Item Weightage in Stage for Payment Percentage
Percentage to weightage
the
Contract Price
1 2 3 4
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-2
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Item Weightage in Stage for Payment Percentage
Percentage to weightage
the
Contract Price
1 2 3 4
B.1- Widening and Repair of
underpasses/ overpasses
(b) RUB
(1) Foundation
0.00%
(2) Sub-structure 0.00%
(3) Super- structure 0.00%
(including bearings)
(4) Wearing Coat: (a) in case of ROB-
wearing coat including expansion 0.00%
joints complete in all respects as
specified and (b) in case of RUB- rigid
pavement under RUB including
drainage facility complete in all
respects as specified.
(5) Miscellaneous Items like hand 0.00%
rails, crash barriers, road markings etc.
(6) Wing walls/ return walls 0.00%
(7) Approaches (including Retaining
0.00%
walls, stone pitching and protection
works)
B.2- New ROB/ RUB
(a) ROB
(b) RUB
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-4
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Item Weightage in Stage for Payment Percentage
Percentage to weightage
the
Contract Price
1 2 3 4
(1) Foundation
16.24%
(2) Sub-structure 6.03%
(3) Super- structure 28.56%
(including bearings)
(4) Wearing Coat: (a) in case of ROB-
wearing coat including expansion 0.87%
joints complete in all respects as
specified and (b) in case of RUB- rigid
pavement under RUB including
drainage facility complete in all
respects as specified
(5) Miscellaneous Items like hand
0.84%
rails, crash barriers, road markings etc.
(6) Wing walls/ return walls 0.00%
(7) Approaches (including Retaining
walls/Reinforced Earth walls, stone 7.04%
pitching and protection works)
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-5
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Item Weightage in Stage for Payment Percentage
Percentage to weightage
the
Contract Price
1 2 3 4
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-6
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Item Weightage in Stage for Payment Percentage
Percentage to weightage
the
Contract Price
1 2 3 4
(vi) Protection works other than 5.27%
approaches to the bridges,
elevated sections/
flyovers/ grade separators
and ROBs/ RUBs.
Table 1.3.1
Stage of Payment Percentage- Payment Procedure
weightage
(6) Widening and repair of culverts 0.00% Cost of completed culverts shall be
determined on pro rata basis with
respect to the total number of
culverts. The payment shall be made
on the completion of atleast five
culverts.
B.1- Reconstruction/ New 8-lane Unit of measurement is linear length.
realignment/ bypass Payment of each stage shall be made
on pro rata basis on completion of a
(Flexible pavement) stage in full length or 5 (five) km
length, whichever is less.
(1) Earthwork up to top of the 0.00%
sub-grade
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-7
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of Payment Percentage- Payment Procedure
weightage
(Rigid pavement)
(Rigid pavement)
Unit of measurement is linear length.
(1) Earthwork up to top of the Payment of each stage shall be made
sub-grade 0.00% on pro rata basis on completion of a
stage in full length or 5 (five) km
(2) Sub Base Course 0.00% length, whichever is less.
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-8
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of Payment Percentage- Payment Procedure
weightage
Cost per km = P x weightage for road work x weightage for bituminous work x (1/L)
L = Total length in km
Similarly, the rates per km for other stages shall be worked out accordingly.
Note: The length affected due to law and order problems or litigation during execution due to which the
Contractor is unable to execute the work, may be deducted from the total project length for
payment purposes. The total length calculated here is only for payment purposes and will not
affect and referred in other clauses of the Contract Agreement.
1.3.2 Minor Bridges and Underpasses/ Overpasses.
Procedure for estimating the value of Minor bridge and Underpasses/ Overpasses shall be as stated
in table 1.3.2:
Table 1.3.2
Stage of Payment Weightage Payment Procedure
A.1 - Widening and repairs of Cost of each Minor Bridge shall be
Minor Bridges determined on pro-rata basis with
0.00% respect to the total linear length of
(length > 6m and < 60m) the minor bridges. Payment shall be
made on the completion of widening
and repair works of a minor bridge.
A.2- New minor bridges (i) Foundation + SubStructure:
Cost of each Minor Bridge shall be
(i) Foundation + Sub-Structure: On determined on pro-rata basis with
completion of the foundation respect to the total linear length
work including foundations for (m) of the minor bridges.
wing and return walls, abutments, 31.28% Payment against foundation + sub-
piers up to the abutment/ pier cap. structure shall be made on pro-rata
basis on completion of a stage i.e.
not less than 25% of the scope of
foundation + sub-structure of each
bridge subject to completion of at
least two foundations along with
sub-structure up to abutment/ pier
cap level of each bridge.
In case where load testing is
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H-9
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of Payment Weightage Payment Procedure
required for foundation, the trigger
of first payment shall include load
testing also where specified.
(ii) Super-structure: On completion (ii) Super-structure:
of the super structure in all Payment shall be made on pro-rata
respects including wearing coat, basis on completion of a stage i.e.
bearings, expansion joints, hand completion of super-structure of at
rails, crash barriers, road signs 24.52% least one span in all respects as
and markings, tests on specified in the column of Stage
completion etc. complete in all of Payment in this sub-clause.
respect.
(iv) Guide Bunds and River 0.00% (iv) Guide Bunds and River
Training Works: On completion of Training Works: Payment shall
guide Bunds and river Training Works be made on pro-rata basis on
complete in all respect. completion of a stage i.e.
completion of Guide Bunds and
River training Works in all
respects as specified.
Procedure for estimating the value of Major Bridge works, ROB / RUB and structures shall be as
stated in table 1.3.3:
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 11
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Table 1.3.3
Stage of payment Weightage Payment procedure
(iv) Wearing Coat including 0.00% (iv) Wearing Coat: Payment shall
expansion joints be made on completion of wearing
coat including expansion joints
complete in all respects as specified.
(vi) Wing walls/ return walls 0.00% (vi) Wing walls/ return walls:
Payment shall be made on
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 12
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure
specified.
(iv) Wearing Coat including 0.14% (iv) Wearing Coat: Payment shall
expansion joints be made on completion of wearing
coat including expansion joints
complete in all respects as specified.
(vi) Wing walls/ return walls 0.00% (vi) Wing walls/ return walls:
Payment shall be made on
completion of all wing walls/ return
walls complete in all respects as
specified.
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 14
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure
(iv) Wearing Coat including 0.00% (iv) Wearing Coat: Payment shall
expansion joints in case of ROB. In be made on completion of (a) in case
case of RUB, rigid pavement under of ROB- wearing coat including
RUB including drainage facility as expansion joints complete in all
specified. respects as specified and (b) in case
of RUB- rigid pavement under RUB
including drainage facility complete
in all respects as specified.
(v) Miscellaneous Items like hand
0.00% (v) Miscellaneous: Payment shall
rails, crash barriers, road markings
be made on completion of all
etc.
miscellaneous works like hand rails,
crash barriers, road markings etc.
complete in all respects as specified.
(vi) Wing walls/ return walls (vi) Wing walls/ return walls:
0.00% Payment shall be made on
completion of all wing walls/ return
walls complete in all respects as
specified.
B.2- New
(a) ROB
(b) RUB
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 15
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 16
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure
specified.
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 17
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure
(v) Miscellaneous Items like hand 0.00% (v) Miscellaneous: Payments shall
rails, crash barriers, road markings be made on completion of all
etc. miscellaneous works like hand rails,
crash barriers, road markings etc.
complete in all respects as specified.
(vi) Wing walls/ return walls 0.00% (vi) Wing walls/ return walls:
Payment shall be made on
completion of all wing walls/ return
walls complete in all respects as
specified.
(i) Foundation
0.00%
(i) Foundation: Cost of each
structure shall be determined on pro
rata basis with respect to the total
linear length (m) of the structures.
Payment against foundation shall be
made on pro-rata basis on
completion of a stage i.e. not less
than 25% of the scope of foundation
of the structure subject to
completion of at least two
foundations of the structure.
(i) Foundation
10.28% (i) Foundation: Cost of each
structure shall be determined on pro
rata basis with respect to the total
linear length (m) of the structures.
Payment against foundation shall be
made on pro-rata basis on
completion of a stage i.e. not less
than 25% of the scope of foundation
of the structure subject to
completion of at least two
foundations of the structure.
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 19
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 20
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of payment Weightage Payment procedure
Note: (1) In case of innovative Major Bridge projects like cable suspension/ cable stayed/
Extra Dozed and exceptionally long span bridges, the schedule may be modified as per site
requirements before bidding with due approval of DG (RD) & SS, MoRT&H.
(2) The Schedule for exclusive tunnel projects may be prepared as per site requirements before
bidding with due approval of DG (RD) & SS, MoRT&H.
Procedure for estimating the value of other works done shall be as stated in table 1.3.4:
Table 1.3.4
Stage of Payment Weightage Payment Procedure
Construction of Six lane Vadodara Kim Expressway from Km 254.430 to Km 279.000 (Kim to Ankleshwar Section of H - 21
Vadodara Mumbai Expressway) in the State of Gujarat under NHDP Phase - VI on EPC mode (Phase IA-Package
V)
National Highways Authority of India Request for Proposal Bid Documents
Stage of Payment Weightage Payment Procedure
(vi) Protection works other than stage in a length of not less than
approaches to the bridges, elevated 5.27% 10% (ten per cent) of the total
sections/ flyovers/grade separators length.
and ROBs/ RUBs.
2.2 Payment for Maintenance shall be made in quarterly installments in accordance with the
provisions of Clause 19.7.