Professional Documents
Culture Documents
.,~
,
.....
SOUTHEAST SECTION
JACKSONVILLE, FLORIDA
INTRODUCTION
drawings.
The third phase of the ship design is tlie Detail Design, which
(1)
SHIPYARD
CAPABILITIES
OWNERJ
'
REQUIREMENTS
DEVELOP & VALIDATE
DET~IL
REGULATORY PRELI,..INARY CONt:RACT
BODY DESIGN SHIP
DESIGN DESIGN
REQUIREMENTS
Design. The complexity and scope of the detail design are primarily
the shipyard.
vessel.
ment techniques and practices. See Fig. 2. The first step in success-
done, also list what will not be done. Such activity is intended
design, and too often lacks the necessary commitment of top manage-
.,.
PROJ;ECT
MANAGER
PROJECT _/ \_ _/ \_ _( \_
TECH'NICAL
STAFF
1-- - - T . -.- T -- T - -l
,..._.._-..~. _ __
:.
DESIGNERS/ DESIGNERS/ DESIGNERS/ DESIGNERS/
DRAFTSMEN DRAFTSMEN DRAFTSMEN DRAFTSMEN
Fig. 3
l
(4)
design controls.
tion.
Following is a detailed analysis of some of the key project
management objectives.
SCOPE OF WORK
The Scope of Work is a baseline document that identifies the
(5)
shipyard's needs and the detail of the Contract Plans and Specifica-
for long lead times for the purchase of such material. Exact
the Scope of Work. Although this Scope of Work has been tailored
SCOPE OF ENGINEERING
SERVICES
Inclusions (Do's)
The Design Agent will provide total design and engineering services
required for the construction of the identified vessel in accordance
with the Contract Specifications and related Contract Plans. In
all cases, the following apply to the first vessel only.
ment plans.
7. Prepare bill of materials for hull, piping, electrical,
mechanical, and ventilation systems which will be included
on the respective working plan arrangements. Shipyard
will put its material identification numbers on the
drawings.
B. Heating, yentilation, and Air Conditioning Diagrams and
Arrangements, including Noise Analysis Report.
9. Electrical and Electronic Plans, including Wireways.
10 . Naval Architecture, Marine Engineering, Electrical
Engineering, and other associated engineering to support
development of the working plans. Calculations developed
in support of such plans will be delivered to the Ship-
yard.
11. All working plans will be prepared on Mylar in pencil
to microfilm quality in accordance with Shipyard practices,
standards, and erection sequence. (Data to be provided
by Shipyard.)
12. Design Agent will maintain working plans and other engineer-
ing documents requiring Owner approval up to and including
first approval. After first approval, original tracing
will be forwarded to the shipyard for plan maintenance.
13. All sections in the Contract Specifications will be re-
viewed by the Design Agent to ascertain the basic design
requirements. This review will include Contract plans,
Guidance plans, other Owner furnished information. Any
conflict between the Specifications, Contract Plans, and
Guidance Plans will be called to the attention of the
Shipyard.
14. Prepare, maintain, and issue the following schedules for
items under cognizance of the Design Agent:
EXCLUSIONS (Dont's)
SCHEDULING
The successful scheduling of a detail ship design requires the
(11)
Further, one must take into account the time required to obtain
ABS, Coast Guard, and Public Health. Only after the above scheduling
activity has been completed can one construct an overall time esti-
mate with accuracy and proceed to identify the critical paths in the
SHIPYARD SCHEDULE
FIRST YEAR SECOND YEAR THIRD YEAR
-
1ST QTR 2ND QTR 3RD QTR 4TH QTR 1ST QTR 2ND QTR 3RD QTR 4TH QTR 1ST QTR 2ND QTR 3RD QTR 4TH QTR
I HuLL LOFTING I
I STEEL PRE-FAB
I .
..
I
~
ERECT MODULES I. .
.
I INSTALL MAJOR EQPT I
I OTHER OUTFITTING I I
LAUNCH
... I
~ELIVERY -/\
-Fig. 4
{ 12)
drawing to use such data, but also for each interrelated drawing.
data (for piping calculations and electrical load analysis), and others.
......
ENGINEERING SCHEDULE :I
.
. FIRST YEAR SECOND YEAR
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6
DESIGN REVIEW
Fig. 5
(13)
the double bottom mid-body structure plans leading the rest of the
forgings such as the stem or struts must allow for foundry lead
time.
control.
plans may require the re-sizing of fan rooms and major trunks.
formance data) for any equipments that use or process the particular
accordingly. This would include firemains, lube oil, fuel oil, and
the use of bar charts or networks, depending upon the complexity and
CPM (Critical Path Method) are similar management aids that show
system must be able to deal rapidly with changes as the design and
construction progress.
corporate the following steps: First, break down the project into
the work into individual time using activities (drawings) that must
network chart that shows the relationships between all parts of the
project. Putting such steps on paper will also help to show the
DRAWING PROCEDURES
with the shipyard the preferred drawing formats and content as well
to be considered.
make the drawing too large and unmanageable for use in the shop
less drawing detail than those yards without as high a level of skill.
addressed, and can be expected to range between 96" and 144". The
waterfront.
fitting shop will take a piping drawing which contains pipe sizes,
design agent for the shipyard. This will require an assessment of the
for such activities as vendor plan review and processing and inter-
ference control.
hull structure shapes and plates. Such techniques can eliminate the
need for hand produced drawings but still require the services of a
hull designer/engineer.
INTERFACE ACTIVITY
and notice of authority for all major elements of the ship construc-
tion project.
DESIGN CONTROLS
ment and may cause more harm than good by wasting engineering talent.
On the other hand, serious efforts at interference control can pay big
management.
for this method. The outfit items would typically include piping,
wireways, vent duct, and equipment. Allowances are also made for
service trunks. Plan views are prepared for various ranges of eleva-
p
(20)
high cost, models are generally used only for the most congested of
may be the only way to avoid rework by the shipyard production depart-
ment.
close-spaced penetrations.
programs available for piping systems. Such tools have great poten-
fabrication.
Quality control is a key issue to be addressed by the designer.
(21)
Cost controls for the detail ship design effort are essential
ment assess the impact of the subject change order on the drawings
maximize the efficiency of the detail ship design. The goal of the
rework, and must be timely and accurate. The notice should clearly
identify the changes made and the reason for the change (incorporate
tion requiring design changes must ensure that such changes are
The control process for the detail ship design requires the
the manager may soon become bogged down and lose his or her overall
CONTRACT DOCUMENT:
2. DESCRIBE PROBLEM: .,
. .
SUBMITTED BY: OWNER ACTION REQD BY: (DATE)
.
DATE:
.
OWNER RESPONSE:
FIG. 6
(24)
CONCLUSIONS
The two primary reasons for the failure of a detail ship design
the design effort and hence the production effort as well. The inter-
change orders by the Owner, too much time identifying and solving
ability to plan, schedule, and control the design activities with the
The author is the General Manager of the Cape May - Lewes Ferry
ACKNOWLEDGEMENTS
particular the guidance and support of Mr. A.C. Brown, Senior Vice