CUSTOMER : KS ORKA RENEWABLES PTE.LTD.

CONTRACT NO : MASTER SCHEDULE DOC NO. PROJ-MS-001 . REV : 0


REF.PT.SPC JOB NO :-
SPC JN : A.06.1128 EXPANSION WAREHOUSE SMGP PREP BY : Shandy S. DATE : 12.JUNE.2017

ID Name Remaining Start Finish Predecessors August


Duration 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1 Expansion warehouse SMGP 36 days Wed 7/12/17 Wed 8/16/17
2 Preparation 5 days Wed 7/12/17 Sun 7/16/17
3 Civil Work 26 days Thu 7/13/17 Mon 8/7/17
4 Survey 2 days Thu 7/13/17 Fri 7/14/17
5 Topography 1 day Thu 7/13/17 Thu 7/13/17 2SS+1 day
6 Leveling 1 day Fri 7/14/17 Fri 7/14/17 5
7 Earth Work 10 days Sat 7/15/17 Mon 7/24/17
8 Excavation 2 days Sat 7/15/17 Sun 7/16/17 6
9 Backfill 1 day Sun 7/23/17 Sun 7/23/17 8,15,16
10 Grabbing for leveling floor 1 day Mon 7/24/17 Mon 7/24/17 9
11 Steel Work 9 days Mon 7/17/17 Tue 7/25/17
12 Cutting Re-Bar 4 days Mon 7/17/17 Thu 7/20/17 2
13 Bar-Bending 3 days Tue 7/18/17 Thu 7/20/17 12FS-3 days
14 Installation Re-bar 7 days Wed 7/19/17 Tue 7/25/17
15 Footplate 4 days Wed 7/19/17 Sat 7/22/17 13FS-2 days
16 Coloum 4 days Wed 7/19/17 Sat 7/22/17 15SS
17 Tie Beam 3 days Sun 7/23/17 Tue 7/25/17 16
18 Concrete Work 22 days Mon 7/17/17 Mon 8/7/17
19 Bekisting 2 days Mon 7/17/17 Tue 7/18/17 12SS
20 Lean Concrete 2 days Wed 7/19/17 Thu 7/20/17 19
21 Footplate Concrete 3 days Fri 7/21/17 Sun 7/23/17 20
22 Coloum Concrete 4 days Mon 7/24/17 Thu 7/27/17 21
23 Tie Beam Concrete 3 days Fri 7/28/17 Sun 7/30/17 17,22
24 Floor Slab 8 days Mon 7/31/17 Mon 8/7/17 10,23
25 Steel Structure 20 days Mon 7/17/17 Sat 8/5/17
26 Fabrication 11 days Mon 7/17/17 Thu 7/27/17
27 Fit-up & Cutting 3 days Mon 7/17/17 Wed 7/19/17
28 Coloum WF-250x250x9x14 3 days Mon 7/17/17 Wed 7/19/17 2
29 Tie Beam WF-150x75x5x7 3 days Mon 7/17/17 Wed 7/19/17 2
30 Rafter 1 WF-250x250x9x14 3 days Mon 7/17/17 Wed 7/19/17 2
31 Rafter 2 WF-250x250x9x14 3 days Mon 7/17/17 Wed 7/19/17 2
32 Base Plate 3 days Mon 7/17/17 Wed 7/19/17 2
33 Welding 4 days Thu 7/20/17 Sun 7/23/17
34 Coloum WF-250x250x9x14 4 days Thu 7/20/17 Sun 7/23/17 28,32
35 Tie Beam WF-150x75x5x7 4 days Thu 7/20/17 Sun 7/23/17 29
36 Rafter 1 WF-250x250x9x14 4 days Thu 7/20/17 Sun 7/23/17 30
37 Rafter 2 WF-250x250x9x14 4 days Thu 7/20/17 Sun 7/23/17 31
38 NDT 1 day Mon 7/24/17 Mon 7/24/17
39 Coloum WF-250x250x9x14 1 day Mon 7/24/17 Mon 7/24/17 34
40 Tie Beam WF-150x75x5x7 1 day Mon 7/24/17 Mon 7/24/17 35
41 Rafter 1 WF-250x250x9x14 1 day Mon 7/24/17 Mon 7/24/17 36
42 Rafter 2 WF-250x250x9x14 1 day Mon 7/24/17 Mon 7/24/17 37
43 Sandblasting & Painting 3 days Tue 7/25/17 Thu 7/27/17
44 Coloum WF-250x250x9x14 3 days Tue 7/25/17 Thu 7/27/17 39
45 Tie Beam WF-150x75x5x7 3 days Tue 7/25/17 Thu 7/27/17 40
46 Rafter 1 WF-250x250x9x14 3 days Tue 7/25/17 Thu 7/27/17 41
47 Rafter 2 WF-250x250x9x14 3 days Tue 7/25/17 Thu 7/27/17 42
48 Installation 9 days Fri 7/28/17 Sat 8/5/17
49 Mobilization 5 days Fri 7/28/17 Tue 8/1/17 44,45,46,47
50 Erection 4 days Wed 8/2/17 Sat 8/5/17
51 Coloum WF-250x250x9x14 4 days Wed 8/2/17 Sat 8/5/17 22,49
52 Tie Beam WF-150x75x5x7 4 days Wed 8/2/17 Sat 8/5/17 49
53 Rafter 1 WF-250x250x9x14 4 days Wed 8/2/17 Sat 8/5/17 49
54 Rafter 2 WF-250x250x9x14 4 days Wed 8/2/17 Sat 8/5/17 49
55 Gordeng & Listplank CNP-150x50x20x3.2 4 days Wed 8/2/17 Sat 8/5/17 49
56 Architecture 15 days Wed 8/2/17 Wed 8/16/17
57 Fabrication 7 days Wed 8/2/17 Tue 8/8/17
58 Steel Door + accessories 2 days Wed 8/2/17 Thu 8/3/17 49
59 Slidding Steel Door + accessories 2 days Fri 8/4/17 Sat 8/5/17 58
60 Personnal Steel Door + accessories 3 days Sun 8/6/17 Tue 8/8/17 59
61 Installation 11 days Sun 8/6/17 Wed 8/16/17
62 Roof Structure Work 11 days Sun 8/6/17 Wed 8/16/17
63 Wiremesh M6 3 days Sun 8/6/17 Tue 8/8/17 51,52,53,54,55
64 Alumunium Foil 3 days Sun 8/6/17 Tue 8/8/17 51,52,53,54,55
65 Glass wool 3 days Sun 8/6/17 Tue 8/8/17 51,52,53,54,55
66 Zincalume Color Bond 3 days Wed 8/9/17 Fri 8/11/17 63,64,65
67 Sky Light 2 days Sat 8/12/17 Sun 8/13/17 66
68 Exhaust Fan 3 days Mon 8/14/17 Wed 8/16/17 67
69 Wall Work 3 days Sun 8/6/17 Tue 8/8/17
70 Frame Work 2 days Sun 8/6/17 Mon 8/7/17 55
71 Zincalume work 2 days Mon 8/7/17 Tue 8/8/17 70FS-1 day
72 Office & Building 9 days Tue 8/8/17 Wed 8/16/17
73 Hollow Block work 4 days Tue 8/8/17 Fri 8/11/17 71FS-2 days,24
74 Plesteran + aci 2 days Sat 8/12/17 Sun 8/13/17 73
75 Frame of Platfond 2 days Mon 8/14/17 Tue 8/15/17 74
76 Painting 1 day Wed 8/16/17 Wed 8/16/17 75
77 Other Installation 6 days Wed 8/9/17 Mon 8/14/17
78 Steel Door + accessories 1 day Wed 8/9/17 Wed 8/9/17 71,60
79 Slidding Steel Door + accessories 2 days Thu 8/10/17 Fri 8/11/17 78
80 Personnal Steel Door + accessories 3 days Sat 8/12/17 Mon 8/14/17 79
81 Mechanical, Electrical & Plumbing 7 days Thu 8/10/17 Wed 8/16/17
82 Electrical 7 days Thu 8/10/17 Wed 8/16/17
83 Box Panel 1 day Thu 8/10/17 Thu 8/10/17 78
84 Cable Tray 2 days Fri 8/11/17 Sat 8/12/17 83
85 Pulling Cable 2 days Sat 8/12/17 Sun 8/13/17 84FS-1 day
86 Lamp of Warehouse 2 days Mon 8/14/17 Tue 8/15/17 85
87 Lamp of Office & Building 2 days Mon 8/14/17 Tue 8/15/17 85
88 Termination 1 day Wed 8/16/17 Wed 8/16/17 86,87
89 Plumbing 7 days Thu 8/10/17 Wed 8/16/17
90 Spout down 4 days Thu 8/10/17 Sun 8/13/17 83SS
91 Fresh water installation 4 days Thu 8/10/17 Sun 8/13/17 90SS
92 Black Water installation 4 days Thu 8/10/17 Sun 8/13/17 91SS
93 Separator 4 days Thu 8/10/17 Sun 8/13/17 92SS
94 Completed 0 days Wed 8/16/17 Wed 8/16/17 88,76,68,80,93,92,91,90 8/16

Project: A.06.1128 Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Wed 7/12/17
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 1 Dist : Client, Construction team, Admin, Engineering, QC