Professional Documents
Culture Documents
CON4541 - CCM - Chapter 4 - 10 PDF
CON4541 - CCM - Chapter 4 - 10 PDF
4. Contract Administration (refer Private Standard Form with Quantities for HK)
Contd
Interim Certificate
The Architect shall rely on the Quantity Surveyor to advise him as to the sum
which should be stated as due in any such certificate.
Stage payments are more appropriate to contracts where the stages are often
readily or satisfactorily definable. i.e. Lift & Escalator Installations, etc.
Note: The Architect shall issue the first Interim Certificate within 42 days after
the Commencement Date. The first Interim Certificate will set the program of
certificates for the subsequent payments due in the Contract. e.g. 3rd May for
the issue date of the first I.C. then , the next certificate date of issue to be 3rd
June. Thus, it is important to decide from the start a fixed date in each month
on which to do valuations. ( the valuation date )
B. General Procedure
@VTC2013 1 of 9
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
From the total value so arrived at (accumulated total) , less the previous
payments on account if any, leaving a balance due for payment for that
month.
It is important that the QS should not attempt to value in isolation the work
done and the unfixed materials delivered since the last valuation.
The QSs first task on visiting the Site for valuation purposes ( having first
made his presence known to the site agent and clerk of works), is to tour the
Works, making notes as necessary of the extent of work done and listing the
quantities of the various unfixed materials and goods stored on the Site.
It should be noted that the PQS has no obligation to make use of them,
although he may find it convenient to use them as a basis for his own
valuation by checking each of the constituent amounts and, if necessary,
amending any as he sees fit.
D. Inclusions in Valuations
The amounts to be included in the gross valuation and the Interim Certificate
are set out in Clause 32.2. Briefly, these are the value of :
1. Preliminaries
2. Main contractors work ( work properly executed as billed )
3. Variations
4. Unfixed materials properly stored on Site
5. Unfixed materials properly stored off Site if Cl.32.3 applies (deal with
great care)
6. Amounts directed for payment to N.S.C. and N.S.
7. Fluctuations in cost of labor, materials etc. if Cl.38 applies
8. Amount ascertained for direct loss and/or expense
9. Retention
1. Preliminaries
a) Breakdown of Preliminaries
@VTC2013 2 of 9
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
The preliminaries constituent will then need to be broken down into separate
amounts such as would normally be seen in the preliminaries section of a bill
of quantities.
Those which are cost-related ( e.g. water for the Works, construction levies,
etc. ) depend for their value on that of the reminder of the Contract Sum or of
its labour content.
b) Valuation of Preliminaries
It is not uncommon to deal with the total value of the preliminaries as if the
items were either all cost-related or all time-related.
For time-related case, the total of the preliminaries is divided by the contract
period ( in months ) and the resulting sum is multiplied by the number of
months which have elapsed to date. This amount is then included in the
valuation as the total amount for Preliminaries.
Where the time-related method is used and if the contract runs behind
schedule, there will be a danger of overpayment, unless the fixed monthly
amounts are adjusted.
@VTC2013 3 of 9
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
The value of the work carried out by the main contractors own workforce is
ascertainable from the measured work sections of the bills of quantities.
It should be noted that the price contained in the bills of quantities ( the
Contract Bills ) must be used in the valuation of the main contractors work,
regardless of whether the contractor under-priced or over-priced the work
when compiling the tender.
The notes made during the initial tour and inspection of the Works ( include
only those works that are properly executed ) is used in assessing
approximately the value of completed works. The completed work as a
percentage of the whole item should be indicated opposite the bill reference.
3. Variations
4. Materials on Site
The value of material and goods brought on Site may be included in the
Interim Certificate. The materials and goods must be reasonably, properly and
not prematurely delivered and protected.
The QS will need to be satisfied that the materials and goods are physically
stored on the Site and to ascertain approximately how much of each material
or good there is.
The Contractors surveyor may be required to provide the QS a list of all the
materials with their respective quantities to be claimed under the materials on
Site item together with their supporting delivery notes and invoices.
(c) any materials or goods which have been delivered prematurely, i.e. when
the length of time before they are likely to be required is unreasonably long.
@VTC2013 4 of 9
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
Note : the sums included for Nominated Sub-contractors work are also the
cumulative value of total work done up to the date of valuation in each month.
The goods and materials are properly protected and stored, not damaged or
defective.
7. Retention
@VTC2013 5 of 9
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
The second half of the retention monies is released when the Defects Liability
Period stated in the Appendix of the Conditions of Contract has expired and
upon the issue of the Certificate of Completion of Making Good Defects by
the Architect.
Under the Conditions of Contract, the Contractor can determine his own
employment in accordance to Clause 36.1 if the Employer fails to honor an
Interim Certificate, but not fail to issue an Interim Certificate.
If the Contractor does not receive his copy of an Interim Certificate at the
proper time. Notices stating the absence of receipt of Interim Certificate
should be given to the Architect and to request for the issue. Otherwise, the
Contractor can go for Arbitration.
Such notice :
refer to the Interim Certificate in question
inform the Architect of the dissatisfaction of the Contractor of the amount
included
give a brief explanation of the reason for the dissatisfaction.
request that the Architect immediately issue a revised Interim Certificate.
G. Set-off
@VTC2013 6 of 9
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
the cost to the Employer of the failure of the Contractor to comply with
Architects Instructions.
the cost to the Employer of insurance following the failure of the Contractor to
insure.
Note :
No deduction can be made from Retention monies until they have been
included in an Interim Certificate.
The Conditions require Employer to inform the Main Contractor for the
exercise of the set-off (including the reason for making the deduction).
Final account (FA) is a summary of the total Final Contract Sum taking into
consideration of all monetary adjustments to the Contract Bill as required.
Before the Final Certificate can be issued, the final account has to be
prepared by the Quantity Surveyor, who is required to adjust the Contract
Sum in the Contract Bills to include all the monetary additions and omissions
of the following items :
1. Contingency sum
2. Architects Instructions
3. Provisional Quantities and Items
4. Provisional Sums and Prime Cost Sums
5. Fluctuations
6. Agreed amount of Contractors direct loss and/or expense
The Period of Final Measurement and Valuation should begin with issue of
the Certificate of Substantial Completion and be completed within the time
stated in the Appendix; twelve months unless otherwise stated.
All adjustments made to the Contract Sum should be agreed by the main
contractors quantity surveyor. When the final account together with the Final
Contract Sum has been agreed, a summary is prepared setting out all the
adjustments, which should be signed by the Contractor, the Quantity Surveyor
and the Architect.
@VTC2013 7 of 9
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
Where the interim certificates represent a fair evaluation of all the work
contained in the contract, including billed items, variations and extras, the
settlement of the final account should not be too difficult.
In practice many factors combine to prevent this ideal arrangement taking
place.
Not later than 6 months after Substantial Completion of the whole of the
Works or 3 months before the end of the period for completion of the final
account, whichever is earlier, the Contractor shall submit to the Quantity
Surveyor all the documents that are, in opinion of the Quantity Surveyor,
reasonably necessary for the adjustment of the Contract Sum including those
relating to NSC and NS.
Most of the information should already be with the Quantity Surveyor in the
form of the following documentation:
2. the records and other cost data relating to Variations which have usually
been submitted to and discussed with the Architect/Engineers
3. the full and detailed particulars of all claims for direct loss and expense
which should have been delivered as soon as reasonable to the QS
Although not necessary the Contractor will submit his own statement of final
account to the Quantity Surveyor for agreement, the Contractor will take the
opportunity to substitute accurate amounts for earlier approximations, correct
any errors and, in the case of claims covering activities which continued up to
the end of the construction period, it is probable that he can now provide all
the necessary supporting financial data.
Work of NSC or NS
The QS will prepare the final accounts for Nominated Sub-contractors and
Nominated Suppliers similar to the main contract.
@VTC2013 8 of 9
CON4541 CONSTRUCTION CONTRACT MANAGEMENT
The Final Certificate is issued to certify that the Works have been entirely
completed to the Employers satisfaction in accordance with the terms of the
Contract between the two parties.
(a) the materials, goods, workmanship and work were provided or carried out
to the Architects satisfaction;
(b) the final account is prepared and arrived with the Final Contract Sum.
(d) all claims including direct loss and expense for breach of contract, duty of
care, statutory duty, etc. have been settled.
Cl 32.8(1) provides that the Architect shall issue the Final Certificate to each
parties by special delivery soon after the issue of Defects Rectification
Certificate provided that the Final Certificate shall not be issued until 28 days
after a copy of the signed final account has been given to each parties.
The Final Certificate will include the sum of all amounts previously certified
and the Contact Sum adjusted as necessary in accordance with the
Conditions of the Contract. The difference between these two sums (i.e. Final
Contract Sum less previous amount certified in Interim Certificates) will be
expressed as a balance due to Contractor from the Employer or to the
Employer from the Contractor as the case may be.
This balance due shall be a debt payable 28 days after the issue of the Final
Certificate either by the Employer or Contractor as the case maybe but
subject to:
The balance due to either party is described as a debt payable and these
words make it certain that a final payment can be properly the subject of the
High Court action if that payment is not made after 28 days prescribed.
@VTC2013 9 of 9