In this document Im going to explain inter-Company Stock transport Order with SD Delivery,
Billing & Logistics Invoice verification.
Prerequisites:
1. Knowledge of MM & SD
2. Two organization structures: one for purchasing and another for sales
Purchasing: Company Code:8888, Plant: 8881, Sto. Loc: 0002, Purchase Organization: 8881,
Sales: Company Code:6666, Delivering Plant: 6661, Sto. Loc: 0001, Sales Area: 6666, 66, 66,
Shipping Point 6666.
In Purchasing Data, Goto Menu Bar, Extras > & click on Additional Purchasing Data. Here
Maintain the supplying plant(6661) so that it is linked to the vendor master.
Note: A Plant can only be assigned to one vendor number. So we have to extend the same
vendor number to different Pur.Org if required.
Note: If You are not able to see tax condition types or not maintaining any tax indicators then it
is not possible to Create a delivery against STO. Same applies to Customer Master in Step2.
In Sales Org2 View, Maintain Item category Group Ex. Norm (Standard Item)
.
Note: The Item Category group maintained here is preferred over general item category group
and used to determine Item Category in Delivery Ex. NLC(For Inter Company) NLN(For
Intra-Company).
SPRO > Materials Management > Purchasing > Purchase Order > Setup Stock Transport Order
For Supplying Plant(6661), assign Sales Area(6666,66,66) as shown below.
For Receiving Plant(8881), assign Customer Number(100216) Created in Step2.
Step6. If required Create a Checking Rule by entering a two digit code & Description. Ex. B
SD Delivery(Standard)
Step7. Define Checking rule Created in Step6 in combination with Availability Check
Group(01) assigned in material master Step3. Here select the stocks, receipts & requirements as
per requirement.
Step8. Assign Delivery type & Checking rule
Here Assign Delivery type(NLCC) & Checking rule(B) to the Purchase order Document
type(NB) & Supplying plant(6661) Combination as shown below.
Step9. Assign Document type, One Step Procedure & Under delivery Tolerance.
Here for Supplying & Receiving Plant(6661 & 8881 respectively) Combination Assign PO
Document Type(NB).
Select One step Check box to post the Goods receipt while doing PGI itself. Otherwise Goods
Receipt have to be carried out in another step.
If You Select tolerance limits check box, Then SAP closes the STO by marking final delivery
Check box, if delivered Quantity is within the under delivery tolerance limits maintained in
delivery tab of PO. It depends on Partial deliveries allowed or not. Then the remaining quantity
will not be shown as open in requirements.
Step10. Define Shipping Point Determination in below path
SPRO > Logistics Execution > Shipping > Basic Shipping Function > Shipping point
Determination > Assign Shipping Points.
Here assign Shipping Point(6666) for the Combination of Shipping Condition(01) (customer
master step2), Loading Group(0001) (material master step3) & Supplying Plant(6661).
Here assign Item Category (NLC Replenishment delivery inter Company) for the combination
of Delivery Document type (NLCC), Item Category Group (NORM), Usage V (Purchase order)
& Higher level item category group ( -blank) as shown below.
Assign Sales pricing procedure ICAA01 to the combination of Sales Area(6666,66,66),
Document pricing grp I (for billing doument type IV) & Costomer pricing grp 1
Testing:
Make sure You have sufficient stock in issuing storage location (0001) of supplying plant
Step1. Create Purchase Order in Transaction ME21N with Document type NB, Vendor(2122),
Material(2116), PurOrg(8881) Pur Grp(001), Company Code(8888), Receiving Plant(8881).
Note: If you are using one step procedure the enter the receiving storage location(0002).
Here Observe the shipping tab with the above details as shown. Here first of all SAP checks for
any plant assigned in vendor Master. if not assigned then it will be a standard PO
Note: You Can process inter Company STO by using PO document type UB with Clearing
accounts, without delivery, w/o billing, w/o invoice(Mov.types 351 &101). If You are using
document type NB then it is only possible with delivery & trigger point is vendor master.
make sure you have proper sales tax setup in SD > Basic Functions > Taxes.. Customer &
Material Master is assigned to tax indicators. Create condition record for output tax condition
type in Trasaction VK11. Ex. MWST output tax
In Transaction VK11 Create Condition Record for Condition type PR00 with the sales price if
required.
Note: To adopt price from purchasing in to billing create a condition type with same name as
PB00. In copy control enter reference as application purchasing & condition type PB00. Now
assign this condition type in procedure ICAA01 after step of condition type IV01. Now the PO
price is adopted in to billing.
Step2. Generate Outbound delivery against purchase order in Transaction VL10G or VL10D
Here make sure that delivery date is in between the dates entered. & enter the shipping point
triggered in PO shipping tab. Then Execute.
Then Select the Purchase order line item & click on back ground.
Note: If you are able to see an extra line item with status green proceed to next step or else click
on log button as shown above.
Now click on line item & click on notes. now you will see some error messages & solve them.
Step3. Select the Line item & Click on Log Icon. Now click on documents & note down the
outbound delivery document number.
Go to Transaction VL02N. Enter the outbound delivery document number & Click enter. Here in
picking tab enter the issuing storage location & picked Quantity.
Check the Delivery item Category NLC. In Goods Movement tab observe the movement type
643( two step). In item Conditions Tab Observe conditions as shown below.
If You are not able to process PGI, then check WM is activated in storage location or if one step
procedure check PO whether receiving storage location entered or not.
Check The Accounting Document where stock account from BSX is credited & Cogs Account
from GBB-VAX is debited with the price as per supplying plant material master
Step4. In Transaction VF01 Create billing document with reference to outbound delivery.
Make Sure Account determination has been done and Save the billing document. Observe the
accounting document. Where Customer account is debited with the sum of revenues(credited) &
Tax(credited).
Step5. In Transaction MIGO do Goods receipt wrt Outbound delivery. Enter the receiving
storage location & post the goods receipt.
Check the accounting document. Whre stock account from BSX is debited & GR/IR account
from WRX is Credited with the price in PO.
Step6. In transaction MIRO carryout Logistics Invoice verification in receiving company
code(8888).
Post the invoice & observe the accounting document. Where the vendor account is credited with
the sum of amount entered in PO to GR/IR A/c(debited) & Input tax account(debited)
NAVICUTS (Check Points for Error Messages):-
1. Not possible to determine shipping point for item 00010 Message no. 06855
2. There is no item category available in item category determination in the delivery (table
T184L) for the following entries: NLCC NORM V
4. No sales and distribution data maintained for material & Message no. 06854
Check Step3.
5. No delivery type defined for supplying plant 6661 and document type NB Message no. 06694
Check Step8
6. Please maintain sales org./division/distr. channel in supplying plant 6661 Message no. 06846
Check Step5
Check Step5
8. Not possible to determine shipping data for material & Message no.06280
This Error Message will not come in inter company stock transport orders & Will only come in
Intra company STO with Delivery & W/o Billing