Siemens concept)
point with earlier acceleration and loading of Normal fluctuations in the balance between can be used to mobilise a further power
the turbine. generation and consumption are reflected in reserve of around 12 MW.
fluctuations in grid frequency which can be Fast Wet Compression consists of spraying
3FDFOUPQFSBUJOHSFTVMUT compensated for by means of routine demineralised water into the compressor
The features described above have been frequency control measures. The frequency inlet. The mass of the injected water increases
implemented in plants across Europe and can, however, also decrease or even increase the mass flow through the compressor. The
excellent results have been achieved in single significantly in the event of unusually large evaporating water also cools the air flow at
shaft as well as in multi shaft configurations. disturbances. the compressor inlet. The air density and
Two notable examples are the Pont sur Sambre Unfortunately a decrease in grid frequency consequently the mass flow through the
F-class single shaft plant in France and the F- also means a reduction in turbine speed and compressor increase due to this cooling
class multi shaft configuration at Irsching 5 in subsequently a decrease of power output. This process. Rapid activation of the system
Germany, Figures 6 and 7, respectively. decrease in speed causes the compressor in a constitutes a challenge to control systems, as
Both units have demonstrated the capability gas turbine to produce a reduced volumetric the fast increase in power output requires
to start-up and reach full load in about 30 flow, thus decreasing gas turbine output if perfect co-ordination between the gas
minutes folowing an overnight shut down, appropriate compensatory measures are not turbine control system and the water
without compromising efficiency, achieving implemented. injection.
levels of over 58% and over 59%, respectively. The United Kingdom grid code stipulates These grid support features have been
It is noteworthy, that the single shaft that power output must be maintained for a validated and demonstrated in the
operating concept allows parallel start up of minimum of 5 minutes in the event of a Marchwood F-class multi shaft plant in the
several units at a site, resulting in multiples of, frequency drop, down to 49.5 Hz so as to UK, at a power output of about 840 MW and
eg, 430 MW, being available in around 30 avoid further taxing of the grid due to under- over 58% efficiency (Figure 9).
minutes, as has been demonstrated at Sloe frequency. If a greater decrease in frequency Plots from the Marchwood tests are shown
Centrale, with its two units. occurs, the grid code permits a maximum in Figure 10. It can be seen that an 18 MW
decrease in output of 5%, down to 47 Hz, as increase was achieved (for each gas turbine)
(SJETVQQPSU illustrated in Figure 8. by opening the compressor IGVs and then
In liberalised electricity markets, the To counteract this decrease in power output, initiating fast wet compression, thus meeting
minimum requirements for power plant several measures for increased output can be the requirement of the United Kingdom grid
dynamics are set out in grid codes. Some of the implemented at short notice. The decrease in code.
3$ 3FHJTUFSFE$BQBDJUZ
Primary Secondary
response response
1SJNBSZTFDPOEBSZIJHIGSFRVFODZSFTQPOTFMFWFM PO3$
.( .JOJNVN(FOFSBUJPO
%.0- %FTJHOFE.JOJNVN .8 )[
0QFSBUJOH-FWFM
%ZOBNJD QMBOUMPBE
QSJNBSZ .#:$&@92]1&-.8
PQFSBUJOH .#:%6@92]98'T
[POF GSFRVFODZSFTQPOTF
JODSFBTFCZT
53.7 MW in 30 sec
-PBEJOH PO3$
45 MW in 10 sec
%.0-
.(
Simulated net
frequency
1SJNBSZTFDPOEBSZ)JHI 1MBOUEFQFOEFOUSFRVJSFNFOU
5
$0.#*/&%$:$-&
'JHVSF*TMBOEPQFSBUJPOUFTUBU.BSDIXPPE EBUBGPSPOF(5
'JHVSF5ZQJDBMFMFDUSJDJUZQSJDFDVSWF .8I
DPNQBSFEXJUI
HBTBOE$0DPTUT +BOVBSZ
&VSPQFBO&OFSHZ&YDIBOHF
Simulated grid
frequency
Power output
269.5 -140.0 -11.1
&MFDUSJDJUZQSJDF&&9
0.000 0.000 0.000
(BT$0 DPTUTBUGVMMMPBE
10:11:11 00:00:04 00:00:04
M:1 M:2 M:3
1SJNBSZBOETFDPOEBSZGSFRVFODZ Figure 12 illustrates the results of tests done smaller than 55% of rated power in this case.
SFTQPOTF on the Marchwood plant and clearly shows This load reduction must be effected
The purpose of load stabilisation at low that the required additional power is achieved sufficiently quickly that the island frequency
frequencies is to prevent further both after 10 seconds and after 30 seconds. In remains below 52 Hz. Grid studies based on
destabilisation of the grid when the frequency fact, performance is significantly better than the UK National Grid requirements show that
decreases due to major disturbances. Primary that required by the grid code in both the load reduction must take place within
and secondary frequency responses are now instances. around 8 seconds.
required for grid support during normal Another aspect of the grid code, also shown The power plant must detect island
operation. For this purpose the UK grid code in Figure 11, is high frequency response, formation automatically and take immediate
stipulates that a power plant operating at part namely that load must be reduced by 10% of action. As soon as island operating mode is
load must be capable of making additional rated power within 10 seconds in the event of activated, permitted load change ramps are
power available. Figure 11 illustrates the over-frequencies of up to 500 mHz. However, set to the maximum value. The inlet guide
relevant part of the UK grid code. We can see when it comes to load reduction the island vanes in the gas turbine compressor are
that a power plant operating at under 80% operation requirement (see next section) is closed without delay. At the same time the
load must be able to make available at least even more stringent. various closed-loop controls ensure that the
10% of its rated power within 10 seconds in power is decreased at the maximum rate of
the event of a decrease in frequency. For Island operation capability change for load. Maintaining flame stability
secondary frequency response 10% of its rated The primary objective of island operation and avoiding potential flash backs in the
power must be made available within 30 capability is to stabilise the grid, in the event combustion system are the main objectives
seconds. Figure 11 shows that the of excess power and an abrupt drop in of closed-loop control optimisation, so
requirements are reduced when the plant is consumption within an islanded portion of the as to avoid emergency shutdown of the
operating at loads over 80%. grid, resulting in a very rapid frequency gas turbine.
Unlike load stabilisation at low frequency, increase. The power plant must react to this Figure 13 illustrates an island operation test
there is no need to look for a further power frequency increase by throttling back to at Marchwood. The gas turbine output was
reserve in this case. The challenge lies more in stabilise the frequency, thus avoiding a forced decreased by 52% within 4 seconds as the result
the speed at which the power must be made shut-down due to over-frequency. of a simulated fast frequency increase of 0.9
available. Uncontrolled shut-down of power plants Hz, without initiating a plant trip. A further
To meet the requirements of the grid code, can result in a grid collapse, which is why the decrease of 4% was achieved in the following
we rely on fast repositioning of the compressor UK grid code stipulates that power plants 4 seconds. Thus performance again exceeded
IGVs coupled with fuel control optimised to must be capable of rapidly decreasing from grid code requirements.
such an extent that load ramps are possible rated power to the design minimum operating
without destabilising combustion. level (DMOL). The DMOL must not be Transfer to the H
Meanwhile, these basic plant features
'JHVSF(SJEDPEFUFTUBU*STDIJOH demonstrated in F-class plants are being
44$)
JOPQFODZDMFNPEF transferred also to H-class technology and
have already been validated in open cycle
operation at Irsching 4 (Figure 14),
demonstrating that even this latest and
highest efficiency technology is capable of
supporting the same stringent grid code
requirements.
5IFCPUUPNMJOFCFOFGJUTUPUIF
PQFSBUPS
ca. 380 MW The previous sections clearly demonstrate that
FACY and Start on the Fly permit a reduction
in start-up times as well as an increased
number of start-ups, enabling nightly power
60 % / 225 MW load 60 % / 225 MW load plant shut-downs. The latter offers two
reduction in < 1 min. increase in < 1 min. additional benefits:
Carbon dioxide emissions are minimised by
shortening inefficient plant start-ups.
Active Maximum electrical efficiency is reached
power faster and total emissions are reduced.
Since nightly shutdowns and reliable start-
ups become economically feasible, overall
carbon dioxide emissions are further
reduced as inefficient overnight parking at
6
$0.#*/&%$:$-&
4FWFSO1PXFSIBOEFEPWFS
0OFPGUIFMBUFTUBEEJUJPOTUPUIFGMFFUPGGMFYJCMF4JFNFOTDPNCJOFEDZDMFQMBOUTJODPNNFSDJBM
PQFSBUJPOJT4FWFSO1PXFS
6TLNPVUI
OFBS/FXQPSUJO8BMFT
6,5IJTXBTIBOEFEPWFSUP%POH
&OFSHZPO/PWFNCFS
POFXFFLBIFBEPGTDIFEVMF5IF.8F'DMBTTTJOHMFTIBGUQMBOU
JTFRVJQQFEXJUINBOZPGUIFDZDMJOHBOEGBTUTUBSUVQGFBUVSFTEFTDSJCFEJOUIFNBJOBSUJDMF
BOE
MJLFPUIFSQMBOUTNFOUJPOFEUIFSF
JTBCMFUPBDIJFWFGVMMPVUQVUJOPOMZNJOVUFTGPMMPXJOHBO
PWFSOJHIUTIVUEPXO
8JUI'BTU8FU$PNQSFTTJPOBOEPUIFSGFBUVSFT
UFTUTBU4FWFSOIBWFJOEJDBUFEUIBUJUTQFSGPSNBODF
JOUFSNTPG6,HSJEDPEFTVQQPSUJTBUMFBTUBTHPPEBTUIBUPG.BSDIXPPE TFFQQ
5IFQMBOUTIJHIEFHSFFPGPQFSBUJOHGMFYJCJMJUZBMTPNFBOTUIBUJUJTDBQBCMFPGWFSZRVJDLMZ
DPNQFOTBUJOHGPSUIFGMVDUVBUJOHGFFEJOGSPNXJOEUVSCJOFT
6TFPGBOBJSDPPMFEDPOEFOTFSJOTUFBEPGBDPPMJOHUPXFSBOEBQQMJDBUJPOPGBOJOOPWBUJWFXBTUF
XBUFSDPODFQUBMTPNJOJNJTFTXBUFSDPOTVNQUJPO
&GGJDJFODZJTBCPVUBOE
UIBOLTUPBEWBODFECVSOFSUFDIOPMPHZ
UIFQMBOUTOJUSPHFOPYJEFFNJTTJPOMFWFMTBSFWFSZMPX
BSPVOEQQN
*OUFSNTPGIFBMUITBGFUZEVSJOHDPOTUSVDUJPO
UIFQSPKFDUIBTBMTPCFFOFYFNQMBSZ
DMPDLJOHVQNPSFUIBOUISFFNJMMJPOXPSLJOHIPVSTXJUIPVUBMPTU
UJNFBDDJEFOU
XJUIPWFSXPSLFSTPOUIFTJUFBUQFBLUJNFT
- 50%
Power / frequency in 4s
Primary frequency response: Power / frequency
Primary Secondary )[
resp. response r'SFRVFODZN)[
.8
.8 )[ r3FRVJSFEMPBENJOT
Island operation:
-PBEJOHCZ r"DIJFWFE.8 BQQS
1MVT r'PSTJOHMFTIBGUPOMZQPTTJCMFXJUI
.JOVT JOUFHSBUFE(UBOE45DPOUSPM
TPMVUJPO
Time
Time
3FTVMUTPGHSJEDPEFTVQQPSUUFTUTBUUIFOFX4FWFSO1PXFSDPNCJOFEDZDMFQMBOU
7
This article appeared in:
Modern Power Systems
January 2011, Page 3541
Copyright 2011 by
Modern Power Systems
www.siemens.com/energy