You are on page 1of 22

National Highways Authority of India Request for Proposal Bid Documents

Schedule-H
(See Clauses 10.1.4 and 19.3)

Contract Price Weightages

1.1 The Contract Price for this Agreement is Rs (.)


1.2 Proportions of the Contract Price for different stages of Construction of the Project Highway
shall be as specified below:

Item Weightage in Stage for Payment Percentage


Percentage to weightage
the
Contract Price
1 2 3 4
Road works 40% A- Widening and strengthening of
including existing road
culverts,
widening and (1) Earthwork up to top of the sub- 0.00%
repair of grade
culverts. (2) Sub-Base Course 0.00%
(3) Non Bituminous Base Course 0.00%
(4) Bituminous Base Course 0.00%
(5) Wearing Coat 0.00%
(6) Widening and repair of culverts 0.00%

B.1- Reconstruction/ New 8 lane


realignment/ bypass (Flexible
pavement)

(1) Earthwork up to top of the sub-


grade 0.00%
(2) Sub Base Course 0.00%
(3) Non Bituminous Base Course 0.00%
(4) Bituminous Base Course 0.00%
(5) Wearing Coat 0.00%
B.2- Reconstruction/ New 8 lane
realignment/ bypass (Rigid
Pavement)
(1) Earthwork up to top of the sub-
grade 30.74%
(2) Sub Base Course 5.69%
(3) Dry Lean Concrete (DLC) Course 8.76%
(4) Pavement Quality Control (PQC) 46.50%
Course
C.1- Reconstruction/ New service
road (Flexible pavement)

(1) Earthwork up to top of the sub-


grade 0.05%
(2) Sub Base Course 0.13%
(3) Non-Bituminous Base Course 0.17%
(4) Bituminous Base Course 0.17%
(5) Wearing Coat 0.12%

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-1
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Item Weightage in Stage for Payment Percentage
Percentage to weightage
the
Contract Price
1 2 3 4

C.2- Reconstruction/ New service


road (Rigid pavement)
(1) Earthwork up to top of the sub-
grade 0.00%
(2) Sub Base Course 0.00%
(3) Dry Lean Concrete (DLC) Course 0.00%
(4) Pavement Quality Control (PQC) 0.00%
Course

D- Re-construction and New


culverts on existing road,
realignments, bypasses:

Culverts (length < 6 m) 7.67%

Minor Bridges/ 20% A.1- Widening and Repair of Minor


Underpasses/ Bridges (length > 6 m and < 60 m)
Overpasses
Minor Bridges 0.00%

A.2- New Minor bridges (length > 6


m and < 60 m)

(1) Foundation + Sub- Structure: On


completion of the foundation work
including foundations for wing and 31.28%
return walls, abutments, piers up to the
abutment/ pier cap.

(2) Super- structure: On completion


of the super- structure in all respects
including wearing coat, bearings,
expansion joints, hand rails, crash 24.52%
barriers, road signs and markings, tests
on completion etc. complete in all
respect.
(3) Approaches: On completion of
approaches including Retaining walls,
stone pitching, protection works 3.27%
complete in all respect and fit for use.
(4) Guide Bunds and River Training
Works:
On completion of Guide Bunds and
river Training Works complete in all 0.00%
respects

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-2
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Item Weightage in Stage for Payment Percentage
Percentage to weightage
the
Contract Price
1 2 3 4
B.1- Widening and Repair of
underpasses/ overpasses

Underpasses/ Overpasses 0.00%


B.2- New underpasses/ Overpasses

(1) Foundation + Sub- Structure: On


completion of the foundation work
including foundations for wing and 11.89%
return walls, abutments, piers up to the
abutment/ pier cap.

(2) Super- structure: On completion


of the super- structure in all respects
including wearing coat, bearings,
expansion joints, hand rails, crash 23.21%
barriers, road signs and markings, tests
on completion etc. complete in all
respect.

Wearing Coat a) in case of Overpass-


wearing coat including expansion
joints complete in all respects as
specified and (b) in case of underpass-
rigid pavement including drainage
facility complete in all respects as
specified.
(3) Approaches: On completion of
approaches including Retaining walls/
Reinforced earth walls, stone pitching, 5.83%
protection works complete in all
respect and fit for use.

Major Bridge 23% A.1- Widening and repairs of Major


(length > 60 m) Bridges
works and ROB/
RUB/ elevated (1) Foundation 0.00%
sections/ (2) Sub-structure 0.00%
flyovers (3) Super- structure 0.00%
including
(including bearings)
viaducts, if any
(4) Wearing Coat including expansion 0.00%
joints
(5) Miscellaneous Items like hand 0.00%
rails, crash barriers, road markings etc.
(6) Wing walls/ return walls 0.00%
(7) Guide Bunds, River Training 0.00%
works etc.
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-3
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Item Weightage in Stage for Payment Percentage
Percentage to weightage
the
Contract Price
1 2 3 4
(8) Approaches (including Retaining 0.00%
walls, stone pitching and protection
works)
A.2- New Major Bridges
(1) Foundation 3.40%
(2) Sub-structure 1.05%
(3) Super- structure
1.96%
(including bearings)
(4) Wearing Coat including expansion 0.14%
joints
(5) Miscellaneous Items like hand 0.11%
rails, crash barriers, road markings etc.
(6) Wing walls/ return walls 0.00%
(7) Guide Bunds, River Training 0.00%
works etc.
(8) Approaches (including Retaining 0.24%
walls, stone pitching and protection
works)
B.1- Widening and repair of
(a) ROB

(b) RUB
(1) Foundation
0.00%
(2) Sub-structure 0.00%
(3) Super- structure 0.00%
(including bearings)
(4) Wearing Coat: (a) in case of ROB-
wearing coat including expansion 0.00%
joints complete in all respects as
specified and (b) in case of RUB- rigid
pavement under RUB including
drainage facility complete in all
respects as specified.
(5) Miscellaneous Items like hand 0.00%
rails, crash barriers, road markings etc.
(6) Wing walls/ return walls 0.00%
(7) Approaches (including Retaining
0.00%
walls, stone pitching and protection
works)
B.2- New ROB/ RUB
(a) ROB

(b) RUB
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-4
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Item Weightage in Stage for Payment Percentage
Percentage to weightage
the
Contract Price
1 2 3 4
(1) Foundation
16.24%
(2) Sub-structure 6.03%
(3) Super- structure 28.56%
(including bearings)
(4) Wearing Coat: (a) in case of ROB-
wearing coat including expansion 0.87%
joints complete in all respects as
specified and (b) in case of RUB- rigid
pavement under RUB including
drainage facility complete in all
respects as specified
(5) Miscellaneous Items like hand
0.84%
rails, crash barriers, road markings etc.
(6) Wing walls/ return walls 0.00%
(7) Approaches (including Retaining
walls/Reinforced Earth walls, stone 7.04%
pitching and protection works)

C.1- Widening and repair of


Elevated Section/ Flyovers/ Grade
Separators
0.00%
(1) Foundation
0.00%
(2) Sub-structure
(3) Super- structure 0.00%
(including bearings)
(4) Wearing Coat including expansion 0.00%
joints.
(5) Miscellaneous Items like hand 0.00%
rails, crash barriers, road markings etc.
(6) Wing walls/ return walls 0.00%
0.00%
(7) Approaches (including Retaining
walls/ Reinforced earth wall, stone
pitching and protection works)
C.2(a)- New Elevated Section/
Flyovers/ Grade Separators
0.00%
(1) Foundation
0.00%
(2) Sub-structure
(3) Super- structure 0.00%
(including bearings)
(4) Wearing Coat including expansion 0.00%
joints.
(5) Miscellaneous Items like hand 0.00%
rails, crash barriers, road markings etc.

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-5
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Item Weightage in Stage for Payment Percentage
Percentage to weightage
the
Contract Price
1 2 3 4

(6) Wing walls/ return walls


0.00%
(7) Approaches (including Retaining
0.00%
walls/ Reinforced earth wall, stone
pitching and protection works)
C.2 (b)Interchange
(aa) Structures
(1) Foundation 10.28%
3.25%
(2) Sub-structure
(3) Super- structure 6.32%
(including bearings)
(4) Wearing Coat including expansion 0.29%
joints.
(5) Miscellaneous Items like hand 0.31%
rails, crash barriers, road markings etc.
(6) Wing walls/ return walls 0.00%
(7) Approaches (including
0.52%
Retaining walls/ Reinforced earth
wall, stone pitching and protection
works)

(bb) Loops & Ramp


(1) Earthwork up to top of the sub- 4.43%
grade of Loops/Ramps
(2) Sub Base Course of Loops/Ramps 0.84%
(3) Dry Lean Concrete (DLC) Course 1.13%
of Loops/Ramps
(4) Pavement Quality Control (PQC) 6.15%
Course of Loops/Ramps
Other Works 17% (i) Toll Plaza 6.58%
(ii) Road side drains 16.73%
(iii) Road signs, markings, km 24.65%
stones, safety devices

(iv) Project facilities

(a) Bus Bays 0.00%


(b) Truck lay-byes 0.00%
(c) Rest areas 21.04%
(d) Others (Junctions, 19.32%
Gantry, Lighting,
Utility Duct)
(v) Road side plantation 5.87%

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-6
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Item Weightage in Stage for Payment Percentage
Percentage to weightage
the
Contract Price
1 2 3 4
(vi) Protection works other than 5.27%
approaches to the bridges,
elevated sections/
flyovers/ grade separators
and ROBs/ RUBs.

(vii) Safety and traffic 0.54%


management during
construction.

1.3 Procedure of estimating the value of work done.


1.3.1 Road works.
Procedure for estimating the value of road work done shall be as follows:

Table 1.3.1
Stage of Payment Percentage- Payment Procedure
weightage

A-Widening and strengthening of Unit of measurement is linear length.


existing road Payment of each stage shall be made
on pro rata basis on completion of a
(1) Earthwork up to top of the sub- 0.00% stage in a length of not less than 10
grade (ten) percent of the total length.
(2) Sub-Base Course 0.00%

(3) Non Bituminous Base Course 0.00%

(4) Bituminous Base Course 0.00%

(5) Wearing Coat 0.00%

(6) Widening and repair of culverts 0.00% Cost of completed culverts shall be
determined on pro rata basis with
respect to the total number of
culverts. The payment shall be made
on the completion of atleast five
culverts.
B.1- Reconstruction/ New 8-lane Unit of measurement is linear length.
realignment/ bypass Payment of each stage shall be made
on pro rata basis on completion of a
(Flexible pavement) stage in full length or 5 (five) km
length, whichever is less.
(1) Earthwork up to top of the 0.00%
sub-grade

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-7
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of Payment Percentage- Payment Procedure
weightage

(2) Sub Base Course 0.00%

(3) Non Bituminous Course 0.00%

(4) Bituminous Base Course 0.00%

(5) Wearing Coat 0.00%

B.2- Reconstruction/ New 8- lane


realignment/ bypass

(Rigid pavement)

(1) Earthwork up to top of the


sub-grade 30.74%
Unit of measurement is linear length.
(2) Sub Base Course 5.69% Payment of each stage shall be made
on pro rata basis on completion of a
stage in full length or 1 (One) km
(3) Dry Lean Concrete (DLC) 8.76% length, whichever is less.
Course

(4) Pavement Quality Control 46.50%


(PQC) Course

C.1- Reconstruction/ New service


road (Flexible pavement)
Unit of measurement is linear length.
(1) Earthwork up to top of the 0.05%
Payment of each stage shall be made
sub-grade
on pro rata basis on completion of a
(2) Sub Base Course 0.13%
stage in full length or 1 (One) km
(3) Non- Bituminous Course 0.17%
length, whichever is less.
(4) Bituminous Base Course 0.17%
(5) Wearing Coat 0.12%

C.2- Reconstruction/ New service


road

(Rigid pavement)
Unit of measurement is linear length.
(1) Earthwork up to top of the Payment of each stage shall be made
sub-grade 0.00% on pro rata basis on completion of a
stage in full length or 5 (five) km
(2) Sub Base Course 0.00% length, whichever is less.

(3) Dry Lean Concrete (DLC) 0.00%


Course

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-8
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of Payment Percentage- Payment Procedure
weightage

(4) Pavement Quality Control 0.00%


(PQC) Course
D- Re-construction and New Cost of each culvert shall be
culverts on existing road, determined on pro rata basis with
realignments, bypasses: respect to the total number of
culverts. Payment shall be made on
(1) Culverts (length < 6m) 7.67% the completion of at least five
culverts.
@ . For example, if the total length of bituminous work to be done is 100 km, the cost per km of
bituminous work shall be determined as follows:

Cost per km = P x weightage for road work x weightage for bituminous work x (1/L)

Where P = Contract Price

L = Total length in km

Similarly, the rates per km for other stages shall be worked out accordingly.
Note: The length affected due to law and order problems or litigation during execution due to which the
Contractor is unable to execute the work, may be deducted from the total project length for
payment purposes. The total length calculated here is only for payment purposes and will not
affect and referred in other clauses of the Contract Agreement.
1.3.2 Minor Bridges and Underpasses/ Overpasses.

Procedure for estimating the value of Minor bridge and Underpasses/ Overpasses shall be as stated
in table 1.3.2:
Table 1.3.2
Stage of Payment Weightage Payment Procedure
A.1 - Widening and repairs of Cost of each Minor Bridge shall be
Minor Bridges determined on pro-rata basis with
0.00% respect to the total linear length of
(length > 6m and < 60m) the minor bridges. Payment shall be
made on the completion of widening
and repair works of a minor bridge.
A.2- New minor bridges (i) Foundation + SubStructure:
Cost of each Minor Bridge shall be
(i) Foundation + Sub-Structure: On determined on pro-rata basis with
completion of the foundation respect to the total linear length
work including foundations for (m) of the minor bridges.
wing and return walls, abutments, 31.28% Payment against foundation + sub-
piers up to the abutment/ pier cap. structure shall be made on pro-rata
basis on completion of a stage i.e.
not less than 25% of the scope of
foundation + sub-structure of each
bridge subject to completion of at
least two foundations along with
sub-structure up to abutment/ pier
cap level of each bridge.
In case where load testing is
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-9
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of Payment Weightage Payment Procedure
required for foundation, the trigger
of first payment shall include load
testing also where specified.
(ii) Super-structure: On completion (ii) Super-structure:
of the super structure in all Payment shall be made on pro-rata
respects including wearing coat, basis on completion of a stage i.e.
bearings, expansion joints, hand completion of super-structure of at
rails, crash barriers, road signs 24.52% least one span in all respects as
and markings, tests on specified in the column of Stage
completion etc. complete in all of Payment in this sub-clause.
respect.

(iii) Approaches: On 3.27% (iii) Approaches: Payment shall


completion of approaches be made on pro-rata basis on
including Retaining walls, completion of a stage i.e.
stone pitching, protection completion of approaches in all
works complete in all respects as specified in the column
respects & fit for use. of Stage of Payment in this sub-
clause.

(iv) Guide Bunds and River 0.00% (iv) Guide Bunds and River
Training Works: On completion of Training Works: Payment shall
guide Bunds and river Training Works be made on pro-rata basis on
complete in all respect. completion of a stage i.e.
completion of Guide Bunds and
River training Works in all
respects as specified.

B.1- Widening and repairs of 0.00% Cost of each underpass/ overpass


underpasses/ overpasses shall be determined on pro-rata basis
with respect to the total linear length
of the underpasses/ overpasses.
Payment shall be made on the
completion of widening and repair
works of an underpass/ overpass.

B.2- New Underpasses/ Overpasses: (i) Foundation + Sub + Structure:


Cost of each Underpass/ Overpass
(i) Foundation + Sub-Structure: On shall be determined on pro rata basis
completion of the foundation work 11.89% with respect to the total linear length
including foundations for wing and (m) of the Underpasses/ Overpasses.
return walls, abutments, piers up to the Payment against foundation + sub-
abutment/ pier cap. structure shall be made on pro-rata
basis on completion of a stage i.e.
not less than 25% of the scope of
foundation + sub-structure of each
Underpass/Overpass subject to
completion of at least two
foundations along with sub-structure
up to abutment/ pier cap level each
Underpass/overpass.
In case where load testing is
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 10
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of Payment Weightage Payment Procedure
required for foundation, the trigger
of first payment shall include load
testing also where specified.

(ii) Super Structure :


(ii) Super Structure: On completion
of the super structure in all respects Payment shall be made on pro-rata
including wearing coat, bearings, 23.21% basis on completion of a stage i.e.
expansion joints, hand rails, crash completion of Super-structure of at
barriers, road signs & markings, tests least one span in all respects as
on completion etc. complete in all specified in the column of Stage of
respect. Payment in this sub-clause.

Wearing Coat (a) in case of Overpass


wearing coat including expansion
joints complete in all respects as
specified and (b) in case of Underpass-
rigid pavement including drainage
facility complete in all respects as
specified.

(iii) Approaches: Payment shall be


(iii) Approaches: On completion of made on pro-rata basis on
approaches including Retaining 5.83% completion of a stage i.e. completion
walls/Reinforced Earth walls, stone of approaches in all respect as
pitching, protection works complete in specified.
all respects & fit for use.

1.3.3 Major Bridge works, ROB/ RUB and Structures.

Procedure for estimating the value of Major Bridge works, ROB / RUB and structures shall be as
stated in table 1.3.3:

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 11
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Table 1.3.3
Stage of payment Weightage Payment procedure

A.1- Widening and repairs of


Major Bridges

(i) Foundation 0.00% (i) Foundation: Cost of each Major


Bridge shall be determined on pro
rata basis with respect to the total
linear length (m) of the Major
Bridge. Payment against foundation
shall be made on pro-rata basis on
completion of a stage i.e. not less
than 25% of the scope of foundation
of the major Bridge subject to
completion of at least two
foundations of the major Bridge.

In case where load testing is


required for foundation, the trigger
of first payment shall include load
testing also where specified.

(ii) Sub-structure 0.00% (ii) Sub-Structure: Payment against


Sub-structure shall be made on pro-
rata basis on completion of a stage
i.e. not less than 25% of the scope of
sub-structure of the major bridge
subject to completion of at least two
sub-structures of abutments/ piers up
to abutment/ pier cap level of the
major bridge.

(iii) Super-structure (including 0.00% (iii) Super-structure: Payment shall


bearings) be made on pro-rata basis on
completion of a stage i.e. completion
of super structure including bearings
of at least one span in all respects as
specified.

(iv) Wearing Coat including 0.00% (iv) Wearing Coat: Payment shall
expansion joints be made on completion of wearing
coat including expansion joints
complete in all respects as specified.

(v) Miscellaneous Items like hand (v) Miscellaneous: Payment shall


rails, crash barriers, road markings 0.00% be made on completion of all
etc. miscellaneous works like hand rails,
crash barriers, road markings etc.
complete in all respects as specified.

(vi) Wing walls/ return walls 0.00% (vi) Wing walls/ return walls:
Payment shall be made on

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 12
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure

completion of all wing walls/ return


walls complete in all respects as
specified.

(vii) Guide Bunds, River Training (vii) Guide Bunds, River


works etc. 0.00% Training works: Payment shall be
made on completion of all guide
bunds/ river training works etc.
complete in all respects as specified.

(viii) Approaches (including (viii) Approaches: Payment shall be


Retaining walls, stone pitching and 0.00% made on completion of both
protection works) approaches including stone pitching,
protection works, etc. complete in
all respects as specified.

A.2- New Major Bridges

(i) Foundation: Cost of each Major


(i) Foundation 3.40% Bridge shall be determined on pro
rata basis with respect to the total
linear length (m) of the Major
Bridge. Payment against foundation
shall be made on pro-rata basis on
completion of a stage i.e. not less
than 25% of the scope of foundation
of the major Bridge subject to
completion of at least two
foundations of the major Bridge.

In case where load testing is


required for foundation, the trigger
of first payment shall include load
testing also where specified.

(ii) Sub-structure 1.05% (ii) Sub-Structure: Payment against


Sub-structure shall be made on pro-
rata basis on completion of a stage
i.e. not less than 25% of the scope of
sub-structure of the major bridge
subject to completion of at least two
sub-structures of abutments/ piers up
to abutment/ pier cap level of the
major bridge.

(iii) Super-structure (including (iii) Super-structure: Payment shall


bearings) 1.96% be made on pro-rata basis on
completion of a stage i.e. completion
of super-structure including bearings
of at least one span in all respects as
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 13
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure

specified.

(iv) Wearing Coat including 0.14% (iv) Wearing Coat: Payment shall
expansion joints be made on completion of wearing
coat including expansion joints
complete in all respects as specified.

(v) Miscellaneous Items like hand (v) Miscellaneous: Payment shall


rails, crash barriers, road markings 0.11% be made on completion of all
etc. miscellaneous works like hand rails,
crash barriers, road markings etc.
complete in all respects as specified.

(vi) Wing walls/ return walls 0.00% (vi) Wing walls/ return walls:
Payment shall be made on
completion of all wing walls/ return
walls complete in all respects as
specified.

(vii) Guide Bunds, River Training (vii) Guide Bunds, River


works etc. 0.00% Training works: Payment shall be
made on completion of all guide
bunds/ river training works etc.
complete in all respects as specified.

(viii) Approaches (including (viii) Approaches: Payment shall be


Retaining walls, stone pitching and 0.24% made on completion of both
protection works) approaches including stone pitching,
protection works, etc. complete in
all respects as specified.
B.1- Widening and repairs of
(a) ROB
(b) RUB

(i) Foundation (i) Foundation: Cost of each ROB/


0.00% RUB shall be determined on pro rata
basis with respect to the total linear
length (m) of the ROBs/ RUBs.
Payment against foundation shall be
made on pro-rata basis on
completion of a stage i.e. not less
than 25% of the scope of foundation
of the ROB/ RUB subject to
completion of at least two
foundations of the ROB/ RUB.

In case where load testing is


required for foundation, the trigger
of first payment shall include load
testing also where specified.

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 14
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure

(ii) Sub-structure 0.00% (ii) Sub-Structure: Payment against


Sub-structure shall be made on pro-
rata basis on completion of a stage
i.e. not less than 25% of the scope of
sub-structure of the ROB/ RUB
subject to completion of at least two
sub-structures of abutments/ piers up
to abutment/ pier cap level of the
ROB/ RUB.

(iii) Super-structure (including (iii) Super-structure: Payment shall


bearings) 0.00% be made on pro-rata basis on
completion of a stage i.e. completion
of super-structure including bearings
of at least one span in all respects as
specified.

(iv) Wearing Coat including 0.00% (iv) Wearing Coat: Payment shall
expansion joints in case of ROB. In be made on completion of (a) in case
case of RUB, rigid pavement under of ROB- wearing coat including
RUB including drainage facility as expansion joints complete in all
specified. respects as specified and (b) in case
of RUB- rigid pavement under RUB
including drainage facility complete
in all respects as specified.
(v) Miscellaneous Items like hand
0.00% (v) Miscellaneous: Payment shall
rails, crash barriers, road markings
be made on completion of all
etc.
miscellaneous works like hand rails,
crash barriers, road markings etc.
complete in all respects as specified.

(vi) Wing walls/ return walls (vi) Wing walls/ return walls:
0.00% Payment shall be made on
completion of all wing walls/ return
walls complete in all respects as
specified.

(vii) Approaches: Payment shall be


(vii) Approaches (including
0.00% made on completion of both
Retaining walls, stone pitching approaches including stone pitching,
and protection works) protection works, etc. complete in
all respects as specified.

B.2- New
(a) ROB
(b) RUB

(i) Foundation 16.24% (i) Foundation: Cost of each ROB/


RUB shall be determined on pro rata

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 15
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure

basis with respect to the total linear


length (m) of the ROBs/ RUBs.
Payment against foundation shall be
made on pro-rata basis on
completion of a stage i.e. not less
than 25% of the scope of foundation
of the ROB/ RUB subject to
completion of at least two
foundations of the ROB/ RUB.

In case where load testing is


required for foundation, the trigger
of first payment shall include load
testing also where specified.

(ii) Sub-structure 6.03% (ii) Sub-Structure: Payment against


Sub-structure shall be made on pro-
rata basis on completion of a stage
i.e. not less than 25% of the scope of
sub-structure of the ROB/ RUB
subject to completion of at least two
sub-structures of abutments/ piers up
to abutment/ pier cap level of the
ROB/ RUB.

(iii) Super-structure (including 28.56% (iii) Super-structure: Payment shall


bearings) be made on pro-rata basis on
completion of a stage i.e. completion
of super-structure including bearings
of at least one span in all respects as
specified.

(iv) Wearing Coat including (iv) Wearing Coat: Payment shall


expansion joints in case of ROB. In 0.87% be made on completion of (a) in case
case of RUB, rigid pavement under of ROB- wearing coat including
RUB including drainage facility as expansion joints complete in all
specified. respects as specified and (b) in case
of RUB- rigid pavement under RUB
including drainage facility complete
in all respects as specified.
(v) Miscellaneous Items like hand
0.84% (v) Miscellaneous: Payment shall
rails, crash barriers, road markings
etc. be made on completion of all
miscellaneous works like hand rails,
crash barriers, road markings etc.
complete in all respects as specified.
(vi) Wing walls/ return walls
0.00% (vi) Wing walls/ return walls:
Payment shall be made on
completion of all wing walls/ return
walls complete in all respects as

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 16
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure

specified.

(vii) Approaches (including 7.04% (vii) Approaches: Payment shall be


Retaining walls, stone pitching made on completion of both
and protection works) approaches including stone pitching,
protection works, etc. complete in
all respects as specified.

C.1- Widening and repairs of


Elevated Section/ Flyovers/
Grade Separators
0.00% (i) Foundation: Cost of each
(i) Foundation structure shall be determined on pro
rata basis with respect to the total
linear length (m) of the structures.
Payment against foundation shall be
made on pro-rata basis on
completion of a stage i.e. not less
than 25% of the scope of foundation
of the structure subject to
completion of at least two
foundations of the structure.

In case where load testing is


required for foundation, the trigger
of first payment shall include load
testing also where specified.

0.00% (ii) Sub-Structure: Payment against


(ii) Sub-structure Sub-structure shall be made on pro-
rata basis on completion of a stage
i.e. not less than 25% of the scope of
sub-structure of the structure subject
to completion of at least two sub-
structures of abutments/ piers up to
abutment/ pier cap level of the
structure.
(iii) Super-structure (including 0.00% (iii) Super-structure: Payment shall
bearings) be made on pro-rata basis on
completion of a stage i.e. completion
of super-structure including bearings
of at least one span in all respects as
specified.
(iv) Wearing Coat including 0.00% (iv) Wearing Coat: Payment shall
expansion joints be made on completion of wearing
coat including expansion joints
complete in all respects as specified.

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 17
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure

(v) Miscellaneous Items like hand 0.00% (v) Miscellaneous: Payments shall
rails, crash barriers, road markings be made on completion of all
etc. miscellaneous works like hand rails,
crash barriers, road markings etc.
complete in all respects as specified.

(vi) Wing walls/ return walls 0.00% (vi) Wing walls/ return walls:
Payment shall be made on
completion of all wing walls/ return
walls complete in all respects as
specified.

(vii) Approaches (including (vii) Approaches: Payment shall be


Retaining walls/ Reinforced 0.00% made on completion of both
earth wall, stone pitching and approaches including stone pitching,
protection works) protection works, etc. complete in
all respects as specified.
C.2(a)- New Elevated Section/
Flyovers/ Grade Separators

(i) Foundation
0.00%
(i) Foundation: Cost of each
structure shall be determined on pro
rata basis with respect to the total
linear length (m) of the structures.
Payment against foundation shall be
made on pro-rata basis on
completion of a stage i.e. not less
than 25% of the scope of foundation
of the structure subject to
completion of at least two
foundations of the structure.

In case where load testing is


required for foundation, the trigger
of first payment shall include load
testing also where specified.
(ii) Sub-structure
0.00%
(ii) Sub-Structure: Payment against
Sub-structure shall be made on pro-
rata basis on completion of a stage
i.e. not less than 25% of the scope of
sub-structure of the structure subject
to completion of at least two sub-
structures of abutments/ piers up to
abutment/ pier cap level of the
structure.

(iii) Super-structure (including


0.00%
bearings) (iii) Super-structure: Payment shall
be made on pro-rata basis on
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 18
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure

completion of a stage i.e. completion


of super-structure including bearings
of at least one span in all respects as
specified.
(iv) Wearing Coat including
expansion joints 0.00% (iv) Wearing Coat: Payment shall
be made on completion of wearing
coat including expansion joints
complete in all respects as specified.

(v) Miscellaneous Items like hand


rails, crash barriers, road markings 0.00% (v) Miscellaneous: Payments shall
etc. be made on completion of all
miscellaneous works like hand rails,
crash barriers, road markings etc.
complete in all respects as specified.
(vi) Wing walls/ return walls
0.00% (vi) Wing walls/ return walls:
Payment shall be made on
completion of all wing walls/ return
walls complete in all respects as
specified.
(vii) Approaches (including
Retaining walls/ Reinforced
0.00% (vii) Approaches: Payment shall be
earth wall, stone pitching and
made on completion of both
protection works)
approaches including stone pitching,
protection works, etc. complete in
C.2 (b) Interchange all respects as specified.
(aa) Structures

(i) Foundation
10.28% (i) Foundation: Cost of each
structure shall be determined on pro
rata basis with respect to the total
linear length (m) of the structures.
Payment against foundation shall be
made on pro-rata basis on
completion of a stage i.e. not less
than 25% of the scope of foundation
of the structure subject to
completion of at least two
foundations of the structure.

In case where load testing is


required for foundation, the trigger
of first payment shall include load
testing also where specified.
(ii) Sub-structure
3.25% (ii) Sub-Structure: Payment against
Sub-structure shall be made on pro-

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 19
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure

rata basis on completion of a stage


i.e. not less than 25% of the scope of
sub-structure of the structure subject
to completion of at least two sub-
structures of abutments/ piers up to
abutment/ pier cap level of the
structure.
(iii) Super-structure (including
bearings) 6.32% (iii) Super-structure: Payment shall
be made on pro-rata basis on
completion of a stage i.e. completion
of super-structure including bearings
of at least one span in all respects as
specified.
(iv) Wearing Coat including
expansion joints 0.29% (iv) Wearing Coat: Payment shall
be made on completion of wearing
coat including expansion joints
complete in all respects as specified.
(v) Miscellaneous Items like hand
rails, crash barriers, road markings 0.31% (v) Miscellaneous: Payments shall
etc. be made on completion of all
miscellaneous works like hand rails,
crash barriers, road markings etc.
complete in all respects as specified.
(vi) Wing walls/ return walls
0.00% (vi) Wing walls/ return walls:
Payment shall be made on
completion of all wing walls/ return
walls complete in all respects as
specified.
(vii) Approaches (including
Retaining walls/ Reinforced 0.52% (vii) Approaches: Payment shall be
made on completion of both
earth wall, stone pitching and
approaches including stone pitching,
protection works)
protection works, etc. complete in
all respects as specified.
(bb) Loops & Ramp

1) Earthwork up to top of the sub-


grade of Loops/Ramps 4.43% Cost of each Ramp & loop shall be
(2) Sub Base Course of determined on pro rata basis with
Loops/Ramps 0.84% respect to the total linear length (m)
(3) Dry Lean Concrete (DLC) of the Ramp & loop.
Course of Loops/Ramps 1.13% Payment shall be made on
(4) Pavement Quality Control completion as under.
(PQC) Course of Loops/Ramps 6.15% (1) Completion of the
earthwork up to subgrade of
a loop/ramp
(2) Completion of Sub base of a
loop/ramp

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 20
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure

(3) Completion of DLC of a


loop/ramp
(4) Completion of PQC of a
loop/ramp

Note: (1) In case of innovative Major Bridge projects like cable suspension/ cable stayed/
Extra Dozed and exceptionally long span bridges, the schedule may be modified as per site
requirements before bidding with due approval of DG (RD) & SS, MoRT&H.
(2) The Schedule for exclusive tunnel projects may be prepared as per site requirements before
bidding with due approval of DG (RD) & SS, MoRT&H.

1.3.4 Other works.

Procedure for estimating the value of other works done shall be as stated in table 1.3.4:

Table 1.3.4
Stage of Payment Weightage Payment Procedure

(i) Toll plaza Unit of measurement is each


6.58% completed toll plaza. Payment of
each toll plaza shall be made on pro
rata basis with respect to the total of
all toll plazas.
(ii) Road side drains 16.73% Unit of measurement is linear length
in km. Payment shall be made on
pro rata basis on completion of a
(iii) Road signs, markings, km 24.65% stage in a length of not less than
stones, safety devices, 10% (ten per cent) of the total
length.
(iv) Project Facilities

a) Bus bays 0.00%


b) Truck lay-byes 0.00% Payment shall be made on pro rata
c) Rest areas 21.04% basis for completed facilities.
d) Others (Junctions, Gantry,
Lighting, Utility Duct) 19.32%
(v) Roadside plantation 5.87% Unit of measurement is linear
length. Payment shall be made on
pro rata basis on completion of a

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 21
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of Payment Weightage Payment Procedure

(vi) Protection works other than stage in a length of not less than
approaches to the bridges, elevated 5.27% 10% (ten per cent) of the total
sections/ flyovers/grade separators length.
and ROBs/ RUBs.

(vii) Safety and traffic Payment shall be made on pro rata


management during construction 0.54% basis every three months.

2. Procedure for payment for Maintenance

2.1 The cost for maintenance shall be as stated in Clause 14.1.1.

2.2 Payment for Maintenance shall be made in quarterly installments in accordance with the
provisions of Clause 19.7.

Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 22
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)

You might also like