Professional Documents
Culture Documents
Mitsubishi Heavy Industries, Ltd. (MHI) received an order from Singapore District Cooling Pte, Ltd., for a district cooling plant
with a cooling capacity of 57 MW (16,210 RT). This project was an engineering, procurement, and construction contract that
included the design, manufacture, procurement, construction, and commissioning of a high-efficiency district cooling plant that
would serve as a model for South East Asia where the year-round cooling demand is high. One year has now elapsed since the start
of commercial operation, and this plant is currently operating at higher efficiency than originally planned. This report describes the
performance improvement technologies, such as the centrifugal chiller and ice storage system, that were introduced to achieve this
increased efficiency.
this area from Singapore District Cooling Pte, Ltd. (SDC)Note, Quantity Quantity
and delivered and handed over the plant in 2007 as a model of Chillers during at time of
first stage completion
high-efficiency technology.
We were awarded this contract despite serious international Single-type chilled water centrifugal
1 1
chiller (3 MW/chiller)
competitive bidding because MHI’s plant was recognized
Parallel-type chilled water centrifugal
to be superior in both cost and performance. Five district chiller (7 MW/chiller)
2 4
cooling plants are planned for the Marina South area, and
Ice storage system:
MHI delivered the portion of the first stage construction Compound-type brine centrifugal chiller 2 6
of 57-M W (16, 210 -R T ) No. 1 plant in the f irst stage of + ice storage tank (20 MW/system)
construction to supply chilled water to two office buildings
Amount of chilled water 57 MW 151 MW
and one commercial facility near the plant. supplied by the plant (16210 RT) (42943 RT)
Note: The customer, SDC is a joint venture between Singapore
Power and the French company Dalkia.
3. Centrifugal chiller
2. Outline of plant facilities
3.1 Description
Table 1 shows the ma in equipment of heat source A h i g h - r e l i a b i l i t y, h i g h - e f f i c i e n c y N A R T- s e r i e s
c om p one nt s a t t he p l a nt . D u r i n g t he f i r s t s t a ge of compressor was used i n t he cent r i f uga l chil ler. T he
construction, MHI delivered one 3-MW centrifugal chiller, compressor’s high efficiency is due to its aero dynamic
two 7-MW centrifugal chillers, and two 20-MW ice storage profile that minimizes mechanical loss. As well, the heat
systems. During the plant design, MHI made every effort to transfer efficiency of the heat exchanger was improved by
facilitate smooth workflow on site using a three-dimensional optimizing the shape and configuration of its array of tubes.1
(3D) computer-aided design (CA D) that integrated all 3.2 Application technologies in this project
information on the machinery, piping, air conditioning ducts, (1) Heat exchanger configuration change
electrical and control equipment, and architectural details to The 7-MW chilled water centrifugal chiller is a parallel-
optimize the layout of the plant space. MHI also made a great type chiller with two compressors. In this project, our aim
effort to simplify maintenance after delivery by integrating was to improve the chiller performance using a vertical
4.5°C 4.5°C
Evaporator 13°C Evaporator 13°C
division type evaporator and condenser divided into two centrif ugal chillers w ith three compressors for ice
sections configured so that two independent chillers storage. This improved the performance compared to that
could be connected in series. Figure 1 and Table 2 show of our conventional machine by switching the number
the comparison with a conventional machine, and Fig. 2 of operating compressors according to the operational
shows a 3D model of the 7-MW parallel-type chilled water mode of either ice storage or chilled water discharge.
centrifugal chiller. Since a brine centrifugal chiller has a different brine
( 2 ) Sw it ch i ng t he nu mber of operat i ng compressors outlet temperature depending on the operational mode,
according to operational mode the compression ratio of the refrigerant changes. Since
In this project, for the first time, MHI used brine the compressor for a brine centrifugal chiller is normally
selected for the ice-storage mode with a certain greater
compression ratio and fixed rotational speed setting, the
Table 2 Comparison of performance improvement values for
the 7-MW parallel type chilled water centrifugal chiller performance during the chilled water discharge operation
where the compression ratio is smaller tends to be
Applied chiller neglected. Figure 3 shows the flow of our conventional
MHI’s
Item (heat exchanger
conventional machine machine.
vertical division type)
Higher efficiency operation is possible for both ice
Cooling 7 MW (2000 RT) 7 MW (2000 RT)
capacity storage and chiller water discharge modes by using three
Chilled water 13°C at inlet/ 13°C at inlet/ compressors for the chiller, operating two low-stage
condition 4.5°C at outlet 4.5°C at outlet compressors and one high-stage compressor during ice
Cooling water 30°C at inlet/ 30°C at inlet/ storage when the required compression ratio is greater,
condition 35.8°C at outlet 35.8°C at outlet and operating only two low-stage compressors during
Electrical power 1240 kW 1074 kW chilled water discharge operation when the required
COP 5.67 6.55 compression ratio is smaller.
No.1 compressor
No.2 compressor
Evaporator
Condenser
Brine Cooling
water
Economizer 1
Subcooler
Economizer 2
Fig. 2 Three dimensional model of the 7-MW parallel type Fig. 3 Flow of the brine centrifugal chiller
chilled water centrifugal chiller (MHI’s conventional machine)
Subcooler Subcooler
Economizer 2 Economizer 3 Economizer 2 Economizer 3
Fig. 4 Flow of the compound type brine centrifugal chiller (for Fig. 5 Flow of the compound type brine centrifugal chiller (for
ice storage operation) chilled water discharge operation)
During ice storage operation with a high compression ratio, the During chilled water discharge operation with a low compression
pressure is raised by the No. 3 high-stage compressor, and then ratio, only the No. 1 and No. 2 low-stage compressors operate.
increased to a medium pressure by the No. 1 and No. 2 low-stage
compressors.
Agitation caused by
air during ice discharge Path of rising air bubbles
Air blower
Dimensions of ice storage coil: length 4.6 m, width 1.475 m, and height 1.8 m
27m
5.7m
12.5m
10.0
Chiller capacity (MW)
8.0
Chiller COP
Performance measurement data
6.0
Chiller electrical power (MW)
4.0
2.0
Ice storage time
0.0
0 : 00 1 : 12 2 : 24 3 : 36 4 : 48 6 : 00 7 : 12 8 : 24 9 : 36
Brine inlet temperature (°C)
-2.0
-6.0
-8.0
Fig. 12 Performance characteristics of the 10-MW brine centrifugal chiller measured during ice storage operation
The figure shows performance data measured during operation in ice storage mode.
20000 Ice discharge of ice storage 3-MW chilled water centrifugal chiller
5000
09 00
02 00
03 00
04 00
05 00
06 00
07 00
08 00
11 00
12 00
13 00
16 00
17 00
18 00
19 00
20 00
21 00
22 : 00
23 00
0
14 0
15 00
10 00
:0
:0
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
–5000
:
:
01
–20000
complete to achieve high efficiency. The average brine outlet • Daytime cooling load (8:00–20:00):
temperature of the chiller was –4.3°C. Since the operation 10-MW brine centrifugal chiller chilled water discharge
takes place at a temperature higher than the –5°C specified and ice discharge series operation, as well as 3-MW
for ice storage, this contributes to reducing the electric chilled water centrifugal chiller operation.
power required by the brine centrifugal chiller. • Nighttime ice storage (23:00–8:00):
10-MW brine centrifugal chiller ice storage operation.
5. Historical plant operational data
Figure 14 shows the cooling load and the plant electrical
5.1 Outline power consumption data for the selected day (October
One year has passed since the start of operations at 1, 2007). The electrical power consumption shifted from
the Marina South Area District Cooling Plant. The plant day t ime, when the elect r icit y unit pr ice was high, to
operation experience to date is summarized below. nighttime, when the electricity unit price was low, since the
T h e p e a k c o ol i n g l o a d o f t h i s p l a nt f o r u s e r s i s brine centrifugal chiller operation takes place at night and
approximately 17 MW (4,834 RT). Figure 13 shows the the ice storage tank ice discharge operation takes place
cooling load and the operational data of the main equipment during the day.
of heat source on a t ypical day (October 1, 2007). T he 5.2 7-MW parallel chilled water centrifugal chiller
operational data of the main equipment of heat source is as The 7-MW centrifugal chiller operates over a wide load
follows: range at high efficiency because the number of operating
• Nighttime cooling load (20:00–8:00): compressors is controlled according to the cooling load and
chilled water supplied by 7-MW centrifugal chiller. a variable speed drive control is used for the chilled water
pump. Figure 15, which shows the relationship between
Electrical power consumption (kWe)
2000 5.0
Two compressors operating
1000 4.0
0
3.0
0
0
0
0
0
0
0
0
0
0
0
0
:0
:0
:0
:0
:0
:0
:0
:0
:0
:0
23
15
19
09
01
07
03
05
13
17
21
11
Fig. 14 Plant electrical power consumption on the typical day Fig. 15 7-MW chilled water centrifugal chiller COP
The figure shows the plant electric power consumption on the The figure shows the measured COP data for the 7-MW parallel-
typical day (October 1, 2007). type chilled water centrifugal chiller.
COP (-)
the measured COP value data of the brine centrif ugal discharge operation:
4.0
chiller on October 1, 2007, indicates that the efficiency of approximately 7.0
3.0
the operation is equal to or greater than the planned value
2.0 : No. 1 machine
because the COP during the night-time ice storage operation
1.0 : No. 2 machine
is approximately 5.1 and the COP during the daytime chilled
water discharge operation is 7.0 or higher. 0.0
0:00 2:00 4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00
5.4 Total plant efficiency
Time
The COP of the plant is calculated from the electrical
power consumption through electrical power supply line
Fig. 16 Measured data for the 10-MW brine centrifugal chiller
of the Marina South District Cooling Plant and the amount The figure shows the measured COP data for the 10-MW brine
of chilled water sold to users, both of which are measured centrifugal chiller on the typical day (October 1, 2007).
simultaneously. The electrical power consumption includes
all the electrical power used in the plant, including the main
equipment of heat source, sub-equipment, air conditioning high air conditioning cooling load, and it decreases during
and ventilation equipment, and lighting, amongst others. weekends when there is a low air conditioning cooling load.
Figure 17 shows the total COP of the plant during the period The total weekday COP of the plant is approximately 3.7 as of
from February to October, 2007. October, 2007. This COP significantly exceeds the average
As the users of this plant are mainly office buildings, the total district cooling plant COP of 3.0 because of the ice
total COP of the plant depends on the day of the week. The storage system, and this contributes to reducing the plant
total COP of the plant increases during weekdays due to the life-cycle cost.
Actual total COP of the Marina South District Cooling Plant, Singapore
4.5
4.0
Total COP of the plant (-)
3.5
3.0
2.5
1.5
12
6
07 23
20 7/3 6
07 /23
20 07/ 0
20 7/4 3
0
20 07/ 7
20 7/5 1
8
07 25
20 /6 5
2
20 07/ 9
20 7/7 3
20 /7/ 0
20 7/ 7
20 7/8 0
20 /8 7
4
20 07/ 1
20 7/9 4
20 /9 1
20 07/ 28
/1 / 5
20 7/2 /9
20 07/ /2
20 7/3 /9
20 7/4 6
20 7/5 /4
20 07 /1
20 7/6 /8
20 7/7 /6
07 8/3
20 7/9 7
07 /1
0 /1
0 /1
07 /2
2
0 /1
07 /1
07 /1
07 /2
2
0 /1
07 /2
0 2
0 /1
07 /1
07 /2
3
0 /1
07 /2
0 4/
0 9/
07 10
0 2
20 /3
0 3
0 5
20 /6
0 /6
0 7
0/
20 /2/
20 /3/
20 /4/
20 /5/
20 /6/
20 /8/
/
20 /8
20 07/
20
Date
Reference
1. Sek i et a l., High-Eff iciency Turbo Chiller ( NA RT Ser ies),
Mitsubishi Heavy Industries Technical Review Vol.39 No.2
(2002)