StorageTankInspectionandTestPlan
ActivityBy Remark
No. InspectionandTestPlan ReferenceDocument AcceptanceCriteria VerifyingDocument
Manuf. TPI Client
BeforManufacturing
ApprovalofMechanical
2 Datasheets,PO,Spec. API650,Spec. CalcualtionBook H H A
CalculationBooks
ApprovalofFabrication
3 DWG,Spec. API650,Spec. DWG H H A
Drawings
Materials
Reviewmilltest
4 DWG,Certificates ASMESECII Certificates H W R
certificatesofplates
Reviewmilltest
5 certificatesofpipe,flange, DWG,Certificates ASMESECII,16.5 Certificates H W R
etc.
Reviewmilltest
6 certificatesofwelding WPS,Certificates ASMESECII Certificates H W R
consumablematerial
Visual&Dimensional
7 DWG,Spec. ASMESECII Report H W R
Check
DuringmanufacturingMarking,Cutting,BevelingandGrinding
Anchor
bolts(Distance,
33 DWG,Spec. API650,Spec. Report H H R
Projection,etc.)as
required
DuringManufacturingWelding
Welder/Welding
35 Operator DWG,WPS,WQT,Spec ASMESECIX Report H R/A R
Qualification
NDTOperator
36 Certificates API650,Spec. Report H R/A R
CertificateCheck
NDTofannularplate
43 Spec. API650,Spec. Report H H R
/VacuumTest(Ifrequired)
ManholeElevation,
57 DWG,Spec. API650,Spec. Report H H R
OrientationandProjection
DuringManufacturingHydroStaticTest
Verificationof
58 Reports API650,Spec. Report H H R
TestPackage
Hydrotest(Water
59 Spec. API650,Spec. Report H H H
level/Holdingtime)
Settlementcheck
60 (Refertoapplicable DWG,Spec. API650,Spec. Report H H R
procedure)
61 Waterdischarge Spec. API650,Spec. Report H W R
DuringManufacturingPaintingActivities
Paintingmaterial
63 Spec. API650,Spec. Report H H R
identification/check
Weathercondition&
64 SurfacePreparation Spec. API650,Spec. Report H H R
(Blasting)
PrimerLayerInspection
65 (IncludingDryThickness Spec. API650,Spec. Report H H R
check)
Intermediate/FinalLayer
66 Inspection(Including Spec. API650,Spec. Report H H R
DryThicknesscheck)
DuringManufacturingCathodicProtectionandElectrical
www.inspectionforindustry.com
Checkofmaterialpriorto
67 Spec. API650,Spec. Report H H R
installation
InstallationofEarthing
68 Spec. API650,Spec. Report H H R
Bosses
ChecktheTestBox,
73 Spec. API650,Spec. Report H H R
ReferenceElectrode
installationofreference
74 Spec. API650,Spec. Report H H R
electrodeincludingcable
Abbreviations:
H:HoldPoint=HoldontheproductiontillTPIInspectorperformsinspectionandsupervisetherequiredtest
W:WitnessPoint=ManufactureshallnotifyclientandTPIInspectorbutthereisnoholdontheproduction;
ClientcanwaivethisinspectionbasedonhisdiscretionandinformsTPIInspectoraccordingly.
R:DocumentReview=ReviewmeansReviewdocument,whichincludesofmaterialtestcertificates,WPS,PQR,NDTProceduresandetc.
A:Approval
SW:SpotWitness=foritemswithspotwitnessmanufactureshallnotifyTPIinspectorasfulfillingthemonitoring;
ForexampleonerandomvisitforwholeUTtestsoroneortwovisitsforwholesurfacepreparationworksforpainting.
MOM:MinuteofMeeting
P.O:PurchaseOrder