Professional Documents
Culture Documents
18101-11 Rotary Kyln W3W01
18101-11 Rotary Kyln W3W01
Note!
1. GENERAL
2. WELDING MACHINERY
2.1
Fi11er material
A filler material consisting of unalloyed rod and a
manganese-alloy welding powder is used for submerged arc
welding of kiln shells during erection.
18101-11
C Mn Si
0,07 1,0 0,8
Mechanical properties:
Tensile strength 550 Mpa
Yield point 460 Mpa
Elongation >22%
Charpy-V, 0C 40 J
Fig. 1
3.1
Welding on travelling wheels
For transport purposes the kiln is delivered in short
belts which are welded together on site to form kiln shell
sections of a suitable erection length.
The erection length of the kiln shell sections is shown on
the shipping drawing.
The kiln belts are welded together on the ground supported
by travelling wheels, and this work can be carried out
concurrently with the installation of the support
components.
It will be necessary to arrange part of the erection area
especially for welding on travelling wheels. Such an area
is shown to the right of fig. 6 on enclosure I. It
consists of two concrete floors for the travelling wheels
and a gantry crane for loading and unloading of the kiln
belts.
Figs. 7 - 11 on enclosures I-III show how reception,
unloading and parking of kiln belts can be arranged.
Fig. 12 on enclosure IV shows a welding set-up. The two
kiln belts to be welded together are placed on a set of
travelling wheels. The automatic welding machine is placed
on a gantry across the belts. Tarpaulins over the place of
welding provide weather protection.
18101-11
3.2
Erection welding
3.2.1
Barring
When the kiln shell sections have been placed on the
supports and the kiln gearing has been equipped with a
gear unit and a barring gear unit, erection welding can be
started.
The kiln must be barred continuously at a speed matching
the welding speed which is 250-420 mm/min. as mentioned.
To this end, it will be necessary to connect an infinitely
variable electric motor (or infinitely variable gear unit)
to the high-speed shaft of the barring gear.
It must be possible to remote-control barring from the
place of welding, both when circular seams, guide blocks
and cooler supports are to be welded. It may be done e.g.
by mounting a remote-control cable and a control box with
push-buttons.
The kiln gearing has one or two drives. Fig. 2 shows an
example of how the speed of the high-speed shaft of the
barring gear unit can be calculated. For automatic welding
it will suffice to use one drive, and the calculation,
therefore, applies to both gearings.
18101-11
Example:
Normal motor rating for barring at welding speed is from 2 -3.5 kW. At low
speeds/high gear ratios the barring gear may easily be overloaded if too
large a motor is used.
If the kiln has a hydraulic barring motor, it can be used for barring during
welding when the yield of the pump unit is changed.
18101-11
3.2.2
Scaffolds for external erection welding
It is not possible to give a general description of the
construction of scaffolds as it will depend an the
scaffold material available in every single case.
Fig. 14 an enclosure V shows an example of haw to
construct a welding platform for performance of the
external erection welds.
The platform can be built up of tubes or light sections to
be mounted in the travelling erection crane in frames
which are welded to the crane. A number of hales in the
frames make it possible to raise or lower the platform in
order that the automatic welder can be placed at the
correct distance from the kiln shell.
Other types of scaffold are described in the welding
programme in section 7, sub-section 7.3.2.1.
3.2.3
Internal erection welds
Figs. 15 and 16 on enclosure VI show the welding machinery
for internal welds. The set-up is the same for travelling
wheel welding and erection welding.
The automatic welding machine is run in as follows: The
trolley of the automatic welding machine must run directly
on the bottom of the kiln shell. Clamp a not too sensitive
spirit level to the automatic welding machine to check its
position. Select a suitable barring speed for the kiln and
start barring. Set the speed control of the automatic
welding machine trolley until barring speed and trolley
speed coincide and the spirit level bubble is stationary,
i.e. the trolley moves on the kiln shell at the same speed
as the shell, but in the opposite direction. When this is
so, welding can be started.
18101-11
4. PRIHEATING
10
11
6.1
All welded seams must be ground and cleaned of weld
splashes, among other reasons because of the subsequent
ultrasound testing.
6.2
In UNAX kilns the circular seam A above the heavy belt for
the 'movable' UNAX cooler supports (see fig. 3) is exposed
to a very high dynamic load.
Fig. 3
12
Fig. 4
Fig. 5
18101-11
13
7.1
General
7.1.1
A 4.5 x 75 m UNAX kiln is chosen as basis for the
example.
Planning is divided into two tables as shown in en-
closures VII and VIII.
The table on enclosure VII represents the total kiln
erection and shows the individual welders' positions in
the course of welding.
The table on enclosure VIII deals with details of the
welding of the kiln and the welding together of the burner
tunnel. The example is based on automatic welding of the
circular seams of the kiln shell and that the tube girder
is welded on the ground and is not mounted until the kiln
has been finish-welded.
The table on enclosure VII also includes the welding work
to be done in connection with the UNAX cooler supports.
This work is described in a separate instruction manual.
18101-11
14
7.1.2
7.1.3
When the erection joints of the kiln shell have been
welded inside and out, final alignment of the tyres must
be carried out and the tyres be secured with stop blocks
in the longitudinal direction of the kiln. This work will
have to be carried out on the welding team's days off as
it cannot be done concurrently with the welding
operations.
The final fine alignment of the gear rim must not be
carried out until the kiln welding work, including welding
of the tyre guide blocks, has been completed. The
alignment work may be carried out together with welding of
the cooler supports when this is done on the second shift
because all welders will be working on the day shift
during this period.
7.2
Crew
It is anticipated that six certified welders will be
required for the welding work, three of whom must be
certified for both manual and automatic welding.
In addition, a number of assistants varying in numbers
from two to tive during the entire process.
18101-11
15
7.3
7.3.2
Enclosure VIII, welding of kiln shell A. Kiln sections
7.3.2.1
Erection of scaffolds for welding machine
To be able to carry out the welding operations con-
tinuously it will be necessary to have two scaffolds. The
scaffolds must be able to bear the welding machine and its
crew and be so steady that the movements of the crew will
not set up vibrations which may interfere with the welding
operations.
18101-11
16
7.3.2.4
Tack-welding and manual welding of bottom run
Two runs have to be made at a time, with one welder on
either side of the kiln. Complete all bottom runs and
inspect them visually before automatic welding is started.
7.3.2.5
External welding including grinding of welded seams
These welds are made by two welders on the day shift. Note
that the welding time of some seams is longer than a
normal work day for the day shift, and so the night shaft
will have to finish the seams.
18101-11
17
7.3.2.6
Dismounting of stiffening crosses, mounting bolts, angle
irons and locking pieces
Remove the mounting bolts during the external welding
operation. Removal of stiffening crosses, mounting irons
and adjusting irons ('horses') must be carried out by the
use of carbon arc chipping.
This work will be done by the night shift.
Gouging of stiffening crosses, mounting irons and
adjusting irons will leave scars on the kiln shell. It is
very important that the kiln shell should be repaired by
welding and subsequent grinding.
This work will also be done by the night shift.
7.3.2.7
Back-grooving of welded seams inside the kiln shell
Gradually as the external welded seams are finished, they
will have to be back-grooved from the inside until the
throat of the weld is clean and without cracks and slag
inclusions.
This work will also be done by the night shift.
After internal back-grooving, the throat must be ground
absolutely clean with a high-speed angle grinder.
This work will also be done by the night shift.
18101-11
18
7.3.2.8
Automatic welding of internal welded seams
Automatic welding of the internal seams is carried out by two welders
on the day shift. After welding, the seams are to be ground and all
weld splashes removed. Do not forget ventilation!
7.3.2.9
Ultrasonic NDT (Non Destructive Testing) of the welded seams
This work will have to be done by an NDT expert in compliance with
the instruction manual for this work.
7.3.2.10
Repair of defective seams
Defective welded seams are repaired by back-grooving with a carbon
arc or angle grinder and subsequent manual welding. The work will be
done concurrently with the NDT on the day or night shift as required
and in such a way that it will not interfere with the automatic
welding inside the kiln.
7.3.2.11
Removal of scaffolds for external welding
See sub-section 7.3.2.1
B. Guide blocks
7.3.2.13
Scaffolds for welding of guide blocks
Scaffolds will have to erected at all tyres so that the guide blocks
can be welded flat-downhand (2F).
18101-11
19
7.3.2.14
Fine alignment of tyres, tack-welding and welding of guide
b1ocks
When the erection joints have been welded inside and out,
the guide blocks must be aligned and placed correctly
relative to the supporting rollers before welding can be
started.
The alignment will have to be co-ordinated with the
erection programme.
The work of tack-welding and welding the guide blocks is
done by two welders on the night shift.
C. Gearing
7.3.2.16
Scaffold at gear rim
The purpose of the scaffold at the gear rim is to allow
flat-downhand welding (2F) of the gear rim springs.
The gear rim must be aligned prior to welding and
inspected as described in the instruction manual for this
work.
The work must be co-ordinated with the erection programme.
7.3.2.17
We1ding of gear rim springs
This work is done by two welders on the day shift.
D. Burner tunnel
7.3.2.19
Scaffold for welding
The necessary scaffolds must be erected for external and
internal welding of the joints.
18101-11
20
7.3.2.20
Welding of burner tunnel
This work is done by two welders. When welding has been
carried out from one side, the seams are chipped from the
other side until a clean weld metal appears. Stiffening
crosses, mounting and adjusting irons must be gouged and
all scars be removed by welding and subsequent grinding.
7.3.2.21
NDT control
The NDT control is to be carried out by an NDT expert in
compliance with the directions on the drawing.
---o0o---