You are on page 1of 44

1

INSTRUCTORS RESOURCE MANUAL

CHAPTER NINE
Project Scheduling:
Networks, Duration Estimation, and Critical Path

To Accompany

PROJECT MANAGEMENT:
Achieving Competitive Advantage

By
Jeffrey K. Pinto

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


2

CHAPTER NINE
PROJECT FOCUS The Spallation Neutron Source Project
INTRODUCTION
9.1 PROJECT SCHEDULING
9.2 KEY SCHEDULING TERMINOLOGY
9.3 DEVELOPING A NETWORK
Labeling Nodes
Serial Activities
Concurrent Activities
Burst Activities
Merge Activities
9.4 DURATION ESTIMATION
9.5 CONSTRUCTING THE CRITICAL PATH
Calculating the Network
The Forward Pass
The Backward Pass
Laddering Activities
Hammock Activities
Steps to Reduce the Critical Path
Project Management Research in Brief Software Development Delays and Solutions
Summary
Key Terms
Solved Problems
Discussion Questions
Problems
Internet Exercises
MSProject Exercises
PMP Certification Sample Questions
Bibliography

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


3

TRANSPARENCIES

9.1 RULES FOR DEVELOPING ACTIVITY NETWORKS

1. Some determination of activity precedence ordering must be done


prior to creating the network.

2. Network diagrams usually flow from left to right.

3. An activity cannot begin until all preceding connected activities


have been completed.

4. Arrows on networks indicate precedence and logical flow. Arrows


can cross over each other, although it is helpful for claritys sake
to limit this effect when possible.

5. Each activity should have a unique identifier associated with it


(number, letter, code, etc.).

6. Looping, or recycling through activities, is not permitted.

7. Although not required, it is common to start a project from a


single beginning node. A single node point also is typically used as
a project end indicator.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


4

9.2 LABELS FOR ACTIVITY NODE

Early ID Number Early


Start Finish

Activity Activity Descriptor


Float

Late Activity Late


Start Duration Finish

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


5

9.3 PROJECT ACTIVITIES LINKED IN SERIES

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


6

9.4 ACTIVITIES LINKED IN PARALLEL (CONCURRENT)

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


7

9.5 MERGE ACTIVITIES

Activity A

Activity B Activity D

Activity C

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


8

9.6 BURST ACTIVITIES

Activity B

Activity A Activity C

Activity D

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


9

9.7 EXAMPLE OF CREATING A PROJECT ACTIVITY


NETWORK

Information for Network Construction


Name: Project Delta

Activity Description Predecessors

A Contract signing None

B Questionnaire design A

C Target market ID A

D Survey sample B, C

E Develop presentation B

F Analyze results D

G Demographic analysis C

H Presentation to client E, F, G

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


10

9.8 ACTIVITY NETWORK FOR EXAMPLE

E
Dev. Present.
B
Design

A D F H
Contract Survey Analysis Present

C
Market ID G
Demog.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


11

9.9 ACTIVITY DURATION ESTIMATION BETA


DISTRIBUTION

ESTIMATED TIME FORMULA

TE = A + 4(B) + C
6

WHERE:

A = MOST OPTIMISTIC TIME

B = MOST LIKELY TIME

C = MOST PESSIMISTIC TIME

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


12

9.10 CONSTRUCTING THE CRITICAL PATH

INFORMATION FOR PROJECT DELTA

Activity Description Predecessors Estimated Duration

A Contract signing None 5

B Questionnaire design A 5

C Target market ID A 6

D Survey sample B, C 13

E Develop presentation B 6

F Analyze results D 4

G Demographic analysis C 9

H Presentation to client E, F, G 2

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


13

9.10 (Cond)

Partial Project Activity Network with Task Durations

B E
Design Dev. Present
5 6

A D F H
Contract Survey Analysis Present
5 13 4 2

C G
Market ID Demog.
6 9

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


14

RULES WHEN USING THE FORWARD PASS

1. Add all activity times along each path as we move through the
network (ES + Dur = EF),

2. Carry the EF time to the activity nodes immediately succeeding


the recently completed node. That EF becomes the ES of the next
node, unless the succeeding node is a merge point.

3. At a merge point, the largest preceding EF becomes the ES for


that node.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


15

9.12 ACTIVITY NETWORK WITH FORWARD PASS

5 B 10 10 E 16
Design Dev. Present
5 6

0 A 5 11 D 24 24 F 28 28 H 30
Contract Survey Analysis Present
5 13 4 2

5 C 11 11 G 20
Market ID Demog.
6 9

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


16

9.13 RULES FOR USING THE BACKWARD PASS

1. Subtract activity times along each path as you move through the
network (LF Dur = LS),

2. Carry back the LS time to the activity nodes immediately


preceding the successor node. That LS becomes the LF of the next
node, unless the preceding node is a burst point.

3. In the case of a burst point, the smallest succeeding LS becomes


the LF for that node.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


17

ACTIVITY NETWORK WITH BACKWARD PASS

5 B 10 10 E 16
Design Dev. Present
6 5 11 22 6 28

0 A 5 11 D 24 24 F 28 28 H 30
Contract Survey Analysis Presentation
0 5 5 11 13 24 24 4 28 28 2 30

5 C 11 11 G 20
Market ID Demograph.
5 6 11 19 9 28

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


18

9.15 COMPLETED ACTIVITY NETWORK WITH CRITICAL PATH AND ACTIVITY


SLACK TIMES IDENTIFIED

Critical Path is indicated in bold

5 B 10 10 E 16
1 Design 12 Dev. Present
6 5 11 22 6 28

0 A 5 11 D 24 24 F 28 28 H 30
0 Contract 0 Survey 0 Analysis 0 Presentation
0 5 5 11 13 24 24 4 28 28 2 30

5 C 11 11 G 20
0 Market ID 8 Demograph.
5 6 11 19 9 28
ES ID EF

Slack Task Name

LS Duration LF
Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall
19

9.16 ACTIVITY NETWORK DEMONSTRATING LADDERING TECHNIQUE

A1 A2 A3
Design Design Design

A1 A2 A3
Coding Coding Coding

A1 A2 A3
Debugging Debugging Debugging

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


20

9.17 NETWORK DEMONSTRATING HAMMOCK ACTIVITY

5 B 9 12 G 21
13 10
18 4 22 22 9 31

0 A 5 5 C 12 12 H 22 31 I 35
0 9 9 0
0 5 5 14 7 21 21 10 31 31 4 35

5 D 11 11 E 25 25 F 31
0 user needs 0 Coding 0 Debugging
5 6 11 11 14 25 25 6 31

5 A 31
Hammock
26

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


21

9.18 STEPS TO REDUCE THE CRITICAL PATH

1. ELIMINATE TASKS ON THE CRITICAL PATH

2. REPLAN SERIAL PATHS TO BE PARALLEL

3. OVERLAP SEQUENTIAL TASKS

4. SHORTEN THE DURATION ON CRITICAL PATH

ACTIVITIES

5. SHORTEN EARLY TASKS

6. SHORTEN LONGEST TASKS

7. SHORTEN EASIEST TASKS

8. SHORTEN TASKS THAT COST THE LEAST TO SPEED UP

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


22

DISCUSSION QUESTIONS

1. Define the following terms:

a. Path: group of activities sequenced by relationship through project network logic

b. Activity: any piece of work that will be performed during the project which has an
expected time and cost for completion

c. Early start: the earliest possible date upon which an uncompleted activity or project can
start based on sequencing and scheduling constraints

d. Early finish: the earliest possible date upon which an uncompleted activity or project
can be completed

e. Late start: the latest date an activity may start without delaying other project milestones
or the projects expected completion date

f. Late finish: the latest date an activity may end without delaying other project
milestones or the projects expected completion date

g. Forward pass: a process that works forward though the project network to determine
the earliest start and earliest finish time for an activity

h. Backward pass: a process that works backwards through the project network to
calculate the latest finish times for an uncompleted activity

i. Node: a convergence point of dependent paths in a network

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


23

j. AON: Activity on Node; a method of logic that determines activity networks in which
a node depicts an activity and arrows indicate sequencing between nodes

k. Float: a calculation which determines the amount of time an activity can be delayed
from its earliest start date without delaying the projects completion date l.

l. Critical Path: the path through the project network having the least amount of float time
and the longest time duration

m. PERT: Project Evaluation and Review Technique; a network analysis system based on
events and probability used when activities and their duration are difficult to define

2. Distinguish between serial activities and concurrent activities. Why do we seek to use
concurrent activities as a way to shorten a projects length?

Serial activities begin with the first step and proceeding to subsequent steps one at a time
sequentially until the project is completed. Serial activities must be completed in order
and one at a time. Therefore, step 2 can not begin until step1 has been completed, and so
on. Concurrent activities allow more than one activity to be performed during the same
time period. This means step 1 may still be in progress when step 2 is started. Project
teams seek out concurrent activities because they allow multiple phases of the project to
be progressing simultaneously. Time savings occur from several activities being
completed at the same time and delays in one step do not created delays in other
concurrent activities. This method allows activities to work more independently which
means the project can progress at a faster pace.

3. List three methods for deriving duration estimates for project activities. What are the
strengths and weaknesses associated with each method?

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


24

One method for deriving time estimates is past experience. This method is beneficial in
that it is easy and uses past examples of similar activities to predict future time estimates.
However, it is limited in that estimates can be distorted by extenuating circumstances,
changes in time and conditions, and information obsolescence. Another method uses
expert opinion. Again, the approach is simple to use and draws on experience and
knowledge of experts. The shortcomings here involve potential inadequacy of staff (at
least relative to the expert giving the opinion) and project-specific complications. A third
method employs mathematical derivations. This approach is more objective and allows
multiple estimates (based on best, most likely and worst case analysis). The weaknesses
of this method are that it is slightly more difficult to use and it disregards past failures
(a.k.a. lessons learned).

4. In your opinion, what are the chief benefits and drawbacks of using beta distribution
calculations (based on PERT techniques) to derive activity duration estimates?

Beta distribution allows for the likelihood that optimistic and pessimistic times will not
be symmetrical. By including realistic estimates of pessimistic and optimistic durations
beta distribution creates a more accurate distribution of alternative duration times. One
drawback to this method is that it is relies on estimates of pessimistic and optimistic time
estimates which not be reliable. There has also been some debate related to how the time
estimates in this method should be calculated and/or interpreted.

5. The shortest total length of a project is determined by the longest path through the
network. Explain the concept behind this statement. Why does the longest path
determine the shortest project length?

This is based on the concept of critical path. The critical path combines the project
activity network (the order to be followed for start/completion of activities) and the
estimated time duration of activities in the sequence (how long each activity will take to

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


25

complete) to determine the length of time required to complete the project. The longest
path of sequential events is used to establish the projects duration because the events in
the path must be performed one after another. Adding the duration times of activities in
the critical path will result in the shortest project length (i.e. how long it will take to
perform required serial activities).

6. The float associated with each project task can only be derived following the
completion of the forward and backward passes. Explain why this is true.

The forward pass establishes the earliest time that activities in the network can begin and
end. The backward pass determines the latest time activities in the network can begin
and end. Float time is the difference between the tasks latest and earliest end time (or
the tasks latest and earliest start time). Hence, float cannot be calculated until the
forward and backward pass have been completed.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


26

PROBLEMS

1. Consider a project, such as moving to a new neighborhood, completing a long-


term school assignment, or even cleaning your bedroom. Develop a set of
activities necessary to accomplish that project and then order them in a
precedence manner to create sequential logic. Explain and defend the number of
steps you identified and the order in which you placed those steps for best
completion of the project.

SOLUTION:

This problem is intended to get students thinking sequentially; that is, developing first a
set of activities or tasks and then applying some informal sequential logic to the order so
that they can become familiar with concepts such as predecessor and successor activities.
The key is to challenge their sequencing to determine if they have correctly identified
both the necessary activities and the order in which they should be considered.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


27

2. What is the time estimate of the following activity in which the optimistic
estimate is 4 days, pessimistic is 12 days, and most likely is 5 days? Show your
work.

SOLUTION:

Using the Beta distribution for probabilistic estimation, the formula is given as:

TE = (a + 4m + b)/6

Where:

TE = Estimated time for activity

a = most optimistic time to complete the activity

m = most likely time to complete the activity, the mode of the distribution

b = most pessimistic time to complete the activity

The solution to this problem is:

TE = (4 + 4(5) + 12)/6, or

=6

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


28

3. Consider the following project tasks and their identified best, likely, and worst
case estimates of task duration. Assume the organization you work for computes
TE based on the standard formula. Calculate the TE for each of the following
tasks (round to the nearest integer):

Activity Best Likely Worst TE

A 5 5 20

B 3 5 9

C 7 21 26

D 4 4 4

E 10 20 44

F 3 15 15

G 6 9 11

H 32 44 75

I 12 17 31

J 2 8 10

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


29

SOLUTION:

Using the Beta distribution for probabilistic estimation, the formula is given as:

TE = (a + 4m + b)/6

Where:

TE = Estimated time for activity

a = most optimistic time to complete the activity

m = most likely time to complete the activity, the mode of the distribution

b = most pessimistic time to complete the activity

Activity Best Likely Worst TE

A 5 5 20 8

B 3 5 9 5

C 7 21 26 20

D 4 4 4 4

E 10 20 44 22

F 3 15 15 13

G 6 9 11 9

H 32 44 75 47

I 12 17 31 19

J 2 8 10 7

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


30

4. Construct a network activity diagram based on the following information:

Activity Preceding activities

A -

B -

C A

D B, C

E B

F C, D

G E

H F

I G, H

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


31

SOLUTION:

A C F

D I

E G

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


32

5. Consider a project with the following information:

Activity Duration Predecessors


A 3 --
B 5 A
C 7 A
D 3 B, C
E 5 B
F 4 D
G 2 C
H 5 E, F, G

Activity Duration ES EF LS LF Slack


A 3 0 3 0 3 --
B 5 3 8 5 10 2
C 7 3 10 3 10 --
D 3 10 13 10 13 --
E 5 8 13 12 17 4
F 4 13 17 13 17 --
G 2 10 12 15 17 5
H 5 17 22 17 22 --

A. Construct the project activity network using AON methodology and label each
node.

B. Identify the critical path and other paths through the network.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


33

Solution:

a.

a. The Critical Path is: A C D F - H

Alternative paths are: ABE H


ABDFH
ACGH

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


34

6. An advertising project manager has developed a program for a new advertising


campaign. In addition, the manager has gathered the time information for each
activity, as shown in the table below.

a) Calculate the expected activity times (round to nearest integer).


b) Calculate the activity slacks. What is the total project length? Make sure you
fully label all nodes in the network.
c) Identify the critical path. What are the alternative paths and how much slack
time is associated with each feeder path?
d) Identify the burst activities and the merge activities.

Time Estimates (wk)


Activity Optimistic Most Likely Pessimistic Immediate
Predecessor(s)
A 1 4 7 -
B 2 6 7 -
C 3 3 6 B
D 6 13 14 A
E 3 6 12 A, C
F 6 8 16 B
G 1 5 6 D, E, F

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


35

Solution:

a) Calculated activity times are:


Activity Expected Duration
A 4
B 6
C 4
D 12
E 7
F 9
G 5

b)

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


36

The total project length is 22 weeks.

c) The critical path is: B C E G

Path Slack
Other paths are: ADG 2 days
AE G 1 day
BFG 2 days

d) Burst Activities: A and B


Merge Activities: E and G

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


37

7. Using the following information, create an AON network activity diagram,


calculate each activity TE (rounding to the nearest integer), the total duration of
the project, its early start, early finish, late start and late finish times, and slack for
each activity. Finally, show the projects critical path.

Activity Preceding activities Best Likely Worst TE

A - 12 15 25 16

B A 4 6 11 7

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


38

C - 12 12 30 15

D B, C 8 15 20 15

E A 7 12 15 12

F E 9 9 42 15

G D, E 13 17 19 17

H F 5 10 15 10

I G 11 13 20 14

J G, H 2 3 6 3

K J, I 8 12 22 13

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


39

Solution:

Total duration of the project is 82 days.

Critical Path: A-B-D-G-I-K

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


40

a. Now, assume that activity E has taken 10 days past its anticipated duration to
complete. What happens to the projects schedule? Has the duration changed? Is
there a new critical path? Show your conclusions.

Solution:

Because Activity E has 10 days of slack associated with it, delaying the completion of
E by 10 days uses up all the slack; therefore, Activity E is now part of the projects
critical path. The overall projects schedule remains unchanged except there is a new
critical path: A-E-G-I-K

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


41

MSProject EXERCISES

Exercise 9.1

Consider the following information that you have compiled regarding the steps needed to
complete a project. You have identified all relevant steps and have made some
determination regarding predecessor/successor relationships. Using MSProject, develop
a simple Network diagram for this project, showing the links among the project activities.

Activity Predecessors

A Survey site -
B Install sewer and storm drainage A
C Install gas and electric power lines A
D Excavate site for spec house B, C
E Pour foundation D

Solution:

Entering the activities and assigning the predecessor relationships using MSProject, the
Network Diagram should resemble the following:

Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


42

Exercise 9.2

Suppose we have a complete activity predecessor table (shown below) and we wish to
create a Network diagram highlighting the activity sequence for this project. Using
MSProject, enter the activities and their predecessors and create a complete activity
Network diagram for this project.

Project - Remodeling an Appliance

Activity Predecessors
A. Conduct competitive analysis -
B. Review field sales reports -
C. Conduct tech capabilities assessment -
D. Develop focus group data A, B, C
E. Conduct telephone surveys D
F. Identify relevant specification improvements E
G. Interface with Marketing staff F
H. Develop engineering specifications G
I. Check and debug designs H
J. Develop testing protocol G
K. Identify critical performance levels J
L. Assess and modify product components I, K
M. Conduct capabilities assessment L
N. Identify selection criteria M
O. Develop RFQ M
P. Develop production master schedule N, O
Q. Liaison with Sales staff P
R. Prepare product launch Q

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


43

Solution:

Entering the above values and predecessor relationships, we would derive the following network diagram. Note that as in the case of
Exercise 9.1, without duration estimates, all activities are assumed to be of similar duration, making every activity in the network part
of the critical path.

Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall


44

Exercise 9.3

Suppose that we add some duration estimates to each of the activities from exercise 9.1.
A portion of the revised table is shown below. Recreate the Network diagram for this
project and note how MSProject uses nodes to identify activity durations, start and finish
dates, and predecessors. What is the critical path for this network diagram? How do we
know?

Activity Duration Predecessors

A Survey site 5 days -


B Install sewer and storm drainage 9 days A
C Install gas and electric power lines 4 days A
D Excavate site for spec house 2 days B, C
E Pour foundation 2 days D

Solution:

Entering the above values and durations, the network diagram would resemble the
following. If this network were shown on a computer screen, you would note that the
critical path is highlighted in red, identifying the activities A B D E as lying on the
critical path.

Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

You might also like