Professional Documents
Culture Documents
Robert Mcgill PDF
Robert Mcgill PDF
Project
Evaluation Concept/Scoping Pre-feasibility Feasibility
Phase
Mine
Construction Detailed design Project Execution
Phase
Mine
Production Build-up Steady state
Phase
Capital Cost
Assess the potential value of the Does the potential value from the opportunity
+ / -25%
opportunity justify further investigation?
Define the work required to assess the The thoroughness of evaluation of alternative
opportunity technology, costing and implementation
Establish a plan for the Pre-Feasibility approaches.
phase Integrity of Pre-feasibility planning.
Have areas of opportunity and risk been
investigated in later stages to enhance
value?
Project
Evaluation Concept/Scoping Pre-feasibility Feasibility
Phase
production solution has been selected and considered and reviewed on an equal basis?
+ 25% to 15%
is a viable business concept aligned to What criteria were used to select the
Capital Cost
business strategy. preferred option?
Demonstration that all the discarded Have all opportunities for optimisation been
project options have been studied and are reasonable pursued?
clearly inferior and have no probability of
re-emerging as viable options.
Are the risks and possible mitigators well
understood?
A workable plan for taking the concept
through the Feasibility development stage.
Does the potential value from the opportunity
still justify further investigation?
Integrity of Feasibility planning.
Project
Evaluation Concept/Scoping Pre-feasibility Feasibility
Phase
+ 15% to 5%
FEASIBILITY
Capital Cost
accuracy for implementation funding. opportunity prior to moving into
Implementation?
Is there an acceptable risk profile?
Is there a workable plan for taking the
Project through the implementation &
Operational readiness stages?
Is the opportunity recommended for
approval?
Typical Project Organogram
Project Manager
Project
Mining Engineering
Services
Ventilation
Geotechnical Mining Discipline Drawing Capital Project Project
Geologist Engineer Mine Planner
Engineer Engineer Engineers Office Estimator Secretary Planner
Key Success Factors for Mine Planning
and Design
Quality/quantity of inputs
Understanding of value chain and link between
inputs and outputs
Experience and skill
Mining operations and projects
Planning tools
Team integration
Consistency and applicability of design criteria
Benchmarking/callibration
Mine Planning and Design Inputs
Ventilation
Mining Engineering
- Empirical design rules-of-
-Mining method
thumb
-Development and stoping rates
-Regulatory design criteria
-Preferred equipment specs
-Mining equipment
specifications -Targeted production schedule
and volumes
Infrastructure
Geotech - Preferred access methodology
-Rock Mass ratings -Requirements for
-Empirical design rules-of- services/transport
thumb
-Capacities and constrants
Geology
Mine Strategic Goals
-Block Model
-Geometric and structure
Design -Life-of-mine
model
-Stratigraphic model
and -Payback Period
-Financial goals
Planning
Mining Method Selection
Declines Criteria:
Drill and blast Depth/Geometry
TBM Timing
Ramps Bottom Access
Shafts Production Volume
Blind-sink Cost and capital
availablity
Raise-bored
Bored
Combinations
84
Project Construction Time
72
Development time in months
60
48
36
24
12
600 800 1000 1200 1400 1600 1800 2000
Depth in metres
29.486 Moz
LoM 43 years (2052)
Building up to 330 Kt/m
To produce up to 800,000
ounces/ year (25 tonnes)
MINERAL RESERVES AND LOM
Current Mine
MINERAL RESERVES AND LOM
Current Mine
MINERAL RESERVES AND LOM
Current Mine
MINERAL RESERVES AND LOM
2
4
Production Profile
600,000
500,000
400,000
Gold Ounces
300,000
200,000
100,000
25
Mine design
Criteria Remarks
Panel Length 25 m to 35 m
25000
Average 23000 tonnes month Average 253m/ month
20000
15000
10000
5000
0
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Thickness and Grade Distribution
THICKNESS COLOUR
<2
2-4
4-6
6-8
>8
GRADE COLOUR
0 - 2.2
2.2 - 4
4-6
6-8
8 - 10
10 - 15
15 - 20
20 - 100
28
Isometric View of Design Options
Longitudinal
Sub Level Open Stoping
Longitudinal
Retreat
29
Animation output
Existing infrastructure
Existing mining
Different colours
represent different
months schedule
Production Report
Planta en caverna
Chancadoras
Expected Developments in Underground
Mining