Professional Documents
Culture Documents
Steam Plants
BY A . S. T H A E L E R , M E M B E R , * AND D . C . M A C M I L L A N , JUNIOR ~V~E/VIBERt
~3rd.Sfage Bleeder
t =4.70; H=17.~5.4
terms of the steam flow between points, and the
actual water rates between these points. F o r '
example, in an installation with steam extracted
.t. I ~0C
,.s zdis.o[o..d
.~/~ t-517.; "H=1195.4
from the main unit at three points, let:
P = total horsepower to be developed,
E = total actual evaporation,
.+: G = steam flow to auxiliaries from boilers,
113Z' Ist. S+ gegle der A, B, C = extraction steam quantities a t third, second
!
~.1~ X=.98.; H=I118.5 and first-stage bleeder points, respectively.
a, b, c, d = actual section water rates between throttle
and third-stage bleeder point, third and second-stage
i- bleeder points, second and first-stage bleeder points and
c" from first-stage to condenser, respectively.
uu I041.5 ~
L.RExhau.s~-
I000 x-.914 ; H=IOIZ The basic equation, then, is as follows:
p=
E-G .jr. E-G-.______~A { E - G - - A : - B _1_ E - - G - A --B--C
a b c d
1~
Sysfem Losses
60,845 Lb. I 375 Lb.G
375Lb " 0 470 ~ I "TZS
I
I I k / l ~llll
Economizer II 71
1
I
~,oLb
~--~
~ /
r<}~
/
r(]~ r44 o~-q=~
~.r.,,
Hi sc Steam Turbine~ Lb.
__ ,IVlJSuperkeaterl | l-n1"~ke-~Pi
I ' [~]==E~]vumps OOLb. ~'~ ~=:~ I Independent
~ kb I Generator
i ~o~o;.~ I
i c~,~,b.l
I ~
,oo~7 ,zz~Lb. ss,b.AJ ~ j
r-- . . . . . b~-~ ~ ~-4~----~----- ------7 --- - - -
Ii h ~ ~.
',1457~b. ~ . . . . .~.~ Lb
I, 36~?. _"____.~k . . . . . .
't3S'/ I 4-Z87Lb. ! 1117OSLb. / 1 Js77~_~_=~. 8LbJA Oearsl
I
.......
~
I
~/:0
I ~'I ,~
qll~ I ~
I
._r
I " C~
i61oncls I L.P.Turbine \ >
Ibso~b.Ii \h
. . . .
I Gland!Seal I ! I , , "
i I Exh.C,)nd'r.! lO__landI ~ b . [ ..... t~
I
I
and Af'k. Cond.~,l-DTi-:_J3ea[ , -z5-o~7 ,-,I IST.3Tag.e I
r~-~_EjecfoE 1627.Lb.IIHFeedHeater; i, _ I ~ : ~ oS u~r g~e T o n k ~p~00~.
I
I,
t~
, ,~--- >- ~ ~ - ~ . -d---~: T ~,~ o~o~<btl~ i~oo~-!..
x,y/" eO,47Stb.i I/IO,4SOLb. ' ", " "/i ' I Au~- F-na'r.
iQ'~. ~ ~i l I t 183r.~_,~_ __ z lO,450Lb, r-:-:_. ~ I ~-~
Ship ~ - ~ Miisc. ...... ~ S"/Main I ~--1
FuelOil - - 7 I Heating ~ !_~He,ating J I i -=_~_
Izoo~I-g~oo
/Cond'r.
I I
~:Jgo o
I~
Heater I Drain [- II
I I
i[ 457Lb'. k, I
Cooler[- u I , X
\x I 400Lb. I O~
I Main Aux.
~ ~sT~. , I
300 Lb. L___I
iT fain/h!r
I
I
200Lb.
I
I
Gondensafe
Pump
Condensate
Pump
. . . . .
I
I
I L_ ~=jecllor
I
I
Fuel0ii i I L 0~,47SLb. _~ ---7 I
Inspection I I ~ i~iC~ ' I Ib~.
Tank I
"]-
I
102_2Lb. I
--'~-~8 --J
Condenser I
t.J
I
I ~00,4"/5Lb,
Afmosp_heri BoosterPump
DrainTank
Fla. 9,.--HEAT BALANCE DIAGRAM. DESIGN A
kO
260 HEAT BALANCE CALCULATIONS
T h e installation assumed is a single-screw, The actual section water rates between the ex-
double-reduction geared turbine, with oil-burning traction points are determined from the Mollier
watertube boilers fitted with economizers. The diagram, and the condition curve for the turbine.
auxiliary generators are driven b y single-reduc- As mentioned above, the condition curve m a y be
tio n geared turbines. All the principal auxiliaries approximated b y applying the same overall Ran-
are motor driven. Steam is extracted from the kine efficiency ratio to the isentropic heat drops
main turbine for two-stage feed heating, and between extraction pressures; or (as in the pres-
for~the fuel-oil heater and evaporator. A drain ent case) a somewhat more correct condition
cooler is provided to cool the feed-heater drains curve obtained b y applying relative efficiencies
before they are rejected to the condenser. for each section to the isentropic drops. T h e
T h e steam conditions assumed are those in fre- relative efficiencies thus used are not strictly stage
quent current u s e - - a pressure of 400 pounds per efficiencies, as they are based on the brake horse-
square inch gage, and t e m p e r a t u r e of 750 de- power, rather than on internal or "indicated"
grees F., both at the superheater outlet. The horsepower. However, this procedure gives a
feed temperature to the economizers is t a k e n as v e r y close approximation to the true condition
235 degrees F. T h e steam conditions a t the curve, and the curve so derived is a m p l y accurate
main turbine inlet allow for a 25-pound drop in for the purpose. T h e determination of the ac-
pressure, and a 25-degree drop in temperature, tual section water rates is given in Table 1.
with the v a c u u m at the condenser assumed as
28 I/2 inches referred to a 30-inch barometer. ACTUAL STEAM CONDITIONS AND BLEEDER
T h e shaft horsepower assumed is 8000. Al- FLOWS
lowing for a reduction-gear efficiency of 97.5 per
T h e actual extraction s t e a m conditions, and
cent, the brake horsepower at the turbine coupling
the actual heat content of extraction steam, to-
is 8200. T h e overall Rankine efficiency ratio,
gether with the bleeder flows (which are evaluated
based on brake horsepower at the turbine cou-
in later paragraphs), are given in T a b l e 2. T h e
pling, is assumed to be 78 per cent.
values of heat content are obtained from the con-
T h e outlet temperatures from the feed heaters
dition curve in Fig. 1.
are selected to give approximately equal tempera-
ture rise in each stage of heating. The bleeder B L E D S T E A M - - T H I R D STAGE ( A )
pressures are then fixed to give approximately a
15-degree difference between the feed outlet Steam supplied from third-stage bleeder at 85
temperature and the saturation t e m p e r a t u r e of pounds absolute, and 470 degrees F., supplied to
the extraction steam. make-up evaporator and fuel-oil heater. T e m -
HEAT BALANCE CALCULATIONS 261
perature of drains from these units at 85 pounds quired to heat one pound of feed from 172 degrees
absolute is 316 degrees F. to 235 degrees equals 63.38 B.t.u., and the total
(a) Evaporator--.~/[ake-up. The average make- heat required is 63.38E.
up required is as follows (see Appendix for allow- (b) Heat Supplied to Feed Heater. T h e heat is
ances) : supplied from four sources: ( 1 ) D r a i n s from
evaporator coils; (2) v a p o r from evaporator
Soot blowers: 16,000 square feet heating sur-
shell; (3) auxiliary exhaust steam from miscel-
face X 2 blows per day X 0.008 = 250 pounds per
laneous steam pumps; (4) bled steam from the
hour.
main turbine. As the second-stage heater is
Whistle: 12-inch diaphragm type. Average
fitted with a trap which discharges condensate at
loss --- 15 pounds per hour.
a temperature of 250 degrees to the first-stage
Miscellaneous losses: 8000 shaft horsepower X
heater, only the heat above liquid at this tempera-
0.05 = 400 pounds per hour.
ture is utilized in the heater. This heat is as
Total make-up = 665 pounds per hour.
follows :
To produce v a p o r at 15 pounds gage with evapo-
(1) Evaporator Coil Drains. H e a t in 765
rator feed at 70 degrees F. requires (1164--38) =
pounds of drains from 316 degrees to 250 degrees
1126 B.t.u. per pound. Hence, the total heat
is 51,715 B.t.u. per hour.
required = 665 X 1126 = 748,790 B.t.u. per
(2) Evaporator Shell Vapor. H e a t in 665
hour. H e a t supplied per pound of bled steam =
pounds of saturated v a p o r above 250 degrees is
1265.4 -- 286.4 = 979 B.t.u. per pound; and bled
628,625 B.t.u. per hour.
steam flow to evaporator coils = 748,790 -- 979 ---
(3) Auxiliary Exhaust. Miscellaneous steam
765 pounds per hour.
pumps, such as bilge, fuel-oil transfer and evapo-
(b) Fuel-Oil Ifeater, and Fuel-Tank Heating
rator feed pumps, supply an average of about 400
Coils. To heat approximately 5000 pounds per
pounds per hour. Of this, approximately 50
hour of fuel oil from 60 degrees to 250 degrees F.,
pounds per hour will be supplied as sealing steam
requires 5000 X (250 -- 60) X 0.47 = 447,000
to the main turbine glands, and 50 pounds per
B.t.u. per hour. H e a t supplied per pound of
hour will be used b y the gland leak-off ejector.
bled steam is the same as to evaporator coils =
Also, to overcome the condensate depression of
979 ]3.t.u. per pound; and bled steam flow to
about 2 degrees in the v a c u u m surge t a n k and
fuel-oil heater and coils = 447,000 + 979 = 457
insure deaeration, about 150 pounds per hour will
pounds per hour.
be used to heat the condensate, leaving a balance
Hence, the total steam bled from the turbine
of 150 pounds per hour available for feed heating
at the third-stage bleeder = A = 765 + 457 =
from this source. Assuming this to be dry satu-
1222 pounds per hour. rated, the heat supplied is as follows :
Heat in 150 pounds of dry saturated steam at
BLED STEA~I~SEcoND STAGE (/3) 15 pounds gage, above 250 degrees, is 141,795
Steam supplied from second-stage bleeder a t B.t.u. per hour.
30 pounds absolute and 312 degrees F., to second- (4) ~3led Steam from ~/Iain Turbine. The quan-
stage feed heater. T e m p e r a t u r e of drains from t i t y of bled steam required from the turbine is
second-stage heater at 30 pounds absolute is 250 not yet known. Let this quantity, in pounds
degrees F. per hour, equal B. The heat per pound of bled
(a) tIeat Required for Feed Heating. T h e steam, above the drain temperature of 250 de-
second-stage feed heater is to raise the feed tem- grees, is (1195.4--218.8), which equals 976.6 B.t.u.
perature to 235 degrees F. The inlet tempera- per pound. Then, equating the total heat re-
ture to the heater equals the first-stage heater quired to the heat released in the heater, we
outlet t e m p e r a t u r e plus the rise through the af- have:
ter and gland seal condenser. In this case, the
first-stage heater feed outlet temperature is 168 de- 63.35E = 51,715 + 628,625 + 141,795 +
grees ; the rise through the after and gland leak-off 976.6/3, o r / 3 = 0.0649E -- 842.
condenser (which m a y be determined from the
approximate feed flow, and the vapor condensed) BLED STEAM--FIRST STAGE (C).
is approximately 4 degrees; the second-stage Steam supplied from first-stage bleeder at S
heater inlet temperature is, hence, 172 degrees pounds absolute and 9$ per cent quality to first-
F. stage feed heater. T e m p e r a t u r e of drains from
Let the total actual evaporation, and the total first-stage heater at S pounds absolute is 18.3 de-
feed, equal E pounds per hour. The B.t.u. re- grees F.
b~
0%
b~
I
I
I I /
/
~ ~" Turbine I III I I ~1
I I Glands ~ - I - - - - - - 1 I I //
|I I
I
I
/
Fuel Oil
I l/8esu:,
', "
~
,
i
~
I
/
gO 'L
iz3~o
-,T~- - - - - -- ~ - - - - - - - -I I
~
!
316 ~ --{:X~l
m.~ ,,,.(~+..o
I I--.0-~-'~'~@-~
?.50 I
I ZOO Lb.J.
I
---,I~
I .
.I.I
. . . . .
I
J.
"g'~---J~"l
T ~ ! CP.To~b~ne \ .
........~ t - - ~ ;~---"' . . . . . . . ,,~ . . . . . . -~ >
/ I FeeaH',eater ~,andlSel ',solb.li !lhbo,b. 133Ztkb. , |150Lb. I \ h
' " ~o ' I OIancl ~ ~s341b. ~ I
' o "~ ~ O~Cll E'~ , a~.a~ C3
I r Surge Tank I
/__~L_,~o'L~ I Cb
I 17z f (--/ ~o8 (- ~ '
! I
~% / ",..-" . ',.5zo~. I
14,sz8 Lb. , 'I I I
~, o'-~n;f' i Heafing~ E~z]He6ting I i - - >
'He~te'r __:..=qb ' ...i - l.i l . 4 Llr .I- - I . ~ izooLb.~o ~ , 19o
O U U L D , ~ - - . ~ - - ~ l ~ LD, ~ I
I aSZih t wroth j------~ i , ~ I I I
~ . . . . \\ Cooler Z
II " "1 _s~ , Do
L~J I Main Aux.
I I Condensate
I 805 Lb.~ llssoLb. 14,528Lb. |I0" ~OOL.b I
Pump
l Condensofe
Pump
I If INin ~ i r
68.73@~.
--~je~,~or
F~q_ I
I
Fuel Oil
Inspection
~I I
II II
II
bonaenser
It oo .
I I
I ~8,75o t.b.
it
Tank ~ ,OTZLb. J I EJ
, , --z~- I
Atmospheric Boosfer Pump
DroinTonk
F I G . 4 . - - H E A T BALANCE DIAGRAM. DESIGN C
t
oh
650Lb.O850 ~t.S44Lb. 38ZOLD.
i
Ex h.(;ond'r. I *~Olan~ I
~150Lb, ~
Pump ~y ~ , I I andAff.C.o-nd.~'- ~eo'i ~,o,,,]nl, ,~+.~*o~e, ,
I I CO
$ urge Tan k I'38~.oLb
L__J ,5o,~.~ II Cb
1~8 ( I I ---~%:. )738zo,~ I
,y/ I It
II14.o57Lb. l C
Ship M!iis~. %~:~ I' '~~ ,'k--." >
Fuel Oil - - - 7 I H eafingJ~__,_l ~ H e ~ f f i n g I I "~ -~ /co~cl'~. I "-,-' o
,zooLr=-%.-l=~o I ', I 19
Healer II 800lb.~_r /~r~SLbl Drain ~ I
"',,, I Cooler I
I ~c~ I I~ I
oo,b., --~J I_~>__1 Do
"1 iI',,300Lb. I L__~_J I' IZOOCb. Main Aux.
I ~O~L~.[', I Condensafe I Condensclfe
I I I
4ain/~ir Pump I Pump
Ejector
Fuel Oil I I I L 034874Lb" ----7 ,I I
Inspecfion I 9o Infer ''
'I II ~3'874Lb"
Tank I I ! Condenser l "ll
,005~. ,~ e3 874t~.t I
, ,-~- '~z /k
Afro ospheric Boosfer Pump
DrainTank
FIG. 5 . - - H E A T BALANEE DIAGRAM. DESIGN D
1200 Lb.G 950 OL489Lb.
I rol,489 I~b. 5oot" Blower5 System Losses
I 44]OLb 385Lb G
Airhea1'erH?',,I ~ IIOOLb.G 600 ~ I r[' - - -- "--~1 740""
I ~ \ ~ I 9x~O~ e65Lb. I
i I 9zs q" II=l I
El 1~ E ['[I I~ " ~ I ' I'llSO bTeam / I~ ~ I 61,489Lb. i ~ L_J
II/\1 c . . . . -~-__~._ I b o l l e r s ~ I#~ IMdke u~ol~ I " T l r l ~ [ n e ~ ',Independent
'~ L _ ~ I I ' Generator
_ i,~.',_:~-I I ]I I I
5168Lb400 Lb.A ~IF I I I
- - ~ I00
- - Lb.A
- - - - J IIII R4H.r.~ion I
- . . . . . LLZiJ '.
?.I5S Lb. 2333 Lb. II I I~ I
--r q ~ II ~eor~ I U:
,~ &, L L ~54 Lb: li I
8-~s.A' I I
C~
>
, I I [[ ~ It I OLO r r II 15712Lb i I-". . . . . . . I. . . . . . . . . .
L -~ - -D- - - - ~ o - / ~ . . . . . . -q~- -, I C~
I i1445 ~ ; I I ~nH R+",~n~ o .... I '. I I IGlands L.PTurbine N
i \
,, I \
G3819
L bl . l L_I I e e d Heater'l Gland Sea, ~UOLDII ~50L6 . . . . . Z154
. . .Lb.. -Ii
o I I I/es.8!9Lb.Ite38mLb E x h . C a n d r : I~loD, d 115,7?Lb I
/ [ Ik-r~-,~__J iZB5 I/ 7Z o n d A f f C o n d . ~ - , ~#eq, I L~o--F]7 IstGtage I 0
I I t j e cjTor '
- ~
L _ _
I~FJl-~ . . . . ,s~s-~ If ~ IFeed Heater ,
1 I 5urge Tank l,
~rd.S1,age ', I I I ~111 Iha63819Lbr~,---~L~41 I[-~-I I , ; ,sOLb. ~ 1144mU~.
Feed Mea1,er I, I ...... )-- ~-~b'~ 9-~~ ~ T I
638 9Lb. .J. ~ M ~ n I:~DH \ ) ~ / / I I ' ii39.6,8~::-[-('~:)-qjt,,,o:b *
uz35: Ilii~ 1 ~P'u'm. . . . " "" I I I
I- k _~ P "< I hm4O,L~ I iF-' I,t~q?~Y~h I/ Au'~.;Cond'r. 0
--7---- 3h~p F - - ~ M~sc "-3 .... b t II 1"83 " - le4~4~$0r
4
Lb. ~- M-a i n /
i. . . . . .
I. .
\t~ s'l
I Heafing~~ea1,in9 18o u , ~1 --
--]]d~--~ .... /Condr I \ /
',"370
1 LD 800 .T ~ ~ r 2%~,.
. . . . Lb.~- '
6 5 Lb. I! I I
I ~.-f::::~: l ! L:~o
Drain I~ ~1 i I ~ ~ I I I o
x I %J I i I
\
\ ClerI7 Y l
~ . . . . . .
1 i I L_~_J L4~_-- O0
I
I [.... I Main Aux.
Fuel Oil I
I Condens~1,e Condenso1,e
Heater I 119.40~b. I10 I200Lb '
I "1 I Main A!ir Pump Pump
570 Lb. I ---~ Ejeci1'or
I I 63819Lb.
I
Fuel Oil I
Inspection I 96 In1,er ---] IiltO0 Lb.
Tank I Condenser, I I
~3819/b.
.I I I I 92
Zoo
Atmospheric Booster P u m p
DrainTank
FIG. 6 . - - H E A T BALANCE DIAGRAM. DESIGN E
t~
266 HEAT BALANCE CALCULATIONS
TABLE 4 . - - A u x I L I A R Y STEAM
Steam
consumption,
pounds
Unit Duty, etc. per hour
Auxiliary generator 220 kilowatts at 15 pounds per kilowatt 3300
Air ejectors 80 pounds air and vapor at 5 pounds per pound mixture 400
Miscellaneous steam pumps Average operation (a) 400
Soot blowers As given above 250
Whistle As given above . 15
Losses As given above 400
Steam heating system Inside temperature = 70 degrees F. ; outside temperature = 0 degrees F. 800
Galley 50 persons at 0.5 pound per person per hour 25
Domestic water heaters 50 persons at 0.75 pound per person per hour 40
(a) Assuming one bilge pump, and one fuel transfer pump, in use three hours per day each.
As the total feed quantity equals E pounds pounds per hour. Hence, if E represents the
per hour, and the B.t.u. required to heat one total actual evaporation, the main turbine throttle
pound of feed from 96 degrees to 168 degrees F. flow is E -- 5630.
equals 72 B.t.u. then the total heat required is
72E. POWER EQUATION
(b) Heat Supplied to Feed Heater and Drain
Cooler. The heat is supplied from three sources: As described above, the unknown total evapora-
(1) Drains from second-stage feed heater; (2) tion is determined b y a single "power equation"
drains from the atmospheric drain tank; (3) containing but one unknown, E. This equation
bled steam from the main turbine. As the drain is now set up, using the actual section water rates
cooler will discharge the drains at a temperature in Table 1, and the bled steam data in T a b l e 2, as
of 110 degrees to the condenser hotwell, only the follows :
heat above liquid at this temperature is utilized. E--5630 . E--6852
This heat is as follows: B.H.P. = 8200 22.79~ -}- ~ -i-
(1) Drains from Second-Stage Heater. These 0.9351E--0010 + 0. 87469E--5770
drains include the following: E v a p o r a t o r coils, 33.073 23. 882
765 pounds per hour; condensed evaporator va-
Solving this, the total evaporation E is found to
por, 665 pounds per hour; condensed auxiliary
be 66,475 pounds per hour.
exhaust, 150 pounds per hour; bled steam con-
With the total evaporation known, the steam
densed in second-stage heater (B), (0.0649E -- 842)
flows in each section of the turbine, the bled steam
pounds per hour; or a total of (0.0649E + 738)
flows and condenser flow m a y all be determined.
pounds per hour. The heat per pound of drains
B y substituting the evaporation E in the power
from 250 degrees to 110 degrees F. = 140.9 B.t.u. ;
equation, the horsepower developed in each sec-
and the total heat = (0.0649E + 738) X 140.9 =
tion of the turbine is found.
(9.144E + 103,985) B.t.u. per hour.
(2) Drains from Atmospheric Drain Tank. The
FUEL CONSUMPTION
atmospheric drain t a n k receives drains from the
fuel-oil inspection tank; the after and gland leak-
In the above, the main turbine and generator
off condenser; and the ship's heating system, gal-
turbines operate on superheated steam, a total of
ley and domestic water heaters, etc. The total
64,145 pounds per hour. The balance of 2330
of these drains is 1622 pounds per hour, and the
pounds per hour is desuperheated steam, from
average t e m p e r a t u r e 200 degrees. The heat per
desuperheating coils in the boiler drums, with
pound of drains from 200 to 110 degrees F. is
desuperheater outlet conditions of 375 pounds
90 B.t.u., and the total heat is 145,980 B.t.u. per
gage pressure and 475 degrees temperature.
hour.
Assuming a boiler efficiency of 88 per cent and
(3) Bled Steam from Main Turbine. T h e
fuel with a heat content of 18,500 B.t.u. per
quantity of bled steam required from the turbine
pound, the total fuel consumption is found to be
is not yet known. Let this quantity, in pounds
4819 pounds per hour, or a rate of 0.602 pound
per hour, equal C. T h e heat per pound of bled
steam above the drain cooler outlet temperature per shaft horsepower.
of 110 degrees is (1118.5 -- 78.0) = 1040.5 B.t.u.
COMPARISON OFTYPICALCASES
per pound.
Then, equating the total heat required to the
heat released in the heater, we have The procedure outlined is, naturally, applicable
to any t y p e of installation, and to any steam con-
72E = (9.144A~E + 103,985) -}- 145,980 -]- ditions desired. The steam conditions assumed
1040.5C, or C -- 0.06041E -- 240. for the example above were selected because of the
prevalence of these conditions in a considerable
GENERATOR LOAD
number of current designs. To afford a com-
parison between the example described and other
The expected generator load is determined b y
t y p e s of installation, several designs have been
detailing the approximate duties of the various
calculated and compared in Table 5. These heat
electric auxiliaries, as given in Table 3.
balances are based on oil-fired watertube boilers
STEAM FLOW and cross-compound, double-reduction geared
turbines of 8000 shaft horsepower.
T h e steam flow to auxiliaries taken from the The purpose of this comparison is not to ad-
boilers is as detailed in Table 4, and equals 5630 vocate a n y particular steam conditions, or type
268 HEAT BALANCE CALCULATIONS
of plant, b u t to indicate i n a general way the used throughout the design period, and during
salient features of each type. Attention is drawn trials and service operation of the actual ship.
to one section of the comparison; the relation be- T h e method here outlined is not necessarily-
tween the total steam rejected to the condensers superior to other methods of calculation which
and the fuel rate. T h e efficiency of the plant m a y be used. I t is believed t h a t its chief m e r i t
is seen to vary, not with the total actual evapo- lies in the fact t h a t it is based on information
ration, but with the heat rejected to the condensers. generally available at the inception of a n y de~
F r o m a thermal standpoint, the cycle which in- sign. The calculations are not particularly elabo-
dicates the greatest a m o u n t of extraction steam, rate or involved, and m a y be m a d e b y anyone
with consequent lowest heat loss to the conden- with a knowledge of the fundamentals of thermo-
ser, is the most efficient cycle. dynamics. T h e effort has been made, in de-
veloping this method, to reduce to a m i n i m u m t h e
SUMMARY
assumptions which m u s t be made. I t is recog-
T h e value of heat balance calculations and the nized t h a t the accuracy of the result depends as
attendant diagrams will increase as the designer much on the correctness of these assumptions as
becomes more familiar with them. Their value on a n y particular method of calculation. N o
lies in the m a n y uses to which tll.ey m a y be put. calculation, however precise it m a y be m a t h e -
T h e y should be regarded as a tool, which m a y be matically, c a n be a n y more correct t h a n the basic:
HEAT BALANCE CALCULATIONS 269
assumptions. Fortunately, they have a rela- signer are important in this regard. In this
tively minor effect on the general accuracy of the field, as in all other phases of engineering, there
result. The judgment and experience of the de- can be no mathematical substitute for experience.
APPENDIX
I I I I
Load - Per C e n t o f Ra~ed P o w e r
9o/5O 0o too I
~ ~ . _.------
I ~0
E:
Q)
"~ 50
LO
t
+o 40 , ~ ~
0
~C
20
10
0
0 I0 ZO :50 40 50 ~0 70 80 90 IO0
c ~ t e d MoJror H o r s e p o w e r
FIG. 7.--EFFICIENCYOF ELECTRIC]~OTORS,FOR DIRECT-CURREN'T~OTORS WITHFIELD CONTROL
270 HEAT BALANCE :CALCULATIONS
IOO
9o
80
a. 50
d
- ..-- "'-A...-.
~ 4o
=
o / I .
L
l O S
IO ZO 30 4O 50. 60 708090100. , "too 300 400 500 O00 700800 I000
Broke Horsepower
FIG. 8.--EFFICIENCY OF AUXILIARY TURBINES
DISCUSSION
MR. J. j. NELIS, Member: This paper presents doubt follow the large land plant where the heat-
in a clear and definite manner data very much re- ing surface, usually known as the boiler, will be-
quired by this industry, now that a number of new come smaller; where the superheater and the heat
shipyards, which have not had time to form a recovery devices will become larger, and the
technical staff are coming into existence. These amount of steam rejected to the condenser will
new shipyards are badly in need of some reliable become smaller. All of these things will be neces-
guidance of this type. The writers of this paper sary as we increase pressures and temperatures in
should be commended not only for the excellence that never-ending search for greater efficiencies.
of their paper but for its timeliness. In some recent high-pressure land plants the boiler
One of its important features is extending the or evaporating surface is less than one-fifth the
heat balance into what will definitely be our future total heat-absorbing surface.
temperatures and pressures. With the improve- The pressures considered in this paper are defi-
ments now being made in the Diesel engine, it is nitely in the range of present standard-design na-
necessary for the steam plant to advance or find tural-circulation boilers. Sometime in the far dis-
itself in the position of the old Scotch boiler and tant future pressures m a y increase to the point
triple engine of a decade ago. I t is good for this where forced-circulation boilers should be seriously
industry to have intense competition between im- considered for marine use. Natural-circulation
proved Diesel and improved steam power. For boilers are in daily use at pressures up to 1S00
large powers, steam will no doubt be used for pounds per square inch.
m a n y generations; in the smaller powers there is A very important feature which also needs con-
an opportunity to check engineering data and fit sideration as we increase the pressures and tem-
into the owner's requirements for his trade the peratures is to keep the marine power plant as
type of power plant best suited, whether it be simple and reliable as possible. The type of
steam or Diesel. This Society should have a simi- operatives we are going to use in our new ships
lar paper giving as fully and clearly the complete have to be trained in the handling of this improved
heat balance of similar size Diesel plants. equipment. If we increase the efficiency of the
An interesting feature that stands out in this plants faster than the mentality of the operatives,
analysis is that, as pressures and temperatures the saving in fuel by the better power plant can
rise, there is a definite field for both types of heat be very quickly lost. This means that we must
recovery apparatus (namely, the economizer and go forward in careful, definite steps. We will
the air heater), especially in the merchant marine probably soon install 600 pounds and $50 degrees
where space is available for the installation of for the average merchant marine power plant. It
these two pieces of heat recovery apparatus. As would seem advisable that sufficient marine power
pressures and temperatures increase, we will no plants at this pressure and temperature be in-
272 HEAT BALANCE CALCULATIONS
stalled and operated for a reasonable period be- A detailed s t u d y of heat balance diagrams and
fore the next step of higher pressures and tem- tables will show where improvements in efficiency
peratures becomes general. can be made, and this is necessary to obtain the
I t is reported t h a t the N a v y is considering highest efficiency, I t is erroneous to assume t h a t
building one high-pressure high-temperature ex- giving attention to these details is unimportant,
perimental marine .plant. I t would be interesting since the total saving b y so doing is usually con-
if some owner of merchant marine equipment built siderable.
an installation leading the way for higher pressures I wish to congratulate the authors on their in-
and temperatures beyond those of 600 pounds and teresting and valuable paper, for which they
850 degrees to get sufficient practical experience should receive the thanks of the Society.
with this t y p e of plant, after which other owners
and designers could more safely install the t y p e
PROFESSOR J. R. Jack, Member: This paper
of higher pressure and temperature .equipment
has great educational value for .young engineers as
which will unquestionably b e c o m e standard
it illustrates a convenient method of applying the
marine practice in the not too distant future.
theoretical principles learned in college to the
actual problems in the designing office. I t is also of
MR. W . . W . SMITH, Vice-President: I t is a
value as giving approximate quantities of steam
pleasure for me to discuss this paper because of
required b y the auxiliaries, which are now so nu-
m y close association with the authors, and be-
merous. T h e requirements of these are a p t to v a r y
cause I know they have made diligent effort to
very considerably and h a v e special influence on
contribute to the Society a valuable scientific
the make-up feed required. For instance, the al-
work. T h e paper is important in t h a t it points
lowance for soot blowers might have to be in-
the way to obtain the highest efficiency b y means
creased several times, if there were a few leaky
of good engineering, and therefore it should be of
rivets in the shell plating, allowing sea water to
especial interest to the Society.
mix with the fuel oil" in the tanks an d producing
During the past ten years, a n u m b e r of ships
h e a v y smoking.
have been built with inefficient machinery. If
Perhaps the worst offender is the steam whistle,
heat balance .diagrams and statements, as de-
which wastes a lot of s t e a m while actually blowing
scribed in the paper, had been prepared, it is prob-
and very often leaks in between the blows. A
able that the machinery would have been much
shipyard whistle of m y acquaintance used to use
more efficient. I t is believed t h a t such diagrams
as much steam as a 100-horsepower compound
and statements should be prepared for new ships,
engine during the t i m e it was actually blowing.
and that they will result in material i m p r o v e m e n t
in efficiency. Feed losses in the turbines themselves are of
course small b u t with the older reciprocating en,
T h e efficiency of a design of machinery depends
gines, some of which had not been too well alined,
on the effieiencies of the various component ele-
these losses could be v e r y serious. In one case
ments. T h e statistical details given in the dia-
where the indicated horsepower did not exceed
grams and statements enable the designer to ap-
2500 the losses were so high t h a t a nominal 40-
praise and control all of these elements so as to
ton evaporator could not keep pace with them.
obtain the best general design. T h e y enable him
These of course are extreme cases, b u t some allow-
to see and comprehend quickly the i m p o r t a n t
ance m u s t be made for practical sea conditions,
essentials involved, without being c o n f u s e d b y
unessential details. which are never as favorable as those visualized
in the designer's office. The comparison of typical
As stated in the paper, the diagrams and state-
cases is exceedingly valuable and points out just
ments are not intended to give the most efficient
how much fuel saving m a y be expected from in-
designs, b u t to illustrate the detail methods of
creased pressures and temperatures. These sav-
making them. T h e y do, however, show t h a t cer-
tain features of design give higher efficiencies than ings m u s t be considered along with the increased
cost of installation and of its consequent unkeep.
Others, as seen from Table 5. I t is i m p o r t a n t to
note that, as pointed out in the paper, the lowest Some economies are worth while striving for,
others m a y be obtained only a t a price which is
fuel consumption results from the lowest heat re-
not economical.
jection to the condenser. The latter, in turn, re-
sults from the highest value of the heat available
in the steam and the m a x i m u m bleeding of the PROFESSOR EVERS BURTNER, Member: T h e
turbine for feed heating. This means t h a t elec- heat balance diagrams and comparison of typical
tric auxiliaries, and three or four stages of feed cases given on page 268 are worthy of study. T h u s
heating are required for the highest efficiency. case A, representing two-stage bleeder heating
HEAT BALANCE CALCULATIONS 275
w i t h electric auxiliaries, has a fuel rate of 0.60 second a p p r o x i m a t i o n , therefore reducing some
p o u n d per shaft horsepower per hour. This is work, which is, of course, desirable. T h e esti-
o n l y 3V, per cent b e t t e r t h a n the 0.62 p o u n d fuel m a t e d fuel b y the new m e t h o d is, however, v e r y
rate of case ]3 where a single-stage feed h e a t e r is n e a r l y the same as e s t i m a t e d b y t h e c o m m o n one,
fitted a n d the feed a n d m a i n circulator p u m p s are exclusive of a n y second a p p r o x i m a t i o n s , the differ-
s t e a m t u r b i n e driven. ence b e i n g o n l y a b o u t I/4 of 1 per c e n t for t h e
As a p a r t of the i n s t r u c t i o n work a t the M a s s a - specific case illustrated in t h e paper.
chusetts I n s t i t u t e of T e c h n o l o g y a n u m b e r of While it is recognized t h a t T a b l e 5 was pre-
h e a t b a l a n c e d i a g r a m s h a v e b e e n calculated. Com- sented p r i m a r i l y to i n d i c a t e t h a t the m e t h o d pro-
p a r i s o n of our c o m p u t e d fuel rates for a two-stage posed applies e q u a l l y well to different designs,
feed-heating s y s t e m h a v i n g electric auxiliaries it is desirable to call a t t e n t i o n to the fact t h a t in
with a single-stage h e a t i n g s y s t e m a n d s t e a m seeking small differences in fuel p e r f o r m a n c e be-
auxiliaries showed an i m p r o v e m e n t of fuel rate of tween different designs it is necessary to e v a l u a t e
some 51/.o per cent for the former a r r a n g e m e n t . these b y a m e t h o d of differences r a t h e r t h a n b y
T h i s difference of 2~/4 per cent in the saving shown overall methods. Otherwise a large p o r t i o n of t h e
b y two-stage feed h e a t i n g a n d electric auxiliaries difference sought m a y be lost.
over t h a t n o t e d in the paper was largely due to To illustrate this point, let us c o m p a r e Design
v a r i a t i o n s in auxiliary s t e a m c o n s u m p t i o n . C with A. Design C has a n a d d i t i o n a l stage of
Personally, I prefer a more logical m e t h o d of feed h e a t i n g a n d the sea service g e n e r a t o r is
finding the m a i n t u r b i n e c o n d i t i o n curve a n d driven b y the m a i n t u r b i n e .
" s e c t i o n a l " m a i n t u r b i n e water rates, even t h o u g h The r e d u c t i o n in oil due to the a t t a c h e d genera-
it m a y be argued t h a t our knowledge of t h e con- tor m a y be e v a l u a t e d t h u s :
dition c u r v e is n o r m a l l y n o t as accurate as is de-
sirable. T h e scheme of c o m p u t i n g the m a i n t u r - Steam sent to main turbine in Design C because of
bine w a t e r rate is ingenious; however, it presup- 6.99 X 240 X 1.:34
generator load 0.95 = 2400 pounds per
poses a close e s t i m a t e of the a u x i l a r y s t e a m con- hour.
s u m p t i o n , which in t u r n is d e p e n d e n t on t h e m a i n Steam sent to generator in Design A = 3300 pounds per
t u r b i n e w a t e r rate. Hence, even with t h e pro- hour.
cedure outlined, I would expect t h a t a p r e l i m i n a r y Reduction in generator steam = 3300 -- 2400 = 900
pounds per hour.
a n d a final solution of m a i n a n d a u x i l a r y s t e a m
Additional saving in steam because of reduced bleeding
rates would b e necessary. requirements will be about 100 pounds per hour.
T h e curves of efficiency ratios of a u x i l a r y s t e a m Total saving in steam due to driving generator by main
t u r b i n e s in t e r m s of the t u r b i n e r e v o l u t i o n s a n d turbine = 1000 pounds per hour.
the shaft horsepower a p p e a r to check r e p o r t e d Converting this into oil per hour = 71 pounds.
values as well as c a n be expected. F o r ranges in This saving in oil amounts to 1.4 per cent over Design A.
r e v o l u t i o n s per m i n u t e b e t w e e n 2000 a n d 6000
a n d for u n i t s of over ,30 shaft horsepower t h e The s a v i n g in oil due to t h e a d d i t i o n a l stage of
curves c a n b e represented b y the expression, feed h e a t i n g m a y be e v a l u a t e d t h u s :