You are on page 1of 1

1.

50

0.10
0.43 0.65 0.43

0.013
BASE
Foundation Z-1 PLATE
See Specification 3.1

0.038
0.43
0.04
Pedestal (P1)
16 Rods #6 (19mm) GROUT
Set of Stirrups

0.04
Rods #3 (13mm) @ 0.25 M

0.70
See Specification 2.1 & 3.1
0.65
1.50

DETAIL No. 1

0.60
SCALE: 1:4
10 Rods # 4 (13mm) @ 0.15M
Both Directions
See Specification 2.1

0.05
0.43

0.05 0.65
PLANT VIEW 0.60

0.10

DETAIL No. 2
Base Plate
Steel Pipe 13mm Thickness
GALVANIZED (A-36)
See Detail QUANTITY: 24 PIECES
See Detail No. 1 No. 2 SCALE: 1:5
U.C.L.

0.65
0.60
+00.300 Pedestal (P1)
0.10

B.W.L.
0.30

+00.00
0.70
DEPTH OF CONCRETE PLATFORM

Compacted Fill RE: Soils Report


VARIABLE ACCORDING TO THE

For Site Prep Requirements And


TERRAIN MINIMUM OF 1.50 M

Backfill
RESISTANCE OF NATURAL

Pedestal (P1)
1.10

16 Rods #6 (19mm)
DETAIL No. 3
0.25

Set of Stirrups
1.55

Rods #3 (10mm) @ 0.25 M DISTRIBUTION OF ANCHORS ON PEDESTAL (P1)


See Specification 2.1 & 3.1 QUANTITY: 3 PEDESTAL'S
SCALE: 1:10

0.40 0.40
0.40

10 Rods # 4 (13mm) @
0.15M Both Directions See
Specification 2.1
0.05

1.- ALL DIMENSIONS AND LEVELS ARE IN METERS


2.- ALL LEVELS OF SLIDES SUPPORT ARE
SECTION "1-1" Compacted Fill RE: Soils REFERENCED AT +00.000
Concrete Template 3.- SEE DRAWINGS C264702-OC-01
Report For Site Prep
See Specification LOCATION OF FOUNDATIONS FOR SLIDES.
Requirements And Backfill
No. 3.2. 4.- LEVELS OF AREA REFERRED TO FINISHED
FLOOR LEVEL +00.000

DETAILS: FOUNDATIONS Z1 AND PEDESTAL (P1)


FOUNDATIONS No. I, II, III F.F.L. FINISH FLOOR LEVEL
F.P.L. FINISH PERIMETRAL LEVEL
SCALE: 1:15 U.C.L. UPPER COLUMN LEVEL
S.S.L. STARTING SLIDE LEVEL
Z1 FOUNDATION No.1
P1 PEDESTAL No.1
STEEL REINFORCEMENT IN FOUNDATION
COLUMN DIMENSIONS RODS A RODS B SEPARATION SPECIFICATIONS:
Z1 1.50 x 1.50 x 0.40 @ 0.15 MTS 1.1.- STRUCTURAL STEEL A-36.
2.1.- REINFORCED STEEL AR-42:
f'y=4200 kg/cm2.

CONCRETE PEDESTAL CONTENT TABLE


3.3.- MINIMUM PERCENTAGE OF STEEL IN
PEDESTAL c d REINFORCING STEEL STIRRUPS ANCHOR BOLTS FOUNDATION BY REGULATION- ACI 318-95
P1 0.65 0.65

IMPORTANT NOTICE:
ITS AN OBLIGATION FOR THE GENERAL
CONTRACTOR TO CHECK OUT ALL DIMENSIONS
AND LEVELS IN THECONSTRUCTION SITE, BEFORE
ANY JOB CAN BE STARTED OR DONE, UNDER A
CIVIL ENGINEER OR ARCHITECT SUPERVISION.
ALSO THE DEPTH IN THE PLUVIAL DRAINAGE
PIPES TO GIVE THE REAL SLOPE IN THE
HYDRAULIC PIPELINES BY GRAVITY.
ANY CHANGES OR MODIFICATIONS TO THE
HYDRAULIC PROYECT, WILL BE SUBJECT TO
FURTHER ANALYSIS IN MATERIAL LIST AND
WATER FEEDING.

COMPANY CONFIDENTIAL THIS DRAWING IS CONFIDENTIAL AND THE PROPERTY OF THE WATERSLIDES DE MEXICO S.A. DE .C.V. COMPANY AND MAY NOT BE REPRODUCED OR DISTRIBUTED WITHOUT WRITTEN PERMISSION FROM THE OWNER AND MUST BE RETURNED UPON REQUEST